FORM WORK
By K.Shah
B.E.(Civil Engg) NIT Rourkela,India
M.Sc. (Environment), University of
Leeds,UK
Ex-GM(Civil & Environment) – MNC
Currently Guest faculty-College of
Technology & Engineering
“ Form work or shuttering is a temporary
construction used as a mould for
structure, in which concrete is placed &
in which it hardens and matures”.
 Construction of form work requires lot of time &
material.
 Cost of form work is 20-25 % of cost of building.
 When required strength of concrete is achieved, form
work is removed.
 operation of removal of form work is called ‘stripping’
• Removed component of form work is reused for
another construction.
• Such forms whose components are used many times
are called ‘Panel Forms’.
• Forms made for non standard structures which can not
be used again is called ‘Stationary Forms’.
Classification of formwork
1. Wooden
2. Plywood
3. Steel
4. Combined (wood & steel)
Wooden form work
 Most common form work
 Disadvantage : Possibility of warping, swelling,
shrinkage.
 Water impermeable coating on wood form work
is applied to reduce warping, swelling,
shrinking
 With impermeable coating shuttering can be
removed easily.
Steel form work
Steel shuttering is used for major work.
Advantages:
a) It can be put to use for high number of times.
b) It provides ease of stripping
c) It gives smooth & even concrete surface
d) It posses high rigidity
e) It is not liable to shrinkage or distortion
f) It is costly.
Requirements of form work
A good form work should satisfy following
requirements:
a) Material of formwork should be cheap & can be reused many time.
b) It should be water proof & should not absorb water from concrete.
Shrinkage & swelling should be minimum.
c) It should be strong enough to take all loads coming on it (dead load of
concrete,live load of labour during pouring, compaction & curing.
d) It should be stiff enough so that deflection is minimum.
e) It should be light as far as possible
f) Surface of form work should be smooth for easy stripping
g) All joints of form work should be stiff so that lateral deformation under
load is minimum. Joints should be leak proof.
Indian Standard of Form work
(IS :456-1964)
(1) General :
The form work :
 shall conform to the shape, lines & dimensions as shown on
the plans.
 Shall be rigid during placing & compacting of concrete.
 Water tight to prevent loss of water from concrete.
(2) Cleaning & treatment of forms
 All rubbish, chippings, saw dust shall be removed from the
interior of form work before placing of concrete.
 Shall be wetted.
Indian Standard of Form work
(IS :456-1964)
(3) STRIPPING TIME
Form work should not removed until good strength has come.
Type of form work Time
Vertical wall, columns 16-24 hrs
Soffit of slab (Prop should be refixed immediately) 3 days
Soffit of beam (Prop should be refixed immediately) 7 days
Props to slab Span < 4.5 m 7 days
Props to slab Span > 4.5 m 14 days
Props of beam (Span < 6 m) 14 days
Props of beam (Span > 6 m) 21 days
Indian Standard of Form work
(IS :456-1964)
(4) Procedure when removing form work
 All form work shall be removed without shock or vibration as it
will damage the concrete.
 Before the soffit (bottom surface ) & struts (pole) are removed, the
concrete shall be exposed, to check that the concrete has
sufficiently hardened.
 Proper precautions shall be taken to allow for decrease in the rate of
hardening in cold water.
(5) Camber
 It is desirable to give form an upward camber (slope) to ensure that
beams do not sag when they have taken up their deflection.
 This should be done only when allowed in the design calculation of
the beam.
Indian Standard of Form work
(IS :456-1964)
(6) Tolerances
Form work shall be so constructed that the internal
dimen sions are within the permissible tolerance
specified by the designer.
LOADS ON FORM WORK
The form work has to take following loads:
a) Live load due to labour
b) Weight of wet concrete
c) Hydrostatic pressure of the fluid concrete acting against the
vertical or inclined faces of form
d) Impact due to pouring of concrete.
 Live loads of labour & equipment including impact may be taken
as 370 Kg/m2.
LOADS ON FORM WORK
HYDROSTATIC PRESSURE:
Hydro static pressure due to fluid of
concrete depends on :
a) Quantity of water in concrete
b) Size of aggregate
c) Rate of pouring
d) Temperature
HYDROSTATIC PRESSURE:
Hydrostatic pressure is maximum during pouring
and decreases when concrete becomes hard.
Setting time may be taken as ¾ to 1 hour.
Only height of concrete poured in ¾ to 1 hour is
taken into account for calculation of hydrostatic
pressure on form work.
For 1.5 m height of concrete, equivalent weight
of concrete may be taken as 2300 kg/m3.
• HYDROSTATIC PRESSURE:
For higher height, the equivalent weight of
concrete is reduced.
When height of concrete in one pour is 6 m, the
equivalent fluid weight may be 1200 kg/m3.
For intermediate heights between 1.5 to 6 m
poured within the setting time of ¾ hour linear
interpolation of unit weight between 1200 to
2300 kg/m3 may be taken.
SHUTTERING FOR COLUMN
SHUTTERING FOR COLUMN
It consists of :
a. Sheeting all round the column periphery
b. Side yokes & end yokes
c. Wedges
d. Bolts with washers
SHUTTERING FOR COLUMN
 The side yokes & end yokes consists of 2
numbers each
 They are suitably spaced along the height of
column
 Two side yokes are comparatively of heavier
section & are connected together by 2 long
bolts.
 Four wedges one at each corner are inserted
between bolts & end yokes
 The sheathing is nailed to yokes.
OCTAGONAL COLUMN
CIRCULAR COLUMN
SHUTTERING FOR BEAM & SLAB FLOOR
 The slab is continuous over number of beams.
 The slab is supported on 2.5 cm thick sheathing laid parallel to
main beam.
 The sheathing is supported on wooden battens which are laid
between the beams, at suitable spacing.
 In order to reduce deflection, the battens may be propped at
middle of the span through joists.
 The side forms of the beam consists 3 mm thick sheathing.
 The bottom sheathing of the beam form may be 5 to 7 cm thick.
SHUTTERING FOR BEAM & SLAB FLOOR
 The end of the battens are supported on ledger which
is fixed to cleats throughout the length.
 Cleats 10 cm x 2 cm x 3 cm are fixed to the forms at
the same spacing as that of battens, so that battens
may be fixed to them.
 The beam forms is supported on a head tree.
 The shore or post is connected to head tree through
cleats.
 At the bottom of shore, two wedges of hard wood are
provided over a sole piece.
SHUTTERING FOR STAIRS
• The sheathing or decking for deck slab is carried on
cross joists
• Cross joists are supported on raking ledgers.
• Ledger is 7.5 cm x 10 cm size.
• Cross joists are 5 cm x 10 cm size
• Riser planks are 4 -5 cm thick
• Planks are bevelled at bottom to permit the whole of the
tread faced to be trovelled.
SHUTTERING FOR STAIRS
• Riser plank are fixed after reinforcement has been fixed
in position.
• Outer end of of risers are carried by a cut string made of
5 cm plank.
• The cut string is strutted to the cross joists by 5 cm x 10
cm struts.
• The wall ends of the riser planks are carried by 5 cm x
10 cm hangers secured to 5 cm thick board fixed to wall.
• Treads are left open for concreting & vibration.
• Stiffner joists of 5 cm x 10 cm is placed along the middle
of the riser planks.
• Stiffner is wired to cross joists through decking.
FORM WORK FOR WALLS
FORM WORK FOR WALLS
a) The boarding is 4 to 5 cm thick for walls of 3 to 4 mt
height.
b) Boards are fixed to 5 cm x 10 cm posts known as
studs or soldiers
c) Studs are paced at spacing of 0.8 m.
d) Horizontal wallings of size 7.5 cm x 10 cm are fixed to
the at suitable interval.
MOVING WALL FORM
MOVING WALL FORM
a) In moving wall forms, panels are made of 0.6 x 1.8 m size so that
handling & stripping is easy.
b) 15 mm ply board is used instead of boarding
c) The panels are installed in such a way that the lower panel can
be removed when concrete is hard and used higher up wall.
d) Framing of size 5 cm x 10 cm is used to ply shutter.
e) The panels are fixed to a central and two end studs.
f) Each stud consists of two pieces of timbers, 5 cm x 15 cm apart.
g) The end strut of each panel secures adjucent panel.
h) Boards are reversed for 1st lift ; for succeeding lifts, bolts pass
through holes formed to previous lift.
i) For rapid construction of a constant thickness wall, continuously
rising form, commonly known as sliding shutter is used
Form Work

More Related Content

What's hot

Plastering and pointing
Plastering and pointingPlastering and pointing
Plastering and pointing
Shrikant Jahagirdar
 
Brick Masonry
Brick MasonryBrick Masonry
Brick Masonry
Joynul Abadin Rasel
 
Chapter 7 stairs & staircases
Chapter 7 stairs & staircasesChapter 7 stairs & staircases
Chapter 7 stairs & staircases
KHUSHBU SHAH
 
Foundation and its types
Foundation and its typesFoundation and its types
Foundation and its types
Satish Kambaliya
 
Arches
ArchesArches
What is wall? Different types of wall.
What is wall? Different types of wall.What is wall? Different types of wall.
What is wall? Different types of wall.
Syed Raja
 
Principles of brick masonry Principles & Significance ppt
Principles of brick masonry Principles & Significance pptPrinciples of brick masonry Principles & Significance ppt
Principles of brick masonry Principles & Significance ppt
shabir rufai
 
Roof and roof covering
Roof and roof coveringRoof and roof covering
Roof and roof covering
Divya Vishnoi
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructure
guasiya
 
BRICK MASONRY PPT BY SUBHENDU SAMUI
BRICK MASONRY PPT BY SUBHENDU SAMUIBRICK MASONRY PPT BY SUBHENDU SAMUI
BRICK MASONRY PPT BY SUBHENDU SAMUI
Subhendu Samui
 
Roofs
RoofsRoofs
Types of pitched roofs
Types of pitched roofsTypes of pitched roofs
Types of pitched roofs
anandcivil103
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU
VATSAL PATEL
 
Brickwork bond ppt
Brickwork bond pptBrickwork bond ppt
Brickwork bond ppt
Lakshmi Radhakrishnan
 
Building construction materials -Tiles
Building construction materials -TilesBuilding construction materials -Tiles
Brick masonary
Brick masonaryBrick masonary
Brick masonary
Vaibhav Girdhar
 
Foundations
FoundationsFoundations
Foundations
Shanik Aromgottil
 
Types of formwork
Types of formworkTypes of formwork
Types of formwork
Aglaia Connect
 
Ch3 stair cont..
Ch3 stair cont..Ch3 stair cont..
Ch3 stair cont..
neharajpl
 
Brick bond
Brick bondBrick bond
Brick bond
Kamrul Hasan Sagar
 

What's hot (20)

Plastering and pointing
Plastering and pointingPlastering and pointing
Plastering and pointing
 
Brick Masonry
Brick MasonryBrick Masonry
Brick Masonry
 
Chapter 7 stairs & staircases
Chapter 7 stairs & staircasesChapter 7 stairs & staircases
Chapter 7 stairs & staircases
 
Foundation and its types
Foundation and its typesFoundation and its types
Foundation and its types
 
Arches
ArchesArches
Arches
 
What is wall? Different types of wall.
What is wall? Different types of wall.What is wall? Different types of wall.
What is wall? Different types of wall.
 
Principles of brick masonry Principles & Significance ppt
Principles of brick masonry Principles & Significance pptPrinciples of brick masonry Principles & Significance ppt
Principles of brick masonry Principles & Significance ppt
 
Roof and roof covering
Roof and roof coveringRoof and roof covering
Roof and roof covering
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructure
 
BRICK MASONRY PPT BY SUBHENDU SAMUI
BRICK MASONRY PPT BY SUBHENDU SAMUIBRICK MASONRY PPT BY SUBHENDU SAMUI
BRICK MASONRY PPT BY SUBHENDU SAMUI
 
Roofs
RoofsRoofs
Roofs
 
Types of pitched roofs
Types of pitched roofsTypes of pitched roofs
Types of pitched roofs
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU
 
Brickwork bond ppt
Brickwork bond pptBrickwork bond ppt
Brickwork bond ppt
 
Building construction materials -Tiles
Building construction materials -TilesBuilding construction materials -Tiles
Building construction materials -Tiles
 
Brick masonary
Brick masonaryBrick masonary
Brick masonary
 
Foundations
FoundationsFoundations
Foundations
 
Types of formwork
Types of formworkTypes of formwork
Types of formwork
 
Ch3 stair cont..
Ch3 stair cont..Ch3 stair cont..
Ch3 stair cont..
 
Brick bond
Brick bondBrick bond
Brick bond
 

Similar to Form Work

Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
KHUSHBU SHAH
 
Formwork
FormworkFormwork
Formwork
Lavanya Singh
 
Formwork-Types and Their Advantages
Formwork-Types and Their AdvantagesFormwork-Types and Their Advantages
Formwork-Types and Their Advantages
Jay1997Singhania
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
Himanshumangal12
 
Formwork
FormworkFormwork
Formwork
kajol panchal
 
Estimating Systems for Homes1
Estimating Systems for Homes1Estimating Systems for Homes1
Estimating Systems for Homes1
Keith Daggett
 
Temporary Works (Form Work)
Temporary Works (Form Work)Temporary Works (Form Work)
Temporary Works (Form Work)
Sujith Velloor Sudarsanakumar Nair
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
GARRE RAVI KUMAR
 
Formwork For Structural Member.pptx
Formwork For Structural Member.pptxFormwork For Structural Member.pptx
Formwork For Structural Member.pptx
Mr Amol Ghogare
 
From work &amp; shuttering
From work &amp; shutteringFrom work &amp; shuttering
From work &amp; shuttering
hamidgujjar
 
FormWork
FormWork FormWork
FormWork
Abhishek Kansara
 
Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar raut
SAGAR RAUT
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
Kishor Ade
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
Est chua
 
Formwork
FormworkFormwork
Formwork
Sneha Kaira
 
Gurme santoshkumar
Gurme santoshkumarGurme santoshkumar
Gurme santoshkumar
santoshkumar gurme
 
Formwork
FormworkFormwork
Formwork
snehakaira
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdf
FaizanSolanki
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
sfQyoom
 
RCC Elements column, beam.
RCC Elements  column, beam.RCC Elements  column, beam.
RCC Elements column, beam.
Puneet Chhonker
 

Similar to Form Work (20)

Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
Formwork
FormworkFormwork
Formwork
 
Formwork-Types and Their Advantages
Formwork-Types and Their AdvantagesFormwork-Types and Their Advantages
Formwork-Types and Their Advantages
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
 
Formwork
FormworkFormwork
Formwork
 
Estimating Systems for Homes1
Estimating Systems for Homes1Estimating Systems for Homes1
Estimating Systems for Homes1
 
Temporary Works (Form Work)
Temporary Works (Form Work)Temporary Works (Form Work)
Temporary Works (Form Work)
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
 
Formwork For Structural Member.pptx
Formwork For Structural Member.pptxFormwork For Structural Member.pptx
Formwork For Structural Member.pptx
 
From work &amp; shuttering
From work &amp; shutteringFrom work &amp; shuttering
From work &amp; shuttering
 
FormWork
FormWork FormWork
FormWork
 
Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar raut
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
Formwork
FormworkFormwork
Formwork
 
Gurme santoshkumar
Gurme santoshkumarGurme santoshkumar
Gurme santoshkumar
 
Formwork
FormworkFormwork
Formwork
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdf
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
RCC Elements column, beam.
RCC Elements  column, beam.RCC Elements  column, beam.
RCC Elements column, beam.
 

More from Kezar Ali. Shah

Design & construction of secure waste landfill
Design & construction of secure waste landfillDesign & construction of secure waste landfill
Design & construction of secure waste landfill
Kezar Ali. Shah
 
Transportation of Concrete - Notes for Civil engineering Students
Transportation of Concrete  - Notes for Civil engineering StudentsTransportation of Concrete  - Notes for Civil engineering Students
Transportation of Concrete - Notes for Civil engineering Students
Kezar Ali. Shah
 
Concrete design mix (ss)
Concrete design mix (ss)Concrete design mix (ss)
Concrete design mix (ss)
Kezar Ali. Shah
 
Handling of Concrete
Handling of ConcreteHandling of Concrete
Handling of Concrete
Kezar Ali. Shah
 
Environment Clearance Procedure-India
Environment Clearance Procedure-IndiaEnvironment Clearance Procedure-India
Environment Clearance Procedure-India
Kezar Ali. Shah
 
Road Safety Awareness (india)
Road Safety Awareness (india)Road Safety Awareness (india)
Road Safety Awareness (india)
Kezar Ali. Shah
 

More from Kezar Ali. Shah (6)

Design & construction of secure waste landfill
Design & construction of secure waste landfillDesign & construction of secure waste landfill
Design & construction of secure waste landfill
 
Transportation of Concrete - Notes for Civil engineering Students
Transportation of Concrete  - Notes for Civil engineering StudentsTransportation of Concrete  - Notes for Civil engineering Students
Transportation of Concrete - Notes for Civil engineering Students
 
Concrete design mix (ss)
Concrete design mix (ss)Concrete design mix (ss)
Concrete design mix (ss)
 
Handling of Concrete
Handling of ConcreteHandling of Concrete
Handling of Concrete
 
Environment Clearance Procedure-India
Environment Clearance Procedure-IndiaEnvironment Clearance Procedure-India
Environment Clearance Procedure-India
 
Road Safety Awareness (india)
Road Safety Awareness (india)Road Safety Awareness (india)
Road Safety Awareness (india)
 

Recently uploaded

An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
DharmaBanothu
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
upoux
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
Digital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptxDigital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptx
aryanpankaj78
 
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
sydezfe
 
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
Paris Salesforce Developer Group
 
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Transcat
 
Open Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surfaceOpen Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surface
Indrajeet sahu
 
Accident detection system project report.pdf
Accident detection system project report.pdfAccident detection system project report.pdf
Accident detection system project report.pdf
Kamal Acharya
 
Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...
Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...
Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...
IJCNCJournal
 
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdfSELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
Pallavi Sharma
 
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICSUNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
vmspraneeth
 
Flow Through Pipe: the analysis of fluid flow within pipes
Flow Through Pipe:  the analysis of fluid flow within pipesFlow Through Pipe:  the analysis of fluid flow within pipes
Flow Through Pipe: the analysis of fluid flow within pipes
Indrajeet sahu
 
Supermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdfSupermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdf
Kamal Acharya
 
SMT process how to making and defects finding
SMT process how to making and defects findingSMT process how to making and defects finding
SMT process how to making and defects finding
rameshqapcba
 
openshift technical overview - Flow of openshift containerisatoin
openshift technical overview - Flow of openshift containerisatoinopenshift technical overview - Flow of openshift containerisatoin
openshift technical overview - Flow of openshift containerisatoin
snaprevwdev
 
Blood finder application project report (1).pdf
Blood finder application project report (1).pdfBlood finder application project report (1).pdf
Blood finder application project report (1).pdf
Kamal Acharya
 
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call GirlCall Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
sapna sharmap11
 
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
PriyankaKilaniya
 
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdfFUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
EMERSON EDUARDO RODRIGUES
 

Recently uploaded (20)

An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
Digital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptxDigital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptx
 
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
 
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
 
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
 
Open Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surfaceOpen Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surface
 
Accident detection system project report.pdf
Accident detection system project report.pdfAccident detection system project report.pdf
Accident detection system project report.pdf
 
Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...
Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...
Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...
 
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdfSELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
 
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICSUNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
 
Flow Through Pipe: the analysis of fluid flow within pipes
Flow Through Pipe:  the analysis of fluid flow within pipesFlow Through Pipe:  the analysis of fluid flow within pipes
Flow Through Pipe: the analysis of fluid flow within pipes
 
Supermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdfSupermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdf
 
SMT process how to making and defects finding
SMT process how to making and defects findingSMT process how to making and defects finding
SMT process how to making and defects finding
 
openshift technical overview - Flow of openshift containerisatoin
openshift technical overview - Flow of openshift containerisatoinopenshift technical overview - Flow of openshift containerisatoin
openshift technical overview - Flow of openshift containerisatoin
 
Blood finder application project report (1).pdf
Blood finder application project report (1).pdfBlood finder application project report (1).pdf
Blood finder application project report (1).pdf
 
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call GirlCall Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
 
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
 
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdfFUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
 

Form Work

  • 1. FORM WORK By K.Shah B.E.(Civil Engg) NIT Rourkela,India M.Sc. (Environment), University of Leeds,UK Ex-GM(Civil & Environment) – MNC Currently Guest faculty-College of Technology & Engineering
  • 2. “ Form work or shuttering is a temporary construction used as a mould for structure, in which concrete is placed & in which it hardens and matures”.
  • 3.  Construction of form work requires lot of time & material.  Cost of form work is 20-25 % of cost of building.  When required strength of concrete is achieved, form work is removed.  operation of removal of form work is called ‘stripping’ • Removed component of form work is reused for another construction. • Such forms whose components are used many times are called ‘Panel Forms’. • Forms made for non standard structures which can not be used again is called ‘Stationary Forms’.
  • 4. Classification of formwork 1. Wooden 2. Plywood 3. Steel 4. Combined (wood & steel)
  • 5. Wooden form work  Most common form work  Disadvantage : Possibility of warping, swelling, shrinkage.  Water impermeable coating on wood form work is applied to reduce warping, swelling, shrinking  With impermeable coating shuttering can be removed easily.
  • 6. Steel form work Steel shuttering is used for major work. Advantages: a) It can be put to use for high number of times. b) It provides ease of stripping c) It gives smooth & even concrete surface d) It posses high rigidity e) It is not liable to shrinkage or distortion f) It is costly.
  • 7. Requirements of form work A good form work should satisfy following requirements: a) Material of formwork should be cheap & can be reused many time. b) It should be water proof & should not absorb water from concrete. Shrinkage & swelling should be minimum. c) It should be strong enough to take all loads coming on it (dead load of concrete,live load of labour during pouring, compaction & curing. d) It should be stiff enough so that deflection is minimum. e) It should be light as far as possible f) Surface of form work should be smooth for easy stripping g) All joints of form work should be stiff so that lateral deformation under load is minimum. Joints should be leak proof.
  • 8. Indian Standard of Form work (IS :456-1964) (1) General : The form work :  shall conform to the shape, lines & dimensions as shown on the plans.  Shall be rigid during placing & compacting of concrete.  Water tight to prevent loss of water from concrete. (2) Cleaning & treatment of forms  All rubbish, chippings, saw dust shall be removed from the interior of form work before placing of concrete.  Shall be wetted.
  • 9. Indian Standard of Form work (IS :456-1964) (3) STRIPPING TIME Form work should not removed until good strength has come. Type of form work Time Vertical wall, columns 16-24 hrs Soffit of slab (Prop should be refixed immediately) 3 days Soffit of beam (Prop should be refixed immediately) 7 days Props to slab Span < 4.5 m 7 days Props to slab Span > 4.5 m 14 days Props of beam (Span < 6 m) 14 days Props of beam (Span > 6 m) 21 days
  • 10. Indian Standard of Form work (IS :456-1964) (4) Procedure when removing form work  All form work shall be removed without shock or vibration as it will damage the concrete.  Before the soffit (bottom surface ) & struts (pole) are removed, the concrete shall be exposed, to check that the concrete has sufficiently hardened.  Proper precautions shall be taken to allow for decrease in the rate of hardening in cold water. (5) Camber  It is desirable to give form an upward camber (slope) to ensure that beams do not sag when they have taken up their deflection.  This should be done only when allowed in the design calculation of the beam.
  • 11. Indian Standard of Form work (IS :456-1964) (6) Tolerances Form work shall be so constructed that the internal dimen sions are within the permissible tolerance specified by the designer.
  • 12. LOADS ON FORM WORK The form work has to take following loads: a) Live load due to labour b) Weight of wet concrete c) Hydrostatic pressure of the fluid concrete acting against the vertical or inclined faces of form d) Impact due to pouring of concrete.  Live loads of labour & equipment including impact may be taken as 370 Kg/m2.
  • 13.
  • 14. LOADS ON FORM WORK HYDROSTATIC PRESSURE: Hydro static pressure due to fluid of concrete depends on : a) Quantity of water in concrete b) Size of aggregate c) Rate of pouring d) Temperature
  • 15. HYDROSTATIC PRESSURE: Hydrostatic pressure is maximum during pouring and decreases when concrete becomes hard. Setting time may be taken as ¾ to 1 hour. Only height of concrete poured in ¾ to 1 hour is taken into account for calculation of hydrostatic pressure on form work. For 1.5 m height of concrete, equivalent weight of concrete may be taken as 2300 kg/m3.
  • 16. • HYDROSTATIC PRESSURE: For higher height, the equivalent weight of concrete is reduced. When height of concrete in one pour is 6 m, the equivalent fluid weight may be 1200 kg/m3. For intermediate heights between 1.5 to 6 m poured within the setting time of ¾ hour linear interpolation of unit weight between 1200 to 2300 kg/m3 may be taken.
  • 18.
  • 19. SHUTTERING FOR COLUMN It consists of : a. Sheeting all round the column periphery b. Side yokes & end yokes c. Wedges d. Bolts with washers
  • 20. SHUTTERING FOR COLUMN  The side yokes & end yokes consists of 2 numbers each  They are suitably spaced along the height of column  Two side yokes are comparatively of heavier section & are connected together by 2 long bolts.  Four wedges one at each corner are inserted between bolts & end yokes  The sheathing is nailed to yokes.
  • 23.
  • 24.
  • 25.
  • 26.
  • 27. SHUTTERING FOR BEAM & SLAB FLOOR  The slab is continuous over number of beams.  The slab is supported on 2.5 cm thick sheathing laid parallel to main beam.  The sheathing is supported on wooden battens which are laid between the beams, at suitable spacing.  In order to reduce deflection, the battens may be propped at middle of the span through joists.  The side forms of the beam consists 3 mm thick sheathing.  The bottom sheathing of the beam form may be 5 to 7 cm thick.
  • 28. SHUTTERING FOR BEAM & SLAB FLOOR  The end of the battens are supported on ledger which is fixed to cleats throughout the length.  Cleats 10 cm x 2 cm x 3 cm are fixed to the forms at the same spacing as that of battens, so that battens may be fixed to them.  The beam forms is supported on a head tree.  The shore or post is connected to head tree through cleats.  At the bottom of shore, two wedges of hard wood are provided over a sole piece.
  • 29.
  • 30.
  • 31.
  • 32.
  • 33. SHUTTERING FOR STAIRS • The sheathing or decking for deck slab is carried on cross joists • Cross joists are supported on raking ledgers. • Ledger is 7.5 cm x 10 cm size. • Cross joists are 5 cm x 10 cm size • Riser planks are 4 -5 cm thick • Planks are bevelled at bottom to permit the whole of the tread faced to be trovelled.
  • 34. SHUTTERING FOR STAIRS • Riser plank are fixed after reinforcement has been fixed in position. • Outer end of of risers are carried by a cut string made of 5 cm plank. • The cut string is strutted to the cross joists by 5 cm x 10 cm struts. • The wall ends of the riser planks are carried by 5 cm x 10 cm hangers secured to 5 cm thick board fixed to wall. • Treads are left open for concreting & vibration. • Stiffner joists of 5 cm x 10 cm is placed along the middle of the riser planks. • Stiffner is wired to cross joists through decking.
  • 35.
  • 36.
  • 37. FORM WORK FOR WALLS
  • 38. FORM WORK FOR WALLS a) The boarding is 4 to 5 cm thick for walls of 3 to 4 mt height. b) Boards are fixed to 5 cm x 10 cm posts known as studs or soldiers c) Studs are paced at spacing of 0.8 m. d) Horizontal wallings of size 7.5 cm x 10 cm are fixed to the at suitable interval.
  • 40. MOVING WALL FORM a) In moving wall forms, panels are made of 0.6 x 1.8 m size so that handling & stripping is easy. b) 15 mm ply board is used instead of boarding c) The panels are installed in such a way that the lower panel can be removed when concrete is hard and used higher up wall. d) Framing of size 5 cm x 10 cm is used to ply shutter. e) The panels are fixed to a central and two end studs. f) Each stud consists of two pieces of timbers, 5 cm x 15 cm apart. g) The end strut of each panel secures adjucent panel. h) Boards are reversed for 1st lift ; for succeeding lifts, bolts pass through holes formed to previous lift. i) For rapid construction of a constant thickness wall, continuously rising form, commonly known as sliding shutter is used
  翻译: