尊敬的 微信汇率:1円 ≈ 0.046239 元 支付宝汇率:1円 ≈ 0.04633元 [退出登录]
SlideShare a Scribd company logo
CreatedBy:
Jay S. Singhania (14….6107)
Pratik Sisodiya(14….6108)
VirenTrivedi (14….6115)
Ajit Shiyal (14….6105)
Civil-B V-Sem
¶ Formwork is the temporary structure used as a mould to caste structural
members at site.
¶ These are also knownas farmas or false work or shuttering.
¶ It is erectedat its correct positionbefore concrete is poured in it.
¶ This poured concrete is then consolidated and allowed to harden to give desired
strength.
¶ It is allowed to remain in position till the poured concrete gains sufficient strength
to withstandthe stresses coming on it in absence of formwork.
¶ After this the formwork is removedand this process is knownas stripping.
 Costly item and its proper design and maintenance can affect
economic considerations considerably.
 It costs almost as much as 20-25% of the total construction cost
of the structural members in building works and even more in
the case of bridges.
 For construction of lot of similar elements, formwork is designed in
such a way that stripping and erection involves least possibilities of
damages and least labor, and also this is made out of separate panels
with provisions of adjustments.
 For this type of formwork, during erection or stripping, only bolts or
pins are to be inserted or removed.
 Such type of formwork should preferably be of structural steel but
timber formwork may also work with being economical, considering
disadvantages of warping, swellingand shrinkage effects.
¥ Requirements of timber formwork:
i. Be well seasoned.
ii. Be light in weight.
iii. Be easily workable with nails without splitting.
iv. Be free from knots.
¥ Standard formworks can be adopted for different components of formwork
for shuttering of different sections of 4.5m span and 3.5m height.
¥ For structures not meeting the above demands, special design of formwork
should be done based on the dead loads and live loads acting on the structure
and also some relevant factors.
¥ For normal constructional work with same dimensions of formwork,
shuttering can be also formed in such a way that it can be moved to the other
location without dismantling and fixed there in the new position.
¥ Each set of formwork can be used 10-12 times for normal constructional
works.
¥ For shuttering of concrete surfaces to be
exposed, smooth and even surfaced
formwork should be used to obtain directly
smooth exposed surface of concrete and
thus eliminating the need of finishing to the
concrete members.
¥ For surfaces that are not exposed directly,
uneven or undressed timber planks can be
used.
¥ The formwork should be jointed using the
grooved and tongued joints.
╬ Consists of panels fabricated of thin steel plates stiffened
along the edge by small steel angles, which can be held
together by clamps and bolts along each edge, and kept in
alignment using vertical or horizontal timber or steel
centring.
╬ Usual size of wall or slab panels vary from 60cm * 60cm to
60cm * 120cm (2’ *2’ to 2’ * 4’).
╬ These type of formwork is mostly used in large
constructional projects and where repeated use is possible.
╬ These are extensively used for pre-cast concrete members
and also the most suitable for shuttering of circular or
curved sections such as tanks, columns, chimneys etc. and
for large structures like large sewer, tunnels, retaining
walls etc.
Use of plywood is getting more popular these days,
and these are attached to the timber frames to
make up panels of desired shapes and sizes.
These types of shuttering can be easily assembled
with the use of bolting, riveting etc.
These types of shuttering is highly suggestive in
the large constructional projects where exposed
concrete surface is large in area such as faces of
retaining walls, concrete dams, floor slabs etc.
 These type of formwork can be used
economically in following considerations:
i. Perfectly smooth and finished external
surface can be obtained and thus expense of
external finishing (plastering) can be saved.
ii. Large sized panels can be formed thus saving
the labour charges for assembling and
dismantling.
iii. Number of re-uses can be increased to 20-25
times.
Easy in erection and stripping.
Can be used repeatedly for many times.
Comparatively stronger.
No possibilities of shrinkage, warping or
swelling.
Easy in erection.
Economical
Can be erected in any shape and size as per
requirement.
Formwork material must be cheap and easily available in local market.
It must be sufficiently rigid to avoid excessive deflections while
concreting.
Must be strongenough to effectively resist all loads comingon it.
Easy to erect and strip.
Must rest on strong and un-yielding supports.
Joints should be stiff and strong and water-tight.
Surface in direct contact (internal surface) must be enough smooth to
give finishedsurface.
It must be water tight and non absorbing to maintain w/c ratio avoiding
leakage/absorbingof water fromthe concrete.
Dead load of green concrete
Hydrostatic pressure of green concrete
Live load of working labors
Impact effect at the time of pouring concrete into the
formwork.
Vibrations in concrete during pouring concrete into
the formwork.
Temporary live load due to labors
and equipments including impact
may be taken as 370 kg/m2.
Planks for formwork of vertical
facing of columns etc. are known
as sheathing.
Planks for formwork of floor
slabs are known as decking.
of concrete, in initial stages of pouring
depends upon amount of water, size of
aggregates, rate of pouring etc.
Hydrostatic pressure is maximum at
the time of pouring, but gradually
decreases with setting of concrete
and hardening.
Hydrostatic pressure mainly depends
on the depth of concrete poured
before starting of setting.
Hydrostatic pressure considerations
may include height of concrete which
Equivalent fluid weight of concrete up to 1.5m height may be
assumedas2300 .
Equivalent fluid weight of concrete may be reduced to 1200
when poured for 6mheightin one hour.
For pouring heights between 1.5-6.0m and setting time ¾-1 hour,
equivalent fluid weight may be calculated by linear interpolation
between 2300-1200 .
Maximum deflection of sheathing and joists must be limited to
2.5m.
3
m
kg
3
m
kg
3
m
kg
CornerAngle Outside CornerForm
Inside Corner Form "L" - type pin & U-clip
Formwork Fittings
Formwork for
Foundations
•It consists of
• Side Supports
• Side Planks
• Cleats
Side Support Side Planks
Cleats
Formwork For Column
•It consists of the following
•Side & End Planks
•Yoke
•Nut & Bolts

Sr.
No Structural Member
OPC
(Ordinary Portland
Cement)
RapidHardening
Cement
1 Beamsides,walls & Columns 2-3Days 2 Days
2 Slab (Vertical Supports remains intact) 4 Days 3 Days
3 Slab (CompleteFormworkremoval) 10 Days 5 Days
4 Beams(Removal of Sheeting, Props
remains intact)
8 Days 5 Days
5 Beams& Arches (Completeformwork
removal) (upto 6 m span)
14 Days 5-8 Days
6 Beams& Arches (Completeformwork
removal) (more than 6 m span)
21 Days 8-10 Days
Formwork-Types and Their Advantages
Formwork-Types and Their Advantages

More Related Content

What's hot

Slipform construction
Slipform constructionSlipform construction
Slipform construction
tivar rose
 
Steel structures
Steel structuresSteel structures
Steel structures
Sukhdarshan Singh
 
What are the types of structural steel framing
What are the types of structural steel framingWhat are the types of structural steel framing
What are the types of structural steel framing
najeeb muhamed
 
REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1
Natalie Ulza
 
Formwork
FormworkFormwork
Formwork
Sneha Kaira
 
Concrete works
Concrete worksConcrete works
Concrete works
Rajiva Gupta
 
SCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNINGSCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNING
VISHNU VIJAYAN
 
BC - Precast Concrete.pdf
BC - Precast Concrete.pdfBC - Precast Concrete.pdf
BC - Precast Concrete.pdf
TesfayeWondimu
 
Crack repair in building construction
Crack repair in building constructionCrack repair in building construction
Crack repair in building construction
Kiran Hadiya
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction
purvi golecha
 
Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
Aglaia Connect
 
Chapter 4 (a) stone masonry
Chapter 4 (a) stone masonryChapter 4 (a) stone masonry
Chapter 4 (a) stone masonry
KHUSHBU SHAH
 
Slabs and types
Slabs and typesSlabs and types
Slabs and types
Surhan Fatima
 
Jacketing
JacketingJacketing
Jacketing
SHAIKH ARSHAD
 
Deterioration of Concrete
Deterioration of ConcreteDeterioration of Concrete
Deterioration of Concrete
Ramanuj Jaldhari
 
Industrial building
Industrial buildingIndustrial building
Industrial building
tausif_k
 
Formwork
FormworkFormwork
Formwork
Shakil Ahmmad
 
Construction process''column,beam,slab''
Construction process''column,beam,slab''Construction process''column,beam,slab''
Construction process''column,beam,slab''
Nabeel Rajpoot
 
What is wall? Different types of wall.
What is wall? Different types of wall.What is wall? Different types of wall.
What is wall? Different types of wall.
Syed Raja
 
Formwork
FormworkFormwork
Formwork
rmeena99
 

What's hot (20)

Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
Steel structures
Steel structuresSteel structures
Steel structures
 
What are the types of structural steel framing
What are the types of structural steel framingWhat are the types of structural steel framing
What are the types of structural steel framing
 
REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1REINFORCEMENT CONCRETE chapter 1
REINFORCEMENT CONCRETE chapter 1
 
Formwork
FormworkFormwork
Formwork
 
Concrete works
Concrete worksConcrete works
Concrete works
 
SCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNINGSCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNING
 
BC - Precast Concrete.pdf
BC - Precast Concrete.pdfBC - Precast Concrete.pdf
BC - Precast Concrete.pdf
 
Crack repair in building construction
Crack repair in building constructionCrack repair in building construction
Crack repair in building construction
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction
 
Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
 
Chapter 4 (a) stone masonry
Chapter 4 (a) stone masonryChapter 4 (a) stone masonry
Chapter 4 (a) stone masonry
 
Slabs and types
Slabs and typesSlabs and types
Slabs and types
 
Jacketing
JacketingJacketing
Jacketing
 
Deterioration of Concrete
Deterioration of ConcreteDeterioration of Concrete
Deterioration of Concrete
 
Industrial building
Industrial buildingIndustrial building
Industrial building
 
Formwork
FormworkFormwork
Formwork
 
Construction process''column,beam,slab''
Construction process''column,beam,slab''Construction process''column,beam,slab''
Construction process''column,beam,slab''
 
What is wall? Different types of wall.
What is wall? Different types of wall.What is wall? Different types of wall.
What is wall? Different types of wall.
 
Formwork
FormworkFormwork
Formwork
 

Similar to Formwork-Types and Their Advantages

Temporary Works (Form Work)
Temporary Works (Form Work)Temporary Works (Form Work)
Temporary Works (Form Work)
Sujith Velloor Sudarsanakumar Nair
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
KHUSHBU SHAH
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
Himanshumangal12
 
Speedy construction presentation
Speedy construction presentationSpeedy construction presentation
Speedy construction presentation
somitra bhardwaj
 
Gurme santoshkumar
Gurme santoshkumarGurme santoshkumar
Gurme santoshkumar
santoshkumar gurme
 
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURESUNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
Venkateswaran S
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALS
SOUMYA KHANDELWAL
 
Formwork
FormworkFormwork
Formwork
Lavanya Singh
 
Types of Formwork & Materials.pptx
Types of Formwork & Materials.pptxTypes of Formwork & Materials.pptx
Types of Formwork & Materials.pptx
Mr Amol Ghogare
 
Wall materials
Wall materialsWall materials
Wall materials
SaloniHosmani
 
CONCRETE TECHNOLOGY
CONCRETE TECHNOLOGYCONCRETE TECHNOLOGY
CONCRETE TECHNOLOGY
HitaishiGupta
 
RCC Floor
RCC FloorRCC Floor
RCC Floor
Hrishi Desai
 
Type of structural joints
Type of structural joints Type of structural joints
Type of structural joints
Hanzlahakhlaq
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
LokeswarSaha1
 
Formwork by chakamba john
Formwork by chakamba johnFormwork by chakamba john
Formwork by chakamba john
John Chakamba
 
Formwork & Falsework Practice_2009(July)_to AK.pdf
Formwork & Falsework Practice_2009(July)_to AK.pdfFormwork & Falsework Practice_2009(July)_to AK.pdf
Formwork & Falsework Practice_2009(July)_to AK.pdf
LiesaStone
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
Mylene Delmoro
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
Mylene Delmoro
 
Control joints
Control jointsControl joints
Control joints
Graciela Hernandez
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
Prasad Thanthratey
 

Similar to Formwork-Types and Their Advantages (20)

Temporary Works (Form Work)
Temporary Works (Form Work)Temporary Works (Form Work)
Temporary Works (Form Work)
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
 
Speedy construction presentation
Speedy construction presentationSpeedy construction presentation
Speedy construction presentation
 
Gurme santoshkumar
Gurme santoshkumarGurme santoshkumar
Gurme santoshkumar
 
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURESUNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALS
 
Formwork
FormworkFormwork
Formwork
 
Types of Formwork & Materials.pptx
Types of Formwork & Materials.pptxTypes of Formwork & Materials.pptx
Types of Formwork & Materials.pptx
 
Wall materials
Wall materialsWall materials
Wall materials
 
CONCRETE TECHNOLOGY
CONCRETE TECHNOLOGYCONCRETE TECHNOLOGY
CONCRETE TECHNOLOGY
 
RCC Floor
RCC FloorRCC Floor
RCC Floor
 
Type of structural joints
Type of structural joints Type of structural joints
Type of structural joints
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 
Formwork by chakamba john
Formwork by chakamba johnFormwork by chakamba john
Formwork by chakamba john
 
Formwork & Falsework Practice_2009(July)_to AK.pdf
Formwork & Falsework Practice_2009(July)_to AK.pdfFormwork & Falsework Practice_2009(July)_to AK.pdf
Formwork & Falsework Practice_2009(July)_to AK.pdf
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 
Control joints
Control jointsControl joints
Control joints
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
 

Recently uploaded

My Airframe Metallic Design Capability Studies..pdf
My Airframe Metallic Design Capability Studies..pdfMy Airframe Metallic Design Capability Studies..pdf
My Airframe Metallic Design Capability Studies..pdf
Geoffrey Wardle. MSc. MSc. Snr.MAIAA
 
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdfFUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
EMERSON EDUARDO RODRIGUES
 
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptxMODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
NaveenNaveen726446
 
SPICE PARK JUL2024 ( 6,866 SPICE Models )
SPICE PARK JUL2024 ( 6,866 SPICE Models )SPICE PARK JUL2024 ( 6,866 SPICE Models )
SPICE PARK JUL2024 ( 6,866 SPICE Models )
Tsuyoshi Horigome
 
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEERDELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
EMERSON EDUARDO RODRIGUES
 
Sri Guru Hargobind Ji - Bandi Chor Guru.pdf
Sri Guru Hargobind Ji - Bandi Chor Guru.pdfSri Guru Hargobind Ji - Bandi Chor Guru.pdf
Sri Guru Hargobind Ji - Bandi Chor Guru.pdf
Balvir Singh
 
Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine
 
Literature review for prompt engineering of ChatGPT.pptx
Literature review for prompt engineering of ChatGPT.pptxLiterature review for prompt engineering of ChatGPT.pptx
Literature review for prompt engineering of ChatGPT.pptx
LokerXu2
 
Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...
Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...
Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...
IJCNCJournal
 
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort ServiceCuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
yakranividhrini
 
CSP_Study - Notes (Paul McNeill) 2017.pdf
CSP_Study - Notes (Paul McNeill) 2017.pdfCSP_Study - Notes (Paul McNeill) 2017.pdf
CSP_Study - Notes (Paul McNeill) 2017.pdf
Ismail Sultan
 
Intuit CRAFT demonstration presentation for sde
Intuit CRAFT demonstration presentation for sdeIntuit CRAFT demonstration presentation for sde
Intuit CRAFT demonstration presentation for sde
ShivangMishra54
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
felixwold
 
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
AK47
 
Butterfly Valves Manufacturer (LBF Series).pdf
Butterfly Valves Manufacturer (LBF Series).pdfButterfly Valves Manufacturer (LBF Series).pdf
Butterfly Valves Manufacturer (LBF Series).pdf
Lubi Valves
 
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
nainakaoornoida
 
Data Communication and Computer Networks Management System Project Report.pdf
Data Communication and Computer Networks Management System Project Report.pdfData Communication and Computer Networks Management System Project Report.pdf
Data Communication and Computer Networks Management System Project Report.pdf
Kamal Acharya
 
comptia-security-sy0-701-exam-objectives-(5-0).pdf
comptia-security-sy0-701-exam-objectives-(5-0).pdfcomptia-security-sy0-701-exam-objectives-(5-0).pdf
comptia-security-sy0-701-exam-objectives-(5-0).pdf
foxlyon
 
AN INTRODUCTION OF AI & SEARCHING TECHIQUES
AN INTRODUCTION OF AI & SEARCHING TECHIQUESAN INTRODUCTION OF AI & SEARCHING TECHIQUES
AN INTRODUCTION OF AI & SEARCHING TECHIQUES
drshikhapandey2022
 
Online train ticket booking system project.pdf
Online train ticket booking system project.pdfOnline train ticket booking system project.pdf
Online train ticket booking system project.pdf
Kamal Acharya
 

Recently uploaded (20)

My Airframe Metallic Design Capability Studies..pdf
My Airframe Metallic Design Capability Studies..pdfMy Airframe Metallic Design Capability Studies..pdf
My Airframe Metallic Design Capability Studies..pdf
 
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdfFUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
 
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptxMODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
 
SPICE PARK JUL2024 ( 6,866 SPICE Models )
SPICE PARK JUL2024 ( 6,866 SPICE Models )SPICE PARK JUL2024 ( 6,866 SPICE Models )
SPICE PARK JUL2024 ( 6,866 SPICE Models )
 
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEERDELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
 
Sri Guru Hargobind Ji - Bandi Chor Guru.pdf
Sri Guru Hargobind Ji - Bandi Chor Guru.pdfSri Guru Hargobind Ji - Bandi Chor Guru.pdf
Sri Guru Hargobind Ji - Bandi Chor Guru.pdf
 
Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024
 
Literature review for prompt engineering of ChatGPT.pptx
Literature review for prompt engineering of ChatGPT.pptxLiterature review for prompt engineering of ChatGPT.pptx
Literature review for prompt engineering of ChatGPT.pptx
 
Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...
Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...
Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...
 
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort ServiceCuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
 
CSP_Study - Notes (Paul McNeill) 2017.pdf
CSP_Study - Notes (Paul McNeill) 2017.pdfCSP_Study - Notes (Paul McNeill) 2017.pdf
CSP_Study - Notes (Paul McNeill) 2017.pdf
 
Intuit CRAFT demonstration presentation for sde
Intuit CRAFT demonstration presentation for sdeIntuit CRAFT demonstration presentation for sde
Intuit CRAFT demonstration presentation for sde
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
 
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
 
Butterfly Valves Manufacturer (LBF Series).pdf
Butterfly Valves Manufacturer (LBF Series).pdfButterfly Valves Manufacturer (LBF Series).pdf
Butterfly Valves Manufacturer (LBF Series).pdf
 
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
 
Data Communication and Computer Networks Management System Project Report.pdf
Data Communication and Computer Networks Management System Project Report.pdfData Communication and Computer Networks Management System Project Report.pdf
Data Communication and Computer Networks Management System Project Report.pdf
 
comptia-security-sy0-701-exam-objectives-(5-0).pdf
comptia-security-sy0-701-exam-objectives-(5-0).pdfcomptia-security-sy0-701-exam-objectives-(5-0).pdf
comptia-security-sy0-701-exam-objectives-(5-0).pdf
 
AN INTRODUCTION OF AI & SEARCHING TECHIQUES
AN INTRODUCTION OF AI & SEARCHING TECHIQUESAN INTRODUCTION OF AI & SEARCHING TECHIQUES
AN INTRODUCTION OF AI & SEARCHING TECHIQUES
 
Online train ticket booking system project.pdf
Online train ticket booking system project.pdfOnline train ticket booking system project.pdf
Online train ticket booking system project.pdf
 

Formwork-Types and Their Advantages

  • 1.
  • 2. CreatedBy: Jay S. Singhania (14….6107) Pratik Sisodiya(14….6108) VirenTrivedi (14….6115) Ajit Shiyal (14….6105) Civil-B V-Sem
  • 3. ¶ Formwork is the temporary structure used as a mould to caste structural members at site. ¶ These are also knownas farmas or false work or shuttering. ¶ It is erectedat its correct positionbefore concrete is poured in it. ¶ This poured concrete is then consolidated and allowed to harden to give desired strength. ¶ It is allowed to remain in position till the poured concrete gains sufficient strength to withstandthe stresses coming on it in absence of formwork. ¶ After this the formwork is removedand this process is knownas stripping.
  • 4.  Costly item and its proper design and maintenance can affect economic considerations considerably.  It costs almost as much as 20-25% of the total construction cost of the structural members in building works and even more in the case of bridges.
  • 5.  For construction of lot of similar elements, formwork is designed in such a way that stripping and erection involves least possibilities of damages and least labor, and also this is made out of separate panels with provisions of adjustments.  For this type of formwork, during erection or stripping, only bolts or pins are to be inserted or removed.  Such type of formwork should preferably be of structural steel but timber formwork may also work with being economical, considering disadvantages of warping, swellingand shrinkage effects.
  • 6.
  • 7. ¥ Requirements of timber formwork: i. Be well seasoned. ii. Be light in weight. iii. Be easily workable with nails without splitting. iv. Be free from knots. ¥ Standard formworks can be adopted for different components of formwork for shuttering of different sections of 4.5m span and 3.5m height. ¥ For structures not meeting the above demands, special design of formwork should be done based on the dead loads and live loads acting on the structure and also some relevant factors. ¥ For normal constructional work with same dimensions of formwork, shuttering can be also formed in such a way that it can be moved to the other location without dismantling and fixed there in the new position. ¥ Each set of formwork can be used 10-12 times for normal constructional works.
  • 8. ¥ For shuttering of concrete surfaces to be exposed, smooth and even surfaced formwork should be used to obtain directly smooth exposed surface of concrete and thus eliminating the need of finishing to the concrete members. ¥ For surfaces that are not exposed directly, uneven or undressed timber planks can be used. ¥ The formwork should be jointed using the grooved and tongued joints.
  • 9.
  • 10. ╬ Consists of panels fabricated of thin steel plates stiffened along the edge by small steel angles, which can be held together by clamps and bolts along each edge, and kept in alignment using vertical or horizontal timber or steel centring. ╬ Usual size of wall or slab panels vary from 60cm * 60cm to 60cm * 120cm (2’ *2’ to 2’ * 4’). ╬ These type of formwork is mostly used in large constructional projects and where repeated use is possible. ╬ These are extensively used for pre-cast concrete members and also the most suitable for shuttering of circular or curved sections such as tanks, columns, chimneys etc. and for large structures like large sewer, tunnels, retaining walls etc.
  • 11.
  • 12.
  • 13. Use of plywood is getting more popular these days, and these are attached to the timber frames to make up panels of desired shapes and sizes. These types of shuttering can be easily assembled with the use of bolting, riveting etc. These types of shuttering is highly suggestive in the large constructional projects where exposed concrete surface is large in area such as faces of retaining walls, concrete dams, floor slabs etc.
  • 14.  These type of formwork can be used economically in following considerations: i. Perfectly smooth and finished external surface can be obtained and thus expense of external finishing (plastering) can be saved. ii. Large sized panels can be formed thus saving the labour charges for assembling and dismantling. iii. Number of re-uses can be increased to 20-25 times.
  • 15. Easy in erection and stripping. Can be used repeatedly for many times. Comparatively stronger. No possibilities of shrinkage, warping or swelling.
  • 16. Easy in erection. Economical Can be erected in any shape and size as per requirement.
  • 17. Formwork material must be cheap and easily available in local market. It must be sufficiently rigid to avoid excessive deflections while concreting. Must be strongenough to effectively resist all loads comingon it. Easy to erect and strip. Must rest on strong and un-yielding supports. Joints should be stiff and strong and water-tight. Surface in direct contact (internal surface) must be enough smooth to give finishedsurface. It must be water tight and non absorbing to maintain w/c ratio avoiding leakage/absorbingof water fromthe concrete.
  • 18. Dead load of green concrete Hydrostatic pressure of green concrete Live load of working labors Impact effect at the time of pouring concrete into the formwork. Vibrations in concrete during pouring concrete into the formwork.
  • 19. Temporary live load due to labors and equipments including impact may be taken as 370 kg/m2. Planks for formwork of vertical facing of columns etc. are known as sheathing. Planks for formwork of floor slabs are known as decking.
  • 20. of concrete, in initial stages of pouring depends upon amount of water, size of aggregates, rate of pouring etc. Hydrostatic pressure is maximum at the time of pouring, but gradually decreases with setting of concrete and hardening. Hydrostatic pressure mainly depends on the depth of concrete poured before starting of setting. Hydrostatic pressure considerations may include height of concrete which
  • 21. Equivalent fluid weight of concrete up to 1.5m height may be assumedas2300 . Equivalent fluid weight of concrete may be reduced to 1200 when poured for 6mheightin one hour. For pouring heights between 1.5-6.0m and setting time ¾-1 hour, equivalent fluid weight may be calculated by linear interpolation between 2300-1200 . Maximum deflection of sheathing and joists must be limited to 2.5m. 3 m kg 3 m kg 3 m kg
  • 22.
  • 23. CornerAngle Outside CornerForm Inside Corner Form "L" - type pin & U-clip Formwork Fittings
  • 24. Formwork for Foundations •It consists of • Side Supports • Side Planks • Cleats Side Support Side Planks Cleats
  • 25. Formwork For Column •It consists of the following •Side & End Planks •Yoke •Nut & Bolts
  • 26.
  • 27.  Sr. No Structural Member OPC (Ordinary Portland Cement) RapidHardening Cement 1 Beamsides,walls & Columns 2-3Days 2 Days 2 Slab (Vertical Supports remains intact) 4 Days 3 Days 3 Slab (CompleteFormworkremoval) 10 Days 5 Days 4 Beams(Removal of Sheeting, Props remains intact) 8 Days 5 Days 5 Beams& Arches (Completeformwork removal) (upto 6 m span) 14 Days 5-8 Days 6 Beams& Arches (Completeformwork removal) (more than 6 m span) 21 Days 8-10 Days
  翻译: