TYPES OF ESTIMATES
Prepared by:-
Simarpreet Singh
A.P, Civil Engg.
ACET, Amritsar
 Contingencies – Indicates incidental expenses of
miscellaneous character which cannot be classified under any
distinct item. (3% to 5% of the estimated cost is provided to
allow for contingencies)
 Work-charged Establishment – Work-charged employees are
temporary staff whose services are terminated at the expiry
of sanctioned period but usually one month notice is given.
(1.5% to 2% of the estimated cost is added)
 Tools and Plants – Normally contractor has to arrange tools
and plants. (1% to 1.5% of estimated cost is provided)
 Centage charges or Departmental charges – Also known as
Supervision charges for works. To meet the expenses of
establishment, designing, planning, supervision etc. (10% to
15% of the estimated cost). When engineering department
takes up work of other department.
TERMINOLOGY
 Report gives brief information of whole project. It should consist of the
following :
 Brief history (with proposal)
 Necessity and feasibility of project
 Selection of site
 Survey
 Brief description of works
 Nature of soil, topography of land etc.
 Basis of design calculations
 Arrangement for water supply, sanitation and electrical installations etc.
 Roads and drains
 Temporary accommodations for staff, labour etc included in misc.
 Manner of execution
 Total cost and how to be financed
 Return or revenue income
 Rent statement
 Time of execution
TERMINOLOGY
 Sub-Head items of work – Works like earthwork, concrete
work, brick work etc. Under each sub head there are different
items of work.
 Sub-Work – Large project may consist of small buildings.
Detailed estimate of each sub-work is prepared separately.
 Schedule of Rates – It is a list of rate of various items of
works maintained by engineering department under the name
“Schedule of Rates Book”. “Road Metal Rate Book” is also
maintained by PWD.
 Administrative Sanction/ Approval – It is the formal
acceptance by the department concerned of the proposal.
After the approval, design, estimates etc. are prepared and
thereafter execution of work.
TERMINOLOGY
 Expenditure Sanction – It represents allotment of money to
meet the expenditure. It is usually accorded by Finance
Department.
 Technical Sanction – It is the sanction of the detailed
estimate, design calculation, quantities of work etc. Technical
sanction is accorded by engineering department and
execution of work is carried out thereafter.
 Quantity Survey – It means estimating of quantities of
different items of works.
 Plinth Area – It is the built up covered area of a building
measured at floor level of any storey by taking external
dimensions of the building at the floor level.
TERMINOLOGY
 Floor Area – It is obtained after deducting area of walls from the
plinth area of building. It should include:
 Door and other openings
 Intermediate pillars and supports
 Circulation Area – It is the floor area of verandahs, passages,
corridors, balconies, staircases, lift etc. which are used for
movements of persons using the building. It is further classified
into Horizontal and Vertical.
 Carpet Area – It is the useful area of the building. It is
determined after deducting :
 Circulation Area
 Sanitary Accommodations
 Kitchen, Pantry, Stores
 For office building approximate 60% to 75% of plinth area
 For residential buildings approximate 50% to 65% of plinth area
TERMINOLOGY
 Site Plan – Plan showing orientation of building, boundaries of
land, position of roads, drains, sewer line, water pipelines and
adjoining plots of lands. North direction is also shown on one
corner of site plan)
 Layout Plan –
 Plan showing proposed buildings, structures etc. showing their locations,
size and orientations.
 Roads, drains, pipe lines , electric lines, parks etc are shown.
 The boundary, main approach roads and adjoining areas are also
indicated.
 Index Plan –
 Plan is usually drawn for Roads, Irrigation, Water supply etc.
 It shows alignment with position of culverts, main outline of whole work
to give idea of the project
 For big project it is drawn with much small scale and is known as key
plan
TERMINOLOGY
 Preliminary/Appx./Abstract/Rough Cost Estimate
 Plinth Area Estimate
 Cube Rate or Cubical Content Estimate
 Appx. Quantity Method Estimate
 Detailed Estimate or Item Rate Estimate
 Revised Estimate
 Supplementary Estimate
 Supplementary and Revised Estimate
 Annual Repair or Maintenance Estimate (A.R or A.M
Estimate)
DIFFERENT TYPES OF ESTIMATES
Preliminary Estimate is prepared by various ways for different
structures as mentioned below :
 Buildings
 Per Unit Basis – Per student for schools and hostels, per class room
for schools, per bed for hospitals, per seat for cinema and theatre
halls, per tenement for residential buildings.
 Plinth area basis
 Cubic content basis
 Appx. Quantity method
 Roads and Highways – Per km basis depending upon nature of
road, width and thickness of metalling.
 Irrigation Channels
 Per km basis
 Per hectare basis (Area of land commanded)
PRELIMINARY ESTIMATE
 Bridges and Culverts – Per running meter of span depending
upon type of structure, type and depth of foundation.
 Sewerage and Water Supply Project
 Per head of population served
 Per hectare basis (Area covered)
 Over Head water Tank – Per liter or per gallon of tank
depending upon type of structure and height of tank.
PRELIMINARY ESTIMATE (Ctd.)
 P.A. is approximate estimate
 Plinth area should be calculated for covered area by taking
external dimensions of the building at the floor level
 Courtyard and other open area should not be included
 For multi storeyed building Plinth Area for each storey is
determined separately.
 Approximate total plinth area may be calculated by adding 30
to 40% of the already calculated area for walls, circulation
and waste etc.
 Plinth area rate is known from cost of similar building in the
locality.
PLINTH AREA ESTIMATE (P.A. ESTIMATE)
 Cube rate estimate is again approximate estimate
 Cubical content of the building is determined by multiplying
length, breadth and height of the building.
 External length and breadth at the floor level are calculated
for the purpose
 Height should be taken from the floor level to the top of roof.
 For multi storeyed building height is taken from floor level of
one storey to top of next higher floor.
 Cube rate estimate is more accurate as compared to the
plinth area estimate.
CUBE RATE ESTIMATE
 Structure divided into two parts – (i) Foundation including
plinth (ii) Superstructure
 Total length of walls is found out.
 To find running meter rate of foundation, appx. quantities of
various items are calculated per running meter
 Similarly for superstructure appx. Quantities of brickwork,
roof, flooring etc is calculated per running meter.
APPROXIMATE QUANTITY METHOD
ESTIMATE
 It is the accurate estimate prepared by working out quantities of
each items of work.
 It is prepared in two stages –
 Details of measurements and calculation of quantities.
 Abstract of estimated cost – 3% to 5% of estimated cost is added to
cover miscellaneous expenditure
 Detailed estimate is prepared work-wise.
 Detailed estimate consists of –
 Report
 General Specifications
 Detailed specifications
 Drawings
 Calculation and designs
 Analysis of rates
 Detailed estimate is prepared for technical sanction, for
arranging contract and for execution of project.
DETAILED ESTIMATE
 Revised estimate is prepared when original sanctioned
estimate is likely to exceed more than 5%.
 When expenditure on work is likely to exceed amount of
administrative sanction by more than 10%
 When there are material deviation from original proposal even
though cost may be met from sanctioned cost.
 It is accompanied by comparative statement showing
variations in each item of works and reason for the same.
REVISED ESTIMATE
 It is the fresh detailed estimate of the additional works in
addition to the original estimate.
 It is required when further development is required during the
progress of work.
 Abstract should show the amount of original estimate and
total amount including supplementary amount.
SUPPLEMENTARY ESTIMATE
 When a work is partially abandoned and estimated cost of
remaining work is less than 95% of original sanctioned
estimate.
 When there are material deviations and changes in the design
 If at any time before or during the execution of work, it is
found that original estimate is excessive then divisional
officer may sanction a revised estimate of reduced amount.
SUPPLEMENTARY AND REVISED
ESTIMATE
 It is prepared to maintain structure or work in proper order
and safe condition
 For buildings like white washing, painting, minor repairs etc.
 For road works A.R. estimate provides for patch repairing,
repairs of bridges and culverts etc.
ANNUAL REPAIR OR MAINTENANCE
ESTIMATE (A.R / A.M ESTIMATE)
Any Questions?
THANK YOU

More Related Content

What's hot

Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line method
malang1214
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
RANJIT KUMAR PANDA
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
Shahin MB
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
DhavalMithaiwala
 
Roof truss
Roof trussRoof truss
Roof truss
Pankajkumar Singh
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
Kailash Chander
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
Ganesh Tatikonda
 
Valuation
ValuationValuation
Valuation
srinivas2036
 
Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2
ArunRavi43
 
Foundation types
Foundation typesFoundation types
Foundation types
Ashwini Ingale
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
Thomas Britto
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
srinivas2036
 
Bar bending schedule
Bar bending scheduleBar bending schedule
Bar bending schedule
bhusan neupane
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
sooricivil
 
Valuation
ValuationValuation
Valuation
gayu pandian
 
Prefabrication
PrefabricationPrefabrication
Prefabrication
Kush Agarwal
 
prefabricated Structures
prefabricated Structuresprefabricated Structures
prefabricated Structures
Boopathi Raja
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-I
Kishor Ade
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...
A Makwana
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specifications
Simran Vats
 

What's hot (20)

Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line method
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
Roof truss
Roof trussRoof truss
Roof truss
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Valuation
ValuationValuation
Valuation
 
Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2
 
Foundation types
Foundation typesFoundation types
Foundation types
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Bar bending schedule
Bar bending scheduleBar bending schedule
Bar bending schedule
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
Valuation
ValuationValuation
Valuation
 
Prefabrication
PrefabricationPrefabrication
Prefabrication
 
prefabricated Structures
prefabricated Structuresprefabricated Structures
prefabricated Structures
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-I
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specifications
 

Viewers also liked

Building estimation methods
Building estimation methodsBuilding estimation methods
Building estimation methods
Simarpreet Singh
 
Point Estimation
Point EstimationPoint Estimation
Point Estimation
DataminingTools Inc
 
Point and Interval Estimation
Point and Interval EstimationPoint and Interval Estimation
Point and Interval Estimation
Shubham Mehta
 
Theory of estimation
Theory of estimationTheory of estimation
Theory of estimation
Tech_MX
 
Preliminary estimate
Preliminary estimatePreliminary estimate
Preliminary estimate
norrizah abd wahab
 
Enlistment rules2014 07
Enlistment rules2014 07Enlistment rules2014 07
Enlistment rules2014 07
Ptpg Stuc
 
WORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-IWORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-I
Avinash Kumar Gupta
 
Nrega Technical Aspects Of Execution Of Works By S.Anwar Hussain
Nrega Technical Aspects Of Execution Of Works  By S.Anwar HussainNrega Technical Aspects Of Execution Of Works  By S.Anwar Hussain
Nrega Technical Aspects Of Execution Of Works By S.Anwar Hussain
Anwar Hussain
 
Introduction to Civil Engineering (Harsh Gupta)
Introduction to Civil Engineering (Harsh Gupta)Introduction to Civil Engineering (Harsh Gupta)
Introduction to Civil Engineering (Harsh Gupta)
Harsh Gupta
 
Estimation of a residential building
Estimation of a residential buildingEstimation of a residential building
Estimation of a residential building
Vardhaman Sethia
 
Probability Distributions
Probability DistributionsProbability Distributions
Probability Distributions
rishi.indian
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
ALI HYDER GADHI
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveying
Awanish Shukla
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
lizwi nyandu
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
Ganesh Murugan
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
ALI HYDER GADHI
 
Probability concept and Probability distribution
Probability concept and Probability distributionProbability concept and Probability distribution
Probability concept and Probability distribution
Southern Range, Berhampur, Odisha
 
RESEARCH METHOD - SAMPLING
RESEARCH METHOD - SAMPLINGRESEARCH METHOD - SAMPLING
RESEARCH METHOD - SAMPLING
Hafizah Hajimia
 

Viewers also liked (18)

Building estimation methods
Building estimation methodsBuilding estimation methods
Building estimation methods
 
Point Estimation
Point EstimationPoint Estimation
Point Estimation
 
Point and Interval Estimation
Point and Interval EstimationPoint and Interval Estimation
Point and Interval Estimation
 
Theory of estimation
Theory of estimationTheory of estimation
Theory of estimation
 
Preliminary estimate
Preliminary estimatePreliminary estimate
Preliminary estimate
 
Enlistment rules2014 07
Enlistment rules2014 07Enlistment rules2014 07
Enlistment rules2014 07
 
WORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-IWORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-I
 
Nrega Technical Aspects Of Execution Of Works By S.Anwar Hussain
Nrega Technical Aspects Of Execution Of Works  By S.Anwar HussainNrega Technical Aspects Of Execution Of Works  By S.Anwar Hussain
Nrega Technical Aspects Of Execution Of Works By S.Anwar Hussain
 
Introduction to Civil Engineering (Harsh Gupta)
Introduction to Civil Engineering (Harsh Gupta)Introduction to Civil Engineering (Harsh Gupta)
Introduction to Civil Engineering (Harsh Gupta)
 
Estimation of a residential building
Estimation of a residential buildingEstimation of a residential building
Estimation of a residential building
 
Probability Distributions
Probability DistributionsProbability Distributions
Probability Distributions
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveying
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
 
Probability concept and Probability distribution
Probability concept and Probability distributionProbability concept and Probability distribution
Probability concept and Probability distribution
 
RESEARCH METHOD - SAMPLING
RESEARCH METHOD - SAMPLINGRESEARCH METHOD - SAMPLING
RESEARCH METHOD - SAMPLING
 

Similar to Types of estimates

Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and Costing
Sakshi Kirar
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for building
Himani762003
 
Ecv
EcvEcv
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdfECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
SURAJITDASBAURI
 
Lec05.pptx
Lec05.pptxLec05.pptx
Lec05.pptx
AHMADAHMAD735251
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
Shabaz Khan
 
type of cost Estimation
type of cost Estimationtype of cost Estimation
type of cost Estimation
Educational Learner
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
Padmasinh Patil
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
NaumanIjaz12
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
lckr117
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
TauheedKhan45
 
Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic terms
meghajain275
 
Aiet e&c lecture_notes
Aiet  e&c lecture_notesAiet  e&c lecture_notes
Aiet e&c lecture_notes
Dr.K.Mohan Das
 
CE6704_uw.pdf
CE6704_uw.pdfCE6704_uw.pdf
CE6704_uw.pdf
hitusp
 
Estimating part 1
Estimating part 1Estimating part 1
Estimating part 1
ArunRavi43
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptx
NSHYAMANANDASINGH
 
EEEC pdf.pdf
EEEC pdf.pdfEEEC pdf.pdf
EEEC pdf.pdf
BSuresh26
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
Vijay325
 
Estimating and Costing
Estimating and CostingEstimating and Costing
Estimating and Costing
Ganesh Tatikonda
 
chapter3-210122050220.pdf
chapter3-210122050220.pdfchapter3-210122050220.pdf
chapter3-210122050220.pdf
Deepak37004
 

Similar to Types of estimates (20)

Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and Costing
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for building
 
Ecv
EcvEcv
Ecv
 
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdfECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
 
Lec05.pptx
Lec05.pptxLec05.pptx
Lec05.pptx
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
 
type of cost Estimation
type of cost Estimationtype of cost Estimation
type of cost Estimation
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
 
Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic terms
 
Aiet e&c lecture_notes
Aiet  e&c lecture_notesAiet  e&c lecture_notes
Aiet e&c lecture_notes
 
CE6704_uw.pdf
CE6704_uw.pdfCE6704_uw.pdf
CE6704_uw.pdf
 
Estimating part 1
Estimating part 1Estimating part 1
Estimating part 1
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptx
 
EEEC pdf.pdf
EEEC pdf.pdfEEEC pdf.pdf
EEEC pdf.pdf
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
 
Estimating and Costing
Estimating and CostingEstimating and Costing
Estimating and Costing
 
chapter3-210122050220.pdf
chapter3-210122050220.pdfchapter3-210122050220.pdf
chapter3-210122050220.pdf
 

Recently uploaded

Slides Peluncuran Amalan Pemakanan Sihat.pptx
Slides Peluncuran Amalan Pemakanan Sihat.pptxSlides Peluncuran Amalan Pemakanan Sihat.pptx
Slides Peluncuran Amalan Pemakanan Sihat.pptx
shabeluno
 
220711130088 Sumi Basak Virtual University EPC 3.pptx
220711130088 Sumi Basak Virtual University EPC 3.pptx220711130088 Sumi Basak Virtual University EPC 3.pptx
220711130088 Sumi Basak Virtual University EPC 3.pptx
Kalna College
 
Non-Verbal Communication for Tech Professionals
Non-Verbal Communication for Tech ProfessionalsNon-Verbal Communication for Tech Professionals
Non-Verbal Communication for Tech Professionals
MattVassar1
 
220711130083 SUBHASHREE RAKSHIT Internet resources for social science
220711130083 SUBHASHREE RAKSHIT  Internet resources for social science220711130083 SUBHASHREE RAKSHIT  Internet resources for social science
220711130083 SUBHASHREE RAKSHIT Internet resources for social science
Kalna College
 
Cross-Cultural Leadership and Communication
Cross-Cultural Leadership and CommunicationCross-Cultural Leadership and Communication
Cross-Cultural Leadership and Communication
MattVassar1
 
Brand Guideline of Bashundhara A4 Paper - 2024
Brand Guideline of Bashundhara A4 Paper - 2024Brand Guideline of Bashundhara A4 Paper - 2024
Brand Guideline of Bashundhara A4 Paper - 2024
khabri85
 
Library news letter Kitengesa Uganda June 2024
Library news letter Kitengesa Uganda June 2024Library news letter Kitengesa Uganda June 2024
Library news letter Kitengesa Uganda June 2024
Friends of African Village Libraries
 
Talking Tech through Compelling Visual Aids
Talking Tech through Compelling Visual AidsTalking Tech through Compelling Visual Aids
Talking Tech through Compelling Visual Aids
MattVassar1
 
CapTechTalks Webinar Slides June 2024 Donovan Wright.pptx
CapTechTalks Webinar Slides June 2024 Donovan Wright.pptxCapTechTalks Webinar Slides June 2024 Donovan Wright.pptx
CapTechTalks Webinar Slides June 2024 Donovan Wright.pptx
CapitolTechU
 
Post init hook in the odoo 17 ERP Module
Post init hook in the  odoo 17 ERP ModulePost init hook in the  odoo 17 ERP Module
Post init hook in the odoo 17 ERP Module
Celine George
 
The Rise of the Digital Telecommunication Marketplace.pptx
The Rise of the Digital Telecommunication Marketplace.pptxThe Rise of the Digital Telecommunication Marketplace.pptx
The Rise of the Digital Telecommunication Marketplace.pptx
PriyaKumari928991
 
BỘ BÀI TẬP TEST THEO UNIT - FORM 2025 - TIẾNG ANH 12 GLOBAL SUCCESS - KÌ 1 (B...
BỘ BÀI TẬP TEST THEO UNIT - FORM 2025 - TIẾNG ANH 12 GLOBAL SUCCESS - KÌ 1 (B...BỘ BÀI TẬP TEST THEO UNIT - FORM 2025 - TIẾNG ANH 12 GLOBAL SUCCESS - KÌ 1 (B...
BỘ BÀI TẬP TEST THEO UNIT - FORM 2025 - TIẾNG ANH 12 GLOBAL SUCCESS - KÌ 1 (B...
Nguyen Thanh Tu Collection
 
220711130095 Tanu Pandey message currency, communication speed & control EPC ...
220711130095 Tanu Pandey message currency, communication speed & control EPC ...220711130095 Tanu Pandey message currency, communication speed & control EPC ...
220711130095 Tanu Pandey message currency, communication speed & control EPC ...
Kalna College
 
managing Behaviour in early childhood education.pptx
managing Behaviour in early childhood education.pptxmanaging Behaviour in early childhood education.pptx
managing Behaviour in early childhood education.pptx
nabaegha
 
How to Download & Install Module From the Odoo App Store in Odoo 17
How to Download & Install Module From the Odoo App Store in Odoo 17How to Download & Install Module From the Odoo App Store in Odoo 17
How to Download & Install Module From the Odoo App Store in Odoo 17
Celine George
 
(T.L.E.) Agriculture: "Ornamental Plants"
(T.L.E.) Agriculture: "Ornamental Plants"(T.L.E.) Agriculture: "Ornamental Plants"
(T.L.E.) Agriculture: "Ornamental Plants"
MJDuyan
 
Keynote given on June 24 for MASSP at Grand Traverse City
Keynote given on June 24 for MASSP at Grand Traverse CityKeynote given on June 24 for MASSP at Grand Traverse City
Keynote given on June 24 for MASSP at Grand Traverse City
PJ Caposey
 
Information and Communication Technology in Education
Information and Communication Technology in EducationInformation and Communication Technology in Education
Information and Communication Technology in Education
MJDuyan
 
220711130097 Tulip Samanta Concept of Information and Communication Technology
220711130097 Tulip Samanta Concept of Information and Communication Technology220711130097 Tulip Samanta Concept of Information and Communication Technology
220711130097 Tulip Samanta Concept of Information and Communication Technology
Kalna College
 
Diversity Quiz Finals by Quiz Club, IIT Kanpur
Diversity Quiz Finals by Quiz Club, IIT KanpurDiversity Quiz Finals by Quiz Club, IIT Kanpur
Diversity Quiz Finals by Quiz Club, IIT Kanpur
Quiz Club IIT Kanpur
 

Recently uploaded (20)

Slides Peluncuran Amalan Pemakanan Sihat.pptx
Slides Peluncuran Amalan Pemakanan Sihat.pptxSlides Peluncuran Amalan Pemakanan Sihat.pptx
Slides Peluncuran Amalan Pemakanan Sihat.pptx
 
220711130088 Sumi Basak Virtual University EPC 3.pptx
220711130088 Sumi Basak Virtual University EPC 3.pptx220711130088 Sumi Basak Virtual University EPC 3.pptx
220711130088 Sumi Basak Virtual University EPC 3.pptx
 
Non-Verbal Communication for Tech Professionals
Non-Verbal Communication for Tech ProfessionalsNon-Verbal Communication for Tech Professionals
Non-Verbal Communication for Tech Professionals
 
220711130083 SUBHASHREE RAKSHIT Internet resources for social science
220711130083 SUBHASHREE RAKSHIT  Internet resources for social science220711130083 SUBHASHREE RAKSHIT  Internet resources for social science
220711130083 SUBHASHREE RAKSHIT Internet resources for social science
 
Cross-Cultural Leadership and Communication
Cross-Cultural Leadership and CommunicationCross-Cultural Leadership and Communication
Cross-Cultural Leadership and Communication
 
Brand Guideline of Bashundhara A4 Paper - 2024
Brand Guideline of Bashundhara A4 Paper - 2024Brand Guideline of Bashundhara A4 Paper - 2024
Brand Guideline of Bashundhara A4 Paper - 2024
 
Library news letter Kitengesa Uganda June 2024
Library news letter Kitengesa Uganda June 2024Library news letter Kitengesa Uganda June 2024
Library news letter Kitengesa Uganda June 2024
 
Talking Tech through Compelling Visual Aids
Talking Tech through Compelling Visual AidsTalking Tech through Compelling Visual Aids
Talking Tech through Compelling Visual Aids
 
CapTechTalks Webinar Slides June 2024 Donovan Wright.pptx
CapTechTalks Webinar Slides June 2024 Donovan Wright.pptxCapTechTalks Webinar Slides June 2024 Donovan Wright.pptx
CapTechTalks Webinar Slides June 2024 Donovan Wright.pptx
 
Post init hook in the odoo 17 ERP Module
Post init hook in the  odoo 17 ERP ModulePost init hook in the  odoo 17 ERP Module
Post init hook in the odoo 17 ERP Module
 
The Rise of the Digital Telecommunication Marketplace.pptx
The Rise of the Digital Telecommunication Marketplace.pptxThe Rise of the Digital Telecommunication Marketplace.pptx
The Rise of the Digital Telecommunication Marketplace.pptx
 
BỘ BÀI TẬP TEST THEO UNIT - FORM 2025 - TIẾNG ANH 12 GLOBAL SUCCESS - KÌ 1 (B...
BỘ BÀI TẬP TEST THEO UNIT - FORM 2025 - TIẾNG ANH 12 GLOBAL SUCCESS - KÌ 1 (B...BỘ BÀI TẬP TEST THEO UNIT - FORM 2025 - TIẾNG ANH 12 GLOBAL SUCCESS - KÌ 1 (B...
BỘ BÀI TẬP TEST THEO UNIT - FORM 2025 - TIẾNG ANH 12 GLOBAL SUCCESS - KÌ 1 (B...
 
220711130095 Tanu Pandey message currency, communication speed & control EPC ...
220711130095 Tanu Pandey message currency, communication speed & control EPC ...220711130095 Tanu Pandey message currency, communication speed & control EPC ...
220711130095 Tanu Pandey message currency, communication speed & control EPC ...
 
managing Behaviour in early childhood education.pptx
managing Behaviour in early childhood education.pptxmanaging Behaviour in early childhood education.pptx
managing Behaviour in early childhood education.pptx
 
How to Download & Install Module From the Odoo App Store in Odoo 17
How to Download & Install Module From the Odoo App Store in Odoo 17How to Download & Install Module From the Odoo App Store in Odoo 17
How to Download & Install Module From the Odoo App Store in Odoo 17
 
(T.L.E.) Agriculture: "Ornamental Plants"
(T.L.E.) Agriculture: "Ornamental Plants"(T.L.E.) Agriculture: "Ornamental Plants"
(T.L.E.) Agriculture: "Ornamental Plants"
 
Keynote given on June 24 for MASSP at Grand Traverse City
Keynote given on June 24 for MASSP at Grand Traverse CityKeynote given on June 24 for MASSP at Grand Traverse City
Keynote given on June 24 for MASSP at Grand Traverse City
 
Information and Communication Technology in Education
Information and Communication Technology in EducationInformation and Communication Technology in Education
Information and Communication Technology in Education
 
220711130097 Tulip Samanta Concept of Information and Communication Technology
220711130097 Tulip Samanta Concept of Information and Communication Technology220711130097 Tulip Samanta Concept of Information and Communication Technology
220711130097 Tulip Samanta Concept of Information and Communication Technology
 
Diversity Quiz Finals by Quiz Club, IIT Kanpur
Diversity Quiz Finals by Quiz Club, IIT KanpurDiversity Quiz Finals by Quiz Club, IIT Kanpur
Diversity Quiz Finals by Quiz Club, IIT Kanpur
 

Types of estimates

  • 1. TYPES OF ESTIMATES Prepared by:- Simarpreet Singh A.P, Civil Engg. ACET, Amritsar
  • 2.  Contingencies – Indicates incidental expenses of miscellaneous character which cannot be classified under any distinct item. (3% to 5% of the estimated cost is provided to allow for contingencies)  Work-charged Establishment – Work-charged employees are temporary staff whose services are terminated at the expiry of sanctioned period but usually one month notice is given. (1.5% to 2% of the estimated cost is added)  Tools and Plants – Normally contractor has to arrange tools and plants. (1% to 1.5% of estimated cost is provided)  Centage charges or Departmental charges – Also known as Supervision charges for works. To meet the expenses of establishment, designing, planning, supervision etc. (10% to 15% of the estimated cost). When engineering department takes up work of other department. TERMINOLOGY
  • 3.  Report gives brief information of whole project. It should consist of the following :  Brief history (with proposal)  Necessity and feasibility of project  Selection of site  Survey  Brief description of works  Nature of soil, topography of land etc.  Basis of design calculations  Arrangement for water supply, sanitation and electrical installations etc.  Roads and drains  Temporary accommodations for staff, labour etc included in misc.  Manner of execution  Total cost and how to be financed  Return or revenue income  Rent statement  Time of execution TERMINOLOGY
  • 4.  Sub-Head items of work – Works like earthwork, concrete work, brick work etc. Under each sub head there are different items of work.  Sub-Work – Large project may consist of small buildings. Detailed estimate of each sub-work is prepared separately.  Schedule of Rates – It is a list of rate of various items of works maintained by engineering department under the name “Schedule of Rates Book”. “Road Metal Rate Book” is also maintained by PWD.  Administrative Sanction/ Approval – It is the formal acceptance by the department concerned of the proposal. After the approval, design, estimates etc. are prepared and thereafter execution of work. TERMINOLOGY
  • 5.  Expenditure Sanction – It represents allotment of money to meet the expenditure. It is usually accorded by Finance Department.  Technical Sanction – It is the sanction of the detailed estimate, design calculation, quantities of work etc. Technical sanction is accorded by engineering department and execution of work is carried out thereafter.  Quantity Survey – It means estimating of quantities of different items of works.  Plinth Area – It is the built up covered area of a building measured at floor level of any storey by taking external dimensions of the building at the floor level. TERMINOLOGY
  • 6.  Floor Area – It is obtained after deducting area of walls from the plinth area of building. It should include:  Door and other openings  Intermediate pillars and supports  Circulation Area – It is the floor area of verandahs, passages, corridors, balconies, staircases, lift etc. which are used for movements of persons using the building. It is further classified into Horizontal and Vertical.  Carpet Area – It is the useful area of the building. It is determined after deducting :  Circulation Area  Sanitary Accommodations  Kitchen, Pantry, Stores  For office building approximate 60% to 75% of plinth area  For residential buildings approximate 50% to 65% of plinth area TERMINOLOGY
  • 7.  Site Plan – Plan showing orientation of building, boundaries of land, position of roads, drains, sewer line, water pipelines and adjoining plots of lands. North direction is also shown on one corner of site plan)  Layout Plan –  Plan showing proposed buildings, structures etc. showing their locations, size and orientations.  Roads, drains, pipe lines , electric lines, parks etc are shown.  The boundary, main approach roads and adjoining areas are also indicated.  Index Plan –  Plan is usually drawn for Roads, Irrigation, Water supply etc.  It shows alignment with position of culverts, main outline of whole work to give idea of the project  For big project it is drawn with much small scale and is known as key plan TERMINOLOGY
  • 8.  Preliminary/Appx./Abstract/Rough Cost Estimate  Plinth Area Estimate  Cube Rate or Cubical Content Estimate  Appx. Quantity Method Estimate  Detailed Estimate or Item Rate Estimate  Revised Estimate  Supplementary Estimate  Supplementary and Revised Estimate  Annual Repair or Maintenance Estimate (A.R or A.M Estimate) DIFFERENT TYPES OF ESTIMATES
  • 9. Preliminary Estimate is prepared by various ways for different structures as mentioned below :  Buildings  Per Unit Basis – Per student for schools and hostels, per class room for schools, per bed for hospitals, per seat for cinema and theatre halls, per tenement for residential buildings.  Plinth area basis  Cubic content basis  Appx. Quantity method  Roads and Highways – Per km basis depending upon nature of road, width and thickness of metalling.  Irrigation Channels  Per km basis  Per hectare basis (Area of land commanded) PRELIMINARY ESTIMATE
  • 10.  Bridges and Culverts – Per running meter of span depending upon type of structure, type and depth of foundation.  Sewerage and Water Supply Project  Per head of population served  Per hectare basis (Area covered)  Over Head water Tank – Per liter or per gallon of tank depending upon type of structure and height of tank. PRELIMINARY ESTIMATE (Ctd.)
  • 11.  P.A. is approximate estimate  Plinth area should be calculated for covered area by taking external dimensions of the building at the floor level  Courtyard and other open area should not be included  For multi storeyed building Plinth Area for each storey is determined separately.  Approximate total plinth area may be calculated by adding 30 to 40% of the already calculated area for walls, circulation and waste etc.  Plinth area rate is known from cost of similar building in the locality. PLINTH AREA ESTIMATE (P.A. ESTIMATE)
  • 12.  Cube rate estimate is again approximate estimate  Cubical content of the building is determined by multiplying length, breadth and height of the building.  External length and breadth at the floor level are calculated for the purpose  Height should be taken from the floor level to the top of roof.  For multi storeyed building height is taken from floor level of one storey to top of next higher floor.  Cube rate estimate is more accurate as compared to the plinth area estimate. CUBE RATE ESTIMATE
  • 13.  Structure divided into two parts – (i) Foundation including plinth (ii) Superstructure  Total length of walls is found out.  To find running meter rate of foundation, appx. quantities of various items are calculated per running meter  Similarly for superstructure appx. Quantities of brickwork, roof, flooring etc is calculated per running meter. APPROXIMATE QUANTITY METHOD ESTIMATE
  • 14.  It is the accurate estimate prepared by working out quantities of each items of work.  It is prepared in two stages –  Details of measurements and calculation of quantities.  Abstract of estimated cost – 3% to 5% of estimated cost is added to cover miscellaneous expenditure  Detailed estimate is prepared work-wise.  Detailed estimate consists of –  Report  General Specifications  Detailed specifications  Drawings  Calculation and designs  Analysis of rates  Detailed estimate is prepared for technical sanction, for arranging contract and for execution of project. DETAILED ESTIMATE
  • 15.  Revised estimate is prepared when original sanctioned estimate is likely to exceed more than 5%.  When expenditure on work is likely to exceed amount of administrative sanction by more than 10%  When there are material deviation from original proposal even though cost may be met from sanctioned cost.  It is accompanied by comparative statement showing variations in each item of works and reason for the same. REVISED ESTIMATE
  • 16.  It is the fresh detailed estimate of the additional works in addition to the original estimate.  It is required when further development is required during the progress of work.  Abstract should show the amount of original estimate and total amount including supplementary amount. SUPPLEMENTARY ESTIMATE
  • 17.  When a work is partially abandoned and estimated cost of remaining work is less than 95% of original sanctioned estimate.  When there are material deviations and changes in the design  If at any time before or during the execution of work, it is found that original estimate is excessive then divisional officer may sanction a revised estimate of reduced amount. SUPPLEMENTARY AND REVISED ESTIMATE
  • 18.  It is prepared to maintain structure or work in proper order and safe condition  For buildings like white washing, painting, minor repairs etc.  For road works A.R. estimate provides for patch repairing, repairs of bridges and culverts etc. ANNUAL REPAIR OR MAINTENANCE ESTIMATE (A.R / A.M ESTIMATE)