FORMWORK
by Er. Ankaj Kumar
Formwork
(Shuttering)
What is Formwork?
• Formwork is a mould including all supporting
structures, used to shape and support the
concrete until it attains sufficient strength to
carry its own weight.
• It should be capable of carrying all imposed
dead and live loads apart from its own weight.
Formwork is commonly made of
• Steel andTimber
TIMBER FORMWORK
STEEL FORMWORK
• Formwork has been in use since the beginning
of concrete construction.
• New materials such as steel, plastics and
fibreglass are used in formwork.
• Greater attention is being given to the design,
fabrication, erection and dismantling of
formwork
• Formwork is designed according to The ACI
document SP-4.
Qualities of Formwork
• It should be water tight.
• It should be strong.
• It can be reusable.
• Its contact surface should be uniform.
• It should be according to the size of member.
In order to successfully carry out its function, formwork
must achieve a balance of following requirements:
• Containment
• Strength
• Resistance To Leakage
• Accuracy
• Ease Of Handling
• Finish And Reuse Potential
• Access For Concrete
• Economy
• Containment: formwork must be capable of
shaping and supporting the fluid concrete
until it cures.
• Strength: formwork must be capable of safely
withstanding without distortion or danger the
dead weight of the fluid concrete is placed on
it, labour weight, equipment weight and any
environmental loadings.
• Ease of Handling: form panels and units
should be designed so that their maximum
size does not exceed that which can be easily
handled by hand or mechanical means. – In
addition all formwork must also be designed
and constructed to include facilities for
adjustments, levelling, easing and striking
without damage to the form work or concrete
• Economy: All the formwork is very expensive. On
average about 35% of the total cost of any
finished concrete unit or element can be
attributed to its formwork; of this just over 40%
can be taken for material for formwork and 60%
for labour. – The formwork designer must
therefore not only consider the maximum
number of times that any form can be reused,
but also produce a design that will minimize the
time taken for erection and striking
Major objectives considered in
formwork:
➢ Quality
➢ Safety
➢ Economy
• Quality: Forms must be designed and built
with sufficient stiffness and accuracy so that
the size, shape, position, and finish of the cast
concrete are maintained. so that they have
• Safety: Forms must be built sufficient strength
and factor of safety the capable of all
supporting loads.
• Economy: Forms must be built efficiently,
minimizing time and cost.
Requirements of formwork:
• Material should be cheap and re usable,
• It should be practically water proof, so that it should
not absorb water from concrete,
• Swelling and shrinkage should be minimum,
• Strong enough to with stand all external loads,
• Deflection should be minimum,
• Surface should be smooth, and afford easy striping,
• Light in weight, so that easy to transfer,
• Joints should be stiff, so that lateral deformation and
leak is minimum .
Three stages in the process :
a) Assembly and erection
b) Concrete placement.
c) Stripping and dismantling.
Formwork detail for different
structural members
• In concrete construction formwork is commonly
provided for the following structural members.
• Wall
• Column
• Slabs & Beams
• Stairs o Chimneys
• Water tanks
• Cooling Towers
Formwork for Wall
It consists of
Timber sheeting
• Vertical posts
• Horizontal members
• Rackers
• Stakes
• Wedges
➢ After completing one
side of formwork
reinforcement is provided
at the place then the
second side formwork is
provided.
Formwork for Column
It consists of the
following – Side & End
Planks – Yoke – Nut &
Bolts
• Two end & two side
planks are joined by the
yokes and bolts.
Formwork for columns
Formwork for Slabs & beams
It consistsof
– Sole plates
– Wedges
– Props
– Head tree
– Planks
– Batten
– Ledgers
• Beam formworkrests on
headtree
• Slab form work restson battens
andjoists
• If prop height aremore than 8’
provide horizontalbraces.
Lintel or Beam Formwork
FORMWORK FOR SLAB
FORMWORK FOR STAIRS
It consists of
– Vertical & inclined
posts
– Inclined members
-- Wooden Planks or
sheeting
– Stringer
– Riser Planks
FORMWORK FOR STAIRS
FORMWORK FOR SPIRAL STAIRS
FORMWORK FOR CHIMNEYS
For tall chimneys two
types of forms
techniques are in
generally use in our
country
a) Jump form
b) Slip form
Removal of formwork
• Time of formwork removal depends on the following factors:
Type of Cement
Rapid hardening cements require lesser time as compared to OPC
(Ordinary Portland Cement)
Ratio of concrete mix
Rich ratio concrete gain strength earlier as compared to weak
ratio concrete.
Weather condition
Hydration process accelerates in hot weather conditions as
compared to cold and humid weather conditions
Time of Removal of formwork
Comparison between Steel and
Timber Formwork
• Steel forms are stronger, durable, and have a longer life
than timber formwork and their reuses are more in
number.
• Steel forms can be installed and dismantled with greater
ease and speed.
• The quality of exposed concrete surface by using steel
forms is good and such surfaces need no further
treatment.
• Steel formwork does not absorb moisture from concrete.
• Steel formwork does not shrink or warp.
Cantilever slab
First free end's support
should be removed.
• And then from right to
left it
should be proceed.
• If we are removing
from the
mid span then it will act
as a
prop cantilever.
Simply supported slab
In simply supported
we have to remove
the support from the
mid span to the
ends.
• To meet the design
behavior.
Maintenance of formwork
• Due to continuous use wooden planks & steel
plates surfaces become uneven and require
maintenance.
• For wooden formwork use cardboard or plastic
fiber board. Bolt hole places must also be
repaired.
• For steel formwork plates must be leveled by
mallet and loose corners must be welded.
Cost of formwork
• For normal works cost of formwork is about 30%-
40% of the concrete cost.
➢ For special works cost of formwork is about
50%-60% of the concrete cost.
➢ Formwork cost is controlled by the following
factors
• Formwork Material cost
• Formwork erecting cost
• Formwork removal cost
• Formwork jointing cost (Nails and Cables)
• Labor charges
Advantages of steel form work
• It can be used for a no. of times.
▪ It is non absorbent.
▪ Smooth finish surface obtained.
▪ No shrinkage of formwork occurs.
▪ Easy to use.
▪ Its volume is less
▪ Its strength is more
LOADS ON FORMWORK
Dead load
▪ Self weight of formwork
▪ Pressure and loads from fresh concrete
▪ Reinforcement
• Imposed load
▪ Construction workers
▪ Stacking of materials
• Horizontal loads
• Environmental loads
▪ Accidental loads
▪ Wind loads
References
• R.C.C Design by B.C.Punmia
• R.C.C Design by H.J.Shah
• Formwork Design Section 1500
• Doka Formwork Design
• Design of safe timber structures by Eva and
Tomi Torrati
THANK YOU

More Related Content

What's hot

Underpinning
UnderpinningUnderpinning
Underpinning
Khuzema Olia
 
Formwork
FormworkFormwork
Formwork
Jitesh Dhule
 
All you need to know about Construction Formwork
All you need to know about Construction FormworkAll you need to know about Construction Formwork
All you need to know about Construction Formwork
Ankit Singhai
 
Finishing works (Building Construction)
Finishing works (Building Construction)Finishing works (Building Construction)
Finishing works (Building Construction)
Zairul Zaiky
 
Repairing of masonry structures
Repairing of masonry structuresRepairing of masonry structures
Repairing of masonry structures
Dhaval Jalalpara
 
Construction Technology I Presentation Slides
Construction Technology I Presentation SlidesConstruction Technology I Presentation Slides
Construction Technology I Presentation Slides
JiaYu36
 
Formwork
FormworkFormwork
Formwork
Lavanya Singh
 
Chapter 10 wall finishes ( plastering,pointing & painting)
Chapter 10 wall finishes ( plastering,pointing & painting)Chapter 10 wall finishes ( plastering,pointing & painting)
Chapter 10 wall finishes ( plastering,pointing & painting)
KHUSHBU SHAH
 
Chapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipmentsChapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipments
KHUSHBU SHAH
 
Mivan tech
Mivan techMivan tech
Mivan tech
rishi mahajan
 
Construction Machines and Plants
Construction Machines and PlantsConstruction Machines and Plants
Construction Machines and Plants
Xubitech
 
Scaffolding, underepinning and shoring
Scaffolding, underepinning and shoringScaffolding, underepinning and shoring
Scaffolding, underepinning and shoring
laxman singh
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
KHUSHBU SHAH
 
FORMWORK, SCAFFOLDING, CENTERING
FORMWORK, SCAFFOLDING, CENTERINGFORMWORK, SCAFFOLDING, CENTERING
FORMWORK, SCAFFOLDING, CENTERING
TANMAY SHETTY
 
Mortars and Plasters
Mortars and PlastersMortars and Plasters
Mortars and Plasters
GAURAV. H .TANDON
 
Building maintenance
Building maintenanceBuilding maintenance
Building maintenance
Ir. Abdul Aziz Abas
 
Masonry Presentation
Masonry PresentationMasonry Presentation
Masonry Presentation
flrbc1avtech
 
Diaphragm Wall
 Diaphragm Wall Diaphragm Wall
Diaphragm Wall
Reasat E Noor
 
JUMP FORM WORK
JUMP FORM WORKJUMP FORM WORK
JUMP FORM WORK
Pranay Kumar Tode
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction technique
IEI GSC
 

What's hot (20)

Underpinning
UnderpinningUnderpinning
Underpinning
 
Formwork
FormworkFormwork
Formwork
 
All you need to know about Construction Formwork
All you need to know about Construction FormworkAll you need to know about Construction Formwork
All you need to know about Construction Formwork
 
Finishing works (Building Construction)
Finishing works (Building Construction)Finishing works (Building Construction)
Finishing works (Building Construction)
 
Repairing of masonry structures
Repairing of masonry structuresRepairing of masonry structures
Repairing of masonry structures
 
Construction Technology I Presentation Slides
Construction Technology I Presentation SlidesConstruction Technology I Presentation Slides
Construction Technology I Presentation Slides
 
Formwork
FormworkFormwork
Formwork
 
Chapter 10 wall finishes ( plastering,pointing & painting)
Chapter 10 wall finishes ( plastering,pointing & painting)Chapter 10 wall finishes ( plastering,pointing & painting)
Chapter 10 wall finishes ( plastering,pointing & painting)
 
Chapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipmentsChapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipments
 
Mivan tech
Mivan techMivan tech
Mivan tech
 
Construction Machines and Plants
Construction Machines and PlantsConstruction Machines and Plants
Construction Machines and Plants
 
Scaffolding, underepinning and shoring
Scaffolding, underepinning and shoringScaffolding, underepinning and shoring
Scaffolding, underepinning and shoring
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
FORMWORK, SCAFFOLDING, CENTERING
FORMWORK, SCAFFOLDING, CENTERINGFORMWORK, SCAFFOLDING, CENTERING
FORMWORK, SCAFFOLDING, CENTERING
 
Mortars and Plasters
Mortars and PlastersMortars and Plasters
Mortars and Plasters
 
Building maintenance
Building maintenanceBuilding maintenance
Building maintenance
 
Masonry Presentation
Masonry PresentationMasonry Presentation
Masonry Presentation
 
Diaphragm Wall
 Diaphragm Wall Diaphragm Wall
Diaphragm Wall
 
JUMP FORM WORK
JUMP FORM WORKJUMP FORM WORK
JUMP FORM WORK
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction technique
 

Similar to FORMWORK.pptx

Formwork
FormworkFormwork
Formwork
snehakaira
 
Formwork
FormworkFormwork
Formwork
kajol panchal
 
Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar raut
SAGAR RAUT
 
Formwork
FormworkFormwork
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction Technology
I'mMiss Lily
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdf
FaizanSolanki
 
FormWork
FormWork FormWork
FormWork
Abhishek Kansara
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
Kishor Ade
 
Introduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineeringIntroduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineering
UjasPandya2
 
CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)CHE :- 6 form work (MODULE 3)
Formwork
FormworkFormwork
Formwork
Shakil Ahmmad
 
Formwork 151220193813
Formwork 151220193813Formwork 151220193813
Formwork 151220193813
Anoop Banshiwal
 
types of formwork.pdf
types of formwork.pdftypes of formwork.pdf
types of formwork.pdf
ReigerRoyal
 
Gurme santoshkumar
Gurme santoshkumarGurme santoshkumar
Gurme santoshkumar
santoshkumar gurme
 
Form Work
Form Work Form Work
Form Work
Kezar Ali. Shah
 
Steel formwork
Steel formworkSteel formwork
Steel formwork
Musahiddin Md Zainal
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU
VATSAL PATEL
 
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
FaizanSolanki
 
A presentation on Formwork
A presentation on FormworkA presentation on Formwork
A presentation on Formwork
Esri India
 
castingprocessprocess mouling gating .ppt
castingprocessprocess mouling gating .pptcastingprocessprocess mouling gating .ppt
castingprocessprocess mouling gating .ppt
Praveen Kumar
 

Similar to FORMWORK.pptx (20)

Formwork
FormworkFormwork
Formwork
 
Formwork
FormworkFormwork
Formwork
 
Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar raut
 
Formwork
FormworkFormwork
Formwork
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction Technology
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdf
 
FormWork
FormWork FormWork
FormWork
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
 
Introduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineeringIntroduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineering
 
CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)
 
Formwork
FormworkFormwork
Formwork
 
Formwork 151220193813
Formwork 151220193813Formwork 151220193813
Formwork 151220193813
 
types of formwork.pdf
types of formwork.pdftypes of formwork.pdf
types of formwork.pdf
 
Gurme santoshkumar
Gurme santoshkumarGurme santoshkumar
Gurme santoshkumar
 
Form Work
Form Work Form Work
Form Work
 
Steel formwork
Steel formworkSteel formwork
Steel formwork
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU
 
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
 
A presentation on Formwork
A presentation on FormworkA presentation on Formwork
A presentation on Formwork
 
castingprocessprocess mouling gating .ppt
castingprocessprocess mouling gating .pptcastingprocessprocess mouling gating .ppt
castingprocessprocess mouling gating .ppt
 

More from ErankajKumar

Construction Materials.pptx
Construction Materials.pptxConstruction Materials.pptx
Construction Materials.pptx
ErankajKumar
 
WATERPROOFING.pptx
WATERPROOFING.pptxWATERPROOFING.pptx
WATERPROOFING.pptx
ErankajKumar
 
Bricks_MCQ_SSC_JE_2007-18
Bricks_MCQ_SSC_JE_2007-18Bricks_MCQ_SSC_JE_2007-18
Bricks_MCQ_SSC_JE_2007-18
ErankajKumar
 
Cement & Lime_SSC JE_MCQ_SOLVED_2007-2018
Cement & Lime_SSC JE_MCQ_SOLVED_2007-2018Cement & Lime_SSC JE_MCQ_SOLVED_2007-2018
Cement & Lime_SSC JE_MCQ_SOLVED_2007-2018
ErankajKumar
 
TILES, MANUFACTURE,TYPES, CHARACTERISTICS OF GOOD TILES
TILES, MANUFACTURE,TYPES, CHARACTERISTICS OF GOOD TILESTILES, MANUFACTURE,TYPES, CHARACTERISTICS OF GOOD TILES
TILES, MANUFACTURE,TYPES, CHARACTERISTICS OF GOOD TILES
ErankajKumar
 
construction tools & equipments.pptx
construction tools & equipments.pptxconstruction tools & equipments.pptx
construction tools & equipments.pptx
ErankajKumar
 
construction tools.pptx
construction tools.pptxconstruction tools.pptx
construction tools.pptx
ErankajKumar
 
PLASTER.pptx
PLASTER.pptxPLASTER.pptx
PLASTER.pptx
ErankajKumar
 
BRICK MASONRY.pptx
BRICK MASONRY.pptxBRICK MASONRY.pptx
BRICK MASONRY.pptx
ErankajKumar
 
EXPERIMENTAL INVESTIGATION ON M25 & M30 CONCRETE WITH CONSTRUCTION & DEMOLITI...
EXPERIMENTAL INVESTIGATION ON M25 & M30 CONCRETE WITH CONSTRUCTION & DEMOLITI...EXPERIMENTAL INVESTIGATION ON M25 & M30 CONCRETE WITH CONSTRUCTION & DEMOLITI...
EXPERIMENTAL INVESTIGATION ON M25 & M30 CONCRETE WITH CONSTRUCTION & DEMOLITI...
ErankajKumar
 
FOUNDATION.pptx
FOUNDATION.pptxFOUNDATION.pptx
FOUNDATION.pptx
ErankajKumar
 
Foundation Engineering Lab Manual
Foundation Engineering Lab ManualFoundation Engineering Lab Manual
Foundation Engineering Lab Manual
ErankajKumar
 
Module on fibre reinforced and foam concrete
 Module on fibre reinforced and foam concrete Module on fibre reinforced and foam concrete
Module on fibre reinforced and foam concrete
ErankajKumar
 
Module on Special and high performance concrete
Module on Special and high performance concreteModule on Special and high performance concrete
Module on Special and high performance concrete
ErankajKumar
 
Module on pozzolanic materials and fly ash
Module on pozzolanic materials and fly ash Module on pozzolanic materials and fly ash
Module on pozzolanic materials and fly ash
ErankajKumar
 
Module on admixture , polymer and exposy resins
Module on admixture , polymer and exposy resinsModule on admixture , polymer and exposy resins
Module on admixture , polymer and exposy resins
ErankajKumar
 
Module on light and heavy weight concrete
Module on light and heavy weight concreteModule on light and heavy weight concrete
Module on light and heavy weight concrete
ErankajKumar
 
special concrete and high performance concrete
special concrete and high performance concretespecial concrete and high performance concrete
special concrete and high performance concrete
ErankajKumar
 
pozzolanic and flyash
pozzolanic and flyashpozzolanic and flyash
pozzolanic and flyash
ErankajKumar
 
lightweight and heavy weight concrete
lightweight and heavy weight concretelightweight and heavy weight concrete
lightweight and heavy weight concrete
ErankajKumar
 

More from ErankajKumar (20)

Construction Materials.pptx
Construction Materials.pptxConstruction Materials.pptx
Construction Materials.pptx
 
WATERPROOFING.pptx
WATERPROOFING.pptxWATERPROOFING.pptx
WATERPROOFING.pptx
 
Bricks_MCQ_SSC_JE_2007-18
Bricks_MCQ_SSC_JE_2007-18Bricks_MCQ_SSC_JE_2007-18
Bricks_MCQ_SSC_JE_2007-18
 
Cement & Lime_SSC JE_MCQ_SOLVED_2007-2018
Cement & Lime_SSC JE_MCQ_SOLVED_2007-2018Cement & Lime_SSC JE_MCQ_SOLVED_2007-2018
Cement & Lime_SSC JE_MCQ_SOLVED_2007-2018
 
TILES, MANUFACTURE,TYPES, CHARACTERISTICS OF GOOD TILES
TILES, MANUFACTURE,TYPES, CHARACTERISTICS OF GOOD TILESTILES, MANUFACTURE,TYPES, CHARACTERISTICS OF GOOD TILES
TILES, MANUFACTURE,TYPES, CHARACTERISTICS OF GOOD TILES
 
construction tools & equipments.pptx
construction tools & equipments.pptxconstruction tools & equipments.pptx
construction tools & equipments.pptx
 
construction tools.pptx
construction tools.pptxconstruction tools.pptx
construction tools.pptx
 
PLASTER.pptx
PLASTER.pptxPLASTER.pptx
PLASTER.pptx
 
BRICK MASONRY.pptx
BRICK MASONRY.pptxBRICK MASONRY.pptx
BRICK MASONRY.pptx
 
EXPERIMENTAL INVESTIGATION ON M25 & M30 CONCRETE WITH CONSTRUCTION & DEMOLITI...
EXPERIMENTAL INVESTIGATION ON M25 & M30 CONCRETE WITH CONSTRUCTION & DEMOLITI...EXPERIMENTAL INVESTIGATION ON M25 & M30 CONCRETE WITH CONSTRUCTION & DEMOLITI...
EXPERIMENTAL INVESTIGATION ON M25 & M30 CONCRETE WITH CONSTRUCTION & DEMOLITI...
 
FOUNDATION.pptx
FOUNDATION.pptxFOUNDATION.pptx
FOUNDATION.pptx
 
Foundation Engineering Lab Manual
Foundation Engineering Lab ManualFoundation Engineering Lab Manual
Foundation Engineering Lab Manual
 
Module on fibre reinforced and foam concrete
 Module on fibre reinforced and foam concrete Module on fibre reinforced and foam concrete
Module on fibre reinforced and foam concrete
 
Module on Special and high performance concrete
Module on Special and high performance concreteModule on Special and high performance concrete
Module on Special and high performance concrete
 
Module on pozzolanic materials and fly ash
Module on pozzolanic materials and fly ash Module on pozzolanic materials and fly ash
Module on pozzolanic materials and fly ash
 
Module on admixture , polymer and exposy resins
Module on admixture , polymer and exposy resinsModule on admixture , polymer and exposy resins
Module on admixture , polymer and exposy resins
 
Module on light and heavy weight concrete
Module on light and heavy weight concreteModule on light and heavy weight concrete
Module on light and heavy weight concrete
 
special concrete and high performance concrete
special concrete and high performance concretespecial concrete and high performance concrete
special concrete and high performance concrete
 
pozzolanic and flyash
pozzolanic and flyashpozzolanic and flyash
pozzolanic and flyash
 
lightweight and heavy weight concrete
lightweight and heavy weight concretelightweight and heavy weight concrete
lightweight and heavy weight concrete
 

Recently uploaded

Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...
Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...
Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...
Dr.Costas Sachpazis
 
Butterfly Valves Manufacturer (LBF Series).pdf
Butterfly Valves Manufacturer (LBF Series).pdfButterfly Valves Manufacturer (LBF Series).pdf
Butterfly Valves Manufacturer (LBF Series).pdf
Lubi Valves
 
AN INTRODUCTION OF AI & SEARCHING TECHIQUES
AN INTRODUCTION OF AI & SEARCHING TECHIQUESAN INTRODUCTION OF AI & SEARCHING TECHIQUES
AN INTRODUCTION OF AI & SEARCHING TECHIQUES
drshikhapandey2022
 
Sri Guru Hargobind Ji - Bandi Chor Guru.pdf
Sri Guru Hargobind Ji - Bandi Chor Guru.pdfSri Guru Hargobind Ji - Bandi Chor Guru.pdf
Sri Guru Hargobind Ji - Bandi Chor Guru.pdf
Balvir Singh
 
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
simrangupta87541
 
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
sydezfe
 
Data Communication and Computer Networks Management System Project Report.pdf
Data Communication and Computer Networks Management System Project Report.pdfData Communication and Computer Networks Management System Project Report.pdf
Data Communication and Computer Networks Management System Project Report.pdf
Kamal Acharya
 
Call Girls Chennai +91-8824825030 Vip Call Girls Chennai
Call Girls Chennai +91-8824825030 Vip Call Girls ChennaiCall Girls Chennai +91-8824825030 Vip Call Girls Chennai
Call Girls Chennai +91-8824825030 Vip Call Girls Chennai
paraasingh12 #V08
 
Impartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 StandardImpartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 Standard
MuhammadJazib15
 
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEERDELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
EMERSON EDUARDO RODRIGUES
 
My Airframe Metallic Design Capability Studies..pdf
My Airframe Metallic Design Capability Studies..pdfMy Airframe Metallic Design Capability Studies..pdf
My Airframe Metallic Design Capability Studies..pdf
Geoffrey Wardle. MSc. MSc. Snr.MAIAA
 
TENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineeringTENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineering
SnehalChavan75
 
Technological Innovation Management And Entrepreneurship-1.pdf
Technological Innovation Management And Entrepreneurship-1.pdfTechnological Innovation Management And Entrepreneurship-1.pdf
Technological Innovation Management And Entrepreneurship-1.pdf
tanujaharish2
 
Covid Management System Project Report.pdf
Covid Management System Project Report.pdfCovid Management System Project Report.pdf
Covid Management System Project Report.pdf
Kamal Acharya
 
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
nainakaoornoida
 
Call Girls Madurai 8824825030 Escort In Madurai service 24X7
Call Girls Madurai 8824825030 Escort In Madurai service 24X7Call Girls Madurai 8824825030 Escort In Madurai service 24X7
Call Girls Madurai 8824825030 Escort In Madurai service 24X7
Poonam Singh
 
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
sonamrawat5631
 
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort ServiceCuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
yakranividhrini
 
Online train ticket booking system project.pdf
Online train ticket booking system project.pdfOnline train ticket booking system project.pdf
Online train ticket booking system project.pdf
Kamal Acharya
 
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
sexytaniya455
 

Recently uploaded (20)

Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...
Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...
Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...
 
Butterfly Valves Manufacturer (LBF Series).pdf
Butterfly Valves Manufacturer (LBF Series).pdfButterfly Valves Manufacturer (LBF Series).pdf
Butterfly Valves Manufacturer (LBF Series).pdf
 
AN INTRODUCTION OF AI & SEARCHING TECHIQUES
AN INTRODUCTION OF AI & SEARCHING TECHIQUESAN INTRODUCTION OF AI & SEARCHING TECHIQUES
AN INTRODUCTION OF AI & SEARCHING TECHIQUES
 
Sri Guru Hargobind Ji - Bandi Chor Guru.pdf
Sri Guru Hargobind Ji - Bandi Chor Guru.pdfSri Guru Hargobind Ji - Bandi Chor Guru.pdf
Sri Guru Hargobind Ji - Bandi Chor Guru.pdf
 
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
 
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
 
Data Communication and Computer Networks Management System Project Report.pdf
Data Communication and Computer Networks Management System Project Report.pdfData Communication and Computer Networks Management System Project Report.pdf
Data Communication and Computer Networks Management System Project Report.pdf
 
Call Girls Chennai +91-8824825030 Vip Call Girls Chennai
Call Girls Chennai +91-8824825030 Vip Call Girls ChennaiCall Girls Chennai +91-8824825030 Vip Call Girls Chennai
Call Girls Chennai +91-8824825030 Vip Call Girls Chennai
 
Impartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 StandardImpartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 Standard
 
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEERDELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
 
My Airframe Metallic Design Capability Studies..pdf
My Airframe Metallic Design Capability Studies..pdfMy Airframe Metallic Design Capability Studies..pdf
My Airframe Metallic Design Capability Studies..pdf
 
TENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineeringTENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineering
 
Technological Innovation Management And Entrepreneurship-1.pdf
Technological Innovation Management And Entrepreneurship-1.pdfTechnological Innovation Management And Entrepreneurship-1.pdf
Technological Innovation Management And Entrepreneurship-1.pdf
 
Covid Management System Project Report.pdf
Covid Management System Project Report.pdfCovid Management System Project Report.pdf
Covid Management System Project Report.pdf
 
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
 
Call Girls Madurai 8824825030 Escort In Madurai service 24X7
Call Girls Madurai 8824825030 Escort In Madurai service 24X7Call Girls Madurai 8824825030 Escort In Madurai service 24X7
Call Girls Madurai 8824825030 Escort In Madurai service 24X7
 
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
 
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort ServiceCuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
 
Online train ticket booking system project.pdf
Online train ticket booking system project.pdfOnline train ticket booking system project.pdf
Online train ticket booking system project.pdf
 
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
 

FORMWORK.pptx

  • 3. What is Formwork? • Formwork is a mould including all supporting structures, used to shape and support the concrete until it attains sufficient strength to carry its own weight. • It should be capable of carrying all imposed dead and live loads apart from its own weight. Formwork is commonly made of • Steel andTimber
  • 6. • Formwork has been in use since the beginning of concrete construction. • New materials such as steel, plastics and fibreglass are used in formwork. • Greater attention is being given to the design, fabrication, erection and dismantling of formwork • Formwork is designed according to The ACI document SP-4.
  • 7. Qualities of Formwork • It should be water tight. • It should be strong. • It can be reusable. • Its contact surface should be uniform. • It should be according to the size of member.
  • 8. In order to successfully carry out its function, formwork must achieve a balance of following requirements: • Containment • Strength • Resistance To Leakage • Accuracy • Ease Of Handling • Finish And Reuse Potential • Access For Concrete • Economy
  • 9. • Containment: formwork must be capable of shaping and supporting the fluid concrete until it cures. • Strength: formwork must be capable of safely withstanding without distortion or danger the dead weight of the fluid concrete is placed on it, labour weight, equipment weight and any environmental loadings.
  • 10. • Ease of Handling: form panels and units should be designed so that their maximum size does not exceed that which can be easily handled by hand or mechanical means. – In addition all formwork must also be designed and constructed to include facilities for adjustments, levelling, easing and striking without damage to the form work or concrete
  • 11. • Economy: All the formwork is very expensive. On average about 35% of the total cost of any finished concrete unit or element can be attributed to its formwork; of this just over 40% can be taken for material for formwork and 60% for labour. – The formwork designer must therefore not only consider the maximum number of times that any form can be reused, but also produce a design that will minimize the time taken for erection and striking
  • 12. Major objectives considered in formwork: ➢ Quality ➢ Safety ➢ Economy
  • 13. • Quality: Forms must be designed and built with sufficient stiffness and accuracy so that the size, shape, position, and finish of the cast concrete are maintained. so that they have • Safety: Forms must be built sufficient strength and factor of safety the capable of all supporting loads. • Economy: Forms must be built efficiently, minimizing time and cost.
  • 14. Requirements of formwork: • Material should be cheap and re usable, • It should be practically water proof, so that it should not absorb water from concrete, • Swelling and shrinkage should be minimum, • Strong enough to with stand all external loads, • Deflection should be minimum, • Surface should be smooth, and afford easy striping, • Light in weight, so that easy to transfer, • Joints should be stiff, so that lateral deformation and leak is minimum .
  • 15. Three stages in the process : a) Assembly and erection b) Concrete placement. c) Stripping and dismantling.
  • 16. Formwork detail for different structural members • In concrete construction formwork is commonly provided for the following structural members. • Wall • Column • Slabs & Beams • Stairs o Chimneys • Water tanks • Cooling Towers
  • 17. Formwork for Wall It consists of Timber sheeting • Vertical posts • Horizontal members • Rackers • Stakes • Wedges ➢ After completing one side of formwork reinforcement is provided at the place then the second side formwork is provided.
  • 18. Formwork for Column It consists of the following – Side & End Planks – Yoke – Nut & Bolts • Two end & two side planks are joined by the yokes and bolts.
  • 20. Formwork for Slabs & beams It consistsof – Sole plates – Wedges – Props – Head tree – Planks – Batten – Ledgers • Beam formworkrests on headtree • Slab form work restson battens andjoists • If prop height aremore than 8’ provide horizontalbraces.
  • 21. Lintel or Beam Formwork
  • 23. FORMWORK FOR STAIRS It consists of – Vertical & inclined posts – Inclined members -- Wooden Planks or sheeting – Stringer – Riser Planks
  • 26. FORMWORK FOR CHIMNEYS For tall chimneys two types of forms techniques are in generally use in our country a) Jump form b) Slip form
  • 27. Removal of formwork • Time of formwork removal depends on the following factors: Type of Cement Rapid hardening cements require lesser time as compared to OPC (Ordinary Portland Cement) Ratio of concrete mix Rich ratio concrete gain strength earlier as compared to weak ratio concrete. Weather condition Hydration process accelerates in hot weather conditions as compared to cold and humid weather conditions
  • 28. Time of Removal of formwork
  • 29. Comparison between Steel and Timber Formwork • Steel forms are stronger, durable, and have a longer life than timber formwork and their reuses are more in number. • Steel forms can be installed and dismantled with greater ease and speed. • The quality of exposed concrete surface by using steel forms is good and such surfaces need no further treatment. • Steel formwork does not absorb moisture from concrete. • Steel formwork does not shrink or warp.
  • 30. Cantilever slab First free end's support should be removed. • And then from right to left it should be proceed. • If we are removing from the mid span then it will act as a prop cantilever.
  • 31. Simply supported slab In simply supported we have to remove the support from the mid span to the ends. • To meet the design behavior.
  • 32. Maintenance of formwork • Due to continuous use wooden planks & steel plates surfaces become uneven and require maintenance. • For wooden formwork use cardboard or plastic fiber board. Bolt hole places must also be repaired. • For steel formwork plates must be leveled by mallet and loose corners must be welded.
  • 33. Cost of formwork • For normal works cost of formwork is about 30%- 40% of the concrete cost. ➢ For special works cost of formwork is about 50%-60% of the concrete cost. ➢ Formwork cost is controlled by the following factors • Formwork Material cost • Formwork erecting cost • Formwork removal cost • Formwork jointing cost (Nails and Cables) • Labor charges
  • 34. Advantages of steel form work • It can be used for a no. of times. ▪ It is non absorbent. ▪ Smooth finish surface obtained. ▪ No shrinkage of formwork occurs. ▪ Easy to use. ▪ Its volume is less ▪ Its strength is more
  • 35. LOADS ON FORMWORK Dead load ▪ Self weight of formwork ▪ Pressure and loads from fresh concrete ▪ Reinforcement • Imposed load ▪ Construction workers ▪ Stacking of materials • Horizontal loads • Environmental loads ▪ Accidental loads ▪ Wind loads
  • 36. References • R.C.C Design by B.C.Punmia • R.C.C Design by H.J.Shah • Formwork Design Section 1500 • Doka Formwork Design • Design of safe timber structures by Eva and Tomi Torrati