尊敬的 微信汇率:1円 ≈ 0.046239 元 支付宝汇率:1円 ≈ 0.04633元 [退出登录]
SlideShare a Scribd company logo
BY : AADIL ANSAR
ROLL NUMBER : 14H11A0101
DEPARTMENT OF CIVIL ENGINEERING
AL-HABEEB COLLEGE OF ENGINEERING & TECHNOLOGY
Estimating is the technique of
calculating or Computing the
various quantities and the
expected Expenditure to be
incurred on a particular work or
project.
In case the funds available are less than the
estimated cost the work is done in part or by
reducing it or specifications are altered, the
following requirement are necessary for
preparing an estimate.
• Drawings like plan, elevation and sections
of important points.
• Detailed specifications about workmenship
& properties of materials etc.
• Standard schedule of rates of the current
year.
REQUIREMENTS OF ESTIMATION AND COSTING
• Estimate gives an idea of the cost of the work and
hence its feasibility can be determined i.e. whether
the project could be taken up with in the funds
available or not.
• Estimate gives an idea of time required for the
completion of the work.
• Estimate is required to invite the tenders and
Quotations and to arrange contract.
• Estimate is also required to control the expenditure
during the execution of work.
• Estimate decides whether the proposed plan
matches the funds available or not
PROCEDURE OF ESTIMATING
Estimating involves the following
operations
• Preparing detailed Estimate.
• Calculating the rate of each unit of
work
• Preparing abstract of estimate
DATA REQUIRED TO PREPARE AN ESTIMATE
• Drawings i.e. plans, elevations, sections
etc.
• Specifications.
• Rates
TYPES OF ESTIMATES
• Approximate estimate: It is also known as rough
estimate and it is not accurate. It is useful for
preliminary study of project to finalize the budget .
• Detailed estimate: It is accurate estimate, in which
each item of work is worked out separately in the
prescribed format
• Abstract estimate: It gives an accurate cost of the
project .The cost of each item is calculated with the
quantity in detailed estimate and rate arrived at site
in the prescribed format.
Details of measurements form
ABSTRACT OF ESTIMATE FORM
METHODS OF PREPARATION OF APPROXIMATE
ESTIMATE
Following are the methods used for preparation of
approximate estimate.
• Plinth area method
• Cubical content method
METHODS OF TAKING OUT QUANTITIES
The quantities like earth work, foundation
concrete, brickwork in plinth and super
structure etc., can be workout by any of
following two methods:
• Long wall - short wall method
• Centre line method.
LONGWALL-SHORTWALL METHOD
In this method, the wall along the length of room is
considered to be long wall while the wall
perpendicular to long wall is said to be short wall. To
get the length of long wall or short wall, calculate first
the center line lengths of individual walls. Then the
length of long wall, (out to out) may be calculated after
adding half breadth at each end to its center line
length. Thus the length of short wall Measured into in
and may be found by deducting half breadth from its
center line length at each end. The length of long wall
usually decreases from earth work to brick work in
super structure while the short wall increases. These
lengths are multiplied by breadth and depth to get
quantities.
CENTER LINE METHOD
This method is suitable for walls of similar cross
sections. Here the total center line length is
multiplied by breadth and depth of respective
item to get the total quantity at a time.
When cross walls or partitions or verandah
walls join with main all, the center line length
gets reduced by half of breadth for each
junction. Such junction or joints are studied
carefully while calculating total center line
length. The estimates prepared by this method
are most accurate and quick.
UNITS OF MEASUREMENTS
The units of measurements are mainly categorized for their nature,
shape and size and for making payments to the contractor and also. The
principle of units of measurements normally consists the following:
• Single units work like doors, windows, trusses etc., is expressed in
numbers.
• Works consists linear measurements involve length like cornice,
fencing, hand rail, bands of specified width etc., are expressed in
running meters (RM).
• Works consists areal surface measurements involve area like
plastering, white washing, partitions of specified thickness etc., and
are expressed in square meters (m2).
• Works consists cubical contents which involve volume like earth
work, cement concrete, Masonry etc are expressed in Cubic meters.
RULES FOR MEASUREMENT
1. Measurement shall be made for finished
item of work and description of each item
shall include materials, transport, labor,
fabrication tools and plant and all types of
overheads for finishing the work in
required shape, size and specification.
2. In booking, the order shall be in sequence
of length, breadth and height
or thickness
3. All works shall be measured subject to the following
tolerances.
• linear measurement shall be measured to the nearest
0.01m.
• Areas shall be measured to the nearest 0.01 sq. m.
• Cubic contents shall be worked-out to the nearest
0.01 cum.
4. Same type of work under different conditions and
nature shall be measured separately under separate
items.
5. The bill of quantities shall fully describe the materials,
proportions, workmanships and accurately represent
the work to be executed.
Generally all the Civil Engineering
projects like roads, railways, earth
dams , canals, buildings etc
involves under earth work. This
work may be either earth
excavation or earth filling or Some
times both will get according to the
desired shape and level.
• The volume of the earth work is
calculated from length, breadth and
depth of excavation of filling.
• Earth work in filling is called as
“earth work in embankment” and
earth work in excavation as “earth
work in cutting”.
Excavation of Building
Embankment for canal
LEAD : It is the average horizontal
distance between the center of the
excavation to the center of the
deposition.
LIFT : It is the average height
through which the earth has to be
lifted from source to the place of
spreading.
• Normally earthwork is
estimated for 30 meter lead
for distance and 1.5 meter lift
for height or depth and this
distance of 30 meter and the
height of 30 meter are known
as normal lead and lift .
Calculation of Quantity of Earthwork
The quantity of earthwork may be calculated by
various methods
1. Mid sectional area Method
Volume of Earthwork= Area of Mid section *
distance between sections
2. Mean sectional area Method
Volume of Earthwork= Mean cross sectional area
* Distance between them
3. Trapezoidal Rule
Volume of Earthwork=
L(A1/2 + A2 +A3 + ……+A(n-1) + A(n)/2)
where L= length of equal intervals between section ,
A1,A2,A3 ….. A(n) = area of cross sections along the longitudinal sections
4. Prismoidal Formula
Volume of Earthwork =
L/3(A1+A(n))+4(A2+A4+…+A(n-1))+
2(A3+A5+….A(n-2))
where L = length between the sections
A1= Area of cross section at one end
A(n)= Area of cross section at the
other end
A2,A3,A4= Areas of cross sections of
intermediate sections.
QUANTITY OF STEEL IN R.C.C.
ELEMENTS
• Reinforced cement concrete work is usually estimated
under two items. the concrete work including centering
and shuttering and binding of steel bar in position is taken
under one items under one items in cu m(cu ft.)
• the quantity of steel being small no deduction is made for
steel from the volume of concrete. Binding wire is not taken
separately but include in item of RCC work.
• Centering and shuttering may also be taken under a
separate item is sq. m(sq. ft.).Bending and binding of steel
may also be taken separately in quintal (cwt.).
• Steel reinforcement is calculated as per
actual requirement as laid in position
including overlaps, hooks, cranks etc. and is
determined from the detail drawings.
• If the detailed drawings are not available the
steel reinforcement may be calculated
approximately on the percentage basic of
concrete . The density of steel may be taken
as 78.5 quintal per cu m or 7.85 grams per cu
m.
• The percentage of steel reinforcement
depends on the design of structure . In
absence od detailed design the percentage
for steel concrete may be taken
approximately as given below:-
a) lintel , slabs etc. ...... 0.7 to 1%
b) beams ...... 1 to 2%
c) columns ...... 1 to 5%
d) foundation ...... 0.5 to 0.8%
• For small span and light load less steel is
required and for bigger span and heavier
load greater amount of steel is required.
• In RCC work the end or side covers for steel bar
may be taken as 40 mm to 50 mm(1.5" to 2") and the
bottom and top covers may be taken as 12 mm to 20
mm(0.5" to 0.75") for slab and 25 mm to 50 mm(1" to
2") for beams.
• The length of one hook may be taken as 9 dia. of
bar and the total length of straight bar hooked at
both ends may be taken as L+18 dia.
• For 45° cranked or bent up bar the additional length for one
bent up is equal difference in length of hypotenuse and
base
=d/sin45°-d
=d(1/0.707-1)
=d(1.42-1)
=0.42d
where 'd' is the vertical distance between the center of
upper and lower arms of bent up bars
= Total length of beam or slab minus of top and
bottom cover minus dia of bar.
• For 30° cranked or bent up bar inclined length
of crank
=d/sin30°
=2d
horizontal length of crank=d/tan30°
=1.73d
Schedule of bars
• The schedule of bars is list of reinforcement
bars in a tabular form giving the particulars of
bars, shape of bending with sketches, length of
each, total length and total weight.
• For each type of RCC work a schedule of bars
is usually prepared.
• From the schedule of bars the requirement of
different sizes and lengths of bars may be
known , and may be arranged and bent-up
during the time of construction.
The determination of rate per unit of a
particular item of the work, cost of the
quantity of material, the cost of labours
and miscellaneous petty expanses
require for its compilation is known as
Analysis of rates .
• The reasonable profit usually 10% for the
contractor is also included in analysis of rate.
• Rate of the material are usually taken as the
rate delivered at the site of the work and
include the cost at origin , cost of transport
and taxes.
• If the material are to be carried from a
distant place more than 8 km then cost of
the transport is also added.
• Rate of the material and the labour vary
from place to place and therefor, the rate of
the different items of the work also vary
from place to place.
Purpose of Analysis of Rate
• The quantities of material required
and their cost should be known.
• The number of different categories of
labours required.
• The capacity of doing work per
labours and their wages per day
should be known.
Factor depends the rate of a particular item of
work
• Specification of work and materials, quantity of a
material, proportion of mortor method of
constructional operation.
• Quantities of materials and their number of
different type of labours and their rates.
• Location of the site of work and its distance from
the source of material and the rate of transport
and availability of water.
• Profit and miscellaneous and overhead expanses
of the contractor.
Standard Data Book
It is a book in which the quantity of a material
and labour required per unit of various finished
items of work has been standardized.
Standard Schedule of Rate
It is a book in which the rates of all the material
at source, the wages of the labour, conveyance
charge of material where fixed by the competent
engineering authority for each year for various
government department.
Rates of Materials
• 1st class bricks = Rs 4500 per 1000 Nos.
• 2nd class bricks = Rs 4000 per 1000 Nos.
• Brick Ballast = Rs 800 per cum
• Coarse sand = Rs 800 per cum
• Cement 50 kg bag = Rs 350 per bag
• Twisted bars = Rs 5000 per Quintal
• Bitumen = Rs 10 per kg
Rates of Labours
• Mason = Rs 450 per day
• Plaster = Rs 400 per day
• Carpenter = Rs 400 per day
• Bhishti = Rs 250 per day
• Mazdoor = Rs 250 per day
• Painter = Rs 300 per day
Labour required for different work
• Earth work in excavation: Mazdoor = 33
(% cum) Mason = 1.5
• Earth work in Filling : Mazdoor = 18
(% cum) Mason = 0.5
• Cement concrete : Mazdoor = 15
in foundation Mason =1.5
Bhishti = 2
• Plastering work ( 100 sqm) : Mazdoor = 10
Mason = 10
Bhishti = 2
• Distempering/painting/
white washing ( 100 sqm) : Mazdoor = 5
Painter = 4
• RCC (10 cum) : Mazdoor = 40
Mason = 2.5
Bhishti = 5
Blacksmith = 4
Carpenter = 4
Estimating serves a number of purposes in the
construction process including preparation of
bids and cost control. The role of the estimator
includes preparing conceptual estimates,
preliminary estimates, pre-bid estimates, post
bid estimates, cost control, final project cost,
cost on the operating construction period.
As the works gets organized, smaller
contractors can work on the project at lesser
rate.
THANK YOU!!!

More Related Content

What's hot

Types of estimates
Types of estimatesTypes of estimates
Types of estimates
Simarpreet Singh
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
sooricivil
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
srinivas2036
 
Valuation part of Building
Valuation part of Building Valuation part of Building
Valuation part of Building
RAMPRASAD KUMAWAT
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
Aravind Samala
 
Estimation
EstimationEstimation
Estimation
Waqas Aslam
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
Nikhil Kumar
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
Vijay325
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of Rates
Raj Shah
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
Manit Agarwal
 
Long wall and short wall method 1
Long wall and short wall method 1Long wall and short wall method 1
Long wall and short wall method 1
Saiyyed Akbar
 
Valuation
ValuationValuation
Valuation
Aditya Mistry
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
Ar.Vijay Kumar
 
Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
Aglaia Connect
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
Aishwarya Deopujari
 
Design of rcc structures
Design of rcc structuresDesign of rcc structures
Design of rcc structures
R VIJAYAKUMAR
 
BUILDING ESTIMATION (Details Estimate For G+2 Storied Building presentation ...
BUILDING ESTIMATION (Details Estimate For G+2  Storied Building presentation ...BUILDING ESTIMATION (Details Estimate For G+2  Storied Building presentation ...
BUILDING ESTIMATION (Details Estimate For G+2 Storied Building presentation ...
Manoranjan Roy
 
Specifications of buildings
Specifications of buildingsSpecifications of buildings
Specifications of buildings
Simarpreet Singh
 
Pile load test
Pile load testPile load test
Pile load test
Naman Kantesaria
 
Foundation types
Foundation typesFoundation types
Foundation types
Ashwini Ingale
 

What's hot (20)

Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Valuation part of Building
Valuation part of Building Valuation part of Building
Valuation part of Building
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Estimation
EstimationEstimation
Estimation
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of Rates
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
Long wall and short wall method 1
Long wall and short wall method 1Long wall and short wall method 1
Long wall and short wall method 1
 
Valuation
ValuationValuation
Valuation
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
 
Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
 
Design of rcc structures
Design of rcc structuresDesign of rcc structures
Design of rcc structures
 
BUILDING ESTIMATION (Details Estimate For G+2 Storied Building presentation ...
BUILDING ESTIMATION (Details Estimate For G+2  Storied Building presentation ...BUILDING ESTIMATION (Details Estimate For G+2  Storied Building presentation ...
BUILDING ESTIMATION (Details Estimate For G+2 Storied Building presentation ...
 
Specifications of buildings
Specifications of buildingsSpecifications of buildings
Specifications of buildings
 
Pile load test
Pile load testPile load test
Pile load test
 
Foundation types
Foundation typesFoundation types
Foundation types
 

Similar to Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering

Estimation Costing and Valuation Unit 1
Estimation Costing and Valuation Unit 1Estimation Costing and Valuation Unit 1
Estimation Costing and Valuation Unit 1
Padmasinh Patil
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
lckr117
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
Padmasinh Patil
 
Seminar
SeminarSeminar
Lec.3 General rules in quantitative survey. Quantity measuring. Rate analysis
Lec.3  General rules in quantitative survey. Quantity measuring. Rate analysisLec.3  General rules in quantitative survey. Quantity measuring. Rate analysis
Lec.3 General rules in quantitative survey. Quantity measuring. Rate analysis
Muthanna Abbu
 
ESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdf
suchitamantry2002
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
TauheedKhan45
 
Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6
Padmasinh Patil
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptx
NSHYAMANANDASINGH
 
INTERNSHIP (5).pptx
 INTERNSHIP (5).pptx INTERNSHIP (5).pptx
INTERNSHIP (5).pptx
kartik395517
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
DhavalMithaiwala
 
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
AMIT PAYAL
 
Estimation & costing guide
Estimation & costing guideEstimation & costing guide
Estimation & costing guide
Hiren Thakkar
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
gayu pandian
 
B.arch Estimation and Costing
B.arch  Estimation and CostingB.arch  Estimation and Costing
B.arch Estimation and Costing
SamreenFatima29
 
estimation,costingandvaluation.pdf
estimation,costingandvaluation.pdfestimation,costingandvaluation.pdf
estimation,costingandvaluation.pdf
Ictsol
 
Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)
hlksd
 
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdfECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
SURAJITDASBAURI
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for building
Himani762003
 
Estimation and costing of civil engineering works
Estimation and costing of civil engineering worksEstimation and costing of civil engineering works
Estimation and costing of civil engineering works
AnshulPal39
 

Similar to Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering (20)

Estimation Costing and Valuation Unit 1
Estimation Costing and Valuation Unit 1Estimation Costing and Valuation Unit 1
Estimation Costing and Valuation Unit 1
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
 
Seminar
SeminarSeminar
Seminar
 
Lec.3 General rules in quantitative survey. Quantity measuring. Rate analysis
Lec.3  General rules in quantitative survey. Quantity measuring. Rate analysisLec.3  General rules in quantitative survey. Quantity measuring. Rate analysis
Lec.3 General rules in quantitative survey. Quantity measuring. Rate analysis
 
ESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdf
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
 
Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptx
 
INTERNSHIP (5).pptx
 INTERNSHIP (5).pptx INTERNSHIP (5).pptx
INTERNSHIP (5).pptx
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
 
Estimation & costing guide
Estimation & costing guideEstimation & costing guide
Estimation & costing guide
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
B.arch Estimation and Costing
B.arch  Estimation and CostingB.arch  Estimation and Costing
B.arch Estimation and Costing
 
estimation,costingandvaluation.pdf
estimation,costingandvaluation.pdfestimation,costingandvaluation.pdf
estimation,costingandvaluation.pdf
 
Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)
 
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdfECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for building
 
Estimation and costing of civil engineering works
Estimation and costing of civil engineering worksEstimation and costing of civil engineering works
Estimation and costing of civil engineering works
 

Recently uploaded

🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
AK47
 
This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...
DharmaBanothu
 
BBOC407 Module 1.pptx Biology for Engineers
BBOC407  Module 1.pptx Biology for EngineersBBOC407  Module 1.pptx Biology for Engineers
BBOC407 Module 1.pptx Biology for Engineers
sathishkumars808912
 
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdfSELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
Pallavi Sharma
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
felixwold
 
🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...
🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...
🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...
aarusi sexy model
 
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort ServiceCuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
yakranividhrini
 
一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理
一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理
一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理
nonods
 
❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...
❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...
❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...
hotchicksescort
 
Literature review for prompt engineering of ChatGPT.pptx
Literature review for prompt engineering of ChatGPT.pptxLiterature review for prompt engineering of ChatGPT.pptx
Literature review for prompt engineering of ChatGPT.pptx
LokerXu2
 
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
simrangupta87541
 
🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...
🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...
🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...
AK47
 
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdfFUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
EMERSON EDUARDO RODRIGUES
 
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
sydezfe
 
TENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineeringTENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineering
SnehalChavan75
 
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
nainakaoornoida
 
🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...
🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...
🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...
adhaniomprakash
 
comptia-security-sy0-701-exam-objectives-(5-0).pdf
comptia-security-sy0-701-exam-objectives-(5-0).pdfcomptia-security-sy0-701-exam-objectives-(5-0).pdf
comptia-security-sy0-701-exam-objectives-(5-0).pdf
foxlyon
 
AN INTRODUCTION OF AI & SEARCHING TECHIQUES
AN INTRODUCTION OF AI & SEARCHING TECHIQUESAN INTRODUCTION OF AI & SEARCHING TECHIQUES
AN INTRODUCTION OF AI & SEARCHING TECHIQUES
drshikhapandey2022
 
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
DharmaBanothu
 

Recently uploaded (20)

🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
 
This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...
 
BBOC407 Module 1.pptx Biology for Engineers
BBOC407  Module 1.pptx Biology for EngineersBBOC407  Module 1.pptx Biology for Engineers
BBOC407 Module 1.pptx Biology for Engineers
 
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdfSELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
 
🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...
🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...
🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...
 
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort ServiceCuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
 
一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理
一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理
一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理
 
❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...
❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...
❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...
 
Literature review for prompt engineering of ChatGPT.pptx
Literature review for prompt engineering of ChatGPT.pptxLiterature review for prompt engineering of ChatGPT.pptx
Literature review for prompt engineering of ChatGPT.pptx
 
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
 
🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...
🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...
🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...
 
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdfFUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
FUNDAMENTALS OF MECHANICAL ENGINEERING.pdf
 
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
 
TENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineeringTENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineering
 
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
 
🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...
🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...
🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...
 
comptia-security-sy0-701-exam-objectives-(5-0).pdf
comptia-security-sy0-701-exam-objectives-(5-0).pdfcomptia-security-sy0-701-exam-objectives-(5-0).pdf
comptia-security-sy0-701-exam-objectives-(5-0).pdf
 
AN INTRODUCTION OF AI & SEARCHING TECHIQUES
AN INTRODUCTION OF AI & SEARCHING TECHIQUESAN INTRODUCTION OF AI & SEARCHING TECHIQUES
AN INTRODUCTION OF AI & SEARCHING TECHIQUES
 
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
 

Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering

  • 1. BY : AADIL ANSAR ROLL NUMBER : 14H11A0101 DEPARTMENT OF CIVIL ENGINEERING AL-HABEEB COLLEGE OF ENGINEERING & TECHNOLOGY
  • 2. Estimating is the technique of calculating or Computing the various quantities and the expected Expenditure to be incurred on a particular work or project.
  • 3. In case the funds available are less than the estimated cost the work is done in part or by reducing it or specifications are altered, the following requirement are necessary for preparing an estimate. • Drawings like plan, elevation and sections of important points. • Detailed specifications about workmenship & properties of materials etc. • Standard schedule of rates of the current year.
  • 4. REQUIREMENTS OF ESTIMATION AND COSTING • Estimate gives an idea of the cost of the work and hence its feasibility can be determined i.e. whether the project could be taken up with in the funds available or not. • Estimate gives an idea of time required for the completion of the work. • Estimate is required to invite the tenders and Quotations and to arrange contract. • Estimate is also required to control the expenditure during the execution of work. • Estimate decides whether the proposed plan matches the funds available or not
  • 5. PROCEDURE OF ESTIMATING Estimating involves the following operations • Preparing detailed Estimate. • Calculating the rate of each unit of work • Preparing abstract of estimate
  • 6. DATA REQUIRED TO PREPARE AN ESTIMATE • Drawings i.e. plans, elevations, sections etc. • Specifications. • Rates
  • 7. TYPES OF ESTIMATES • Approximate estimate: It is also known as rough estimate and it is not accurate. It is useful for preliminary study of project to finalize the budget . • Detailed estimate: It is accurate estimate, in which each item of work is worked out separately in the prescribed format • Abstract estimate: It gives an accurate cost of the project .The cost of each item is calculated with the quantity in detailed estimate and rate arrived at site in the prescribed format.
  • 10. METHODS OF PREPARATION OF APPROXIMATE ESTIMATE Following are the methods used for preparation of approximate estimate. • Plinth area method • Cubical content method
  • 11. METHODS OF TAKING OUT QUANTITIES The quantities like earth work, foundation concrete, brickwork in plinth and super structure etc., can be workout by any of following two methods: • Long wall - short wall method • Centre line method.
  • 12. LONGWALL-SHORTWALL METHOD In this method, the wall along the length of room is considered to be long wall while the wall perpendicular to long wall is said to be short wall. To get the length of long wall or short wall, calculate first the center line lengths of individual walls. Then the length of long wall, (out to out) may be calculated after adding half breadth at each end to its center line length. Thus the length of short wall Measured into in and may be found by deducting half breadth from its center line length at each end. The length of long wall usually decreases from earth work to brick work in super structure while the short wall increases. These lengths are multiplied by breadth and depth to get quantities.
  • 13. CENTER LINE METHOD This method is suitable for walls of similar cross sections. Here the total center line length is multiplied by breadth and depth of respective item to get the total quantity at a time. When cross walls or partitions or verandah walls join with main all, the center line length gets reduced by half of breadth for each junction. Such junction or joints are studied carefully while calculating total center line length. The estimates prepared by this method are most accurate and quick.
  • 14. UNITS OF MEASUREMENTS The units of measurements are mainly categorized for their nature, shape and size and for making payments to the contractor and also. The principle of units of measurements normally consists the following: • Single units work like doors, windows, trusses etc., is expressed in numbers. • Works consists linear measurements involve length like cornice, fencing, hand rail, bands of specified width etc., are expressed in running meters (RM). • Works consists areal surface measurements involve area like plastering, white washing, partitions of specified thickness etc., and are expressed in square meters (m2). • Works consists cubical contents which involve volume like earth work, cement concrete, Masonry etc are expressed in Cubic meters.
  • 15. RULES FOR MEASUREMENT 1. Measurement shall be made for finished item of work and description of each item shall include materials, transport, labor, fabrication tools and plant and all types of overheads for finishing the work in required shape, size and specification. 2. In booking, the order shall be in sequence of length, breadth and height or thickness
  • 16. 3. All works shall be measured subject to the following tolerances. • linear measurement shall be measured to the nearest 0.01m. • Areas shall be measured to the nearest 0.01 sq. m. • Cubic contents shall be worked-out to the nearest 0.01 cum. 4. Same type of work under different conditions and nature shall be measured separately under separate items. 5. The bill of quantities shall fully describe the materials, proportions, workmanships and accurately represent the work to be executed.
  • 17. Generally all the Civil Engineering projects like roads, railways, earth dams , canals, buildings etc involves under earth work. This work may be either earth excavation or earth filling or Some times both will get according to the desired shape and level.
  • 18. • The volume of the earth work is calculated from length, breadth and depth of excavation of filling. • Earth work in filling is called as “earth work in embankment” and earth work in excavation as “earth work in cutting”.
  • 21.
  • 22. LEAD : It is the average horizontal distance between the center of the excavation to the center of the deposition. LIFT : It is the average height through which the earth has to be lifted from source to the place of spreading.
  • 23. • Normally earthwork is estimated for 30 meter lead for distance and 1.5 meter lift for height or depth and this distance of 30 meter and the height of 30 meter are known as normal lead and lift .
  • 24. Calculation of Quantity of Earthwork The quantity of earthwork may be calculated by various methods 1. Mid sectional area Method Volume of Earthwork= Area of Mid section * distance between sections 2. Mean sectional area Method Volume of Earthwork= Mean cross sectional area * Distance between them 3. Trapezoidal Rule Volume of Earthwork= L(A1/2 + A2 +A3 + ……+A(n-1) + A(n)/2) where L= length of equal intervals between section , A1,A2,A3 ….. A(n) = area of cross sections along the longitudinal sections
  • 25. 4. Prismoidal Formula Volume of Earthwork = L/3(A1+A(n))+4(A2+A4+…+A(n-1))+ 2(A3+A5+….A(n-2)) where L = length between the sections A1= Area of cross section at one end A(n)= Area of cross section at the other end A2,A3,A4= Areas of cross sections of intermediate sections.
  • 26. QUANTITY OF STEEL IN R.C.C. ELEMENTS • Reinforced cement concrete work is usually estimated under two items. the concrete work including centering and shuttering and binding of steel bar in position is taken under one items under one items in cu m(cu ft.) • the quantity of steel being small no deduction is made for steel from the volume of concrete. Binding wire is not taken separately but include in item of RCC work. • Centering and shuttering may also be taken under a separate item is sq. m(sq. ft.).Bending and binding of steel may also be taken separately in quintal (cwt.).
  • 27. • Steel reinforcement is calculated as per actual requirement as laid in position including overlaps, hooks, cranks etc. and is determined from the detail drawings. • If the detailed drawings are not available the steel reinforcement may be calculated approximately on the percentage basic of concrete . The density of steel may be taken as 78.5 quintal per cu m or 7.85 grams per cu m.
  • 28. • The percentage of steel reinforcement depends on the design of structure . In absence od detailed design the percentage for steel concrete may be taken approximately as given below:- a) lintel , slabs etc. ...... 0.7 to 1% b) beams ...... 1 to 2% c) columns ...... 1 to 5% d) foundation ...... 0.5 to 0.8% • For small span and light load less steel is required and for bigger span and heavier load greater amount of steel is required.
  • 29. • In RCC work the end or side covers for steel bar may be taken as 40 mm to 50 mm(1.5" to 2") and the bottom and top covers may be taken as 12 mm to 20 mm(0.5" to 0.75") for slab and 25 mm to 50 mm(1" to 2") for beams. • The length of one hook may be taken as 9 dia. of bar and the total length of straight bar hooked at both ends may be taken as L+18 dia.
  • 30. • For 45° cranked or bent up bar the additional length for one bent up is equal difference in length of hypotenuse and base =d/sin45°-d =d(1/0.707-1) =d(1.42-1) =0.42d where 'd' is the vertical distance between the center of upper and lower arms of bent up bars = Total length of beam or slab minus of top and bottom cover minus dia of bar.
  • 31. • For 30° cranked or bent up bar inclined length of crank =d/sin30° =2d horizontal length of crank=d/tan30° =1.73d
  • 32. Schedule of bars • The schedule of bars is list of reinforcement bars in a tabular form giving the particulars of bars, shape of bending with sketches, length of each, total length and total weight. • For each type of RCC work a schedule of bars is usually prepared. • From the schedule of bars the requirement of different sizes and lengths of bars may be known , and may be arranged and bent-up during the time of construction.
  • 33.
  • 34. The determination of rate per unit of a particular item of the work, cost of the quantity of material, the cost of labours and miscellaneous petty expanses require for its compilation is known as Analysis of rates .
  • 35. • The reasonable profit usually 10% for the contractor is also included in analysis of rate. • Rate of the material are usually taken as the rate delivered at the site of the work and include the cost at origin , cost of transport and taxes. • If the material are to be carried from a distant place more than 8 km then cost of the transport is also added. • Rate of the material and the labour vary from place to place and therefor, the rate of the different items of the work also vary from place to place.
  • 36. Purpose of Analysis of Rate • The quantities of material required and their cost should be known. • The number of different categories of labours required. • The capacity of doing work per labours and their wages per day should be known.
  • 37. Factor depends the rate of a particular item of work • Specification of work and materials, quantity of a material, proportion of mortor method of constructional operation. • Quantities of materials and their number of different type of labours and their rates. • Location of the site of work and its distance from the source of material and the rate of transport and availability of water. • Profit and miscellaneous and overhead expanses of the contractor.
  • 38. Standard Data Book It is a book in which the quantity of a material and labour required per unit of various finished items of work has been standardized. Standard Schedule of Rate It is a book in which the rates of all the material at source, the wages of the labour, conveyance charge of material where fixed by the competent engineering authority for each year for various government department.
  • 39. Rates of Materials • 1st class bricks = Rs 4500 per 1000 Nos. • 2nd class bricks = Rs 4000 per 1000 Nos. • Brick Ballast = Rs 800 per cum • Coarse sand = Rs 800 per cum • Cement 50 kg bag = Rs 350 per bag • Twisted bars = Rs 5000 per Quintal • Bitumen = Rs 10 per kg
  • 40. Rates of Labours • Mason = Rs 450 per day • Plaster = Rs 400 per day • Carpenter = Rs 400 per day • Bhishti = Rs 250 per day • Mazdoor = Rs 250 per day • Painter = Rs 300 per day
  • 41. Labour required for different work • Earth work in excavation: Mazdoor = 33 (% cum) Mason = 1.5 • Earth work in Filling : Mazdoor = 18 (% cum) Mason = 0.5 • Cement concrete : Mazdoor = 15 in foundation Mason =1.5 Bhishti = 2
  • 42. • Plastering work ( 100 sqm) : Mazdoor = 10 Mason = 10 Bhishti = 2 • Distempering/painting/ white washing ( 100 sqm) : Mazdoor = 5 Painter = 4 • RCC (10 cum) : Mazdoor = 40 Mason = 2.5 Bhishti = 5 Blacksmith = 4 Carpenter = 4
  • 43. Estimating serves a number of purposes in the construction process including preparation of bids and cost control. The role of the estimator includes preparing conceptual estimates, preliminary estimates, pre-bid estimates, post bid estimates, cost control, final project cost, cost on the operating construction period. As the works gets organized, smaller contractors can work on the project at lesser rate.
  翻译: