尊敬的 微信汇率:1円 ≈ 0.046374 元 支付宝汇率:1円 ≈ 0.046466元 [退出登录]
SlideShare a Scribd company logo
MANAV RACHNA INTERNATIONAL INSTITUTE OF RESEARCH AND STUDIES,
FARIDABAD
September, 2018
Submitted by
MD AFROZ ALAM
1/15/FET/BCI/1/077
Submitted to
Sonal Bhugra
PRESENTATION ON
CONSTRUCTION PROCESS OF COMMERCIAL BUILDING
In this week,
I did my industrial training from Manomav engineers [P] LTD
company.
First I saw layout plan of the building. There was two V-shape column
which was important to notice and new technology is being used as a
radiant pipe in each slab which will cause cooling effect and there will
be no need of A.C in each room.
I saw the columns , beams and details of reinforcement, lap length ,
development length.
1ST WEEK
 LAP LENGTH
Lap / Overlapping length is provide for maintain the continuity of bars
in order to safely transfer the load one bar to another bar.
 OVER LAPPING OF RODS
 It is done when length of reinforcement bar is small but we need longer
reinforcement.
 Provided in mid span.
 DEVELOPMENT
LENGTH
Development length is provided to transfer the load from
steel to concrete. development length is also known as
anchorage length. Development length is embedded extra
length.
It depend on grade of concrete
M25- Ld. =49d
M30- Ld. =46d
M35- Ld. =43d
 PLACEMENT OF TIES
 Normal spacing = S in mid span
 Spacing near support joint = S/2
 In this week I learn about column and how to make lap joint in column and beam
a/c to general notes Lap joint in column
 The lap joint should be in the lap zone of the column which is l/6 distance from
the bottom and this also known as zone A and remaining distance known as zone
B
 Lapping provided in zone B only
 It depend on grade of concrete
2nd
WEEK
M25- Ld. =49d
M30- Ld. =46d
M35- Ld. =43d , where Ld. is development length
d is diameter of bar.
• Not provide lap at same level.
• Buckling will be occurs at same level.
• lapping should be avoided in tensile zone of member under
construction.
L/6
L/6
 Material used in columns
 Cement
 Coarse aggregate
 Fine aggregate
 Steel bar
 Water
 Shuttering
COLUMN CONSTRUCTION PROCESS
 CONSTRUCTING RCC (REINFORCED CEMENT CONCRETE) COLUMN INVOLVES
FOLLOWING FOUR STAGES OF WORKS
1. COLUMN LAYOUT WORK
2. COLUMN REINFORCEMENT WORK
3. COLUMN FORMWORK
4. POURING CONCRETE INTO COLUMN
1. COLUMN LAYOUT WORK
In this stage of works the location of columns are determined practically in field.
it is done by laying rope according to grids shown in the drawing and then mark
the location of columns related to rope.
2.
COLUMN REINFORCEMENT WORK.
After marking the column locations, we then start to place reinforcement as instructed
in the structural drawing. this is normally described in the drawing like - (c1-12#16
mm⌀ and stirrup-10 mm⌀ @ 4" c/c)
3. Column formwork is a term used for structures that are used to support forms
or molds for poured concrete columns. It can be as simple as a reinforced
cardboard tube for small cylindrical columns or very complex forms constructed
from many pieces of wood and metal.
4. POURING CONCRETE INTO COLUMN
For small quantity of concrete volume we normally depend on machine-mix concrete and
for large concrete quantity we order ready-mix concrete. because, if you use moving pump
with ready-mix concrete and if you want not to exceed 5 feet height range for dropping
concrete that would be difficult.
CURING
Concrete which is moist cured for 7 days is about 50% stronger than uncured concrete.
3rd Week
In this week i learn about the beam reinforcement details, lap joint
and development length in beam and also learn how to calculate
cutting length of stirrups.
Top reinforcement in beam is lapped at mid span since the beam does not undergo any
negative moment at mid-span and so lapping is ideal in that area.
Don’t provide lapping in bottom bar at mid-span.
Bottom reinforcement in beam is lapped adjacent to the ends and the similar concept is
used further because there does not exist any positive moment at the ends of the beam.
The perfect zone for lapping is where the moments remain zero for continuous beams or
in the bending moment diagram, where the values surpass the x-axis or remain at l/4 for
simply supported beams.
You can provide lapping to l/4 in bottom bar.
Lap Joint In Beam
 CUTTING LENGTH OF
STIRRUP
45◦
Bend-1d
90◦
Bend-2d
135◦
Bend-3d
 Hook length = 10d
45◦
45◦
H
l
H= l+0.414H-2(1d)
135◦
90◦b
a
θ
b
L= a+b-(2d) L= a+b-(3d)
4th Week
IN THIS WEEK I LEARN ABOUT THE SHEARWALL ,DETAILING OF REINFORCEMENT OF
THE SHEAR WALL AS GIVEN BELOW IN FIG.
SHEAR WALL IS A STRUCTURAL MEMBER IN A REINFORCED CONCRETE FRAMED
STRUCTURE TO RESIST LATERAL FORCES, SEISMIC LOADS, VERTICAL FORCES
(GRAVITY) SUCH AS WIND FORCES. SHEAR WALLS ARE GENERALLY USED IN HIGH-
RISE BUILDINGS SUBJECT TO LATERAL WIND AND SEISMIC FORCES.
SHEAR WALLS ARE ESPECIALLY IMPORTANT IN HIGH-RISE BUILDINGS.
REDUCES LATERAL SWAY OF THE BUILDING.
RIGID VERTICAL DIAPHRAGM TRANSFERS THE LOADS INTO FOUNDATIONS.
SHEAR WALLS BEHAVIOR DEPENDS UPON: MATERIAL USED, WALL THICKNESS,
WALL LENGTH, WALL POSITIONING IN BUILDING FRAME ALSO.
ADVANTAGES
 Thinner walls.
 Light weight.
 Fast construction time.
 Fast performance
 Enough well distributed reinforcements.
 Cost effectiveness
 Minimized damages to structural and Non-structural elements.
Size of the shear wall = 300 x 3100 mm
Total number of shear wall at site = 2
 COLUMN TIE
The term tie is used to define the transverse reinforcement provided in column where the primary mode of load
transfer is compression.
 STIRRUPS
The term stirrups is used to define the transverse reinforcement provided in
beam where the primary mode of load transfer is through bending and shear.
 COLUMN COVER
5TH WEEK
IN THIS WEEK I LEARN ABOUT SLAB
SLAB IS TRANSFER THE LOAD TO BEAM , IT IS SUPPORTED BY BEAM AND COLUMN
DETAILING OF REINFORCEMENT OF THE SLAB AS GIVEN BELOW.
AT THIS SITE ONLY ONE “ONE WAY” SLAB IS USED IN EACH FLOOR AND OTHER ARE
TWO WAY SLAB.
ONE-WAY SLAB
 One way slab is supported on two
opposite side only thus structural action is
only at one direction. Total load is carried
in the direction perpendicular to the
supporting beam.
 If a slab is supported on all the four sides
but the ratio of longer span (L) to shorten
span (B) is greater than 2, then the slab
will be considered as one way
TWO-WAY SLAB
 Two way slabs are the slabs that are supported on four sides
and the ratio of longer span (L) to shorter span (B) is less than
2.
 In two way slabs, load will be carried in both the directions.
So, main reinforcement is provided in both direction for two
way slabs.
 SLAB LAYING PROCESS
According to work arrangement laying of RCC slab can be done in 4 stages such as formwork or
centering and shuttering, bending and binding MS steel bars and laying of concrete
i. Formwork
ii. Bending and Binding Steel bars
iii. Spacing of steel bars
iv. Laying of Cement Concrete
I. Form work
To retain concrete, formwork or centering and shuttering
is required, which provides the support to the wet of
concrete until it has gained sufficient strength to be self-
supporting.
II. BENDING AND BINDING STEEL BARS
At the time of designing the slab, it is consider that concrete is
strong in compressive strength but weak in tensile strength, so
make the structure safe against the tensile stress, steel bars are
provided
III. SPACING OF STEEL BARS
Steel bars diameter and its spacing in the RCC slab is calculated
by designing the slab according to load and span of the slab. In
general 12mm, 10mm and 8mm diameter steel bars are used in
RCC slab according to the length of span of the slab and
similarly spacing is from 4.5’’ to 6’’ in the main bars and 6’’ to
8’’ in distribution bars.
IV. LAYING OF CEMENT CONCRETE
Make walking way on steel bars by placing wooden plates to
avoid disturbance in steel bars. Now start to lay the cement
concrete mix as per design but not below the 1; 2; 4 ratio. The
mix mechanically mixed and vibrated after laying on the slab
should be mechanically mixed and vibrated after laying on the
slab.
CURING
After laying the RCC slab it should be cure for 28 days for
getting full strength.
6 TH WEEK
In this week laying of reinforcement and cover blocks are completed of 4th floor
Floor area is divided into two part (I) and (II) , both part are competed in this
week
Number of slab = 30 , Clear cover of slab = 20 mm , Grade of concrete = M25
More details as given belowSLAB
MARK
THK BOTTOM REINF.
ALONG SHORT SPAN
(A)
BOTTOM REINF.
ALONG LONG SPAN
(B)
TOP REINF. AT
SUPPORTS ALONG
SHORT SPAN (C)
TOP REINF. AT
SUPPORTS
ALONG LONG
SPAN (D)
S1 140 T10@100 c/c T8@225 c/c T10@125 c/c T8@225 c/c
S2 155 T10@125 c/c T8@225 c/c T10@125 c/c T8@225 c/c
S3 140 T8@100 c/c T8@150 c/c T8@100 c/c T8@150 c/c
S4 140 T8@150 c/c T8@225 c/c T8@150 c/c T8@225 c/c
S5 140 T8@200 c/c T8@200 c/c T8@150 c/c T8@175 c/c
S6 140 T10@125 c/c T8@125 c/c T10@175 c/c T8@100 c/c
7 TH WEEK
In this week I learn about the Radiant pipe,
How to Radiant pipe is laying in each slab, Radiant pipe which
will cause cooling effect and there will be no need of A.C in each
room.
 Radiant pipe is used in form of loop in each slab.
 At the time of concreting pressure of water maintained in radiant pipe 60
psi temperature
 Child water maintained temperature between 15℃- 16℃ at the service time.
 Spacing of radiant pipe is 450 mm
 Cover from bottom is 75 mm
 Cover from top 60 mm + dia. of pipe (20mm)
 Thickness of pipe is 20 mm
In this week concreting is done in part (i)and part (ii) area And
laying of block work of boundary wall.
8th WEEK
LAYING OF BLOCK
AAC BLOCK- Autoclaved aerated concrete
also known as autoclaved lightweight concrete (ALC), autoclaved cellular
concrete (ACC)
 General size of the block is (200 x 600) x 240/245/235 mm3.
(Thick x length) x height
 Compressive strength is 3-4 N/mm2
 BLOCK JOINTING MORTAR
It is the finest eco-friendly block jointing mortar with “super bond technology” especially formulated joining
birla Aerocon AAC blocks. Unlike traditional joining mortar , it give stronger, smoother and cost effective and
water- resistant finish.
 KEY FEATURES
 High strength with thinner joints (3mm thin)
 Faster construction as no curing is required
 Reduces Wastage
 Economical.
 No water percolation Technologically superior and consistent in quality
ADVANTAGE
 Larger size blocks leads to faster masonry work.
 It lighter than 3 times of clay bricks weight.
 Reduces the cost of the project
 Light weight Saves cost & energy in transportation,
 Light weight saves labor expenses.
DISADVANTAGE
 The production cost per unit for ACC is higher than other
ordinary concrete
 It is not as strong as conventional concrete
 Very few contractors who are familiar with autoclaved
aerated concrete.
 Number of manufacturer is limited.
9th WEEK
In this week I learn about shuttering , deshuttering and Rebar of
reinforcement.
 SHUTTERING: - Formwork which support the vertical surface is known as shuttering.
 STAGING: - Material such as wooden bullies, pipes, props support the shuttering and
centering called staging.
Walls, columns and vertical sides of beams = 1 to 3 days
Slab (props left under) = 3 days
Beam soffits (props left under) = 7 days
Removal of props to slab
a. For slabs spanning up to 4.5 m
b. For slabs spanning over 4.5 m
= 7 days
= 14 days
Removal of props to beams and arches
a. Spanning up to 6 m
b. Spanning over 6 m
= 14 days
= 21 days
PERIOD FOR REMOVAL OF FORMWORK
Chemical use in rebar
Hilti Rebarring chemical (Fischer)
REBAR
A rebar spacer is a device that secures the reinforcing steel or "rebar" in reinforced concrete
structures as the rebar is assembled in place prior to the final concrete pour. The spacers are left
in place for the pour to keep the reinforcing in place, and become a permanent part of the
structure.

More Related Content

What's hot

2 column
2 column2 column
2 column
P Ramana
 
Presentation on Slab, Beam & Column
Presentation on Slab, Beam & ColumnPresentation on Slab, Beam & Column
Presentation on Slab, Beam & Column
মু সা
 
Beam Design and Drawing of RCC Structures
Beam Design and Drawing of RCC StructuresBeam Design and Drawing of RCC Structures
Beam Design and Drawing of RCC Structures
Shubham .
 
L- beams or flanged beams
L- beams or flanged beamsL- beams or flanged beams
L- beams or flanged beams
honeysid
 
Beam and slab design
Beam and slab designBeam and slab design
Beam and slab design
Ivan Ferrer
 
Beam and column and its types in detail
Beam and column and its types in detailBeam and column and its types in detail
Beam and column and its types in detail
Bilal Rahman
 
Shear Strenth Of Reinforced Concrete Beams Per ACI-318-02
Shear Strenth Of Reinforced Concrete Beams Per ACI-318-02Shear Strenth Of Reinforced Concrete Beams Per ACI-318-02
Shear Strenth Of Reinforced Concrete Beams Per ACI-318-02
Engr Kamran Khan
 
Reinforced column design
Reinforced column design Reinforced column design
Reinforced column design
Mohamed Azeem Nijamdeen
 
Design of columns as per IS 456-2000
Design of columns as per IS 456-2000Design of columns as per IS 456-2000
Design of columns as per IS 456-2000
PraveenKumar Shanmugam
 
Reinforced concrete beams
Reinforced concrete beamsReinforced concrete beams
Reinforced concrete beams
Shivkumar Yadav
 
Column design1
Column design1Column design1
Column design1
imaduddin91
 
Shear and diagonal tension in beams
Shear and diagonal tension in beamsShear and diagonal tension in beams
Shear and diagonal tension in beams
muhammad musaab
 
Design of column base plates anchor bolt
Design of column base plates anchor boltDesign of column base plates anchor bolt
Design of column base plates anchor bolt
Khaled Eid
 
Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)
mbrsalman
 
I Download (1)
I Download (1)I Download (1)
I Download (1)
Laquiao Ganagan
 
Ductile detailing
Ductile detailingDuctile detailing
Ductile detailing
Binay Shrestha
 
Design and analysis of cantilever beam
Design and analysis of cantilever beamDesign and analysis of cantilever beam
Design and analysis of cantilever beam
College
 
Column detailing, Session 14-15 (DUET)
Column detailing, Session 14-15 (DUET)Column detailing, Session 14-15 (DUET)
Column detailing, Session 14-15 (DUET)
swatapriya
 
Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering IaşiLecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Ursachi Răzvan
 
54307684 beam-column
54307684 beam-column54307684 beam-column
54307684 beam-column
Shashikant Gaur
 

What's hot (20)

2 column
2 column2 column
2 column
 
Presentation on Slab, Beam & Column
Presentation on Slab, Beam & ColumnPresentation on Slab, Beam & Column
Presentation on Slab, Beam & Column
 
Beam Design and Drawing of RCC Structures
Beam Design and Drawing of RCC StructuresBeam Design and Drawing of RCC Structures
Beam Design and Drawing of RCC Structures
 
L- beams or flanged beams
L- beams or flanged beamsL- beams or flanged beams
L- beams or flanged beams
 
Beam and slab design
Beam and slab designBeam and slab design
Beam and slab design
 
Beam and column and its types in detail
Beam and column and its types in detailBeam and column and its types in detail
Beam and column and its types in detail
 
Shear Strenth Of Reinforced Concrete Beams Per ACI-318-02
Shear Strenth Of Reinforced Concrete Beams Per ACI-318-02Shear Strenth Of Reinforced Concrete Beams Per ACI-318-02
Shear Strenth Of Reinforced Concrete Beams Per ACI-318-02
 
Reinforced column design
Reinforced column design Reinforced column design
Reinforced column design
 
Design of columns as per IS 456-2000
Design of columns as per IS 456-2000Design of columns as per IS 456-2000
Design of columns as per IS 456-2000
 
Reinforced concrete beams
Reinforced concrete beamsReinforced concrete beams
Reinforced concrete beams
 
Column design1
Column design1Column design1
Column design1
 
Shear and diagonal tension in beams
Shear and diagonal tension in beamsShear and diagonal tension in beams
Shear and diagonal tension in beams
 
Design of column base plates anchor bolt
Design of column base plates anchor boltDesign of column base plates anchor bolt
Design of column base plates anchor bolt
 
Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)
 
I Download (1)
I Download (1)I Download (1)
I Download (1)
 
Ductile detailing
Ductile detailingDuctile detailing
Ductile detailing
 
Design and analysis of cantilever beam
Design and analysis of cantilever beamDesign and analysis of cantilever beam
Design and analysis of cantilever beam
 
Column detailing, Session 14-15 (DUET)
Column detailing, Session 14-15 (DUET)Column detailing, Session 14-15 (DUET)
Column detailing, Session 14-15 (DUET)
 
Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering IaşiLecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
 
54307684 beam-column
54307684 beam-column54307684 beam-column
54307684 beam-column
 

Similar to Prsesntation on Commercial building Project

Design of Beam- RCC Singly Reinforced Beam
Design of Beam- RCC Singly Reinforced BeamDesign of Beam- RCC Singly Reinforced Beam
Design of Beam- RCC Singly Reinforced Beam
SHAZEBALIKHAN1
 
BEAM.pptx
BEAM.pptxBEAM.pptx
BEAM.pptx
Rishi Nath
 
Beams and columns
Beams and columns Beams and columns
Beams and columns
Prabhat chhirolya
 
Paper
PaperPaper
Paper
Usha -
 
Intze PPT
Intze PPTIntze PPT
IRJET- Cost Analysis of Two-Way Slab and Post Tension Slab
IRJET-  	  Cost Analysis of Two-Way Slab and Post Tension SlabIRJET-  	  Cost Analysis of Two-Way Slab and Post Tension Slab
IRJET- Cost Analysis of Two-Way Slab and Post Tension Slab
IRJET Journal
 
Presentation on Slab, Beam, Column, and Foundation/Footing
Presentation on Slab,  Beam, Column, and Foundation/FootingPresentation on Slab,  Beam, Column, and Foundation/Footing
Presentation on Slab, Beam, Column, and Foundation/Footing
Dhaka University of Engineering & Technology, Gazipur
 
RCC Elements column, beam.
RCC Elements  column, beam.RCC Elements  column, beam.
RCC Elements column, beam.
Puneet Chhonker
 
Intze ppt
Intze pptIntze ppt
14251 a ch3
14251 a ch314251 a ch3
Perhitungan sturktur kolom baja 6162 (4).ppt
Perhitungan sturktur kolom baja 6162 (4).pptPerhitungan sturktur kolom baja 6162 (4).ppt
Perhitungan sturktur kolom baja 6162 (4).ppt
Gidion Turuallo
 
REINFORCED CEMENT CONCRETE
REINFORCED CEMENT CONCRETEREINFORCED CEMENT CONCRETE
REINFORCED CEMENT CONCRETE
Brijesh Alig
 
rcc design tips for beams and footing.pptxa
rcc design tips for beams and footing.pptxarcc design tips for beams and footing.pptxa
rcc design tips for beams and footing.pptxa
nlnmurthy28
 
Building Structure Project 1
Building Structure Project 1Building Structure Project 1
Building Structure Project 1
Gertrude Lee
 
Columns lecture#1
Columns lecture#1Columns lecture#1
Columns lecture#1
Irfan Malik
 
Column
ColumnColumn
Cable stayed bridge
Cable stayed bridgeCable stayed bridge
Cable stayed bridge
Sadek Abdelraheem
 
I download
I downloadI download
I download
Laquiao Ganagan
 
Reinforcement detailing
Reinforcement  detailingReinforcement  detailing
Reinforcement detailing
Ali Ishaqi
 
Experimental study on strength and flexural behaviour of reinforced concrete ...
Experimental study on strength and flexural behaviour of reinforced concrete ...Experimental study on strength and flexural behaviour of reinforced concrete ...
Experimental study on strength and flexural behaviour of reinforced concrete ...
IOSR Journals
 

Similar to Prsesntation on Commercial building Project (20)

Design of Beam- RCC Singly Reinforced Beam
Design of Beam- RCC Singly Reinforced BeamDesign of Beam- RCC Singly Reinforced Beam
Design of Beam- RCC Singly Reinforced Beam
 
BEAM.pptx
BEAM.pptxBEAM.pptx
BEAM.pptx
 
Beams and columns
Beams and columns Beams and columns
Beams and columns
 
Paper
PaperPaper
Paper
 
Intze PPT
Intze PPTIntze PPT
Intze PPT
 
IRJET- Cost Analysis of Two-Way Slab and Post Tension Slab
IRJET-  	  Cost Analysis of Two-Way Slab and Post Tension SlabIRJET-  	  Cost Analysis of Two-Way Slab and Post Tension Slab
IRJET- Cost Analysis of Two-Way Slab and Post Tension Slab
 
Presentation on Slab, Beam, Column, and Foundation/Footing
Presentation on Slab,  Beam, Column, and Foundation/FootingPresentation on Slab,  Beam, Column, and Foundation/Footing
Presentation on Slab, Beam, Column, and Foundation/Footing
 
RCC Elements column, beam.
RCC Elements  column, beam.RCC Elements  column, beam.
RCC Elements column, beam.
 
Intze ppt
Intze pptIntze ppt
Intze ppt
 
14251 a ch3
14251 a ch314251 a ch3
14251 a ch3
 
Perhitungan sturktur kolom baja 6162 (4).ppt
Perhitungan sturktur kolom baja 6162 (4).pptPerhitungan sturktur kolom baja 6162 (4).ppt
Perhitungan sturktur kolom baja 6162 (4).ppt
 
REINFORCED CEMENT CONCRETE
REINFORCED CEMENT CONCRETEREINFORCED CEMENT CONCRETE
REINFORCED CEMENT CONCRETE
 
rcc design tips for beams and footing.pptxa
rcc design tips for beams and footing.pptxarcc design tips for beams and footing.pptxa
rcc design tips for beams and footing.pptxa
 
Building Structure Project 1
Building Structure Project 1Building Structure Project 1
Building Structure Project 1
 
Columns lecture#1
Columns lecture#1Columns lecture#1
Columns lecture#1
 
Column
ColumnColumn
Column
 
Cable stayed bridge
Cable stayed bridgeCable stayed bridge
Cable stayed bridge
 
I download
I downloadI download
I download
 
Reinforcement detailing
Reinforcement  detailingReinforcement  detailing
Reinforcement detailing
 
Experimental study on strength and flexural behaviour of reinforced concrete ...
Experimental study on strength and flexural behaviour of reinforced concrete ...Experimental study on strength and flexural behaviour of reinforced concrete ...
Experimental study on strength and flexural behaviour of reinforced concrete ...
 

Recently uploaded

欧洲杯下注-欧洲杯下注押注官网-欧洲杯下注押注网站|【​网址​🎉ac44.net🎉​】
欧洲杯下注-欧洲杯下注押注官网-欧洲杯下注押注网站|【​网址​🎉ac44.net🎉​】欧洲杯下注-欧洲杯下注押注官网-欧洲杯下注押注网站|【​网址​🎉ac44.net🎉​】
欧洲杯下注-欧洲杯下注押注官网-欧洲杯下注押注网站|【​网址​🎉ac44.net🎉​】
andagarcia212
 
Skimbleshanks-The-Railway-Cat by T S Eliot
Skimbleshanks-The-Railway-Cat by T S EliotSkimbleshanks-The-Railway-Cat by T S Eliot
Skimbleshanks-The-Railway-Cat by T S Eliot
nitinpv4ai
 
Creation or Update of a Mandatory Field is Not Set in Odoo 17
Creation or Update of a Mandatory Field is Not Set in Odoo 17Creation or Update of a Mandatory Field is Not Set in Odoo 17
Creation or Update of a Mandatory Field is Not Set in Odoo 17
Celine George
 
Observational Learning
Observational Learning Observational Learning
Observational Learning
sanamushtaq922
 
Simple-Present-Tense xxxxxxxxxxxxxxxxxxx
Simple-Present-Tense xxxxxxxxxxxxxxxxxxxSimple-Present-Tense xxxxxxxxxxxxxxxxxxx
Simple-Present-Tense xxxxxxxxxxxxxxxxxxx
RandolphRadicy
 
A Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two HeartsA Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two Hearts
Steve Thomason
 
Haunted Houses by H W Longfellow for class 10
Haunted Houses by H W Longfellow for class 10Haunted Houses by H W Longfellow for class 10
Haunted Houses by H W Longfellow for class 10
nitinpv4ai
 
220711130082 Srabanti Bag Internet Resources For Natural Science
220711130082 Srabanti Bag Internet Resources For Natural Science220711130082 Srabanti Bag Internet Resources For Natural Science
220711130082 Srabanti Bag Internet Resources For Natural Science
Kalna College
 
CHUYÊN ĐỀ ÔN TẬP VÀ PHÁT TRIỂN CÂU HỎI TRONG ĐỀ MINH HỌA THI TỐT NGHIỆP THPT ...
CHUYÊN ĐỀ ÔN TẬP VÀ PHÁT TRIỂN CÂU HỎI TRONG ĐỀ MINH HỌA THI TỐT NGHIỆP THPT ...CHUYÊN ĐỀ ÔN TẬP VÀ PHÁT TRIỂN CÂU HỎI TRONG ĐỀ MINH HỌA THI TỐT NGHIỆP THPT ...
CHUYÊN ĐỀ ÔN TẬP VÀ PHÁT TRIỂN CÂU HỎI TRONG ĐỀ MINH HỌA THI TỐT NGHIỆP THPT ...
Nguyen Thanh Tu Collection
 
KHUSWANT SINGH.pptx ALL YOU NEED TO KNOW ABOUT KHUSHWANT SINGH
KHUSWANT SINGH.pptx ALL YOU NEED TO KNOW ABOUT KHUSHWANT SINGHKHUSWANT SINGH.pptx ALL YOU NEED TO KNOW ABOUT KHUSHWANT SINGH
KHUSWANT SINGH.pptx ALL YOU NEED TO KNOW ABOUT KHUSHWANT SINGH
shreyassri1208
 
Creative Restart 2024: Mike Martin - Finding a way around “no”
Creative Restart 2024: Mike Martin - Finding a way around “no”Creative Restart 2024: Mike Martin - Finding a way around “no”
Creative Restart 2024: Mike Martin - Finding a way around “no”
Taste
 
220711130083 SUBHASHREE RAKSHIT Internet resources for social science
220711130083 SUBHASHREE RAKSHIT  Internet resources for social science220711130083 SUBHASHREE RAKSHIT  Internet resources for social science
220711130083 SUBHASHREE RAKSHIT Internet resources for social science
Kalna College
 
Brand Guideline of Bashundhara A4 Paper - 2024
Brand Guideline of Bashundhara A4 Paper - 2024Brand Guideline of Bashundhara A4 Paper - 2024
Brand Guideline of Bashundhara A4 Paper - 2024
khabri85
 
adjectives.ppt for class 1 to 6, grammar
adjectives.ppt for class 1 to 6, grammaradjectives.ppt for class 1 to 6, grammar
adjectives.ppt for class 1 to 6, grammar
7DFarhanaMohammed
 
Data Structure using C by Dr. K Adisesha .ppsx
Data Structure using C by Dr. K Adisesha .ppsxData Structure using C by Dr. K Adisesha .ppsx
Data Structure using C by Dr. K Adisesha .ppsx
Prof. Dr. K. Adisesha
 
THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...
THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...
THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...
indexPub
 
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptxRESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
zuzanka
 
NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...
NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...
NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...
Payaamvohra1
 
Standardized tool for Intelligence test.
Standardized tool for Intelligence test.Standardized tool for Intelligence test.
Standardized tool for Intelligence test.
deepaannamalai16
 
مصحف القراءات العشر أعد أحرف الخلاف سمير بسيوني.pdf
مصحف القراءات العشر   أعد أحرف الخلاف سمير بسيوني.pdfمصحف القراءات العشر   أعد أحرف الخلاف سمير بسيوني.pdf
مصحف القراءات العشر أعد أحرف الخلاف سمير بسيوني.pdf
سمير بسيوني
 

Recently uploaded (20)

欧洲杯下注-欧洲杯下注押注官网-欧洲杯下注押注网站|【​网址​🎉ac44.net🎉​】
欧洲杯下注-欧洲杯下注押注官网-欧洲杯下注押注网站|【​网址​🎉ac44.net🎉​】欧洲杯下注-欧洲杯下注押注官网-欧洲杯下注押注网站|【​网址​🎉ac44.net🎉​】
欧洲杯下注-欧洲杯下注押注官网-欧洲杯下注押注网站|【​网址​🎉ac44.net🎉​】
 
Skimbleshanks-The-Railway-Cat by T S Eliot
Skimbleshanks-The-Railway-Cat by T S EliotSkimbleshanks-The-Railway-Cat by T S Eliot
Skimbleshanks-The-Railway-Cat by T S Eliot
 
Creation or Update of a Mandatory Field is Not Set in Odoo 17
Creation or Update of a Mandatory Field is Not Set in Odoo 17Creation or Update of a Mandatory Field is Not Set in Odoo 17
Creation or Update of a Mandatory Field is Not Set in Odoo 17
 
Observational Learning
Observational Learning Observational Learning
Observational Learning
 
Simple-Present-Tense xxxxxxxxxxxxxxxxxxx
Simple-Present-Tense xxxxxxxxxxxxxxxxxxxSimple-Present-Tense xxxxxxxxxxxxxxxxxxx
Simple-Present-Tense xxxxxxxxxxxxxxxxxxx
 
A Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two HeartsA Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two Hearts
 
Haunted Houses by H W Longfellow for class 10
Haunted Houses by H W Longfellow for class 10Haunted Houses by H W Longfellow for class 10
Haunted Houses by H W Longfellow for class 10
 
220711130082 Srabanti Bag Internet Resources For Natural Science
220711130082 Srabanti Bag Internet Resources For Natural Science220711130082 Srabanti Bag Internet Resources For Natural Science
220711130082 Srabanti Bag Internet Resources For Natural Science
 
CHUYÊN ĐỀ ÔN TẬP VÀ PHÁT TRIỂN CÂU HỎI TRONG ĐỀ MINH HỌA THI TỐT NGHIỆP THPT ...
CHUYÊN ĐỀ ÔN TẬP VÀ PHÁT TRIỂN CÂU HỎI TRONG ĐỀ MINH HỌA THI TỐT NGHIỆP THPT ...CHUYÊN ĐỀ ÔN TẬP VÀ PHÁT TRIỂN CÂU HỎI TRONG ĐỀ MINH HỌA THI TỐT NGHIỆP THPT ...
CHUYÊN ĐỀ ÔN TẬP VÀ PHÁT TRIỂN CÂU HỎI TRONG ĐỀ MINH HỌA THI TỐT NGHIỆP THPT ...
 
KHUSWANT SINGH.pptx ALL YOU NEED TO KNOW ABOUT KHUSHWANT SINGH
KHUSWANT SINGH.pptx ALL YOU NEED TO KNOW ABOUT KHUSHWANT SINGHKHUSWANT SINGH.pptx ALL YOU NEED TO KNOW ABOUT KHUSHWANT SINGH
KHUSWANT SINGH.pptx ALL YOU NEED TO KNOW ABOUT KHUSHWANT SINGH
 
Creative Restart 2024: Mike Martin - Finding a way around “no”
Creative Restart 2024: Mike Martin - Finding a way around “no”Creative Restart 2024: Mike Martin - Finding a way around “no”
Creative Restart 2024: Mike Martin - Finding a way around “no”
 
220711130083 SUBHASHREE RAKSHIT Internet resources for social science
220711130083 SUBHASHREE RAKSHIT  Internet resources for social science220711130083 SUBHASHREE RAKSHIT  Internet resources for social science
220711130083 SUBHASHREE RAKSHIT Internet resources for social science
 
Brand Guideline of Bashundhara A4 Paper - 2024
Brand Guideline of Bashundhara A4 Paper - 2024Brand Guideline of Bashundhara A4 Paper - 2024
Brand Guideline of Bashundhara A4 Paper - 2024
 
adjectives.ppt for class 1 to 6, grammar
adjectives.ppt for class 1 to 6, grammaradjectives.ppt for class 1 to 6, grammar
adjectives.ppt for class 1 to 6, grammar
 
Data Structure using C by Dr. K Adisesha .ppsx
Data Structure using C by Dr. K Adisesha .ppsxData Structure using C by Dr. K Adisesha .ppsx
Data Structure using C by Dr. K Adisesha .ppsx
 
THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...
THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...
THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...
 
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptxRESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
 
NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...
NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...
NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...
 
Standardized tool for Intelligence test.
Standardized tool for Intelligence test.Standardized tool for Intelligence test.
Standardized tool for Intelligence test.
 
مصحف القراءات العشر أعد أحرف الخلاف سمير بسيوني.pdf
مصحف القراءات العشر   أعد أحرف الخلاف سمير بسيوني.pdfمصحف القراءات العشر   أعد أحرف الخلاف سمير بسيوني.pdf
مصحف القراءات العشر أعد أحرف الخلاف سمير بسيوني.pdf
 

Prsesntation on Commercial building Project

  • 1. MANAV RACHNA INTERNATIONAL INSTITUTE OF RESEARCH AND STUDIES, FARIDABAD September, 2018 Submitted by MD AFROZ ALAM 1/15/FET/BCI/1/077 Submitted to Sonal Bhugra
  • 2. PRESENTATION ON CONSTRUCTION PROCESS OF COMMERCIAL BUILDING
  • 3. In this week, I did my industrial training from Manomav engineers [P] LTD company. First I saw layout plan of the building. There was two V-shape column which was important to notice and new technology is being used as a radiant pipe in each slab which will cause cooling effect and there will be no need of A.C in each room. I saw the columns , beams and details of reinforcement, lap length , development length. 1ST WEEK
  • 4.
  • 5.
  • 6.
  • 7.  LAP LENGTH Lap / Overlapping length is provide for maintain the continuity of bars in order to safely transfer the load one bar to another bar.
  • 8.  OVER LAPPING OF RODS  It is done when length of reinforcement bar is small but we need longer reinforcement.  Provided in mid span.
  • 9.  DEVELOPMENT LENGTH Development length is provided to transfer the load from steel to concrete. development length is also known as anchorage length. Development length is embedded extra length. It depend on grade of concrete M25- Ld. =49d M30- Ld. =46d M35- Ld. =43d
  • 10.  PLACEMENT OF TIES  Normal spacing = S in mid span  Spacing near support joint = S/2
  • 11.
  • 12.  In this week I learn about column and how to make lap joint in column and beam a/c to general notes Lap joint in column  The lap joint should be in the lap zone of the column which is l/6 distance from the bottom and this also known as zone A and remaining distance known as zone B  Lapping provided in zone B only  It depend on grade of concrete 2nd WEEK M25- Ld. =49d M30- Ld. =46d M35- Ld. =43d , where Ld. is development length d is diameter of bar.
  • 13. • Not provide lap at same level. • Buckling will be occurs at same level. • lapping should be avoided in tensile zone of member under construction.
  • 15.
  • 16.  Material used in columns  Cement  Coarse aggregate  Fine aggregate  Steel bar  Water  Shuttering
  • 17. COLUMN CONSTRUCTION PROCESS  CONSTRUCTING RCC (REINFORCED CEMENT CONCRETE) COLUMN INVOLVES FOLLOWING FOUR STAGES OF WORKS 1. COLUMN LAYOUT WORK 2. COLUMN REINFORCEMENT WORK 3. COLUMN FORMWORK 4. POURING CONCRETE INTO COLUMN
  • 18. 1. COLUMN LAYOUT WORK In this stage of works the location of columns are determined practically in field. it is done by laying rope according to grids shown in the drawing and then mark the location of columns related to rope. 2. COLUMN REINFORCEMENT WORK. After marking the column locations, we then start to place reinforcement as instructed in the structural drawing. this is normally described in the drawing like - (c1-12#16 mm⌀ and stirrup-10 mm⌀ @ 4" c/c)
  • 19. 3. Column formwork is a term used for structures that are used to support forms or molds for poured concrete columns. It can be as simple as a reinforced cardboard tube for small cylindrical columns or very complex forms constructed from many pieces of wood and metal.
  • 20. 4. POURING CONCRETE INTO COLUMN For small quantity of concrete volume we normally depend on machine-mix concrete and for large concrete quantity we order ready-mix concrete. because, if you use moving pump with ready-mix concrete and if you want not to exceed 5 feet height range for dropping concrete that would be difficult.
  • 21. CURING Concrete which is moist cured for 7 days is about 50% stronger than uncured concrete.
  • 22. 3rd Week In this week i learn about the beam reinforcement details, lap joint and development length in beam and also learn how to calculate cutting length of stirrups.
  • 23.
  • 24. Top reinforcement in beam is lapped at mid span since the beam does not undergo any negative moment at mid-span and so lapping is ideal in that area. Don’t provide lapping in bottom bar at mid-span. Bottom reinforcement in beam is lapped adjacent to the ends and the similar concept is used further because there does not exist any positive moment at the ends of the beam. The perfect zone for lapping is where the moments remain zero for continuous beams or in the bending moment diagram, where the values surpass the x-axis or remain at l/4 for simply supported beams. You can provide lapping to l/4 in bottom bar. Lap Joint In Beam
  • 25.
  • 26.  CUTTING LENGTH OF STIRRUP 45◦ Bend-1d 90◦ Bend-2d 135◦ Bend-3d  Hook length = 10d 45◦ 45◦ H l H= l+0.414H-2(1d) 135◦ 90◦b a θ b L= a+b-(2d) L= a+b-(3d)
  • 27. 4th Week IN THIS WEEK I LEARN ABOUT THE SHEARWALL ,DETAILING OF REINFORCEMENT OF THE SHEAR WALL AS GIVEN BELOW IN FIG. SHEAR WALL IS A STRUCTURAL MEMBER IN A REINFORCED CONCRETE FRAMED STRUCTURE TO RESIST LATERAL FORCES, SEISMIC LOADS, VERTICAL FORCES (GRAVITY) SUCH AS WIND FORCES. SHEAR WALLS ARE GENERALLY USED IN HIGH- RISE BUILDINGS SUBJECT TO LATERAL WIND AND SEISMIC FORCES. SHEAR WALLS ARE ESPECIALLY IMPORTANT IN HIGH-RISE BUILDINGS. REDUCES LATERAL SWAY OF THE BUILDING. RIGID VERTICAL DIAPHRAGM TRANSFERS THE LOADS INTO FOUNDATIONS. SHEAR WALLS BEHAVIOR DEPENDS UPON: MATERIAL USED, WALL THICKNESS, WALL LENGTH, WALL POSITIONING IN BUILDING FRAME ALSO.
  • 28.
  • 29.
  • 30. ADVANTAGES  Thinner walls.  Light weight.  Fast construction time.  Fast performance  Enough well distributed reinforcements.  Cost effectiveness  Minimized damages to structural and Non-structural elements. Size of the shear wall = 300 x 3100 mm Total number of shear wall at site = 2
  • 31.  COLUMN TIE The term tie is used to define the transverse reinforcement provided in column where the primary mode of load transfer is compression.
  • 32.  STIRRUPS The term stirrups is used to define the transverse reinforcement provided in beam where the primary mode of load transfer is through bending and shear.
  • 34. 5TH WEEK IN THIS WEEK I LEARN ABOUT SLAB SLAB IS TRANSFER THE LOAD TO BEAM , IT IS SUPPORTED BY BEAM AND COLUMN DETAILING OF REINFORCEMENT OF THE SLAB AS GIVEN BELOW. AT THIS SITE ONLY ONE “ONE WAY” SLAB IS USED IN EACH FLOOR AND OTHER ARE TWO WAY SLAB. ONE-WAY SLAB  One way slab is supported on two opposite side only thus structural action is only at one direction. Total load is carried in the direction perpendicular to the supporting beam.  If a slab is supported on all the four sides but the ratio of longer span (L) to shorten span (B) is greater than 2, then the slab will be considered as one way
  • 35. TWO-WAY SLAB  Two way slabs are the slabs that are supported on four sides and the ratio of longer span (L) to shorter span (B) is less than 2.  In two way slabs, load will be carried in both the directions. So, main reinforcement is provided in both direction for two way slabs.
  • 36.  SLAB LAYING PROCESS According to work arrangement laying of RCC slab can be done in 4 stages such as formwork or centering and shuttering, bending and binding MS steel bars and laying of concrete i. Formwork ii. Bending and Binding Steel bars iii. Spacing of steel bars iv. Laying of Cement Concrete I. Form work To retain concrete, formwork or centering and shuttering is required, which provides the support to the wet of concrete until it has gained sufficient strength to be self- supporting.
  • 37. II. BENDING AND BINDING STEEL BARS At the time of designing the slab, it is consider that concrete is strong in compressive strength but weak in tensile strength, so make the structure safe against the tensile stress, steel bars are provided III. SPACING OF STEEL BARS Steel bars diameter and its spacing in the RCC slab is calculated by designing the slab according to load and span of the slab. In general 12mm, 10mm and 8mm diameter steel bars are used in RCC slab according to the length of span of the slab and similarly spacing is from 4.5’’ to 6’’ in the main bars and 6’’ to 8’’ in distribution bars.
  • 38.
  • 39. IV. LAYING OF CEMENT CONCRETE Make walking way on steel bars by placing wooden plates to avoid disturbance in steel bars. Now start to lay the cement concrete mix as per design but not below the 1; 2; 4 ratio. The mix mechanically mixed and vibrated after laying on the slab should be mechanically mixed and vibrated after laying on the slab. CURING After laying the RCC slab it should be cure for 28 days for getting full strength.
  • 40. 6 TH WEEK In this week laying of reinforcement and cover blocks are completed of 4th floor Floor area is divided into two part (I) and (II) , both part are competed in this week Number of slab = 30 , Clear cover of slab = 20 mm , Grade of concrete = M25 More details as given belowSLAB MARK THK BOTTOM REINF. ALONG SHORT SPAN (A) BOTTOM REINF. ALONG LONG SPAN (B) TOP REINF. AT SUPPORTS ALONG SHORT SPAN (C) TOP REINF. AT SUPPORTS ALONG LONG SPAN (D) S1 140 T10@100 c/c T8@225 c/c T10@125 c/c T8@225 c/c S2 155 T10@125 c/c T8@225 c/c T10@125 c/c T8@225 c/c S3 140 T8@100 c/c T8@150 c/c T8@100 c/c T8@150 c/c S4 140 T8@150 c/c T8@225 c/c T8@150 c/c T8@225 c/c S5 140 T8@200 c/c T8@200 c/c T8@150 c/c T8@175 c/c S6 140 T10@125 c/c T8@125 c/c T10@175 c/c T8@100 c/c
  • 41.
  • 42. 7 TH WEEK In this week I learn about the Radiant pipe, How to Radiant pipe is laying in each slab, Radiant pipe which will cause cooling effect and there will be no need of A.C in each room.  Radiant pipe is used in form of loop in each slab.  At the time of concreting pressure of water maintained in radiant pipe 60 psi temperature  Child water maintained temperature between 15℃- 16℃ at the service time.  Spacing of radiant pipe is 450 mm  Cover from bottom is 75 mm  Cover from top 60 mm + dia. of pipe (20mm)  Thickness of pipe is 20 mm
  • 43.
  • 44. In this week concreting is done in part (i)and part (ii) area And laying of block work of boundary wall. 8th WEEK
  • 45. LAYING OF BLOCK AAC BLOCK- Autoclaved aerated concrete also known as autoclaved lightweight concrete (ALC), autoclaved cellular concrete (ACC)  General size of the block is (200 x 600) x 240/245/235 mm3. (Thick x length) x height  Compressive strength is 3-4 N/mm2
  • 46.
  • 47.  BLOCK JOINTING MORTAR It is the finest eco-friendly block jointing mortar with “super bond technology” especially formulated joining birla Aerocon AAC blocks. Unlike traditional joining mortar , it give stronger, smoother and cost effective and water- resistant finish.  KEY FEATURES  High strength with thinner joints (3mm thin)  Faster construction as no curing is required  Reduces Wastage  Economical.  No water percolation Technologically superior and consistent in quality
  • 48. ADVANTAGE  Larger size blocks leads to faster masonry work.  It lighter than 3 times of clay bricks weight.  Reduces the cost of the project  Light weight Saves cost & energy in transportation,  Light weight saves labor expenses. DISADVANTAGE  The production cost per unit for ACC is higher than other ordinary concrete  It is not as strong as conventional concrete  Very few contractors who are familiar with autoclaved aerated concrete.  Number of manufacturer is limited.
  • 49. 9th WEEK In this week I learn about shuttering , deshuttering and Rebar of reinforcement.  SHUTTERING: - Formwork which support the vertical surface is known as shuttering.  STAGING: - Material such as wooden bullies, pipes, props support the shuttering and centering called staging.
  • 50. Walls, columns and vertical sides of beams = 1 to 3 days Slab (props left under) = 3 days Beam soffits (props left under) = 7 days Removal of props to slab a. For slabs spanning up to 4.5 m b. For slabs spanning over 4.5 m = 7 days = 14 days Removal of props to beams and arches a. Spanning up to 6 m b. Spanning over 6 m = 14 days = 21 days PERIOD FOR REMOVAL OF FORMWORK
  • 51. Chemical use in rebar Hilti Rebarring chemical (Fischer) REBAR A rebar spacer is a device that secures the reinforcing steel or "rebar" in reinforced concrete structures as the rebar is assembled in place prior to the final concrete pour. The spacers are left in place for the pour to keep the reinforcing in place, and become a permanent part of the structure.
  翻译: