Estimation ,Costing And
Valuation Engineering
Prepared by:-
P.GAYATHRI
A.P, Civil Engg.
AEC
 An estimate is an anticipated or probable cost of a work
and is usually prepared before the construction is taken
up.
 Before undertaking any work or project it is necessary
to know the probable cost which is obtained by
estimating.
 The estimate is prepared by computing the quantities
required and then calculating the cost at suitable rates,
to get the expenditure likely to be incurred in the
construction of the work or structure. Prepared by:-
P.GAYATHRI
A.P, Civil Engg.
AEC
 Drawings( Plans, section, etc)
 Specifications
a) General Specifications: This gives the nature,
quality, class of work and materials in general terms to be used
in various parts of work. It helps to from a general idea of
building.
b) Detailed Specifications: These gives the detailed
description of the various items of work laying down the
Quantities and qualities of materials, their proportions, the
method of preparation workmanship and execution of work.
 Rates :
For preparing the estimate the unit rates of each
item of work are required.
 For arriving at the unit rates of each item.
 The rates of various materials to be used in the
construction.
 The cost of transport materials.
 The wages of labor, skilled or unskilled of masons,
carpenters, Mazdoor etc
Prepared by:-
P.GAYATHRI
A.P, Civil Engg.
AEC
Preliminary/Appx./Abstract/Rough Cost Estimate
Plinth Area Estimate
Cube Rate or Cubical Content Estimate
Appx. Quantity Method Estimate
Detailed Estimate or Item Rate Estimate
Revised Estimate
Supplementary Estimate
Supplementary and Revised Estimate
Annual Repair or Maintenance Estimate (A.R or A.M
Estimate)
Preliminary Estimate is prepared by various ways for different
structures as mentioned below :
Buildings
 Per Unit Basis – Per student for schools and hostels, per class room
for schools, per bed for hospitals, per seat for cinema and theatre
halls, per tenement for residential buildings.
 Plinth area basis
 Cubic content basis
 Appx. Quantity method
Roads and Highways – Per km basis depending upon nature of
road, width and thickness of metalling.
Irrigation Channels
 Per km basis
 Per hectare basis (Area of land commanded)
Bridges and Culverts – Per running meter of span depending
upon type of structure, type and depth of foundation.
Sewerage and Water Supply Project
 Per head of population served
 Per hectare basis (Area covered)
Over Head water Tank – Per liter or per gallon of tank
depending upon type of structure and height of tank.
Plinth area is approximate estimate
Plinth area should be calculated for covered area by taking
external dimensions of the building at the floor level
Courtyard and other open area should not be included
For multi storeyed building Plinth Area for each storey is
determined separately.
Plinth area rate is known from cost of similar building in the
locality.
Estimate is prepared by
Plinth area × Plinth area rate
Cube rate estimate is again approximate estimate
Cubical content of the building is determined by multiplying
length, breadth and height of the building.
External length and breadth at the floor level are calculated
for the purpose
Height should be taken from the floor level to the top of roof.
For multi storeyed building height is taken from floor level of
one storey to top of next higher floor.
Cube rate estimate is more accurate as compared to the
plinth area estimate.
Cubical content= plinth area × height
Structure divided into two parts – (i) Foundation including
plinth (ii) Superstructure
Total length of walls is found out.
Tofind running meter rate of foundation, appx. quantities of
various items are calculated per running meter
Similarly for superstructure appx. Quantities of brickwork,
roof, flooring etc is calculated per running meter.
It is the accurate estimate prepared by working out quantities of
each items of work.
It is prepared in two stages –
 Details of measurements and calculation of quantities.
 Abstract of estimated cost – 3% to 5% of estimated cost is added to
cover miscellaneous expenditure
Detailed estimate is prepared work-wise.
Detailed estimate consists of –
 Report
 General Specifications
 Detailed specifications
 Drawings
 Calculation and designs
 Analysis of rates
Detailed estimate is prepared for technical sanction, for
arranging contract and for execution of project.
 Revised estimate is prepared when original sanctioned
estimate is likely to exceed more than 5%.
 When expenditure on work is likely to exceed
amount of administrative sanction by more than
10%
 When there are material deviation from original proposal
even though cost may be met from sanctioned cost.
 It is accompanied by comparative statement showing
variations in each item of works and reason for the same.
It is the fresh detailed estimate of the additional works in
addition to the original estimate.
It is required when further development is required during the
progress of work.
Abstract should show the amount of original estimate and
total amount including supplementary amount.
When a work is partially abandoned and estimated cost of remaining
work is less than 95% of original sanctioned estimate.
When there are material deviations and changes in the design
If at any time before or during the execution of work, it is found that
original estimate is excessive then divisional officer may sanction a
revised estimate of reduced amount.
It is prepared to maintain structure or work in proper order
and safe condition
For buildings like white washing, painting, minor repairs etc.
For road works A.R. estimate provides for patch repairing,
repairs of bridges and culverts etc.
 Long wall - short wall method
 Centre line method.
 Partly centre line and short wall method
 In this method, the wall along the length of room is
considered to be long wall while the wall perpendicular to
long wall is said to be short wall.
 To get the length of long wall or short wall, calculate first
the centre line lengths of individual walls.
 Then the length of long wall, (out to out) may be calculated
after adding half breadth at each end to its centre line
length. Thus the length of short wall measured into in and
may be found by deducting half breadth from its centre line
length at each end. The length of long wall usually
decreases from earth work to brick work in super structure
while the short wall increases. These lengths are multiplied
by breadth and depth to get quantities.
LONG WALL
SHORT
WALL
 Long wall length (out to out)= centre to
centre length + half breadth on one side+
half a breadth on other side
(Or)=centre to centre length + one breadth
 Short wall length=centre to centre length –
one breadth
 This method is suitable for walls of similar cross
sections.
 Here the total centre line length is multiplied by
breadth and depth of respective item to get the
total quantity at a time.
 When cross walls or partitions or verandah walls
join with main all, the centre line length gets
reduced by half of breadth for each junction.
such junction or joints are studied carefully while
calculating total centre line length.
 The estimates prepared by this method are most
accurate and quick.
Center Line Method
 This method is adopted when external (i.e.,
alround the building) wall is of one thickness
and the internal walls having different
thicknesses.
 In such cases, centre line method is applied
to external walls and long wall short wall
method is used to internal walls.
 This method suits for different thicknesses
walls and different level of foundations.
Because of this reason, all Engineering
departments are practicing this method.
Contingencies – Indicates incidental expenses of
miscellaneous character which cannot be classified under any
distinct item. (3% to 5% of the estimated cost is provided to allow
for contingencies)
Work-charged Establishment – Work-charged employees are
temporary staff whose services are terminated at the expiry of
sanctioned period but usually one month notice is given. (1 .5% to
2% of the estimated cost is added)
Tools and Plants – Normally contractor has to arrange tools and
plants. (1% to 1 .5% of estimated cost is provided)
Centage charges or Departmental charges – Also known as
Supervision charges for works. Tomeet the expenses of
establishment, designing, planning, supervision etc. (10% to 15% of
the estimated cost). When engineering department takes up work of
other department.
Expenditure Sanction – It represents allotment of money to
meet the expenditure. It is usually accorded by Finance
Department.
Technical Sanction – It is the sanction of the detailed
estimate, design calculation, quantities of work etc. Technical
sanction is accorded by engineering department and
execution of work is carried out thereafter.
Quantity Survey – It means estimating of quantities of
different items of works.
Sub-Head items of work – Works like earthwork, concrete
work, brick work etc. Under each sub head there are different items
of work.
Sub- Work – Large project may consist of several buildings.
Detailed estimate of each sub-work is prepared separately.
Schedule of Rates – It is a list of rate of various items of
works maintained by engineering department under the name
“Schedule of Rates Book”. “Road Metal Rate Book” is also
maintained by PWD.
Administrative Sanction/ Approval – It is the formal
acceptance by the department concerned of the proposal. After
the approval, design, estimates etc. are prepared and thereafter
execution of work.
estimation,its types and methods

More Related Content

What's hot

Estimating and costing
Estimating and costingEstimating and costing
Estimating and costing
AyushHajare
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
Vijay325
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
DhavalMithaiwala
 
Types of estimate
Types of estimateTypes of estimate
Types of estimate
Arpit Sethia
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
AshwiniChaudhari13
 
Valuation(1)
Valuation(1)Valuation(1)
Valuation(1)
jagadish108
 
Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
Aglaia Connect
 
Valuation in Civil Engineering
Valuation in Civil EngineeringValuation in Civil Engineering
Valuation in Civil Engineering
Kailash Chander
 
Building bye laws
Building bye lawsBuilding bye laws
Building bye laws
Cul Aditi
 
Foundation types
Foundation typesFoundation types
Foundation types
Ashwini Ingale
 
Job layout per
Job layout perJob layout per
Job layout per
raj balar
 
Dampness in buildings
Dampness in buildingsDampness in buildings
Dampness in buildings
Ashar Gill
 
Terminology used in estimating and costing
Terminology used in estimating and costingTerminology used in estimating and costing
Terminology used in estimating and costing
Janak Mehta
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-I
Kishor Ade
 
Estimation (power point)
Estimation (power point)Estimation (power point)
Estimation (power point)
Waqas Aslam
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of Rates
Raj Shah
 
GUNITING
GUNITINGGUNITING
GUNITING
ARYAN GUPTA
 
Retaining walls
Retaining wallsRetaining walls
Retaining walls
Penchala Vineeth
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
srinivas2036
 
Rate analysis
Rate analysisRate analysis
Rate analysis
DhavalMithaiwala
 

What's hot (20)

Estimating and costing
Estimating and costingEstimating and costing
Estimating and costing
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
Types of estimate
Types of estimateTypes of estimate
Types of estimate
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
 
Valuation(1)
Valuation(1)Valuation(1)
Valuation(1)
 
Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
 
Valuation in Civil Engineering
Valuation in Civil EngineeringValuation in Civil Engineering
Valuation in Civil Engineering
 
Building bye laws
Building bye lawsBuilding bye laws
Building bye laws
 
Foundation types
Foundation typesFoundation types
Foundation types
 
Job layout per
Job layout perJob layout per
Job layout per
 
Dampness in buildings
Dampness in buildingsDampness in buildings
Dampness in buildings
 
Terminology used in estimating and costing
Terminology used in estimating and costingTerminology used in estimating and costing
Terminology used in estimating and costing
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-I
 
Estimation (power point)
Estimation (power point)Estimation (power point)
Estimation (power point)
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of Rates
 
GUNITING
GUNITINGGUNITING
GUNITING
 
Retaining walls
Retaining wallsRetaining walls
Retaining walls
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Rate analysis
Rate analysisRate analysis
Rate analysis
 

Similar to estimation,its types and methods

ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdfECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
SURAJITDASBAURI
 
2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptx2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptx
RaniVishwakarma15
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
Padmasinh Patil
 
Estimating and Costing
Estimating and CostingEstimating and Costing
Estimating and Costing
Ganesh Tatikonda
 
chapter3-210122050220.pdf
chapter3-210122050220.pdfchapter3-210122050220.pdf
chapter3-210122050220.pdf
Deepak37004
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
lckr117
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and Costing
Sakshi Kirar
 
Lec05.pptx
Lec05.pptxLec05.pptx
Lec05.pptx
AHMADAHMAD735251
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
TauheedKhan45
 
type of cost Estimation
type of cost Estimationtype of cost Estimation
type of cost Estimation
Educational Learner
 
Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic terms
meghajain275
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for building
Himani762003
 
Ecv
EcvEcv
Planning and cost analysis of the commercial building
Planning and cost analysis of the commercial buildingPlanning and cost analysis of the commercial building
Planning and cost analysis of the commercial building
ila vamsi krishna
 
ESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdf
suchitamantry2002
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptx
NSHYAMANANDASINGH
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
NaumanIjaz12
 
specification estimation and valuation of a building
specification estimation and valuation of a buildingspecification estimation and valuation of a building
specification estimation and valuation of a building
swethasekhar5
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
Ar Naveen Naveen
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
Shabaz Khan
 

Similar to estimation,its types and methods (20)

ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdfECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
 
2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptx2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptx
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
 
Estimating and Costing
Estimating and CostingEstimating and Costing
Estimating and Costing
 
chapter3-210122050220.pdf
chapter3-210122050220.pdfchapter3-210122050220.pdf
chapter3-210122050220.pdf
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and Costing
 
Lec05.pptx
Lec05.pptxLec05.pptx
Lec05.pptx
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
 
type of cost Estimation
type of cost Estimationtype of cost Estimation
type of cost Estimation
 
Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic terms
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for building
 
Ecv
EcvEcv
Ecv
 
Planning and cost analysis of the commercial building
Planning and cost analysis of the commercial buildingPlanning and cost analysis of the commercial building
Planning and cost analysis of the commercial building
 
ESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdf
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptx
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
 
specification estimation and valuation of a building
specification estimation and valuation of a buildingspecification estimation and valuation of a building
specification estimation and valuation of a building
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
 

Recently uploaded

Cricket management system ptoject report.pdf
Cricket management system ptoject report.pdfCricket management system ptoject report.pdf
Cricket management system ptoject report.pdf
Kamal Acharya
 
🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...
🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...
🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...
adhaniomprakash
 
Covid Management System Project Report.pdf
Covid Management System Project Report.pdfCovid Management System Project Report.pdf
Covid Management System Project Report.pdf
Kamal Acharya
 
This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...
DharmaBanothu
 
paper relate Chozhavendhan et al. 2020.pdf
paper relate Chozhavendhan et al. 2020.pdfpaper relate Chozhavendhan et al. 2020.pdf
paper relate Chozhavendhan et al. 2020.pdf
ShurooqTaib
 
SPICE PARK JUL2024 ( 6,866 SPICE Models )
SPICE PARK JUL2024 ( 6,866 SPICE Models )SPICE PARK JUL2024 ( 6,866 SPICE Models )
SPICE PARK JUL2024 ( 6,866 SPICE Models )
Tsuyoshi Horigome
 
Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...
Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...
Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...
IJCNCJournal
 
Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine
 
Butterfly Valves Manufacturer (LBF Series).pdf
Butterfly Valves Manufacturer (LBF Series).pdfButterfly Valves Manufacturer (LBF Series).pdf
Butterfly Valves Manufacturer (LBF Series).pdf
Lubi Valves
 
Impartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 StandardImpartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 Standard
MuhammadJazib15
 
BBOC407 Module 1.pptx Biology for Engineers
BBOC407  Module 1.pptx Biology for EngineersBBOC407  Module 1.pptx Biology for Engineers
BBOC407 Module 1.pptx Biology for Engineers
sathishkumars808912
 
Introduction to Artificial Intelligence.
Introduction to Artificial Intelligence.Introduction to Artificial Intelligence.
Introduction to Artificial Intelligence.
supriyaDicholkar1
 
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdfSELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
Pallavi Sharma
 
Literature review for prompt engineering of ChatGPT.pptx
Literature review for prompt engineering of ChatGPT.pptxLiterature review for prompt engineering of ChatGPT.pptx
Literature review for prompt engineering of ChatGPT.pptx
LokerXu2
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
felixwold
 
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptxMODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
NaveenNaveen726446
 
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
DharmaBanothu
 
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEERDELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
EMERSON EDUARDO RODRIGUES
 
Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...
Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...
Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...
Dr.Costas Sachpazis
 
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdfFUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
EMERSON EDUARDO RODRIGUES
 

Recently uploaded (20)

Cricket management system ptoject report.pdf
Cricket management system ptoject report.pdfCricket management system ptoject report.pdf
Cricket management system ptoject report.pdf
 
🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...
🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...
🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...
 
Covid Management System Project Report.pdf
Covid Management System Project Report.pdfCovid Management System Project Report.pdf
Covid Management System Project Report.pdf
 
This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...
 
paper relate Chozhavendhan et al. 2020.pdf
paper relate Chozhavendhan et al. 2020.pdfpaper relate Chozhavendhan et al. 2020.pdf
paper relate Chozhavendhan et al. 2020.pdf
 
SPICE PARK JUL2024 ( 6,866 SPICE Models )
SPICE PARK JUL2024 ( 6,866 SPICE Models )SPICE PARK JUL2024 ( 6,866 SPICE Models )
SPICE PARK JUL2024 ( 6,866 SPICE Models )
 
Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...
Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...
Particle Swarm Optimization–Long Short-Term Memory based Channel Estimation w...
 
Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024
 
Butterfly Valves Manufacturer (LBF Series).pdf
Butterfly Valves Manufacturer (LBF Series).pdfButterfly Valves Manufacturer (LBF Series).pdf
Butterfly Valves Manufacturer (LBF Series).pdf
 
Impartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 StandardImpartiality as per ISO /IEC 17025:2017 Standard
Impartiality as per ISO /IEC 17025:2017 Standard
 
BBOC407 Module 1.pptx Biology for Engineers
BBOC407  Module 1.pptx Biology for EngineersBBOC407  Module 1.pptx Biology for Engineers
BBOC407 Module 1.pptx Biology for Engineers
 
Introduction to Artificial Intelligence.
Introduction to Artificial Intelligence.Introduction to Artificial Intelligence.
Introduction to Artificial Intelligence.
 
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdfSELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
 
Literature review for prompt engineering of ChatGPT.pptx
Literature review for prompt engineering of ChatGPT.pptxLiterature review for prompt engineering of ChatGPT.pptx
Literature review for prompt engineering of ChatGPT.pptx
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
 
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptxMODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
 
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
 
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEERDELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
 
Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...
Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...
Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...
 
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdfFUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
 

estimation,its types and methods

  • 1. Estimation ,Costing And Valuation Engineering Prepared by:- P.GAYATHRI A.P, Civil Engg. AEC
  • 2.  An estimate is an anticipated or probable cost of a work and is usually prepared before the construction is taken up.  Before undertaking any work or project it is necessary to know the probable cost which is obtained by estimating.  The estimate is prepared by computing the quantities required and then calculating the cost at suitable rates, to get the expenditure likely to be incurred in the construction of the work or structure. Prepared by:- P.GAYATHRI A.P, Civil Engg. AEC
  • 3.  Drawings( Plans, section, etc)  Specifications a) General Specifications: This gives the nature, quality, class of work and materials in general terms to be used in various parts of work. It helps to from a general idea of building. b) Detailed Specifications: These gives the detailed description of the various items of work laying down the Quantities and qualities of materials, their proportions, the method of preparation workmanship and execution of work.
  • 4.  Rates : For preparing the estimate the unit rates of each item of work are required.  For arriving at the unit rates of each item.  The rates of various materials to be used in the construction.  The cost of transport materials.  The wages of labor, skilled or unskilled of masons, carpenters, Mazdoor etc
  • 6. Preliminary/Appx./Abstract/Rough Cost Estimate Plinth Area Estimate Cube Rate or Cubical Content Estimate Appx. Quantity Method Estimate Detailed Estimate or Item Rate Estimate Revised Estimate Supplementary Estimate Supplementary and Revised Estimate Annual Repair or Maintenance Estimate (A.R or A.M Estimate)
  • 7. Preliminary Estimate is prepared by various ways for different structures as mentioned below : Buildings  Per Unit Basis – Per student for schools and hostels, per class room for schools, per bed for hospitals, per seat for cinema and theatre halls, per tenement for residential buildings.  Plinth area basis  Cubic content basis  Appx. Quantity method Roads and Highways – Per km basis depending upon nature of road, width and thickness of metalling. Irrigation Channels  Per km basis  Per hectare basis (Area of land commanded)
  • 8. Bridges and Culverts – Per running meter of span depending upon type of structure, type and depth of foundation. Sewerage and Water Supply Project  Per head of population served  Per hectare basis (Area covered) Over Head water Tank – Per liter or per gallon of tank depending upon type of structure and height of tank.
  • 9. Plinth area is approximate estimate Plinth area should be calculated for covered area by taking external dimensions of the building at the floor level Courtyard and other open area should not be included For multi storeyed building Plinth Area for each storey is determined separately. Plinth area rate is known from cost of similar building in the locality. Estimate is prepared by Plinth area × Plinth area rate
  • 10. Cube rate estimate is again approximate estimate Cubical content of the building is determined by multiplying length, breadth and height of the building. External length and breadth at the floor level are calculated for the purpose Height should be taken from the floor level to the top of roof. For multi storeyed building height is taken from floor level of one storey to top of next higher floor. Cube rate estimate is more accurate as compared to the plinth area estimate. Cubical content= plinth area × height
  • 11. Structure divided into two parts – (i) Foundation including plinth (ii) Superstructure Total length of walls is found out. Tofind running meter rate of foundation, appx. quantities of various items are calculated per running meter Similarly for superstructure appx. Quantities of brickwork, roof, flooring etc is calculated per running meter.
  • 12. It is the accurate estimate prepared by working out quantities of each items of work. It is prepared in two stages –  Details of measurements and calculation of quantities.  Abstract of estimated cost – 3% to 5% of estimated cost is added to cover miscellaneous expenditure Detailed estimate is prepared work-wise. Detailed estimate consists of –  Report  General Specifications  Detailed specifications  Drawings  Calculation and designs  Analysis of rates Detailed estimate is prepared for technical sanction, for arranging contract and for execution of project.
  • 13.  Revised estimate is prepared when original sanctioned estimate is likely to exceed more than 5%.  When expenditure on work is likely to exceed amount of administrative sanction by more than 10%  When there are material deviation from original proposal even though cost may be met from sanctioned cost.  It is accompanied by comparative statement showing variations in each item of works and reason for the same.
  • 14. It is the fresh detailed estimate of the additional works in addition to the original estimate. It is required when further development is required during the progress of work. Abstract should show the amount of original estimate and total amount including supplementary amount.
  • 15. When a work is partially abandoned and estimated cost of remaining work is less than 95% of original sanctioned estimate. When there are material deviations and changes in the design If at any time before or during the execution of work, it is found that original estimate is excessive then divisional officer may sanction a revised estimate of reduced amount.
  • 16. It is prepared to maintain structure or work in proper order and safe condition For buildings like white washing, painting, minor repairs etc. For road works A.R. estimate provides for patch repairing, repairs of bridges and culverts etc.
  • 17.  Long wall - short wall method  Centre line method.  Partly centre line and short wall method
  • 18.  In this method, the wall along the length of room is considered to be long wall while the wall perpendicular to long wall is said to be short wall.  To get the length of long wall or short wall, calculate first the centre line lengths of individual walls.  Then the length of long wall, (out to out) may be calculated after adding half breadth at each end to its centre line length. Thus the length of short wall measured into in and may be found by deducting half breadth from its centre line length at each end. The length of long wall usually decreases from earth work to brick work in super structure while the short wall increases. These lengths are multiplied by breadth and depth to get quantities.
  • 20.  Long wall length (out to out)= centre to centre length + half breadth on one side+ half a breadth on other side (Or)=centre to centre length + one breadth  Short wall length=centre to centre length – one breadth
  • 21.  This method is suitable for walls of similar cross sections.  Here the total centre line length is multiplied by breadth and depth of respective item to get the total quantity at a time.  When cross walls or partitions or verandah walls join with main all, the centre line length gets reduced by half of breadth for each junction. such junction or joints are studied carefully while calculating total centre line length.  The estimates prepared by this method are most accurate and quick.
  • 23.  This method is adopted when external (i.e., alround the building) wall is of one thickness and the internal walls having different thicknesses.  In such cases, centre line method is applied to external walls and long wall short wall method is used to internal walls.  This method suits for different thicknesses walls and different level of foundations. Because of this reason, all Engineering departments are practicing this method.
  • 24. Contingencies – Indicates incidental expenses of miscellaneous character which cannot be classified under any distinct item. (3% to 5% of the estimated cost is provided to allow for contingencies) Work-charged Establishment – Work-charged employees are temporary staff whose services are terminated at the expiry of sanctioned period but usually one month notice is given. (1 .5% to 2% of the estimated cost is added) Tools and Plants – Normally contractor has to arrange tools and plants. (1% to 1 .5% of estimated cost is provided) Centage charges or Departmental charges – Also known as Supervision charges for works. Tomeet the expenses of establishment, designing, planning, supervision etc. (10% to 15% of the estimated cost). When engineering department takes up work of other department.
  • 25. Expenditure Sanction – It represents allotment of money to meet the expenditure. It is usually accorded by Finance Department. Technical Sanction – It is the sanction of the detailed estimate, design calculation, quantities of work etc. Technical sanction is accorded by engineering department and execution of work is carried out thereafter. Quantity Survey – It means estimating of quantities of different items of works.
  • 26. Sub-Head items of work – Works like earthwork, concrete work, brick work etc. Under each sub head there are different items of work. Sub- Work – Large project may consist of several buildings. Detailed estimate of each sub-work is prepared separately. Schedule of Rates – It is a list of rate of various items of works maintained by engineering department under the name “Schedule of Rates Book”. “Road Metal Rate Book” is also maintained by PWD. Administrative Sanction/ Approval – It is the formal acceptance by the department concerned of the proposal. After the approval, design, estimates etc. are prepared and thereafter execution of work.