å°Šę•¬ēš„ å¾®äæ”걇ēŽ‡ļ¼š1円 ā‰ˆ 0.046166 元 ę”Æä»˜å®ę±‡ēŽ‡ļ¼š1円 ā‰ˆ 0.046257元 [退å‡ŗē™»å½•]
SlideShare a Scribd company logo
Chapter 2
ļ®Process Models
1
Software Engineering: A Practitionerā€™s Approach, 7/e
by Roger S. Pressman
Slides copyright Ā© 1996, 2001, 2005, 2009 by Roger S. Pressman
Software Engineering 9/e
By Ian Sommerville
These slides are designed and adapted from slides provided by Software Engineering: A Practitionerā€™s Approach, 7/e
(McGraw-Hill 2009) by Roger Pressman and Software Engineering 9/e Addison Wesley 2011 by Ian Sommerville
Introduction to Software Engineering
Social Learning Process
ā€¢ Software is embodied knowledge that is initially dispersed,
tacit and incomplete.
ā€¢ In order to convert knowledge into software, dialogues are
needed between users and designers, between designers and
tools to bring knowledge into software.
ā€¢ Software development is essentially an iterative social
learning process, and the outcome is ā€œsoftware capitalā€.
2
What / who / why is
Process Models?
ļ® What: Go through a series of predictable steps--- a road map that helps you
create a timely, high-quality results.
ļ® Who: Software engineers and their managers, clients also. People adapt the
process to their needs and follow it.
ļ® Why: Provides stability, control, and organization to an activity that can if left
uncontrolled, become quite chaotic. However, modern software engineering
approaches must be agile and demand ONLY those activities, controls and
work products that are appropriate.
ļ® What Work products: Programs, documents, and data
ļ® What are the steps: The process you adopt depends on the software that you
are building. One process might be good for aircraft avionic system, while an
entirely different process would be used for website creation.
ļ® How to ensure right: A number of software process assessment mechanisms
that enable us to determine the maturity of the software process. However, the
quality, timeliness and long-term viability of the software are the best
indicators of the efficacy of the process you use.
3
Definition of Software
Process
ā€¢ A framework for the activities, actions, and tasks that are
required to build high-quality software.
ā€¢ SP defines the approach that is taken as software is
engineered.
ā€¢ Is not equal to software engineering, which also
encompasses technologies that populate the processā€“
technical methods and automated tools.
4
A Generic Process Model 5
A Generic Process Model
ļ®As we discussed before, a generic process framework for
software engineering defines five framework activities-
communication, planning, modeling, construction, and
deployment.
ļ®In addition, a set of umbrella activities- project tracking and
control, risk management, quality assurance, configuration
management, technical reviews, and others are applied
throughout the process.
ļ®Next question is: how the framework activities and the
actions and tasks that occur within each activity are
organized with respect to sequence and time? See the
process flow for answer.
6
Process Flow
7
Process Flow
ļ®Linear process flow executes each of the five
activities in sequence.
ļ®An iterative process flow repeats one or more of the
activities before proceeding to the next.
ļ®An evolutionary process flow executes the activities
in a circular manner. Each circuit leads to a more
complete version of the software.
ļ®A parallel process flow executes one or more
activities in parallel with other activities ( modeling
for one aspect of the software in parallel with
construction of another aspect of the software.
8
Identifying a Task Set
ļ®Before you can proceed with the process model, a
key question: what actions are appropriate for a
framework activity given the nature of the problem,
the characteristics of the people and the
stakeholders?
ļ®A task set defines the actual work to be done to
accomplish the objectives of a software engineering
action.
ļ® A list of the task to be accomplished
ļ® A list of the work products to be produced
ļ® A list of the quality assurance filters to be applied
9
Identifying a Task Set
ļ®For example, a small software project requested by
one person with simple requirements, the
communication activity might encompass little more
than a phone all with the stakeholder. Therefore, the
only necessary action is phone conversation, the work
tasks of this action are:
ļ® 1. Make contact with stakeholder via telephone.
ļ® 2. Discuss requirements and take notes.
ļ® 3. Organize notes into a brief written statement of
requirements.
ļ® 4. E-mail to stakeholder for review and approval.
10
Example of a Task Set
for Elicitation
ļ®The task sets for Requirements gathering action for a
simple project may include:
1. Make a list of stakeholders for the project.
2. Invite all stakeholders to an informal meeting.
3. Ask each stakeholder to make a list of features and
functions required.
4. Discuss requirements and build a final list.
5. Prioritize requirements.
6. Note areas of uncertainty.
11
Example of a Task Set for Elicitation
ļ®The task sets for Requirements gathering action for a big
project may include:
1. Make a list of stakeholders for the project.
2. Interview each stakeholders separately to determine overall wants and needs.
3. Build a preliminary list of functions and features based on stakeholder input.
4. Schedule a series of facilitated application specification meetings.
5. Conduct meetings.
6. Produce informal user scenarios as part of each meeting.
7. Refine user scenarios based on stakeholder feedback.
8. Build a revised list of stakeholder requirements.
9. Use quality function deployment techniques to prioritize requirements.
10. Package requirements so that they can be delivered incrementally.
11. Note constraints and restrictions that will be placed on the system.
12. Discuss methods for validating the system.
ļ® Both do the same work with different depth and formality.
Choose the task sets that achieve the goal and still maintain
quality and agility. 12
Process Patterns
ā€¢ A process pattern
ā€¢ describes a process-related problem that is encountered
during software engineering work,
ā€¢ identifies the environment in which the problem has been
encountered, and
ā€¢ suggests one or more proven solutions to the problem.
ā€¢ Stated in more general terms, a process pattern provides you
with a template [Amb98]ā€”a consistent method for describing
problem solutions within the context of the software process.
( defined at different levels of abstraction)
1. Problems and solutions associated with a complete process
model (e.g. prototyping).
2. Problems and solutions associated with a framework activity
(e.g. planning) or
3. an action with a framework activity (e.g. project estimating).
13
Process Pattern Types
ā€¢ Stage patternsā€”defines a problem associated with
a framework activity for the process. It includes
multiple task patterns as well. For example,
EstablishingCommunication would incorporate the
task pattern RequirementsGathering and others.
ā€¢ Task patternsā€”defines a problem associated with a
software engineering action or work task and
relevant to successful software engineering practice
ā€¢ Phase patternsā€”define the sequence of framework
activities that occur with the process, even when the
overall flow of activities is iterative in nature.
Example includes SprialModel or Prototyping.
14
An Example of Process Pattern
ā€¢ Describes an approach that may be applicable when stakeholders have a general idea of
what must be done but are unsure of specific software requirements.
ā€¢ Pattern name. RequiremetnsUnclear
ā€¢ Intent. This pattern describes an approach for building a model that can be assessed
iteratively by stakeholders in an effort to identify or solidify software requirements.
ā€¢ Type. Phase pattern
ā€¢ Initial context. Conditions must be met (1) stakeholders have been identified; (2)
a mode of communication between stakeholders and the software team has been
established; (3) the overriding software problem to be solved has been identified
by stakeholders ; (4) an initial understanding of project scope, basic business
requirements and project constraints has been developed.
ā€¢ Problem. Requirements are hazy or nonexistent. stakeholders are unsure of what
they want.
ā€¢ Solution. A description of the prototyping process would be presented here.
ā€¢ Resulting context. A software prototype that identifies basic requirements.
(modes of interaction, computational features, processing functions) is
approved by stakeholders. Following this, 1. This prototype may evolve through
a series of increments to become the production software or 2. the prototype
may be discarded.
ā€¢ Related patterns. CustomerCommunication, IterativeDesign,
IterativeDevelopment, CustomerAssessment, RequirementExtraction. 15
Process Assessment and Improvement
SP cannot guarantee that software will be delivered on time, meet the needs, or has the desired
technical characteristics. However, the process can be assessed to ensure that it meets a set of
basic process criteria that have been shown to be essential for a successful software engineering.
ā€¢Standard CMMI Assessment Method for Process Improvement (SCAMPI) ā€” provides a five
step process assessment model that incorporates five phases: initiating, diagnosing, establishing,
acting and learning.
ā€¢CMM-Based Appraisal for Internal Process Improvement (CBA IPI)ā€”provides a
diagnostic technique for assessing the relative maturity of a software organization; uses the
SEI CMM as the basis for the assessment [Dun01]
ā€¢SPICEā€”The SPICE (ISO/IEC15504) standard defines a set of requirements for software
process assessment. The intent of the standard is to assist organizations in developing an
objective evaluation of the efficacy of any defined software process. [ISO08]
ā€¢ISO 9001:2000 for Softwareā€”a generic standard that applies to any organization that
wants to improve the overall quality of the products, systems, or services that it provides.
Therefore, the standard is directly applicable to software organizations and companies.
[Ant06]
16
Prescriptive Models
ā€¢ Originally proposed to bring order to chaos.
ā€¢ Prescriptive process models advocate an orderly approach to software
engineering. However, will some extent of chaos (less rigid) be beneficial
to bring some creativity?
That leads to a few questions ā€¦
ā€¢ If prescriptive process models strive for structure and order (prescribe a set
of process elements and process flow), are they inappropriate for a
software world that thrives on change?
ā€¢ Yet, if we reject traditional process models (and the order they imply) and
replace them with something less structured, do we make it impossible to
achieve coordination and coherence in software work?
17
The Waterfall Model
18
It is the oldest paradigm for SE. When requirements are well
defined and reasonably stable, it leads to a linear fashion.
(problems: 1. rarely linear, iteration needed. 2. hard to state all requirements explicitly.
Blocking state. 3. code will not be released until very late.)
The classic life cycle suggests a systematic, sequential approach
to software development.
The V-Model
19
A variation of waterfall model
depicts the relationship of
quality assurance actions to
the actions associated with
communication, modeling and
early code construction
activates.
Team first moves down the left
side of the V to refine the
problem requirements. Once
code is generated, the team
moves up the right side of the
V, performing a series of tests
that validate each of the
models created as the team
moved down the left side.
The Incremental Model
20
The Incremental Model
ā€¢ When initial requirements are reasonably well defined, but
the overall scope of the development effort precludes a
purely linear process. A compelling need to expand a
limited set of new functions to a later system release.
ā€¢ It combines elements of linear and parallel process flows.
Each linear sequence produces deliverable increments of
the software.
ā€¢ The first increment is often a core product with many
supplementary features. Users use it and evaluate it with
more modifications to better meet the needs.
21
Evolutionary Models
ā€¢ Software system evolves over time as requirements often change
as development proceeds. Thus, a straight line to a complete end
product is not possible. However, a limited version must be
delivered to meet competitive pressure.
ā€¢ Usually a set of core product or system requirements is well
understood, but the details and extension have yet to be defined.
ā€¢ You need a process model that has been explicitly designed to
accommodate a product that evolved over time.
ā€¢ It is iterative that enables you to develop increasingly more
complete version of the software.
ā€¢ Two types are introduced, namely Prototyping and Spiral
models. 22
Evolutionary Models: Prototyping
ā€¢ When to use: Customer defines a set of general objectives but does not identify detailed
requirements for functions and features. Or Developer may be unsure of the efficiency
of an algorithm, the form that human computer interaction should take.
ā€¢ What step: Begins with communication by meeting with stakeholders to define the
objective, identify whatever requirements are known, outline areas where further
definition is mandatory. A quick plan for prototyping and modeling (quick design) occur.
Quick design focuses on a representation of those aspects the software that will be
visible to end users. ( interface and output). Design leads to the construction of a
prototype which will be deployed and evaluated. Stakeholderā€™s comments will be used
to refine requirements.
ā€¢ Both stakeholders and software engineers like the prototyping paradigm. Users get a feel
for the actual system, and developers get to build something immediately. However,
engineers may make compromises in order to get a prototype working quickly. The less-
than-ideal choice may be adopted forever after you get used to it. 23
Evolutionary Models: Prototyping
24
Construction
of prototype
communication
Quick
plan
Modeling
Quick design
Construction
of prototype
Deployment
delivery &
feedback
Evolutionary Models: The Spiral
ā€¢ It couples the iterative nature of prototyping with the controlled and systematic aspects of the waterfall
model and is a risk-driven process model generator that is used to guide multi-stakeholder concurrent
engineering of software intensive systems.
ā€¢ Two main distinguishing features: one is cyclic approach for incrementally growing a systemā€™s degree of
definition and implementation while decreasing its degree of risk. The other is a set of anchor point
milestones for ensuring stakeholder commitment to feasible and mutually satisfactory system solutions.
ā€¢ A series of evolutionary releases are delivered. During the early iterations, the release might be a model or
prototype. During later iterations, increasingly more complete version of the engineered system are
produced.
ā€¢ The first circuit in the clockwise direction might result in the product specification; subsequent passes
around the spiral might be used to develop a prototype and then progressively more sophisticated versions
of the software. Each pass results in adjustments to the project plan. Cost and schedule are adjusted based
on feedback. Also, the number of iterations will be adjusted by project manager.
ā€¢ Good to develop large-scale system as software evolves as the process progresses and risk should be
understood and properly reacted to. Prototyping is used to reduce risk.
ā€¢ However, it may be difficult to convince customers that it is controllable as it demands considerable risk
assessment expertise. 25
Evolutionary Models: The Spiral
26
Three Concerns on Evolutionary
Processes
ā€¢ First concern is that prototyping poses a problem to project planning because of
the uncertain number of cycles required to construct the product.
ā€¢ Second, it does not establish the maximum speed of the evolution. If the
evolution occur too fast, without a period of relaxation, it is certain that the
process will fall into chaos. On the other hand if the speed is too slow then
productivity could be affected.
ā€¢ Third, software processes should be focused on flexibility and extensibility
rather than on high quality. We should prioritize the speed of the development
over zero defects. Extending the development in order to reach high quality
could result in a late delivery of the product when the opportunity niche has
disappeared.
27
Still Other Process Models
ā€¢ Component based developmentā€”the process to apply
when reuse is a development objective ( like spiral model)
ā€¢ Formal methodsā€”emphasizes the mathematical
specification of requirements ( easy to discover and
eliminate ambiguity, incompleteness and inconsistency)
ā€¢ Aspect Oriented software development (AOSD)ā€”
provides a process and methodological approach for
defining, specifying, designing, and constructing aspects
ā€¢ Unified Processā€”a ā€œuse-case driven, architecture-centric,
iterative and incremental ā€ software process closely
aligned with the Unified Modeling Language (UML) to
model and develop object-oriented system iteratively and
incrementally.
28
The Unified Process (UP)
29
inception
elaboration
UP Phases
30
UP Work Products
31
Personal Software Process (PSP)
ā€¢ Planning. This activity isolates requirements and develops both size and resource estimates. In
addition, a defect estimate (the number of defects projected for the work) is made. All metrics are
recorded on worksheets or templates. Finally, development tasks are identified and a project
schedule is created.
ā€¢ High-level design. External specifications for each component to be constructed are developed
and a component design is created. Prototypes are built when uncertainty exists. All issues are
recorded and tracked.
ā€¢ High-level design review. Formal verification methods (Chapter 21) are applied to uncover errors
in the design. Metrics are maintained for all important tasks and work results.
ā€¢ Development. The component level design is refined and reviewed. Code is generated,
reviewed, compiled, and tested. Metrics are maintained for all important tasks and work results.
ā€¢ Postmortem. Using the measures and metrics collected (this is a substantial amount of data that
should be analyzed statistically), the effectiveness of the process is determined. Measures and
metrics should provide guidance for modifying the process to improve its effectiveness.
32
Team Software Process (TSP)
ļ® Build self-directed teams that plan and track their work,
establish goals, and own their processes and plans. These can
be pure software teams or integrated product teams (IPT) of
three to about 20 engineers.
ļ® Show managers how to coach and motivate their teams and
how to help them sustain peak performance.
ļ® Accelerate software process improvement by making CMM
Level 5 behavior normal and expected.
ļ® The Capability Maturity Model (CMM), a measure of the effectiveness
of a software process, is discussed in Chapter 30.
ļ® Provide improvement guidance to high-maturity organizations.
ļ® Facilitate university teaching of industrial-grade team skills.
33

More Related Content

Similar to Week_02.pptx

Software models
Software modelsSoftware models
Software models
MOULA HUSSAIN KHATTHEWALE
Ā 
Elementary Probability theory Chapter 2.pptx
Elementary Probability theory Chapter 2.pptxElementary Probability theory Chapter 2.pptx
Elementary Probability theory Chapter 2.pptx
ethiouniverse
Ā 
Lightweight Processes: A Definition
Lightweight Processes: A DefinitionLightweight Processes: A Definition
Lightweight Processes: A Definition
Glen Alleman
Ā 
Sdpl1
Sdpl1Sdpl1
Sdpl1
sraviinthiran
Ā 
Ch 02 s.e software process models 1
Ch 02 s.e software process models   1Ch 02 s.e software process models   1
Ch 02 s.e software process models 1
Badar Waseer
Ā 
Mi0033 software engineering
Mi0033  software engineeringMi0033  software engineering
Mi0033 software engineering
smumbahelp
Ā 
Software testing and introduction to quality
Software testing and introduction to qualitySoftware testing and introduction to quality
Software testing and introduction to quality
DhanashriAmbre
Ā 
Slcm sharbani bhattacharya
Slcm sharbani bhattacharyaSlcm sharbani bhattacharya
Slcm sharbani bhattacharya
Sharbani Bhattacharya
Ā 
UNIT-I.pptx
UNIT-I.pptxUNIT-I.pptx
UNIT-I.pptx
sayalishivarkar1
Ā 
Mi0033 software engineering
Mi0033  software engineeringMi0033  software engineering
Mi0033 software engineering
smumbahelp
Ā 
SOFTWARE ENGINEERING FOR BEGINNERS UNIT 1.pptx
SOFTWARE ENGINEERING FOR BEGINNERS UNIT 1.pptxSOFTWARE ENGINEERING FOR BEGINNERS UNIT 1.pptx
SOFTWARE ENGINEERING FOR BEGINNERS UNIT 1.pptx
MrsShakiraFathimaH
Ā 
Various Process of Software Engineering notes
Various Process of Software Engineering notesVarious Process of Software Engineering notes
Various Process of Software Engineering notes
Dr Anuranjan Misra
Ā 
Softweare Engieering
Softweare Engieering Softweare Engieering
Softweare Engieering
Huda Alameen
Ā 
Se lec 3
Se lec 3Se lec 3
Se lec 3
Huda Alameen
Ā 
Software Engineering Practices and Issues.pptx
Software Engineering Practices and Issues.pptxSoftware Engineering Practices and Issues.pptx
Software Engineering Practices and Issues.pptx
Nikilesh8
Ā 
Chapter 2_Process Models sunorgamisedASE_finalised.ppt
Chapter 2_Process Models sunorgamisedASE_finalised.pptChapter 2_Process Models sunorgamisedASE_finalised.ppt
Chapter 2_Process Models sunorgamisedASE_finalised.ppt
Bule Hora University
Ā 
Chapter-2 ppt for the MBA 4rh seme6y.pdf
Chapter-2 ppt for the MBA 4rh seme6y.pdfChapter-2 ppt for the MBA 4rh seme6y.pdf
Chapter-2 ppt for the MBA 4rh seme6y.pdf
VikasRai405977
Ā 
SoftwareEngineering.pptx
SoftwareEngineering.pptxSoftwareEngineering.pptx
SoftwareEngineering.pptx
DrPrabakaranPerumal
Ā 
SoftwareEngineering.pptx
SoftwareEngineering.pptxSoftwareEngineering.pptx
SoftwareEngineering.pptx
priyaaresearch
Ā 
Lecture 2 introduction to Software Engineering 1
Lecture 2   introduction to Software Engineering 1Lecture 2   introduction to Software Engineering 1
Lecture 2 introduction to Software Engineering 1
IIUI
Ā 

Similar to Week_02.pptx (20)

Software models
Software modelsSoftware models
Software models
Ā 
Elementary Probability theory Chapter 2.pptx
Elementary Probability theory Chapter 2.pptxElementary Probability theory Chapter 2.pptx
Elementary Probability theory Chapter 2.pptx
Ā 
Lightweight Processes: A Definition
Lightweight Processes: A DefinitionLightweight Processes: A Definition
Lightweight Processes: A Definition
Ā 
Sdpl1
Sdpl1Sdpl1
Sdpl1
Ā 
Ch 02 s.e software process models 1
Ch 02 s.e software process models   1Ch 02 s.e software process models   1
Ch 02 s.e software process models 1
Ā 
Mi0033 software engineering
Mi0033  software engineeringMi0033  software engineering
Mi0033 software engineering
Ā 
Software testing and introduction to quality
Software testing and introduction to qualitySoftware testing and introduction to quality
Software testing and introduction to quality
Ā 
Slcm sharbani bhattacharya
Slcm sharbani bhattacharyaSlcm sharbani bhattacharya
Slcm sharbani bhattacharya
Ā 
UNIT-I.pptx
UNIT-I.pptxUNIT-I.pptx
UNIT-I.pptx
Ā 
Mi0033 software engineering
Mi0033  software engineeringMi0033  software engineering
Mi0033 software engineering
Ā 
SOFTWARE ENGINEERING FOR BEGINNERS UNIT 1.pptx
SOFTWARE ENGINEERING FOR BEGINNERS UNIT 1.pptxSOFTWARE ENGINEERING FOR BEGINNERS UNIT 1.pptx
SOFTWARE ENGINEERING FOR BEGINNERS UNIT 1.pptx
Ā 
Various Process of Software Engineering notes
Various Process of Software Engineering notesVarious Process of Software Engineering notes
Various Process of Software Engineering notes
Ā 
Softweare Engieering
Softweare Engieering Softweare Engieering
Softweare Engieering
Ā 
Se lec 3
Se lec 3Se lec 3
Se lec 3
Ā 
Software Engineering Practices and Issues.pptx
Software Engineering Practices and Issues.pptxSoftware Engineering Practices and Issues.pptx
Software Engineering Practices and Issues.pptx
Ā 
Chapter 2_Process Models sunorgamisedASE_finalised.ppt
Chapter 2_Process Models sunorgamisedASE_finalised.pptChapter 2_Process Models sunorgamisedASE_finalised.ppt
Chapter 2_Process Models sunorgamisedASE_finalised.ppt
Ā 
Chapter-2 ppt for the MBA 4rh seme6y.pdf
Chapter-2 ppt for the MBA 4rh seme6y.pdfChapter-2 ppt for the MBA 4rh seme6y.pdf
Chapter-2 ppt for the MBA 4rh seme6y.pdf
Ā 
SoftwareEngineering.pptx
SoftwareEngineering.pptxSoftwareEngineering.pptx
SoftwareEngineering.pptx
Ā 
SoftwareEngineering.pptx
SoftwareEngineering.pptxSoftwareEngineering.pptx
SoftwareEngineering.pptx
Ā 
Lecture 2 introduction to Software Engineering 1
Lecture 2   introduction to Software Engineering 1Lecture 2   introduction to Software Engineering 1
Lecture 2 introduction to Software Engineering 1
Ā 

Recently uploaded

Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
sexytaniya455
Ā 
Call Girls Chennai +91-8824825030 Vip Call Girls Chennai
Call Girls Chennai +91-8824825030 Vip Call Girls ChennaiCall Girls Chennai +91-8824825030 Vip Call Girls Chennai
Call Girls Chennai +91-8824825030 Vip Call Girls Chennai
paraasingh12 #V08
Ā 
šŸ”„Young College Call Girls Chandigarh šŸ’ÆCall Us šŸ” 7737669865 šŸ”šŸ’ƒIndependent Chan...
šŸ”„Young College Call Girls Chandigarh šŸ’ÆCall Us šŸ” 7737669865 šŸ”šŸ’ƒIndependent Chan...šŸ”„Young College Call Girls Chandigarh šŸ’ÆCall Us šŸ” 7737669865 šŸ”šŸ’ƒIndependent Chan...
šŸ”„Young College Call Girls Chandigarh šŸ’ÆCall Us šŸ” 7737669865 šŸ”šŸ’ƒIndependent Chan...
sonamrawat5631
Ā 
Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine
Ā 
Call Girls In Tiruppur šŸ‘Æā€ā™€ļø 7339748667 šŸ”„ Free Home Delivery Within 30 Minutes
Call Girls In Tiruppur šŸ‘Æā€ā™€ļø 7339748667 šŸ”„ Free Home Delivery Within 30 MinutesCall Girls In Tiruppur šŸ‘Æā€ā™€ļø 7339748667 šŸ”„ Free Home Delivery Within 30 Minutes
Call Girls In Tiruppur šŸ‘Æā€ā™€ļø 7339748667 šŸ”„ Free Home Delivery Within 30 Minutes
kamka4105
Ā 
šŸ”„ Hyderabad Call Girls Ā šŸ‘‰ 9352988975 šŸ‘« High Profile Call Girls Whatsapp Numbe...
šŸ”„ Hyderabad Call Girls Ā šŸ‘‰ 9352988975 šŸ‘« High Profile Call Girls Whatsapp Numbe...šŸ”„ Hyderabad Call Girls Ā šŸ‘‰ 9352988975 šŸ‘« High Profile Call Girls Whatsapp Numbe...
šŸ”„ Hyderabad Call Girls Ā šŸ‘‰ 9352988975 šŸ‘« High Profile Call Girls Whatsapp Numbe...
aarusi sexy model
Ā 
Covid Management System Project Report.pdf
Covid Management System Project Report.pdfCovid Management System Project Report.pdf
Covid Management System Project Report.pdf
Kamal Acharya
Ā 
My Airframe Metallic Design Capability Studies..pdf
My Airframe Metallic Design Capability Studies..pdfMy Airframe Metallic Design Capability Studies..pdf
My Airframe Metallic Design Capability Studies..pdf
Geoffrey Wardle. MSc. MSc. Snr.MAIAA
Ā 
Mahipalpur Call Girls Delhi šŸ”„ 9711199012 ā„- Pick Your Dream Call Girls with 1...
Mahipalpur Call Girls Delhi šŸ”„ 9711199012 ā„- Pick Your Dream Call Girls with 1...Mahipalpur Call Girls Delhi šŸ”„ 9711199012 ā„- Pick Your Dream Call Girls with 1...
Mahipalpur Call Girls Delhi šŸ”„ 9711199012 ā„- Pick Your Dream Call Girls with 1...
simrangupta87541
Ā 
Cuttack Call Girls šŸ’ÆCall Us šŸ” 7374876321 šŸ” šŸ’ƒ Independent Female Escort Service
Cuttack Call Girls šŸ’ÆCall Us šŸ” 7374876321 šŸ” šŸ’ƒ Independent Female Escort ServiceCuttack Call Girls šŸ’ÆCall Us šŸ” 7374876321 šŸ” šŸ’ƒ Independent Female Escort Service
Cuttack Call Girls šŸ’ÆCall Us šŸ” 7374876321 šŸ” šŸ’ƒ Independent Female Escort Service
yakranividhrini
Ā 
Technological Innovation Management And Entrepreneurship-1.pdf
Technological Innovation Management And Entrepreneurship-1.pdfTechnological Innovation Management And Entrepreneurship-1.pdf
Technological Innovation Management And Entrepreneurship-1.pdf
tanujaharish2
Ā 
Cricket management system ptoject report.pdf
Cricket management system ptoject report.pdfCricket management system ptoject report.pdf
Cricket management system ptoject report.pdf
Kamal Acharya
Ā 
Basic principle and types Static Relays ppt
Basic principle and  types  Static Relays pptBasic principle and  types  Static Relays ppt
Basic principle and types Static Relays ppt
Sri Ramakrishna Institute of Technology
Ā 
šŸ”„Independent Call Girls In Pune šŸ’ÆCall Us šŸ” 7014168258 šŸ”šŸ’ƒIndependent Pune Esco...
šŸ”„Independent Call Girls In Pune šŸ’ÆCall Us šŸ” 7014168258 šŸ”šŸ’ƒIndependent Pune Esco...šŸ”„Independent Call Girls In Pune šŸ’ÆCall Us šŸ” 7014168258 šŸ”šŸ’ƒIndependent Pune Esco...
šŸ”„Independent Call Girls In Pune šŸ’ÆCall Us šŸ” 7014168258 šŸ”šŸ’ƒIndependent Pune Esco...
AK47
Ā 
Call Girls In Lucknow šŸ”„ +91-7014168258šŸ”„High Profile Call Girl Lucknow
Call Girls In Lucknow šŸ”„ +91-7014168258šŸ”„High Profile Call Girl LucknowCall Girls In Lucknow šŸ”„ +91-7014168258šŸ”„High Profile Call Girl Lucknow
Call Girls In Lucknow šŸ”„ +91-7014168258šŸ”„High Profile Call Girl Lucknow
yogita singh$A17
Ā 
Lateral load-resisting systems in buildings.pptx
Lateral load-resisting systems in buildings.pptxLateral load-resisting systems in buildings.pptx
Lateral load-resisting systems in buildings.pptx
DebendraDevKhanal1
Ā 
Intuit CRAFT demonstration presentation for sde
Intuit CRAFT demonstration presentation for sdeIntuit CRAFT demonstration presentation for sde
Intuit CRAFT demonstration presentation for sde
ShivangMishra54
Ā 
Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...
Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...
Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...
Dr.Costas Sachpazis
Ā 
Call Girls Chandigarh šŸ”„ 7014168258 šŸ”„ Real Fun With Sexual Girl Available 24/7...
Call Girls Chandigarh šŸ”„ 7014168258 šŸ”„ Real Fun With Sexual Girl Available 24/7...Call Girls Chandigarh šŸ”„ 7014168258 šŸ”„ Real Fun With Sexual Girl Available 24/7...
Call Girls Chandigarh šŸ”„ 7014168258 šŸ”„ Real Fun With Sexual Girl Available 24/7...
shourabjaat424
Ā 
SPICE PARK JUL2024 ( 6,866 SPICE Models )
SPICE PARK JUL2024 ( 6,866 SPICE Models )SPICE PARK JUL2024 ( 6,866 SPICE Models )
SPICE PARK JUL2024 ( 6,866 SPICE Models )
Tsuyoshi Horigome
Ā 

Recently uploaded (20)

Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Ā 
Call Girls Chennai +91-8824825030 Vip Call Girls Chennai
Call Girls Chennai +91-8824825030 Vip Call Girls ChennaiCall Girls Chennai +91-8824825030 Vip Call Girls Chennai
Call Girls Chennai +91-8824825030 Vip Call Girls Chennai
Ā 
šŸ”„Young College Call Girls Chandigarh šŸ’ÆCall Us šŸ” 7737669865 šŸ”šŸ’ƒIndependent Chan...
šŸ”„Young College Call Girls Chandigarh šŸ’ÆCall Us šŸ” 7737669865 šŸ”šŸ’ƒIndependent Chan...šŸ”„Young College Call Girls Chandigarh šŸ’ÆCall Us šŸ” 7737669865 šŸ”šŸ’ƒIndependent Chan...
šŸ”„Young College Call Girls Chandigarh šŸ’ÆCall Us šŸ” 7737669865 šŸ”šŸ’ƒIndependent Chan...
Ā 
Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024
Ā 
Call Girls In Tiruppur šŸ‘Æā€ā™€ļø 7339748667 šŸ”„ Free Home Delivery Within 30 Minutes
Call Girls In Tiruppur šŸ‘Æā€ā™€ļø 7339748667 šŸ”„ Free Home Delivery Within 30 MinutesCall Girls In Tiruppur šŸ‘Æā€ā™€ļø 7339748667 šŸ”„ Free Home Delivery Within 30 Minutes
Call Girls In Tiruppur šŸ‘Æā€ā™€ļø 7339748667 šŸ”„ Free Home Delivery Within 30 Minutes
Ā 
šŸ”„ Hyderabad Call Girls Ā šŸ‘‰ 9352988975 šŸ‘« High Profile Call Girls Whatsapp Numbe...
šŸ”„ Hyderabad Call Girls Ā šŸ‘‰ 9352988975 šŸ‘« High Profile Call Girls Whatsapp Numbe...šŸ”„ Hyderabad Call Girls Ā šŸ‘‰ 9352988975 šŸ‘« High Profile Call Girls Whatsapp Numbe...
šŸ”„ Hyderabad Call Girls Ā šŸ‘‰ 9352988975 šŸ‘« High Profile Call Girls Whatsapp Numbe...
Ā 
Covid Management System Project Report.pdf
Covid Management System Project Report.pdfCovid Management System Project Report.pdf
Covid Management System Project Report.pdf
Ā 
My Airframe Metallic Design Capability Studies..pdf
My Airframe Metallic Design Capability Studies..pdfMy Airframe Metallic Design Capability Studies..pdf
My Airframe Metallic Design Capability Studies..pdf
Ā 
Mahipalpur Call Girls Delhi šŸ”„ 9711199012 ā„- Pick Your Dream Call Girls with 1...
Mahipalpur Call Girls Delhi šŸ”„ 9711199012 ā„- Pick Your Dream Call Girls with 1...Mahipalpur Call Girls Delhi šŸ”„ 9711199012 ā„- Pick Your Dream Call Girls with 1...
Mahipalpur Call Girls Delhi šŸ”„ 9711199012 ā„- Pick Your Dream Call Girls with 1...
Ā 
Cuttack Call Girls šŸ’ÆCall Us šŸ” 7374876321 šŸ” šŸ’ƒ Independent Female Escort Service
Cuttack Call Girls šŸ’ÆCall Us šŸ” 7374876321 šŸ” šŸ’ƒ Independent Female Escort ServiceCuttack Call Girls šŸ’ÆCall Us šŸ” 7374876321 šŸ” šŸ’ƒ Independent Female Escort Service
Cuttack Call Girls šŸ’ÆCall Us šŸ” 7374876321 šŸ” šŸ’ƒ Independent Female Escort Service
Ā 
Technological Innovation Management And Entrepreneurship-1.pdf
Technological Innovation Management And Entrepreneurship-1.pdfTechnological Innovation Management And Entrepreneurship-1.pdf
Technological Innovation Management And Entrepreneurship-1.pdf
Ā 
Cricket management system ptoject report.pdf
Cricket management system ptoject report.pdfCricket management system ptoject report.pdf
Cricket management system ptoject report.pdf
Ā 
Basic principle and types Static Relays ppt
Basic principle and  types  Static Relays pptBasic principle and  types  Static Relays ppt
Basic principle and types Static Relays ppt
Ā 
šŸ”„Independent Call Girls In Pune šŸ’ÆCall Us šŸ” 7014168258 šŸ”šŸ’ƒIndependent Pune Esco...
šŸ”„Independent Call Girls In Pune šŸ’ÆCall Us šŸ” 7014168258 šŸ”šŸ’ƒIndependent Pune Esco...šŸ”„Independent Call Girls In Pune šŸ’ÆCall Us šŸ” 7014168258 šŸ”šŸ’ƒIndependent Pune Esco...
šŸ”„Independent Call Girls In Pune šŸ’ÆCall Us šŸ” 7014168258 šŸ”šŸ’ƒIndependent Pune Esco...
Ā 
Call Girls In Lucknow šŸ”„ +91-7014168258šŸ”„High Profile Call Girl Lucknow
Call Girls In Lucknow šŸ”„ +91-7014168258šŸ”„High Profile Call Girl LucknowCall Girls In Lucknow šŸ”„ +91-7014168258šŸ”„High Profile Call Girl Lucknow
Call Girls In Lucknow šŸ”„ +91-7014168258šŸ”„High Profile Call Girl Lucknow
Ā 
Lateral load-resisting systems in buildings.pptx
Lateral load-resisting systems in buildings.pptxLateral load-resisting systems in buildings.pptx
Lateral load-resisting systems in buildings.pptx
Ā 
Intuit CRAFT demonstration presentation for sde
Intuit CRAFT demonstration presentation for sdeIntuit CRAFT demonstration presentation for sde
Intuit CRAFT demonstration presentation for sde
Ā 
Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...
Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...
Sachpazis_Consolidation Settlement Calculation Program-The Python Code and th...
Ā 
Call Girls Chandigarh šŸ”„ 7014168258 šŸ”„ Real Fun With Sexual Girl Available 24/7...
Call Girls Chandigarh šŸ”„ 7014168258 šŸ”„ Real Fun With Sexual Girl Available 24/7...Call Girls Chandigarh šŸ”„ 7014168258 šŸ”„ Real Fun With Sexual Girl Available 24/7...
Call Girls Chandigarh šŸ”„ 7014168258 šŸ”„ Real Fun With Sexual Girl Available 24/7...
Ā 
SPICE PARK JUL2024 ( 6,866 SPICE Models )
SPICE PARK JUL2024 ( 6,866 SPICE Models )SPICE PARK JUL2024 ( 6,866 SPICE Models )
SPICE PARK JUL2024 ( 6,866 SPICE Models )
Ā 

Week_02.pptx

  • 1. Chapter 2 ļ®Process Models 1 Software Engineering: A Practitionerā€™s Approach, 7/e by Roger S. Pressman Slides copyright Ā© 1996, 2001, 2005, 2009 by Roger S. Pressman Software Engineering 9/e By Ian Sommerville These slides are designed and adapted from slides provided by Software Engineering: A Practitionerā€™s Approach, 7/e (McGraw-Hill 2009) by Roger Pressman and Software Engineering 9/e Addison Wesley 2011 by Ian Sommerville Introduction to Software Engineering
  • 2. Social Learning Process ā€¢ Software is embodied knowledge that is initially dispersed, tacit and incomplete. ā€¢ In order to convert knowledge into software, dialogues are needed between users and designers, between designers and tools to bring knowledge into software. ā€¢ Software development is essentially an iterative social learning process, and the outcome is ā€œsoftware capitalā€. 2
  • 3. What / who / why is Process Models? ļ® What: Go through a series of predictable steps--- a road map that helps you create a timely, high-quality results. ļ® Who: Software engineers and their managers, clients also. People adapt the process to their needs and follow it. ļ® Why: Provides stability, control, and organization to an activity that can if left uncontrolled, become quite chaotic. However, modern software engineering approaches must be agile and demand ONLY those activities, controls and work products that are appropriate. ļ® What Work products: Programs, documents, and data ļ® What are the steps: The process you adopt depends on the software that you are building. One process might be good for aircraft avionic system, while an entirely different process would be used for website creation. ļ® How to ensure right: A number of software process assessment mechanisms that enable us to determine the maturity of the software process. However, the quality, timeliness and long-term viability of the software are the best indicators of the efficacy of the process you use. 3
  • 4. Definition of Software Process ā€¢ A framework for the activities, actions, and tasks that are required to build high-quality software. ā€¢ SP defines the approach that is taken as software is engineered. ā€¢ Is not equal to software engineering, which also encompasses technologies that populate the processā€“ technical methods and automated tools. 4
  • 6. A Generic Process Model ļ®As we discussed before, a generic process framework for software engineering defines five framework activities- communication, planning, modeling, construction, and deployment. ļ®In addition, a set of umbrella activities- project tracking and control, risk management, quality assurance, configuration management, technical reviews, and others are applied throughout the process. ļ®Next question is: how the framework activities and the actions and tasks that occur within each activity are organized with respect to sequence and time? See the process flow for answer. 6
  • 8. Process Flow ļ®Linear process flow executes each of the five activities in sequence. ļ®An iterative process flow repeats one or more of the activities before proceeding to the next. ļ®An evolutionary process flow executes the activities in a circular manner. Each circuit leads to a more complete version of the software. ļ®A parallel process flow executes one or more activities in parallel with other activities ( modeling for one aspect of the software in parallel with construction of another aspect of the software. 8
  • 9. Identifying a Task Set ļ®Before you can proceed with the process model, a key question: what actions are appropriate for a framework activity given the nature of the problem, the characteristics of the people and the stakeholders? ļ®A task set defines the actual work to be done to accomplish the objectives of a software engineering action. ļ® A list of the task to be accomplished ļ® A list of the work products to be produced ļ® A list of the quality assurance filters to be applied 9
  • 10. Identifying a Task Set ļ®For example, a small software project requested by one person with simple requirements, the communication activity might encompass little more than a phone all with the stakeholder. Therefore, the only necessary action is phone conversation, the work tasks of this action are: ļ® 1. Make contact with stakeholder via telephone. ļ® 2. Discuss requirements and take notes. ļ® 3. Organize notes into a brief written statement of requirements. ļ® 4. E-mail to stakeholder for review and approval. 10
  • 11. Example of a Task Set for Elicitation ļ®The task sets for Requirements gathering action for a simple project may include: 1. Make a list of stakeholders for the project. 2. Invite all stakeholders to an informal meeting. 3. Ask each stakeholder to make a list of features and functions required. 4. Discuss requirements and build a final list. 5. Prioritize requirements. 6. Note areas of uncertainty. 11
  • 12. Example of a Task Set for Elicitation ļ®The task sets for Requirements gathering action for a big project may include: 1. Make a list of stakeholders for the project. 2. Interview each stakeholders separately to determine overall wants and needs. 3. Build a preliminary list of functions and features based on stakeholder input. 4. Schedule a series of facilitated application specification meetings. 5. Conduct meetings. 6. Produce informal user scenarios as part of each meeting. 7. Refine user scenarios based on stakeholder feedback. 8. Build a revised list of stakeholder requirements. 9. Use quality function deployment techniques to prioritize requirements. 10. Package requirements so that they can be delivered incrementally. 11. Note constraints and restrictions that will be placed on the system. 12. Discuss methods for validating the system. ļ® Both do the same work with different depth and formality. Choose the task sets that achieve the goal and still maintain quality and agility. 12
  • 13. Process Patterns ā€¢ A process pattern ā€¢ describes a process-related problem that is encountered during software engineering work, ā€¢ identifies the environment in which the problem has been encountered, and ā€¢ suggests one or more proven solutions to the problem. ā€¢ Stated in more general terms, a process pattern provides you with a template [Amb98]ā€”a consistent method for describing problem solutions within the context of the software process. ( defined at different levels of abstraction) 1. Problems and solutions associated with a complete process model (e.g. prototyping). 2. Problems and solutions associated with a framework activity (e.g. planning) or 3. an action with a framework activity (e.g. project estimating). 13
  • 14. Process Pattern Types ā€¢ Stage patternsā€”defines a problem associated with a framework activity for the process. It includes multiple task patterns as well. For example, EstablishingCommunication would incorporate the task pattern RequirementsGathering and others. ā€¢ Task patternsā€”defines a problem associated with a software engineering action or work task and relevant to successful software engineering practice ā€¢ Phase patternsā€”define the sequence of framework activities that occur with the process, even when the overall flow of activities is iterative in nature. Example includes SprialModel or Prototyping. 14
  • 15. An Example of Process Pattern ā€¢ Describes an approach that may be applicable when stakeholders have a general idea of what must be done but are unsure of specific software requirements. ā€¢ Pattern name. RequiremetnsUnclear ā€¢ Intent. This pattern describes an approach for building a model that can be assessed iteratively by stakeholders in an effort to identify or solidify software requirements. ā€¢ Type. Phase pattern ā€¢ Initial context. Conditions must be met (1) stakeholders have been identified; (2) a mode of communication between stakeholders and the software team has been established; (3) the overriding software problem to be solved has been identified by stakeholders ; (4) an initial understanding of project scope, basic business requirements and project constraints has been developed. ā€¢ Problem. Requirements are hazy or nonexistent. stakeholders are unsure of what they want. ā€¢ Solution. A description of the prototyping process would be presented here. ā€¢ Resulting context. A software prototype that identifies basic requirements. (modes of interaction, computational features, processing functions) is approved by stakeholders. Following this, 1. This prototype may evolve through a series of increments to become the production software or 2. the prototype may be discarded. ā€¢ Related patterns. CustomerCommunication, IterativeDesign, IterativeDevelopment, CustomerAssessment, RequirementExtraction. 15
  • 16. Process Assessment and Improvement SP cannot guarantee that software will be delivered on time, meet the needs, or has the desired technical characteristics. However, the process can be assessed to ensure that it meets a set of basic process criteria that have been shown to be essential for a successful software engineering. ā€¢Standard CMMI Assessment Method for Process Improvement (SCAMPI) ā€” provides a five step process assessment model that incorporates five phases: initiating, diagnosing, establishing, acting and learning. ā€¢CMM-Based Appraisal for Internal Process Improvement (CBA IPI)ā€”provides a diagnostic technique for assessing the relative maturity of a software organization; uses the SEI CMM as the basis for the assessment [Dun01] ā€¢SPICEā€”The SPICE (ISO/IEC15504) standard defines a set of requirements for software process assessment. The intent of the standard is to assist organizations in developing an objective evaluation of the efficacy of any defined software process. [ISO08] ā€¢ISO 9001:2000 for Softwareā€”a generic standard that applies to any organization that wants to improve the overall quality of the products, systems, or services that it provides. Therefore, the standard is directly applicable to software organizations and companies. [Ant06] 16
  • 17. Prescriptive Models ā€¢ Originally proposed to bring order to chaos. ā€¢ Prescriptive process models advocate an orderly approach to software engineering. However, will some extent of chaos (less rigid) be beneficial to bring some creativity? That leads to a few questions ā€¦ ā€¢ If prescriptive process models strive for structure and order (prescribe a set of process elements and process flow), are they inappropriate for a software world that thrives on change? ā€¢ Yet, if we reject traditional process models (and the order they imply) and replace them with something less structured, do we make it impossible to achieve coordination and coherence in software work? 17
  • 18. The Waterfall Model 18 It is the oldest paradigm for SE. When requirements are well defined and reasonably stable, it leads to a linear fashion. (problems: 1. rarely linear, iteration needed. 2. hard to state all requirements explicitly. Blocking state. 3. code will not be released until very late.) The classic life cycle suggests a systematic, sequential approach to software development.
  • 19. The V-Model 19 A variation of waterfall model depicts the relationship of quality assurance actions to the actions associated with communication, modeling and early code construction activates. Team first moves down the left side of the V to refine the problem requirements. Once code is generated, the team moves up the right side of the V, performing a series of tests that validate each of the models created as the team moved down the left side.
  • 21. The Incremental Model ā€¢ When initial requirements are reasonably well defined, but the overall scope of the development effort precludes a purely linear process. A compelling need to expand a limited set of new functions to a later system release. ā€¢ It combines elements of linear and parallel process flows. Each linear sequence produces deliverable increments of the software. ā€¢ The first increment is often a core product with many supplementary features. Users use it and evaluate it with more modifications to better meet the needs. 21
  • 22. Evolutionary Models ā€¢ Software system evolves over time as requirements often change as development proceeds. Thus, a straight line to a complete end product is not possible. However, a limited version must be delivered to meet competitive pressure. ā€¢ Usually a set of core product or system requirements is well understood, but the details and extension have yet to be defined. ā€¢ You need a process model that has been explicitly designed to accommodate a product that evolved over time. ā€¢ It is iterative that enables you to develop increasingly more complete version of the software. ā€¢ Two types are introduced, namely Prototyping and Spiral models. 22
  • 23. Evolutionary Models: Prototyping ā€¢ When to use: Customer defines a set of general objectives but does not identify detailed requirements for functions and features. Or Developer may be unsure of the efficiency of an algorithm, the form that human computer interaction should take. ā€¢ What step: Begins with communication by meeting with stakeholders to define the objective, identify whatever requirements are known, outline areas where further definition is mandatory. A quick plan for prototyping and modeling (quick design) occur. Quick design focuses on a representation of those aspects the software that will be visible to end users. ( interface and output). Design leads to the construction of a prototype which will be deployed and evaluated. Stakeholderā€™s comments will be used to refine requirements. ā€¢ Both stakeholders and software engineers like the prototyping paradigm. Users get a feel for the actual system, and developers get to build something immediately. However, engineers may make compromises in order to get a prototype working quickly. The less- than-ideal choice may be adopted forever after you get used to it. 23
  • 24. Evolutionary Models: Prototyping 24 Construction of prototype communication Quick plan Modeling Quick design Construction of prototype Deployment delivery & feedback
  • 25. Evolutionary Models: The Spiral ā€¢ It couples the iterative nature of prototyping with the controlled and systematic aspects of the waterfall model and is a risk-driven process model generator that is used to guide multi-stakeholder concurrent engineering of software intensive systems. ā€¢ Two main distinguishing features: one is cyclic approach for incrementally growing a systemā€™s degree of definition and implementation while decreasing its degree of risk. The other is a set of anchor point milestones for ensuring stakeholder commitment to feasible and mutually satisfactory system solutions. ā€¢ A series of evolutionary releases are delivered. During the early iterations, the release might be a model or prototype. During later iterations, increasingly more complete version of the engineered system are produced. ā€¢ The first circuit in the clockwise direction might result in the product specification; subsequent passes around the spiral might be used to develop a prototype and then progressively more sophisticated versions of the software. Each pass results in adjustments to the project plan. Cost and schedule are adjusted based on feedback. Also, the number of iterations will be adjusted by project manager. ā€¢ Good to develop large-scale system as software evolves as the process progresses and risk should be understood and properly reacted to. Prototyping is used to reduce risk. ā€¢ However, it may be difficult to convince customers that it is controllable as it demands considerable risk assessment expertise. 25
  • 27. Three Concerns on Evolutionary Processes ā€¢ First concern is that prototyping poses a problem to project planning because of the uncertain number of cycles required to construct the product. ā€¢ Second, it does not establish the maximum speed of the evolution. If the evolution occur too fast, without a period of relaxation, it is certain that the process will fall into chaos. On the other hand if the speed is too slow then productivity could be affected. ā€¢ Third, software processes should be focused on flexibility and extensibility rather than on high quality. We should prioritize the speed of the development over zero defects. Extending the development in order to reach high quality could result in a late delivery of the product when the opportunity niche has disappeared. 27
  • 28. Still Other Process Models ā€¢ Component based developmentā€”the process to apply when reuse is a development objective ( like spiral model) ā€¢ Formal methodsā€”emphasizes the mathematical specification of requirements ( easy to discover and eliminate ambiguity, incompleteness and inconsistency) ā€¢ Aspect Oriented software development (AOSD)ā€” provides a process and methodological approach for defining, specifying, designing, and constructing aspects ā€¢ Unified Processā€”a ā€œuse-case driven, architecture-centric, iterative and incremental ā€ software process closely aligned with the Unified Modeling Language (UML) to model and develop object-oriented system iteratively and incrementally. 28
  • 29. The Unified Process (UP) 29 inception elaboration
  • 32. Personal Software Process (PSP) ā€¢ Planning. This activity isolates requirements and develops both size and resource estimates. In addition, a defect estimate (the number of defects projected for the work) is made. All metrics are recorded on worksheets or templates. Finally, development tasks are identified and a project schedule is created. ā€¢ High-level design. External specifications for each component to be constructed are developed and a component design is created. Prototypes are built when uncertainty exists. All issues are recorded and tracked. ā€¢ High-level design review. Formal verification methods (Chapter 21) are applied to uncover errors in the design. Metrics are maintained for all important tasks and work results. ā€¢ Development. The component level design is refined and reviewed. Code is generated, reviewed, compiled, and tested. Metrics are maintained for all important tasks and work results. ā€¢ Postmortem. Using the measures and metrics collected (this is a substantial amount of data that should be analyzed statistically), the effectiveness of the process is determined. Measures and metrics should provide guidance for modifying the process to improve its effectiveness. 32
  • 33. Team Software Process (TSP) ļ® Build self-directed teams that plan and track their work, establish goals, and own their processes and plans. These can be pure software teams or integrated product teams (IPT) of three to about 20 engineers. ļ® Show managers how to coach and motivate their teams and how to help them sustain peak performance. ļ® Accelerate software process improvement by making CMM Level 5 behavior normal and expected. ļ® The Capability Maturity Model (CMM), a measure of the effectiveness of a software process, is discussed in Chapter 30. ļ® Provide improvement guidance to high-maturity organizations. ļ® Facilitate university teaching of industrial-grade team skills. 33
  ēæ»čƑļ¼š