尊敬的 微信汇率:1円 ≈ 0.046239 元 支付宝汇率:1円 ≈ 0.04633元 [退出登录]
SlideShare a Scribd company logo
Project on
Design and construction of post tensioning
slab
PRESENTING BY:-
CH .Gopichand (10631A0110)
D.Nagender (10631A0120)
J.Paramesh (10631A0126)
N.Prudhviraj (10631A0129)
S.Sathyanarayana(10631A0147)
CIVIL ENGINEERING
4th YEAR
SRI VENKATESWARA ENGINEERING COLLEGE
INTERNAL GUIDE:
Mrs.P.Jhansi
Objectives
The objective of the present report is
 to summarize the experience available today in the field of
post-tensioning in building construction and in particular to
discuss the design and construction of post tensioned slab
structures, especially post tensioned flat slabs*
 A detailed explanation will be given of the checks to be carried
out, the aspects to be considered in the design and the
construction procedures and sequences of a post-tensioned
slab. The execution of the design will be explained.
Prestressed concrete
 PRINCIPLE – Using high tensile strength
steel alloys producing permanent pre-
compression in areas subjected to Tension.
 A portion of tensile stress is counteracted
thereby reducing the cross-sectional area of
the steel reinforcement .
 METHODS :- a) Pretensioning
b)Post-tensioning
 PRETENSIONING :- Placing of concrete
around reinforcing tendons that have been
stressed to the desired degree.
 POST-TENSIONING :- Reinforcing tendons
are stretched by jacks whilst keeping them in
serted in voids left pre-hand during curing of
concrete.
 These spaces are then pumped full of grout
to bond steel tightly to the concrete.
STEEL BARS BEING
STRETCHED BY JACKS
Introduction
Methods of Pre-stressing
Pre-tensioning
Post-tensioning
Introduction
Pre-tensioning
• Steel tendons are stressed before the concrete is placed
at a precast plant remote from the construction site.
Introduction
Post-tensioning
• Steel tendon are stressed after the concrete has
been placed and gained sufficient strength at
the construction site.
Introduction
Post-tensioning Systems
Un-bonded Post-tensioning System
Bonded Post-tensioning Systems
Single strand
Multi strands flat duct
Multi strands round duct
Single strand
Design of PT Slabs
Flat Plate with Drop Panels
Common geometries*
• Two-way system
• Suitable span: 12.2 m
• Limiting criterion: Deflection
• Rebar**: 2.94 kg/m2
• PT: 3.87 kg/m2
* for typical office/residential buildings using
ACI/UBC requirements
** quantity assume no bottom reinforcement
Materiel properties
CONCRETE:
Fc^28 → Compressive strength of concrete 28 days.
Fcd → Design value for compressive strength on concrete.
→ 0.6 × fc^28 = 21 N/MM^2
PRE STRESSING STEEL:
Ap → cross sectional area of pj steel 146 mm^2
Fpy →yield strength of PT steel 1570 N/MM^2
Fpu → characteristic strength of PT steel 1770 N/MM^2
PRE-TENSIONING STEEL:
Ep → modulus of elasticity of pre stressing steel 1.95 × 10^5 N/MM^2
(very low relaxation (3%)
Admissible stressing 0.75 fpu
Reinforcing steel:
Fsy →yield strength of reinforcing steel is 460 N/MM^2
Long-term losses (assumed to be 10%)
Details of building
Type of structure: commercial building
- Loadings:
Live load p = 2.5 kN/m2
Floor finishes gB = 1.OkN/m2
Walls g w = 1.5 kN/m2
q = 5.0 kN/m2
Plan showing dimensions
Design
Determination of slab thickness:
Assumption l/h = 35
Self wt of slab g = yc × h
L → length of span 8.4
h → 0.24 mt
h → thickness of slab.
Yc → volumetric wt.of concrete →2.5 KN/M^3
→ g=6KN/M^3
→ q =5 KN/M^3
→ (g+q)/g) = 6+5/6 = 1.83 ((g+q) –service load
g→ self wt )
(l/h as a function of (g+q/g))
→ For a value of 1.83 on y- axis l/h is coming to 36
→ 0.233 which is approximately (0.24)
Determination of prestress
µ → it is transfer component from pre stressing / unit length
(g+q/g) → 1.83 based on previous caluculation
Pre stress in longitudinal direction
→ for 1.83 the u/g value in is 1.39
→ u = 8.34 KN/m^2
K → woober’s coefficient =(0.24×10^3)/(8.4^2×25) = 0.136
→h = 0.24
→length of slab = 8.4
→yc =25
£c =concrete tensile stress=1000
Pre tensioning force
→ P = 4×l^2/8×hp
→sag of tendon parabola
Hp →0.178mt (p=8.34× 8.4^2/8×0.178)
P =413 KN/M
P =7.8 × 413 for a width of 78 mt
P = 3221 KN/strand
Pl → pre tensioning force per strand
Pl → Ap × fpu × 0.7 ×10^-3
Ap =416 mm^2
Fpu = 1770 N/mm^2
Pl = 181 KN
strands
No.of strands = p/ pl =413/pl =17.8 =͠ 18
18 strands of dia 15mm on 78 mt width.
For 7.4 mt width =7.4/7.8 ×17.8 =16.88
17 mono strands of dia 15 mm of 7.4 mt width.
On 6.6 mt width = 6.6/7.8 ×17.8 =15.1
16 mono strands of dia 15 mm of 6.6 mt width.
For 2.4 mt width =2.4/7.8 ×17.8 =5.5
6 mono strand of dia of 15mm on 2.4 mt width
Transverse direction:
g+q/g = 1.83
k = 0.24 × 1000/ 7.8 m^2×25
k = 0.158
on design chart 2 for a k value of 0.158 & (g+q/g) value of 1.83 the value of u/g is found be 1.41
→ u= 8.46 kn/m^2
P = (u×l^2/8×hp ) →8.46 ×7.8^2/( 8× 0.167)
P = 3.85 kn/m
On 8.4 mt width p=8.4×385
P =3234 kn
Pc 181 kn
No. Of strands Np = p/pl =3234/181 = 17.9
18 mono strands of dia 15mm on 8.4 mt width
On 7.2 mt width np = 7.2/8.4× 7.9 = 15.3
16 mono strands of dia 15mm on 7.2 mt width.
Execution
Materials & Equipment
Anchorage Markings
Laying of Tendon
Concrete pouring
Pre stressing
grouting
MATERIALS AND EQUIPMENT
a) FORMWORK
b) CONCRETE
c) STRANDS
d) TENDONS
e) DUCTS
f) ANCHORAGES
g) WEDGES
Formwork
strands
Wedges
POST –TENSIONING METHOD
Anchorage marking
Laying of tendons
Concrete pourig
 Mix design of M35
 Grade of Concrete : M35
 Characteristic Strength (Fck) : 35 Mpa
 Standard Deviation : 1.91 Mpa*
 Target Mean Strength : T.M.S.= Fck +1.65 x S.D.
 (from I.S 456-2000) = 35+ 1.65×1.91
 = 38.15 Mpa
 Test Data For Material:
 Aggregate Type : Crushed
 Specific Gravity Cement : 3.15
 Coarse Aggregate : 2.67
 Fine Aggregate : 2.62
 Water Absorption
 Coarse Aggregate : 0.5%
 Fine Aggregate : 1.0 %
Concrete pouring
Mix Design:
 Take Sand content as percentage of total aggregates = 36%
 Select Water Cement Ratio = 0.43 for concrete grade M35
 Select Water Content = 172 Kg
 (From IS: 10262 for 20 mm nominal size of aggregates Maximum Water Content = 186 Kg/m 3 )
Hence, Cement Content= 172 / 0.43 = 400 Kg /m 3
 Formula for Mix Proportion of Fine and Coarse Aggregate:
 1000(1-a 0 )= {(Cement Content / Sp. Gr. Of Cement) + Water Content +(F a / Sp. Gr.* P f )} 1000(1-
a 0 )= {(Cement Content / Sp. Gr. Of Cement) + Water Content +C a / Sp. Gr.* Pc )}
 Where
 C a = Coarse Aggregate Content
 F a = Fine Aggregate Content
 P f = Sand Content as percentage of total Aggregates = 0.36
 P c = Coarse Aggregate Content as percentage of total Aggregates.
 = 0.64
 a 0 = Percentage air content in concrete (As per IS :10262 for 20 mm nominal size of
 aggregates air content is 2 %) = 0.02
 Hence, 1000(1-0.02) = {(400 /3.15) + 172 +(F a / 2.62 x 0.36)}
 Fa = 642 Kg/ Cum
 As the sand is of Zone II no adjustment is required for sand.
 Sand Content = 642 Kg/ Cum
 1000(1-0.02)= {(400 /3.15) + 172 +(C a / 2.67 x 0.64)}
 Hence, Ca = 1165 Kg/ Cum
Prestressing jack
 For prestressing, mono strand stressing jack is used and pressure is
applied in a controlled way with the help of prestressing power pack.
Initially, a gradual pressure of about 5 kg/cm 2 is applied.
 anchorage bursting when prestressing is applied and also to check
anchorage slip. The perimeter of the rod is then marked with paint and
then once the anchorage is known to be stable, the pressure is
increasing up to 430 kg/cm 2 .
Jacks
Prestressing powerpack
Mono strandstressing jack
Grouting
 Grouting is done with the help of grout pump. The mixture of cement,
water and admixtures must be done under a strict mixing time and
velocity control and must not contain lumps nor any air bubbles during
injection into the ducts
EQUIPMENTS :-
 T6Z-08 Air Powered Grout Pump
 Pumps cement grout only, no sand. 32 Gallon Mixing
Tank. Mixes up to 2 sacks of material at once and allows
for grout to be pumped during mixing or mixed without
pumping.
Approximate size 50" long
30.5" high
52" wide
Weight 560 lbs.
Production Rate 8 gallons per
minute
at 150 psi
ADVANTAGES OF POST-TENSIONING
• Longer clear spans
• Thinner slabs
• Lesser floor-to-floor heights
• Shorter building height
• Lesser weight
• Improved seismic performance
• Faster construction cycle
Conclusions
 Prestressed concrete offers great technical advantages in comparison with
other forms of construction such as reinforced concrete and steel. They
possess improved resistance to shearing forces, due to the effect of
compressive prestress, which reduces the principles tensile stress
 Prestressing of concrete helps in improving the ability of the material for
energy absorption under impact loads. The economy of prestressed concrete
is well established for long span structures. Standardized precast bridge
beams between 10m and 30 m long and precast prestressed piles have
proved to be more economical than steel and reinforced concrete.
 Due to utilization of concrete in the tension zone, an extra saving of 15 to 30%
in concrete is possible in comparison with reinforced concrete
Thank You!

More Related Content

What's hot

Post Tension
Post TensionPost Tension
Post Tension
Sashi Kirran
 
1.1 box jacking
1.1 box jacking1.1 box jacking
1.1 box jacking
Bhalchandra Tankkar
 
Advance Construction Technology
Advance Construction Technology Advance Construction Technology
Advance Construction Technology
GAURAV. H .TANDON
 
distress of concrete
distress of concretedistress of concrete
distress of concrete
kamariya keyur
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
Surat Construction PVT LTD
 
Retaining walls
Retaining walls Retaining walls
Retaining walls
Rohan Narvekar
 
Deck slab bridge
Deck slab bridgeDeck slab bridge
Deck slab bridge
Animesh Verma
 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed Concrete
Ravi Savani
 
Failures In Masonry Structures Lec 1
Failures In Masonry Structures Lec 1Failures In Masonry Structures Lec 1
Failures In Masonry Structures Lec 1
Teja Ande
 
Beam design
Beam designBeam design
Raft foundations
Raft foundationsRaft foundations
Raft foundations
hatim ahmed
 
High rise building construction
High rise building constructionHigh rise building construction
High rise building construction
Construction Tech. and Mgmt., VNIT Nagpur
 
Structural analysis and design of multi storey ppt
Structural analysis and design of multi storey pptStructural analysis and design of multi storey ppt
Structural analysis and design of multi storey ppt
SHIVUNAIKA B
 
Jacketing
JacketingJacketing
Jacketing
SHAIKH ARSHAD
 
Retaining wall
 Retaining wall  Retaining wall
Retaining wall
kamariya keyur
 
Non destructive test (ndt) on concrete msu
Non destructive test (ndt) on concrete msuNon destructive test (ndt) on concrete msu
Non destructive test (ndt) on concrete msu
Sagar Vekariya
 
Bridge components
Bridge componentsBridge components
Bridge components
AratiSavant
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
Udisha15
 
Presentation on Slab, Beam & Column
Presentation on Slab, Beam & ColumnPresentation on Slab, Beam & Column
Presentation on Slab, Beam & Column
মু সা
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGE
srinivas cnu
 

What's hot (20)

Post Tension
Post TensionPost Tension
Post Tension
 
1.1 box jacking
1.1 box jacking1.1 box jacking
1.1 box jacking
 
Advance Construction Technology
Advance Construction Technology Advance Construction Technology
Advance Construction Technology
 
distress of concrete
distress of concretedistress of concrete
distress of concrete
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
 
Retaining walls
Retaining walls Retaining walls
Retaining walls
 
Deck slab bridge
Deck slab bridgeDeck slab bridge
Deck slab bridge
 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed Concrete
 
Failures In Masonry Structures Lec 1
Failures In Masonry Structures Lec 1Failures In Masonry Structures Lec 1
Failures In Masonry Structures Lec 1
 
Beam design
Beam designBeam design
Beam design
 
Raft foundations
Raft foundationsRaft foundations
Raft foundations
 
High rise building construction
High rise building constructionHigh rise building construction
High rise building construction
 
Structural analysis and design of multi storey ppt
Structural analysis and design of multi storey pptStructural analysis and design of multi storey ppt
Structural analysis and design of multi storey ppt
 
Jacketing
JacketingJacketing
Jacketing
 
Retaining wall
 Retaining wall  Retaining wall
Retaining wall
 
Non destructive test (ndt) on concrete msu
Non destructive test (ndt) on concrete msuNon destructive test (ndt) on concrete msu
Non destructive test (ndt) on concrete msu
 
Bridge components
Bridge componentsBridge components
Bridge components
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Presentation on Slab, Beam & Column
Presentation on Slab, Beam & ColumnPresentation on Slab, Beam & Column
Presentation on Slab, Beam & Column
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGE
 

Viewers also liked

Gyproc
GyprocGyproc
Final Construction Documents
Final Construction DocumentsFinal Construction Documents
Final Construction Documents
Kaitlin Mergler
 
Post-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for ContractorsPost-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for Contractors
AMSYSCO Inc.
 
Partition walls
Partition wallsPartition walls
Partition walls
Harpreet Oberoi
 
Partition wall
Partition wallPartition wall
Partition wall
Kris Kiran
 
Partitions
PartitionsPartitions
Partitions
Dipesh Patel
 
prestressed concrete
prestressed concreteprestressed concrete
prestressed concrete
Parag Pal
 

Viewers also liked (7)

Gyproc
GyprocGyproc
Gyproc
 
Final Construction Documents
Final Construction DocumentsFinal Construction Documents
Final Construction Documents
 
Post-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for ContractorsPost-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for Contractors
 
Partition walls
Partition wallsPartition walls
Partition walls
 
Partition wall
Partition wallPartition wall
Partition wall
 
Partitions
PartitionsPartitions
Partitions
 
prestressed concrete
prestressed concreteprestressed concrete
prestressed concrete
 

Similar to post tensioning slabs

Design of Composite Pressure Vessel
Design of Composite Pressure VesselDesign of Composite Pressure Vessel
Design of Composite Pressure Vessel
JJ Technical Solutions
 
350 kl overhead water intze tank design
350 kl overhead water intze tank design350 kl overhead water intze tank design
350 kl overhead water intze tank design
Harish Mahavar
 
Structural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowStructural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknow
Anchit Agrawal
 
Jury Presenatation.pptx
Jury Presenatation.pptxJury Presenatation.pptx
Jury Presenatation.pptx
AmokBajracharya2
 
Comparative Study on Flexural Strength of M20 Grade Beam with Lapping of Bars
Comparative Study on Flexural Strength of M20 Grade Beam with Lapping of BarsComparative Study on Flexural Strength of M20 Grade Beam with Lapping of Bars
Comparative Study on Flexural Strength of M20 Grade Beam with Lapping of Bars
IRJET Journal
 
Design of composite steel and concrete structures.pptx
Design of composite steel and concrete structures.pptxDesign of composite steel and concrete structures.pptx
Design of composite steel and concrete structures.pptx
SharpEyu
 
Design of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an AuditoriumDesign of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an Auditorium
IRJET Journal
 
IRJET- Design of the Support Structure for the Pipe Line System
IRJET- Design of the Support Structure for the Pipe Line SystemIRJET- Design of the Support Structure for the Pipe Line System
IRJET- Design of the Support Structure for the Pipe Line System
IRJET Journal
 
Prestressed pipes,tanks,poles
Prestressed pipes,tanks,polesPrestressed pipes,tanks,poles
Prestressed pipes,tanks,poles
PraveenKumar Shanmugam
 
Chap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdfChap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdf
AberaMamoJaleta
 
Construction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.pptConstruction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.ppt
bala506586
 
Important Technical Terms in Concrete Design
Important Technical Terms in Concrete DesignImportant Technical Terms in Concrete Design
Important Technical Terms in Concrete Design
Roshni Ramakrishnan
 
Structural Design
Structural DesignStructural Design
Structural Design
Vj NiroSh
 
bridge final ppt.pptx
bridge final ppt.pptxbridge final ppt.pptx
bridge final ppt.pptx
RajeshKumar25548
 
Qualification under hypothetical accident conditions during transport-R Pal
Qualification under hypothetical accident conditions during transport-R PalQualification under hypothetical accident conditions during transport-R Pal
Qualification under hypothetical accident conditions during transport-R Pal
ProSIM R & D Pvt. Ltd.
 
Experimental Study on Soil Nailing.pptx
Experimental Study on Soil Nailing.pptxExperimental Study on Soil Nailing.pptx
Experimental Study on Soil Nailing.pptx
Samirsinh Parmar
 
New Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxNew Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptx
RajeshKumar25548
 
fiber feinforced concrete.pptx
fiber feinforced concrete.pptxfiber feinforced concrete.pptx
fiber feinforced concrete.pptx
AnujKumarShukla8
 
Experimental behaviour and analysis of stress in rigid pavement
Experimental behaviour and analysis of stress in rigid pavementExperimental behaviour and analysis of stress in rigid pavement
Experimental behaviour and analysis of stress in rigid pavement
Vivek Loyola
 
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptxDESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
subhashini214160
 

Similar to post tensioning slabs (20)

Design of Composite Pressure Vessel
Design of Composite Pressure VesselDesign of Composite Pressure Vessel
Design of Composite Pressure Vessel
 
350 kl overhead water intze tank design
350 kl overhead water intze tank design350 kl overhead water intze tank design
350 kl overhead water intze tank design
 
Structural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowStructural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknow
 
Jury Presenatation.pptx
Jury Presenatation.pptxJury Presenatation.pptx
Jury Presenatation.pptx
 
Comparative Study on Flexural Strength of M20 Grade Beam with Lapping of Bars
Comparative Study on Flexural Strength of M20 Grade Beam with Lapping of BarsComparative Study on Flexural Strength of M20 Grade Beam with Lapping of Bars
Comparative Study on Flexural Strength of M20 Grade Beam with Lapping of Bars
 
Design of composite steel and concrete structures.pptx
Design of composite steel and concrete structures.pptxDesign of composite steel and concrete structures.pptx
Design of composite steel and concrete structures.pptx
 
Design of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an AuditoriumDesign of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an Auditorium
 
IRJET- Design of the Support Structure for the Pipe Line System
IRJET- Design of the Support Structure for the Pipe Line SystemIRJET- Design of the Support Structure for the Pipe Line System
IRJET- Design of the Support Structure for the Pipe Line System
 
Prestressed pipes,tanks,poles
Prestressed pipes,tanks,polesPrestressed pipes,tanks,poles
Prestressed pipes,tanks,poles
 
Chap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdfChap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdf
 
Construction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.pptConstruction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.ppt
 
Important Technical Terms in Concrete Design
Important Technical Terms in Concrete DesignImportant Technical Terms in Concrete Design
Important Technical Terms in Concrete Design
 
Structural Design
Structural DesignStructural Design
Structural Design
 
bridge final ppt.pptx
bridge final ppt.pptxbridge final ppt.pptx
bridge final ppt.pptx
 
Qualification under hypothetical accident conditions during transport-R Pal
Qualification under hypothetical accident conditions during transport-R PalQualification under hypothetical accident conditions during transport-R Pal
Qualification under hypothetical accident conditions during transport-R Pal
 
Experimental Study on Soil Nailing.pptx
Experimental Study on Soil Nailing.pptxExperimental Study on Soil Nailing.pptx
Experimental Study on Soil Nailing.pptx
 
New Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxNew Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptx
 
fiber feinforced concrete.pptx
fiber feinforced concrete.pptxfiber feinforced concrete.pptx
fiber feinforced concrete.pptx
 
Experimental behaviour and analysis of stress in rigid pavement
Experimental behaviour and analysis of stress in rigid pavementExperimental behaviour and analysis of stress in rigid pavement
Experimental behaviour and analysis of stress in rigid pavement
 
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptxDESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
 

Recently uploaded

Covid Management System Project Report.pdf
Covid Management System Project Report.pdfCovid Management System Project Report.pdf
Covid Management System Project Report.pdf
Kamal Acharya
 
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
DharmaBanothu
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
felixwold
 
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEERDELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
EMERSON EDUARDO RODRIGUES
 
paper relate Chozhavendhan et al. 2020.pdf
paper relate Chozhavendhan et al. 2020.pdfpaper relate Chozhavendhan et al. 2020.pdf
paper relate Chozhavendhan et al. 2020.pdf
ShurooqTaib
 
CSP_Study - Notes (Paul McNeill) 2017.pdf
CSP_Study - Notes (Paul McNeill) 2017.pdfCSP_Study - Notes (Paul McNeill) 2017.pdf
CSP_Study - Notes (Paul McNeill) 2017.pdf
Ismail Sultan
 
Sri Guru Hargobind Ji - Bandi Chor Guru.pdf
Sri Guru Hargobind Ji - Bandi Chor Guru.pdfSri Guru Hargobind Ji - Bandi Chor Guru.pdf
Sri Guru Hargobind Ji - Bandi Chor Guru.pdf
Balvir Singh
 
This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...
DharmaBanothu
 
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call GirlCall Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
sapna sharmap11
 
Technological Innovation Management And Entrepreneurship-1.pdf
Technological Innovation Management And Entrepreneurship-1.pdfTechnological Innovation Management And Entrepreneurship-1.pdf
Technological Innovation Management And Entrepreneurship-1.pdf
tanujaharish2
 
Online train ticket booking system project.pdf
Online train ticket booking system project.pdfOnline train ticket booking system project.pdf
Online train ticket booking system project.pdf
Kamal Acharya
 
Data Communication and Computer Networks Management System Project Report.pdf
Data Communication and Computer Networks Management System Project Report.pdfData Communication and Computer Networks Management System Project Report.pdf
Data Communication and Computer Networks Management System Project Report.pdf
Kamal Acharya
 
Lateral load-resisting systems in buildings.pptx
Lateral load-resisting systems in buildings.pptxLateral load-resisting systems in buildings.pptx
Lateral load-resisting systems in buildings.pptx
DebendraDevKhanal1
 
INTRODUCTION TO ARTIFICIAL INTELLIGENCE BASIC
INTRODUCTION TO ARTIFICIAL INTELLIGENCE BASICINTRODUCTION TO ARTIFICIAL INTELLIGENCE BASIC
INTRODUCTION TO ARTIFICIAL INTELLIGENCE BASIC
GOKULKANNANMMECLECTC
 
Introduction to Artificial Intelligence.
Introduction to Artificial Intelligence.Introduction to Artificial Intelligence.
Introduction to Artificial Intelligence.
supriyaDicholkar1
 
Butterfly Valves Manufacturer (LBF Series).pdf
Butterfly Valves Manufacturer (LBF Series).pdfButterfly Valves Manufacturer (LBF Series).pdf
Butterfly Valves Manufacturer (LBF Series).pdf
Lubi Valves
 
Literature review for prompt engineering of ChatGPT.pptx
Literature review for prompt engineering of ChatGPT.pptxLiterature review for prompt engineering of ChatGPT.pptx
Literature review for prompt engineering of ChatGPT.pptx
LokerXu2
 
Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine
 
Cricket management system ptoject report.pdf
Cricket management system ptoject report.pdfCricket management system ptoject report.pdf
Cricket management system ptoject report.pdf
Kamal Acharya
 
Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)
Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)
Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)
Tsuyoshi Horigome
 

Recently uploaded (20)

Covid Management System Project Report.pdf
Covid Management System Project Report.pdfCovid Management System Project Report.pdf
Covid Management System Project Report.pdf
 
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
 
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEERDELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
 
paper relate Chozhavendhan et al. 2020.pdf
paper relate Chozhavendhan et al. 2020.pdfpaper relate Chozhavendhan et al. 2020.pdf
paper relate Chozhavendhan et al. 2020.pdf
 
CSP_Study - Notes (Paul McNeill) 2017.pdf
CSP_Study - Notes (Paul McNeill) 2017.pdfCSP_Study - Notes (Paul McNeill) 2017.pdf
CSP_Study - Notes (Paul McNeill) 2017.pdf
 
Sri Guru Hargobind Ji - Bandi Chor Guru.pdf
Sri Guru Hargobind Ji - Bandi Chor Guru.pdfSri Guru Hargobind Ji - Bandi Chor Guru.pdf
Sri Guru Hargobind Ji - Bandi Chor Guru.pdf
 
This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...
 
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call GirlCall Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
 
Technological Innovation Management And Entrepreneurship-1.pdf
Technological Innovation Management And Entrepreneurship-1.pdfTechnological Innovation Management And Entrepreneurship-1.pdf
Technological Innovation Management And Entrepreneurship-1.pdf
 
Online train ticket booking system project.pdf
Online train ticket booking system project.pdfOnline train ticket booking system project.pdf
Online train ticket booking system project.pdf
 
Data Communication and Computer Networks Management System Project Report.pdf
Data Communication and Computer Networks Management System Project Report.pdfData Communication and Computer Networks Management System Project Report.pdf
Data Communication and Computer Networks Management System Project Report.pdf
 
Lateral load-resisting systems in buildings.pptx
Lateral load-resisting systems in buildings.pptxLateral load-resisting systems in buildings.pptx
Lateral load-resisting systems in buildings.pptx
 
INTRODUCTION TO ARTIFICIAL INTELLIGENCE BASIC
INTRODUCTION TO ARTIFICIAL INTELLIGENCE BASICINTRODUCTION TO ARTIFICIAL INTELLIGENCE BASIC
INTRODUCTION TO ARTIFICIAL INTELLIGENCE BASIC
 
Introduction to Artificial Intelligence.
Introduction to Artificial Intelligence.Introduction to Artificial Intelligence.
Introduction to Artificial Intelligence.
 
Butterfly Valves Manufacturer (LBF Series).pdf
Butterfly Valves Manufacturer (LBF Series).pdfButterfly Valves Manufacturer (LBF Series).pdf
Butterfly Valves Manufacturer (LBF Series).pdf
 
Literature review for prompt engineering of ChatGPT.pptx
Literature review for prompt engineering of ChatGPT.pptxLiterature review for prompt engineering of ChatGPT.pptx
Literature review for prompt engineering of ChatGPT.pptx
 
Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024
 
Cricket management system ptoject report.pdf
Cricket management system ptoject report.pdfCricket management system ptoject report.pdf
Cricket management system ptoject report.pdf
 
Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)
Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)
Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)
 

post tensioning slabs

  • 1. Project on Design and construction of post tensioning slab PRESENTING BY:- CH .Gopichand (10631A0110) D.Nagender (10631A0120) J.Paramesh (10631A0126) N.Prudhviraj (10631A0129) S.Sathyanarayana(10631A0147) CIVIL ENGINEERING 4th YEAR SRI VENKATESWARA ENGINEERING COLLEGE INTERNAL GUIDE: Mrs.P.Jhansi
  • 2. Objectives The objective of the present report is  to summarize the experience available today in the field of post-tensioning in building construction and in particular to discuss the design and construction of post tensioned slab structures, especially post tensioned flat slabs*  A detailed explanation will be given of the checks to be carried out, the aspects to be considered in the design and the construction procedures and sequences of a post-tensioned slab. The execution of the design will be explained.
  • 3. Prestressed concrete  PRINCIPLE – Using high tensile strength steel alloys producing permanent pre- compression in areas subjected to Tension.  A portion of tensile stress is counteracted thereby reducing the cross-sectional area of the steel reinforcement .  METHODS :- a) Pretensioning b)Post-tensioning  PRETENSIONING :- Placing of concrete around reinforcing tendons that have been stressed to the desired degree.  POST-TENSIONING :- Reinforcing tendons are stretched by jacks whilst keeping them in serted in voids left pre-hand during curing of concrete.  These spaces are then pumped full of grout to bond steel tightly to the concrete. STEEL BARS BEING STRETCHED BY JACKS
  • 5. Introduction Pre-tensioning • Steel tendons are stressed before the concrete is placed at a precast plant remote from the construction site.
  • 6. Introduction Post-tensioning • Steel tendon are stressed after the concrete has been placed and gained sufficient strength at the construction site.
  • 7. Introduction Post-tensioning Systems Un-bonded Post-tensioning System Bonded Post-tensioning Systems Single strand Multi strands flat duct Multi strands round duct Single strand
  • 8. Design of PT Slabs Flat Plate with Drop Panels Common geometries* • Two-way system • Suitable span: 12.2 m • Limiting criterion: Deflection • Rebar**: 2.94 kg/m2 • PT: 3.87 kg/m2 * for typical office/residential buildings using ACI/UBC requirements ** quantity assume no bottom reinforcement
  • 9.
  • 10. Materiel properties CONCRETE: Fc^28 → Compressive strength of concrete 28 days. Fcd → Design value for compressive strength on concrete. → 0.6 × fc^28 = 21 N/MM^2 PRE STRESSING STEEL: Ap → cross sectional area of pj steel 146 mm^2 Fpy →yield strength of PT steel 1570 N/MM^2 Fpu → characteristic strength of PT steel 1770 N/MM^2 PRE-TENSIONING STEEL: Ep → modulus of elasticity of pre stressing steel 1.95 × 10^5 N/MM^2 (very low relaxation (3%) Admissible stressing 0.75 fpu Reinforcing steel: Fsy →yield strength of reinforcing steel is 460 N/MM^2 Long-term losses (assumed to be 10%)
  • 11. Details of building Type of structure: commercial building - Loadings: Live load p = 2.5 kN/m2 Floor finishes gB = 1.OkN/m2 Walls g w = 1.5 kN/m2 q = 5.0 kN/m2
  • 13. Design Determination of slab thickness: Assumption l/h = 35 Self wt of slab g = yc × h L → length of span 8.4 h → 0.24 mt h → thickness of slab. Yc → volumetric wt.of concrete →2.5 KN/M^3 → g=6KN/M^3 → q =5 KN/M^3 → (g+q)/g) = 6+5/6 = 1.83 ((g+q) –service load g→ self wt )
  • 14. (l/h as a function of (g+q/g)) → For a value of 1.83 on y- axis l/h is coming to 36 → 0.233 which is approximately (0.24)
  • 15. Determination of prestress µ → it is transfer component from pre stressing / unit length (g+q/g) → 1.83 based on previous caluculation
  • 16. Pre stress in longitudinal direction → for 1.83 the u/g value in is 1.39 → u = 8.34 KN/m^2 K → woober’s coefficient =(0.24×10^3)/(8.4^2×25) = 0.136 →h = 0.24 →length of slab = 8.4 →yc =25 £c =concrete tensile stress=1000 Pre tensioning force → P = 4×l^2/8×hp →sag of tendon parabola Hp →0.178mt (p=8.34× 8.4^2/8×0.178) P =413 KN/M P =7.8 × 413 for a width of 78 mt P = 3221 KN/strand Pl → pre tensioning force per strand Pl → Ap × fpu × 0.7 ×10^-3 Ap =416 mm^2 Fpu = 1770 N/mm^2 Pl = 181 KN
  • 17. strands No.of strands = p/ pl =413/pl =17.8 =͠ 18 18 strands of dia 15mm on 78 mt width. For 7.4 mt width =7.4/7.8 ×17.8 =16.88 17 mono strands of dia 15 mm of 7.4 mt width. On 6.6 mt width = 6.6/7.8 ×17.8 =15.1 16 mono strands of dia 15 mm of 6.6 mt width. For 2.4 mt width =2.4/7.8 ×17.8 =5.5 6 mono strand of dia of 15mm on 2.4 mt width Transverse direction: g+q/g = 1.83 k = 0.24 × 1000/ 7.8 m^2×25 k = 0.158 on design chart 2 for a k value of 0.158 & (g+q/g) value of 1.83 the value of u/g is found be 1.41 → u= 8.46 kn/m^2 P = (u×l^2/8×hp ) →8.46 ×7.8^2/( 8× 0.167) P = 3.85 kn/m On 8.4 mt width p=8.4×385 P =3234 kn Pc 181 kn No. Of strands Np = p/pl =3234/181 = 17.9 18 mono strands of dia 15mm on 8.4 mt width On 7.2 mt width np = 7.2/8.4× 7.9 = 15.3 16 mono strands of dia 15mm on 7.2 mt width.
  • 18. Execution Materials & Equipment Anchorage Markings Laying of Tendon Concrete pouring Pre stressing grouting
  • 19. MATERIALS AND EQUIPMENT a) FORMWORK b) CONCRETE c) STRANDS d) TENDONS e) DUCTS f) ANCHORAGES g) WEDGES
  • 26. Concrete pourig  Mix design of M35  Grade of Concrete : M35  Characteristic Strength (Fck) : 35 Mpa  Standard Deviation : 1.91 Mpa*  Target Mean Strength : T.M.S.= Fck +1.65 x S.D.  (from I.S 456-2000) = 35+ 1.65×1.91  = 38.15 Mpa  Test Data For Material:  Aggregate Type : Crushed  Specific Gravity Cement : 3.15  Coarse Aggregate : 2.67  Fine Aggregate : 2.62  Water Absorption  Coarse Aggregate : 0.5%  Fine Aggregate : 1.0 %
  • 28. Mix Design:  Take Sand content as percentage of total aggregates = 36%  Select Water Cement Ratio = 0.43 for concrete grade M35  Select Water Content = 172 Kg  (From IS: 10262 for 20 mm nominal size of aggregates Maximum Water Content = 186 Kg/m 3 ) Hence, Cement Content= 172 / 0.43 = 400 Kg /m 3  Formula for Mix Proportion of Fine and Coarse Aggregate:  1000(1-a 0 )= {(Cement Content / Sp. Gr. Of Cement) + Water Content +(F a / Sp. Gr.* P f )} 1000(1- a 0 )= {(Cement Content / Sp. Gr. Of Cement) + Water Content +C a / Sp. Gr.* Pc )}  Where  C a = Coarse Aggregate Content  F a = Fine Aggregate Content  P f = Sand Content as percentage of total Aggregates = 0.36  P c = Coarse Aggregate Content as percentage of total Aggregates.  = 0.64  a 0 = Percentage air content in concrete (As per IS :10262 for 20 mm nominal size of  aggregates air content is 2 %) = 0.02  Hence, 1000(1-0.02) = {(400 /3.15) + 172 +(F a / 2.62 x 0.36)}  Fa = 642 Kg/ Cum  As the sand is of Zone II no adjustment is required for sand.  Sand Content = 642 Kg/ Cum  1000(1-0.02)= {(400 /3.15) + 172 +(C a / 2.67 x 0.64)}  Hence, Ca = 1165 Kg/ Cum
  • 29. Prestressing jack  For prestressing, mono strand stressing jack is used and pressure is applied in a controlled way with the help of prestressing power pack. Initially, a gradual pressure of about 5 kg/cm 2 is applied.  anchorage bursting when prestressing is applied and also to check anchorage slip. The perimeter of the rod is then marked with paint and then once the anchorage is known to be stable, the pressure is increasing up to 430 kg/cm 2 .
  • 31. Grouting  Grouting is done with the help of grout pump. The mixture of cement, water and admixtures must be done under a strict mixing time and velocity control and must not contain lumps nor any air bubbles during injection into the ducts
  • 32. EQUIPMENTS :-  T6Z-08 Air Powered Grout Pump  Pumps cement grout only, no sand. 32 Gallon Mixing Tank. Mixes up to 2 sacks of material at once and allows for grout to be pumped during mixing or mixed without pumping. Approximate size 50" long 30.5" high 52" wide Weight 560 lbs. Production Rate 8 gallons per minute at 150 psi
  • 33. ADVANTAGES OF POST-TENSIONING • Longer clear spans • Thinner slabs • Lesser floor-to-floor heights • Shorter building height • Lesser weight • Improved seismic performance • Faster construction cycle
  • 34. Conclusions  Prestressed concrete offers great technical advantages in comparison with other forms of construction such as reinforced concrete and steel. They possess improved resistance to shearing forces, due to the effect of compressive prestress, which reduces the principles tensile stress  Prestressing of concrete helps in improving the ability of the material for energy absorption under impact loads. The economy of prestressed concrete is well established for long span structures. Standardized precast bridge beams between 10m and 30 m long and precast prestressed piles have proved to be more economical than steel and reinforced concrete.  Due to utilization of concrete in the tension zone, an extra saving of 15 to 30% in concrete is possible in comparison with reinforced concrete
  翻译: