This document provides details of a project report submitted for a Bachelor of Technology degree in Civil Engineering. It summarizes the industrial training completed at a construction site for a multi-story residential building project in Lucknow, India. The report describes the construction steps and processes, including site clearance, excavation, foundation work, concrete work, formwork used, and quality control measures. It also provides an overview of the materials and equipment used at the construction site.
Summer Internship Report of Civil Engineering in Construction SiteRAVI KUMAR
The document provides details about the internship completed by Ravi Kumar at Fidesto Projects Private Limited from June 17 to July 30, 2019. It includes an acknowledgement, information about the organization and the proposed residential project in Pune on which Ravi Kumar worked. Safety protocols at construction sites like use of safety equipment and formwork are also summarized. The key steps involved in building construction are outlined.
final year civil engineering training report Poojan Patel
The document provides details about a training project involving laying RCC drainage gravity line by microtunneling method. It describes the project scope, which involves providing and laying 1400/1800 mm diameter RCC jacking pipes over 5.1 km between Gorwa A.P.S. and Shrenikpark Junction in Vadodara, Gujarat. It also provides information about microtunneling technology and its advantages over traditional open-cut construction methods. The training involved various construction activities like RCC pipe casting, shaft construction, MTBM launching, jacking and receiving.
This document provides an overview of formwork and safety procedures during construction of a residential building project by Amrapali Ltd. It discusses the importance of formwork in concrete construction and outlines key safety considerations like using protective equipment and reporting unsafe conditions. The introduction also describes common building types and the project involves constructing 672 housing units across 7 towers over 28 floors at Crystal Homes in Noida, India.
CONSTRUCTION OF DISTRICT CONTROL BUILDING, CENTRAL STORE BUILDING & 33/11KV POWER SUBSTATION CONTROL ROOM AT CHAPRA,BIHAR
An Internship Report submitted in partial fulfilment of the
requirements for the degree
of
B.Tech (Civil Engineering)
by
VIJAY KUMAR SINGH
13BCL0001
VIT UNIVERSITY
VELLORE – 632 014, TAMILNADU
The document is a summer internship report submitted by Sumit Singh detailing his internship from 09/06/2016 - 23/07/2016 with Skyline engineering contracts (India) pvt. Ltd. on a residential building project. The report includes details of the project such as building materials used including cement, sand, aggregates, reinforcement steel. It also describes the machinery used on site such as batching plants, concrete pumps, transit mixers etc. and procedures followed for demarcation, concrete casting of slabs and beams, staircase construction and brickwork.
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTIONAbhishek Singh
This document appears to be an internship report submitted by four students - Abhishek Singh, Naval Tej Singh Ahuja, Sahil Thakur, and Swapnil Singh - to their supervisor Mr. Kapil Bhardwaj at Universal Buildwell Pvt. Ltd. in Gurgaon, Haryana, India. The report provides details about a residential construction project called Universal Aura, including project specifications, building materials used, and work ongoing at the site during the students' summer internship from June 13 to July 13, 2016.
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTIONVed Jangid
This document provides a summer internship report for a civil engineering student's internship at the Public Works Department in Ajmer, Rajasthan, India from May 10th to July 10th, 2018. The internship involved working on the construction of a 10-room and 2-store building at the Revenue Research and Training Institute campus in Ajmer. The report details the project overview, building components, construction materials used, construction processes and the intern's weekly progress and conclusions.
Internship report
The report is prepared on request from Maaz and Shahrukh for their 4-week internship program.
The data has been provided by them.
This report includes theoretical, pictorial and mathematical material.
Summer Internship Report of Civil Engineering in Construction SiteRAVI KUMAR
The document provides details about the internship completed by Ravi Kumar at Fidesto Projects Private Limited from June 17 to July 30, 2019. It includes an acknowledgement, information about the organization and the proposed residential project in Pune on which Ravi Kumar worked. Safety protocols at construction sites like use of safety equipment and formwork are also summarized. The key steps involved in building construction are outlined.
final year civil engineering training report Poojan Patel
The document provides details about a training project involving laying RCC drainage gravity line by microtunneling method. It describes the project scope, which involves providing and laying 1400/1800 mm diameter RCC jacking pipes over 5.1 km between Gorwa A.P.S. and Shrenikpark Junction in Vadodara, Gujarat. It also provides information about microtunneling technology and its advantages over traditional open-cut construction methods. The training involved various construction activities like RCC pipe casting, shaft construction, MTBM launching, jacking and receiving.
This document provides an overview of formwork and safety procedures during construction of a residential building project by Amrapali Ltd. It discusses the importance of formwork in concrete construction and outlines key safety considerations like using protective equipment and reporting unsafe conditions. The introduction also describes common building types and the project involves constructing 672 housing units across 7 towers over 28 floors at Crystal Homes in Noida, India.
CONSTRUCTION OF DISTRICT CONTROL BUILDING, CENTRAL STORE BUILDING & 33/11KV POWER SUBSTATION CONTROL ROOM AT CHAPRA,BIHAR
An Internship Report submitted in partial fulfilment of the
requirements for the degree
of
B.Tech (Civil Engineering)
by
VIJAY KUMAR SINGH
13BCL0001
VIT UNIVERSITY
VELLORE – 632 014, TAMILNADU
The document is a summer internship report submitted by Sumit Singh detailing his internship from 09/06/2016 - 23/07/2016 with Skyline engineering contracts (India) pvt. Ltd. on a residential building project. The report includes details of the project such as building materials used including cement, sand, aggregates, reinforcement steel. It also describes the machinery used on site such as batching plants, concrete pumps, transit mixers etc. and procedures followed for demarcation, concrete casting of slabs and beams, staircase construction and brickwork.
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTIONAbhishek Singh
This document appears to be an internship report submitted by four students - Abhishek Singh, Naval Tej Singh Ahuja, Sahil Thakur, and Swapnil Singh - to their supervisor Mr. Kapil Bhardwaj at Universal Buildwell Pvt. Ltd. in Gurgaon, Haryana, India. The report provides details about a residential construction project called Universal Aura, including project specifications, building materials used, and work ongoing at the site during the students' summer internship from June 13 to July 13, 2016.
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTIONVed Jangid
This document provides a summer internship report for a civil engineering student's internship at the Public Works Department in Ajmer, Rajasthan, India from May 10th to July 10th, 2018. The internship involved working on the construction of a 10-room and 2-store building at the Revenue Research and Training Institute campus in Ajmer. The report details the project overview, building components, construction materials used, construction processes and the intern's weekly progress and conclusions.
Internship report
The report is prepared on request from Maaz and Shahrukh for their 4-week internship program.
The data has been provided by them.
This report includes theoretical, pictorial and mathematical material.
This document is Rajat Kumar's industrial training report submitted in partial fulfillment of the requirements for a Bachelor of Technology degree from Shoolini University. It includes a declaration by Rajat Kumar stating that the report is his original work. It also includes certificates from the chairperson of the Civil Engineering department and the head of the School of Mechanical and Civil Engineering confirming Rajat Kumar completed the training under their supervision. The report contains chapters on different types of roads, pavements, materials used in construction like cement, sand and aggregates, different brick bonds, the construction process for columns and foundations, and types of foundations.
Building Industrial Training report for CIVIL ENGINEERINGCESatvirSingh1
This document is a project report submitted by Mr. Satvir Singh for their summer internship in civil engineering. The report details their internship working on the construction of an SDO Civil Complex building in Ratia, Haryana. The report includes sections on introduction to types of buildings and safety procedures, construction steps like site clearance, surveying, excavation, foundation work, and materials used. It provides an overview of the internship experience working on an active construction site.
Summer training report in civil engineeringalok0025
This document provides a report on a summer training completed by Alok Kumar Singh from May 5th to July 4th, 2015 at a construction site for the Panchsheel Apartments project. The report details the construction process, materials used, safety procedures, and Alok's contributions during his training. It includes sections on site layout, excavation, foundation work, concrete mixing and pouring, wall and slab construction, quality control measures, and photos from the construction site. The training provided Alok with valuable practical experience in civil engineering and construction project management.
Industrial Summer Training Report at Construction Site of CPWD Alok Mishra
Construction of Police Station Khajuri Khas, Near Sonia Vihar, Delhi (SH: C/o Police Station Building, Electric sub Station & External Development Work i.e. Internal Electrical Installations)
The document is a practical training report submitted by Sumit Kumar, a civil engineering student, documenting his six-week internship with PKS Buildmart Pvt. Ltd. It provides an overview of the company and details of the commercial building construction project he worked on, which involved tasks in both the office and on-site, including setting out, excavation, concrete work, and masonry. The report documents the materials, procedures, and Sumit's contributions on the project over the training period.
Industrial Training report Civil Engineering.JAPJEETSINGH13
Industrial training report for civil engineering major training final year. All rights to the images, blueprints and content is reserved.
Only available for educational purposes.
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGAmritpal Singh
The document provides details of a project report for the design of a residential building in India. It includes an introduction, study area details, floor plans for 1BHK, 2BHK and 3BHK units, specifications, construction process and materials used such as cement, coarse aggregate, fine aggregate, and bricks. The summary is as follows:
The document is a project report for the design of a residential building in India that includes details of the site location, floor plans for different unit types (1BHK, 2BHK, 3BHK), building specifications, construction process, and materials used such as cement, aggregates, and bricks.
minor project report on design of residential buildingtushar garg
This document is a minor project report submitted by Tushar Garg to Rajendra Kumar Khyalia for a Bachelor of Technology degree. It includes an acknowledgement, abstract, declaration, and table of contents sections. The content covers the aim of designing a residential building, including selecting a plot, surveying the site, requirements for residential buildings, building bye laws and regulations, room arrangements, and sanitation provisions. Drawings and photos are also included.
Construction of residential building summer training pptSumit Singh
Sumit Singh completed a summer training project on the construction of a residential building complex called Assotech Blith Group Housing in Gurgaon, Haryana, India. The project involved constructing 7 towers ranging from G+18 to G+25 floors over an area of 12 acres. Singh learned about the various stages of construction including land acquisition, excavation, formwork, reinforcement placement, casting, and finishing. He was trained in activities like shuttering, bar placing, staircase construction, brickwork, and safety requirements. The training helped improve his confidence and choice to study civil engineering.
Industrial Training Report of Construction Site in Civil EngineeringRAVI KUMAR
This document provides details about Ravi Kumar's industrial training project at Arete India Project Pvt Ltd. It includes an index, acknowledgements, introduction to the project, project details, construction process, machinery used, quantity estimations, quality control tests and more. The project involved the construction of a multi-story residential and commercial building project called Imperia Aashiyara with 26 towers and 1136 flats over 48 months. Key steps in the construction process and machinery used are described.
This document provides an overview of a multi-story residential building project constructed by the Rajasthan Housing Board. It discusses the project details, company overview, construction materials used including cement, aggregates, reinforcement, foundation preparation, equipment, brick masonry bonds, plastering, and building bylaws. The presentation covers the construction process and materials in detail to familiarize the trainee with multi-story building construction.
Industrial training report of construction of the residential buildingsuraj jha
This document summarizes a presentation on a residential building construction project. It provides an overview of the project, including the location, number of floors, timeline, and project manager. It also describes the company undertaking the project, M k mehta enterprise, and its past projects. Additionally, it outlines the various steps of construction including site clearance, surveying, excavation, foundation, concreting, beams and columns. Key materials and equipment used are also summarized such as cement, aggregates, bricks, water, admixtures, and concrete pumping equipment. Building bylaws regarding plinth area regulations are also briefly mentioned.
Internship Report on Building ConstructionEsmael Aragaw
K2N Architecture and Engineering Consultancy PLC is an Ethiopian consulting firm providing architectural, engineering, and project management services. The company aims to provide quality services that exceed client expectations while adhering to high technical and ethical standards. K2N has experience on various project types both in Ethiopia and internationally. The document provides details on K2N's vision, mission, values, organizational structure, management, areas of expertise, and example projects.
building consturction training report at cpwd (MNIT)rahul jangid
This document provides a practical training report on the construction site of a girls' hostel at MNIT Jaipur, India. It discusses the various construction processes used at the site, including laying the foundation with isolated and combined footings, formwork, reinforcement placement, slab casting, finishing work, and quality control measures. The document includes photos from the construction site and discusses the technologies used, such as total stations, batching plants, and tower cranes. The daily work reports provide details on the trainee's activities over two weeks, including learning reinforcement distribution, slab casting, and finishing work.
This document provides an overview of Coastal Projects Limited (CPL), an infrastructure construction company, and CPL's role in the Bangalore Metro Rail Project. It discusses CPL's vision, mission, values and quality assurance policies. It then describes the Majestic Metro Station project, including station layout details. CPL is constructing the underground Majestic Metro Station, which will be an interchange station for the Purple and Green metro lines. Construction is proceeding according to a grid-wise plan from the center of Zone E outwards in all directions.
This document provides details about a residential building project constructed by Raunak Group in Mumbai. It includes a 13 storey building with 93 flats of 3 BHK configuration. The building uses shallow foundations consisting of individual, strip and raft foundations due to the soil conditions. The superstructure is constructed with reinforced concrete using materials like cement, fine and coarse aggregates, and water. Construction techniques like brick masonry and plastering are also discussed.
Report is about the Internship of a Civil Engineer.
This Report is for the students of civil engineering. In this report u can find the format of the Report, Mechanism of the internship report. It is very useful to understand some civil engineering terms.
Training report done on Bridge ConstructionSukhdeep Jat
The document provides details about an in-plant training report submitted by Sukhdeep Singh Jat at BSCPL Infrastructure Pvt. Ltd during the construction of a bridge over the Mahanadi River in NH-53 in India. It discusses the company profile, ongoing major projects including road and bridge construction projects, and specifics of the bridge project over the Mahanadi River including the design process, materials used such as different grades of concrete, and machinery employed.
This industrial training report summarizes work done on a 250-unit residential building project in TDI City. Key aspects summarized include:
1) The building consists of ground + 2 floors with approximately 1750 sqft per unit built on a 250 sqyd plot.
2) Construction equipment used included transit mixers, backhoes, concrete pumps, and scaffolding.
3) Construction procedures described include excavation, laying of foundations with OPC and isolation footings, formwork, reinforcement, concreting of columns, beams and slabs.
4) Safety measures like scaffolding and safety nets were emphasized.
5) The trainee concluded it was a comprehensive training that bridged
The document summarizes an industrial training report on the construction of a multistoried building. It describes two multistoried residential projects - Verna and Tana constructed by SI Property. Key details include the foundations using pile foundations and raft foundations, concrete mixes used, and reinforcement details of columns, beams and slabs. Amenities provided in the projects like parking, fitness center, kids play area are also mentioned. The report also provides information on new building materials seen during a visit to another project GIE Asteria, including Siporex blocks, Weber glue and fiberglass mesh.
The document summarizes Om Prakash Yadav's summer internship report on a construction project. It includes sections on construction steps, materials and equipment used, and quality control measures. Key details are an internship at Larsen & Toubro constructing Kaveri Apartments for Lucknow Development Authority. Construction involved site clearance, surveying, excavation, foundation work, and erecting the building frame through beams and columns before finishing work. Aluminum formwork and a total station were utilized.
This document provides a report on a summer training project involving the construction of a shopping complex. It includes sections on introduction, construction steps, materials and equipment used, quality control, the student's contributions, and photos. The student gained practical experience in construction techniques like site clearing, surveying, excavation, foundation work, concreting, and formwork during their training at the project site. The report was submitted to fulfill the requirements of the student's civil engineering program.
This document is Rajat Kumar's industrial training report submitted in partial fulfillment of the requirements for a Bachelor of Technology degree from Shoolini University. It includes a declaration by Rajat Kumar stating that the report is his original work. It also includes certificates from the chairperson of the Civil Engineering department and the head of the School of Mechanical and Civil Engineering confirming Rajat Kumar completed the training under their supervision. The report contains chapters on different types of roads, pavements, materials used in construction like cement, sand and aggregates, different brick bonds, the construction process for columns and foundations, and types of foundations.
Building Industrial Training report for CIVIL ENGINEERINGCESatvirSingh1
This document is a project report submitted by Mr. Satvir Singh for their summer internship in civil engineering. The report details their internship working on the construction of an SDO Civil Complex building in Ratia, Haryana. The report includes sections on introduction to types of buildings and safety procedures, construction steps like site clearance, surveying, excavation, foundation work, and materials used. It provides an overview of the internship experience working on an active construction site.
Summer training report in civil engineeringalok0025
This document provides a report on a summer training completed by Alok Kumar Singh from May 5th to July 4th, 2015 at a construction site for the Panchsheel Apartments project. The report details the construction process, materials used, safety procedures, and Alok's contributions during his training. It includes sections on site layout, excavation, foundation work, concrete mixing and pouring, wall and slab construction, quality control measures, and photos from the construction site. The training provided Alok with valuable practical experience in civil engineering and construction project management.
Industrial Summer Training Report at Construction Site of CPWD Alok Mishra
Construction of Police Station Khajuri Khas, Near Sonia Vihar, Delhi (SH: C/o Police Station Building, Electric sub Station & External Development Work i.e. Internal Electrical Installations)
The document is a practical training report submitted by Sumit Kumar, a civil engineering student, documenting his six-week internship with PKS Buildmart Pvt. Ltd. It provides an overview of the company and details of the commercial building construction project he worked on, which involved tasks in both the office and on-site, including setting out, excavation, concrete work, and masonry. The report documents the materials, procedures, and Sumit's contributions on the project over the training period.
Industrial Training report Civil Engineering.JAPJEETSINGH13
Industrial training report for civil engineering major training final year. All rights to the images, blueprints and content is reserved.
Only available for educational purposes.
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGAmritpal Singh
The document provides details of a project report for the design of a residential building in India. It includes an introduction, study area details, floor plans for 1BHK, 2BHK and 3BHK units, specifications, construction process and materials used such as cement, coarse aggregate, fine aggregate, and bricks. The summary is as follows:
The document is a project report for the design of a residential building in India that includes details of the site location, floor plans for different unit types (1BHK, 2BHK, 3BHK), building specifications, construction process, and materials used such as cement, aggregates, and bricks.
minor project report on design of residential buildingtushar garg
This document is a minor project report submitted by Tushar Garg to Rajendra Kumar Khyalia for a Bachelor of Technology degree. It includes an acknowledgement, abstract, declaration, and table of contents sections. The content covers the aim of designing a residential building, including selecting a plot, surveying the site, requirements for residential buildings, building bye laws and regulations, room arrangements, and sanitation provisions. Drawings and photos are also included.
Construction of residential building summer training pptSumit Singh
Sumit Singh completed a summer training project on the construction of a residential building complex called Assotech Blith Group Housing in Gurgaon, Haryana, India. The project involved constructing 7 towers ranging from G+18 to G+25 floors over an area of 12 acres. Singh learned about the various stages of construction including land acquisition, excavation, formwork, reinforcement placement, casting, and finishing. He was trained in activities like shuttering, bar placing, staircase construction, brickwork, and safety requirements. The training helped improve his confidence and choice to study civil engineering.
Industrial Training Report of Construction Site in Civil EngineeringRAVI KUMAR
This document provides details about Ravi Kumar's industrial training project at Arete India Project Pvt Ltd. It includes an index, acknowledgements, introduction to the project, project details, construction process, machinery used, quantity estimations, quality control tests and more. The project involved the construction of a multi-story residential and commercial building project called Imperia Aashiyara with 26 towers and 1136 flats over 48 months. Key steps in the construction process and machinery used are described.
This document provides an overview of a multi-story residential building project constructed by the Rajasthan Housing Board. It discusses the project details, company overview, construction materials used including cement, aggregates, reinforcement, foundation preparation, equipment, brick masonry bonds, plastering, and building bylaws. The presentation covers the construction process and materials in detail to familiarize the trainee with multi-story building construction.
Industrial training report of construction of the residential buildingsuraj jha
This document summarizes a presentation on a residential building construction project. It provides an overview of the project, including the location, number of floors, timeline, and project manager. It also describes the company undertaking the project, M k mehta enterprise, and its past projects. Additionally, it outlines the various steps of construction including site clearance, surveying, excavation, foundation, concreting, beams and columns. Key materials and equipment used are also summarized such as cement, aggregates, bricks, water, admixtures, and concrete pumping equipment. Building bylaws regarding plinth area regulations are also briefly mentioned.
Internship Report on Building ConstructionEsmael Aragaw
K2N Architecture and Engineering Consultancy PLC is an Ethiopian consulting firm providing architectural, engineering, and project management services. The company aims to provide quality services that exceed client expectations while adhering to high technical and ethical standards. K2N has experience on various project types both in Ethiopia and internationally. The document provides details on K2N's vision, mission, values, organizational structure, management, areas of expertise, and example projects.
building consturction training report at cpwd (MNIT)rahul jangid
This document provides a practical training report on the construction site of a girls' hostel at MNIT Jaipur, India. It discusses the various construction processes used at the site, including laying the foundation with isolated and combined footings, formwork, reinforcement placement, slab casting, finishing work, and quality control measures. The document includes photos from the construction site and discusses the technologies used, such as total stations, batching plants, and tower cranes. The daily work reports provide details on the trainee's activities over two weeks, including learning reinforcement distribution, slab casting, and finishing work.
This document provides an overview of Coastal Projects Limited (CPL), an infrastructure construction company, and CPL's role in the Bangalore Metro Rail Project. It discusses CPL's vision, mission, values and quality assurance policies. It then describes the Majestic Metro Station project, including station layout details. CPL is constructing the underground Majestic Metro Station, which will be an interchange station for the Purple and Green metro lines. Construction is proceeding according to a grid-wise plan from the center of Zone E outwards in all directions.
This document provides details about a residential building project constructed by Raunak Group in Mumbai. It includes a 13 storey building with 93 flats of 3 BHK configuration. The building uses shallow foundations consisting of individual, strip and raft foundations due to the soil conditions. The superstructure is constructed with reinforced concrete using materials like cement, fine and coarse aggregates, and water. Construction techniques like brick masonry and plastering are also discussed.
Report is about the Internship of a Civil Engineer.
This Report is for the students of civil engineering. In this report u can find the format of the Report, Mechanism of the internship report. It is very useful to understand some civil engineering terms.
Training report done on Bridge ConstructionSukhdeep Jat
The document provides details about an in-plant training report submitted by Sukhdeep Singh Jat at BSCPL Infrastructure Pvt. Ltd during the construction of a bridge over the Mahanadi River in NH-53 in India. It discusses the company profile, ongoing major projects including road and bridge construction projects, and specifics of the bridge project over the Mahanadi River including the design process, materials used such as different grades of concrete, and machinery employed.
This industrial training report summarizes work done on a 250-unit residential building project in TDI City. Key aspects summarized include:
1) The building consists of ground + 2 floors with approximately 1750 sqft per unit built on a 250 sqyd plot.
2) Construction equipment used included transit mixers, backhoes, concrete pumps, and scaffolding.
3) Construction procedures described include excavation, laying of foundations with OPC and isolation footings, formwork, reinforcement, concreting of columns, beams and slabs.
4) Safety measures like scaffolding and safety nets were emphasized.
5) The trainee concluded it was a comprehensive training that bridged
The document summarizes an industrial training report on the construction of a multistoried building. It describes two multistoried residential projects - Verna and Tana constructed by SI Property. Key details include the foundations using pile foundations and raft foundations, concrete mixes used, and reinforcement details of columns, beams and slabs. Amenities provided in the projects like parking, fitness center, kids play area are also mentioned. The report also provides information on new building materials seen during a visit to another project GIE Asteria, including Siporex blocks, Weber glue and fiberglass mesh.
The document summarizes Om Prakash Yadav's summer internship report on a construction project. It includes sections on construction steps, materials and equipment used, and quality control measures. Key details are an internship at Larsen & Toubro constructing Kaveri Apartments for Lucknow Development Authority. Construction involved site clearance, surveying, excavation, foundation work, and erecting the building frame through beams and columns before finishing work. Aluminum formwork and a total station were utilized.
This document provides a report on a summer training project involving the construction of a shopping complex. It includes sections on introduction, construction steps, materials and equipment used, quality control, the student's contributions, and photos. The student gained practical experience in construction techniques like site clearing, surveying, excavation, foundation work, concreting, and formwork during their training at the project site. The report was submitted to fulfill the requirements of the student's civil engineering program.
The document discusses the preliminary works of a construction site including site layout, safety features, machinery and equipment, site clearance, setting out, and earthworks and excavation that must be completed before main construction can begin in order to properly prepare the site. Safety is a top priority and features such as signage, barriers, and personal protective equipment help ensure safety of all personnel. The preliminary works lay the foundation for the subsequent construction phases including building foundations, structures, walls and more.
BCON Project 1: Experiencing Construction Charlotte Chin
Building Construction I (BLD 60303)
Experiencing, Documenting and Analysing the Construction Process
Carmen Chan Shen Wen 0326485
Charlotte Chin Ya-Le 0326940
Chevally Lo Zhao Shyen 0326497
Calvin Chen Qinh Yao 0326658
Chan Jia Chin 0326560
This document provides information about a construction site visit assignment by a group of students to two development projects in Selangor, Malaysia.
The first project visited was the SENJA Residences, a 278 unit residential development located near Seri Kembangan. It will be completed in phases by 2017. The second project was a 650 square meter warehouse in Shah Alam for construction materials.
The document then discusses site safety, personal protective equipment, machinery, transportation vehicles, material handling equipment, and the importance of safety attitudes on construction sites. Various photos of the sites and equipment are included. Safety protocols for working at heights, machinery operation, electricity, and fire prevention are covered.
The document provides information on preliminary construction works for two project sites - Alam Impian Show Unit and Tamarind Square. It discusses soil investigation, site clearing works like grubbing and excavation using cut and fill techniques. It also covers setting out of buildings, provision of temporary site facilities like security, site office and signages. Drainage and sewerage systems are outlined to carry waste water and matter away from the construction sites.
The document discusses the preliminary works being carried out at a construction site. It describes how site clearance is the first step, involving demolishing existing structures, removing vegetation, and leveling the land. Formwork and scaffolding are then erected to support concrete works during construction. Temporary site facilities like welfare buildings and storage areas are also set up to support workers.
Vijay Verma completed a summer training internship with Ahluwalia Contracts (India) Limited. He gained experience working on the Candor Gurgaon One Realty project located in Sector 48, Gurgaon. His report provides details on the construction steps being used, including site clearance, surveying, excavation, foundation work, and formwork. It also discusses the importance of safety procedures and quality control measures at the construction site.
The document provides information on two construction sites - Elmina Valley Phase EV1A residential development and a residential project in Mukim Lunas, Daerah Kulim, Kedah. It discusses the site layout, safety measures, plants and machinery used, and construction processes for foundations, superstructure, roofs and services at the sites. Safety is taken very seriously, with signage, bulletin boards, and requirements for personal protective equipment. Various earthmoving, lifting, transport and construction equipment are used, including excavators, compactors, cranes, concrete mixers, trucks and bar bending machines. Preliminary works establish site access, drainage and storage areas to facilitate construction.
The document provides information on two construction sites - Elmina Valley Phase EV1A residential development and a residential project in Mukim Lunas, Kedah.
It describes the location, layout and details of the projects such as unit types, project duration, and completion dates. Safety protocols at the Elmina Valley site are stringent, requiring workers to wear protective equipment and register with security. Signage and bulletin boards provide safety information.
The document also outlines the site layout and facilities at Elmina Valley, including amenities for workers. Preliminary works such as site access, drainage and storage areas are discussed. Various plant and machinery used are described, including earthmoving, lifting, transport and concrete mixing equipment.
The document provides information on two construction sites - Elmina Valley Phase EV1A residential development and a residential project in Mukim Lunas, Daerah Kulim, Kedah. It discusses the site layout, safety measures, plants and machinery used, and construction processes for foundations, superstructure, roofs and services at the sites. Detailed site plans and photographs are included to illustrate the various construction elements and safety protocols like signage, personal protective equipment. Preliminary works covered include site access, drainage, storage areas, and green zones. Foundation types, construction steps for beams, columns, walls and staircases are described.
A report on the procedures and construction process of buildings based on real life site visits at Taman Bukit Segar, Cheras and Glenmarie Cove, Klang.
By students of Bsc(Hons) Architecture of Taylor's University.
The document provides information about a low density housing development called Ramal Villa located in Kajang, Malaysia. It consists of 71 units including single detached homes and semi-detached homes. The development emphasizes modern design with flat roofs and simple facades. Each unit also has a rooftop garden. The site is well connected to major highways near LDP and Sungai Besi Highway, making it easily accessible. The document includes a location plan and site plan showing the layout of the different housing types.
Building Construction: Experiencing ConstructionJoyce Wee
The document provides information about a low density housing development called Ramal Villa located in Kajang, Malaysia. It consists of 71 units including single detached homes and semi-detached homes. The development emphasizes modern design with flat roofs and simple facades. Each unit also has a rooftop garden. The site is well connected to major highways near LDP and Sungai Besi Highway, making it easily accessible. The document includes a location plan and site plan showing the layout of the different housing types.
The document summarizes the construction process observed at a construction site visited by the authors. It describes the site location and type of buildings being constructed. Safety measures at the site include signage and required protective equipment. Various plants and machinery used at different stages are discussed, including excavators, backhoes, cranes and concrete mixers. Foundations works involving piling and excavations are mentioned.
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxNaveenVerma126
This document is a report on a summer training completed by Naveen Verma from July 16th to July 16th 2022 as part of their Civil Engineering degree. The training took place at the Uttar Pradesh Nirman Nigam construction site of a Homeopathic Hospital building near Alambagh Station in Lucknow, Uttar Pradesh. During the training, Naveen learned about construction processes like excavation, formwork, construction steps, and safety protocols. They gained practical experience in surveying, layout works, and witnessed different types of footings like isolated, combined, and raft footings being used at the construction site.
This document is a training report submitted by Masud Alam Ansari from January 1st to May 2nd, 2020 for their internship constructing a 5-storey building at Ram Raja Campus in Kalaiya Sub-Metropolitan City. It discusses the construction company, materials and equipment used, and steps taken in constructing the building, including site clearance, surveying, excavation, foundation, and concrete works. Quality control measures are also outlined.
The document reports on the construction of three sites - a fire station in Kuala Lumpur, an eco-friendly mosque in Cyberjaya, and terrace houses in Klang. It introduces the projects, provides an overview of each site, and discusses site safety precautions, machinery and equipment used, site preparation processes, and various construction stages. Updates are given on the progress of each project and construction methods like industrialized building systems are explained.
The document reports on the construction of three sites - a fire station in Kuala Lumpur, an eco-friendly mosque in Cyberjaya, and terrace houses in Klang. It introduces the projects, provides an overview of each site, and discusses site safety precautions, machinery and equipment used, site preparation processes, and various construction stages. Photos are included to illustrate the different elements discussed in the report.
Similar to Industrial trainning project report for Civil Engineering (20)
Data Communication and Computer Networks Management System Project Report.pdfKamal Acharya
Networking is a telecommunications network that allows computers to exchange data. In
computer networks, networked computing devices pass data to each other along data
connections. Data is transferred in the form of packets. The connections between nodes are
established using either cable media or wireless media.
Cricket management system ptoject report.pdfKamal Acharya
The aim of this project is to provide the complete information of the National and
International statistics. The information is available country wise and player wise. By
entering the data of eachmatch, we can get all type of reports instantly, which will be
useful to call back history of each player. Also the team performance in each match can
be obtained. We can get a report on number of matches, wins and lost.
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...DharmaBanothu
The Network on Chip (NoC) has emerged as an effective
solution for intercommunication infrastructure within System on
Chip (SoC) designs, overcoming the limitations of traditional
methods that face significant bottlenecks. However, the complexity
of NoC design presents numerous challenges related to
performance metrics such as scalability, latency, power
consumption, and signal integrity. This project addresses the
issues within the router's memory unit and proposes an enhanced
memory structure. To achieve efficient data transfer, FIFO buffers
are implemented in distributed RAM and virtual channels for
FPGA-based NoC. The project introduces advanced FIFO-based
memory units within the NoC router, assessing their performance
in a Bi-directional NoC (Bi-NoC) configuration. The primary
objective is to reduce the router's workload while enhancing the
FIFO internal structure. To further improve data transfer speed,
a Bi-NoC with a self-configurable intercommunication channel is
suggested. Simulation and synthesis results demonstrate
guaranteed throughput, predictable latency, and equitable
network access, showing significant improvement over previous
designs
This is an overview of my current metallic design and engineering knowledge base built up over my professional career and two MSc degrees : - MSc in Advanced Manufacturing Technology University of Portsmouth graduated 1st May 1998, and MSc in Aircraft Engineering Cranfield University graduated 8th June 2007.
Industrial trainning project report for Civil Engineering
1. 1
PROJECT REPORT ON INDUSTRIAL TRAINING
A PROJECT REPORT
Submitted by
PRAKASH KUMAR JHA 99150120022
In partial fulfillment for the award of the degree
Of
BACHELOR OF TECHNOLOGY
In
CIVIL ENGINEERING
DEPARTMENT OF CIVIL ENGINEERING
GIANI ZAIL SINGH CAMPUS COLLEGE OF ENGINEERING &
TECHNOLOGY, BATHINDA
MARAJA RANJIT SINGH PUNJAB TECHNICAL UNIVERSITY,
BATHINDA
2. 2
ACKNOWLEDGEMENT
We express our sincere thanks to Dr. Manjeet Bansal, Head of Civil Engineering
Department for his support and guidance for doing the project.
We express our indebtedness and gratitude to our guide Prof. G.S Bath, Department of
Civil Engineering, GIANI ZAIL SINGH CAMPUS COLLEGE OF ENGINEERING &
TECHNOLOGY, for his guidance and care taken by him in helping us to complete the project
work successfully.
3. 3
DETAILED CONTENTS
TOPICS PAGES
1. Introduction (5-13)
1.1. Types of building
1.2. Safety Induction
1.3. Site Location
1.4. Form Work
2. Construction Steps of Building (14-21)
2.1. Site Clearance
2.2. Surveying and Layout
2.3. Excavation
2.4. Foundation
2.5. Concreting
2.6. Wall Construction
2.7. Beam & Columns Construction
2.8. Slab Construction
3. Materials & Equipment (22-28)
3.1. Material Used at Site
3.2. equipment Used
4. Quality Control (29-30)
4.1. Quality Control in Concrete work
4.2. Quality Control In Reinforcement
5. Contribution (31-35)
5.1. Reinforcement and Casting of slab
5.2. Construction of retaining wall
5.3. Construction of shear wall
5.4. Column reinforcement & concreting
4. 4
PANCHSHEELAPARTMENTS
PROJECT DETAILS
Project Name: PANCHSHEEL APARTMENT scheme launched by LUCKNOW
DEVELOPMENT AUTHORITY and contract for the construction of this multistoried
residential finished house is awarded to NCC LIMITED.
Scope: Design and construction of multistoried finished houses including basement parking,
based on R.C.C. monolithic shear wall concept, using aluminium form work.
No. of Towers- 4
No. of Flats- 400
Construction period – 36 months
Type of contract – Lump Sum
Architect- Arinem Consultancy Limited
Estimated project cost – 100 crore
Agency – NCC Limited
Consultant – Manish Shrikhande (Assoc. Professor, Civil Engg. Dept. IIT Roorkee)
Design of concrete mix by –Department of Civil Engg. IIT Kanpur
Client name –Lucknow Development Authority (LDA)
5. 5
CHAPTER-1 INTRODUCTION
The basics needs of human existences are food, clothing’s & shelter. From times
immemorial man has been making efforts in improving their standard of living. The point of
his efforts has been to provide an economic and efficient shelter. The possession of shelter
besides being a basic, used, gives a feeling of security, responsibility and shown the social
status of man.
Every human being has an inherent liking for a peaceful environment needed for his pleasant
living, this object is achieved by having a place of living situated at the safe and convenient
location, such a place for comfortable and pleasant living requires considered and kept in view.
A Peaceful environment.
Safety from all natural source & climate conditions
General facilities for community of his residential area.
The engineer has to keep in mind the municipal conditions, building bye laws,
environment, financial capacity, water supply, sewage arrangement, provision of future,
aeration, ventilation etc., in suggestion a particular type of plan to any client.
1.1 TYPES OF BUILDING
Buildings are classified on the basis of character of occupancy and type of use as.
1.1.1 Residential Building
1.1.2 Educational Building
1.1.3 Institutional Building
1.1.4 Industrial Building
1.1.1 RESIDENTIAL BUILDING
In such building sleeping accommodation is provided. IT includes the living room, bed room,
kitchen, hall, toilet and bath room. It may be a single storey building or apartments.
6. 6
1.1.2 EDUCATIONAL BUILDING
These include any building using for school, college, assembly for instruction, education or
recreation.
1.1.3 INSTITUTIONAL BUILDING
These building are used for different purposes, such as medical or other treatment or care of a
person suffering from a physical or mental illnesses. These building include hospital, sanatoria,
jail etc.
1.1.4 INDUSTRIAL BUILDING
These are buildings in which products or material s of all kind of properties are fabricated,
assembled, processed. For example refineries, gas plant, mills etc.
1.2 SAFETY INDUCTION
Safety is very important part of any work. An induction video was showed which highlighted the
need and importance of safety at construction site. Most accidents can be prevented by taking
simple measures or adopting proper working procedures. It is very important to discuss issues on
safety and health that should be paid attention to on construction sites for easy reference by the
workers. If we work carefully and take appropriate safety measures, there will definitely be
fewer work injury cases, and our sites will become a safe and secure place to work in. It is
important to educate everyone in the site regarding safety for following purposes.
Workers safety
Construction progress
Standard procedure
Legal cases
Working efficiency
Two standard guidelines are followed for health & environment safety
■ ISO 14001-2004
■ OHSAS 18001-2007
7. 7
Precautions at site for safety-
Wear protective equipment.
Do not drink or take drugs while working.
Pay attention to personal hygiene.
Do not play in the workplace.
Report to your supervisor immediately if you notice any unsafe condition.
1.2.1 Equipment used for safety at constructionsite
Safety Belt
Helmet
Nets
8. 8
1.2.2 Possible types of accidents and ill health
Construction Site Fall
Crane Accidents
Scaffolding Accidents
Electrical Accidents
Trench Collapses
Fires and Explosions
Welding Accidents
Cutting Accidents
Structure Failure
Building Collapse
Supervisor Negligence
Punch Press Malfunctions
Compressor Accidents
Exploding Compressor
Gas Explosions During Welding
Run-Over by Operating Equipment
Unsafe/ Dangerous Equipment Accidents
1.3 Site Location
PANCHSHEEL APARTMENTS SCHEME, SHAHID PATH NH – 28, LUCKNOW
1.3.1 Advantages of this site
Land.
Store.
Parking space.
Health unit.
Transportation facilities.
10. 10
1.4 Form Work
Formwork is a mould or die used to support or shape the concrete until it attains sufficient
strength to carry its self-weight. Formwork holds the concrete until it hardens to required
shape & size.
1.4.1. Significance of formwork
Formwork constitutes 30% of cost & 60% of time in concrete construction.
Quality of concrete finish and soundness of concrete depends very much on type of
formwork system.
Desired shape of concrete is not possible if formwork is not done properly.
Formwork should be properly designed fabricated and erected to receive
concrete.
Accidents happen because of faulty formwork and scaffolding or staging.
1.4.2. Safety in using formwork-
Components are light in weight for manual holding.
Loose or hanging components are minimal.
Appropriate use of tools.
Minimum operations are involved in each reuse.
1.4.3. Types of formwork
Flex system
Good company ply is used
A.1 Components of flex system
H beam primary or secondary.
CT prop.
Foue way head.
Folding tripod.
Assembly wedge clamp.
Supporting head.
Beam forming head.
11. 11
Quick deck system.
B-Aluform system
Panels with aluminums frame and plywood fitted in it.
Used in raft, shear wall and columns.
Components of aluform system.
Alufo panel.
Framing clamp.
Tie rod.
Wig nut.
Steel waler.
CT prop.
Foot adopter.
Head adopter.
Brackets for safety.
C-Aluminium formwork
Aluminium formwork is widely used by Construction Company at site.
Components of aluminium formwork-
Kicker.
Rocker.
Wall panel.
Slab corner.
External and internal corner.
Prop length.
Prop head.
Stub pin.
Wall tie.
Formwork used at constructionsite.
14. 14
CHAPTER-2 CONSTRUCTION STEPS OF BUILDING
1 Site clearance
2 Surveying and layout.
3 Excavation.
4 Bar binding and positioning of foundation steel.
5 Concreting.
6 Wall construction.
7 Beam and Columns.
8 Finishing and whitewashing.
2.1 SITE CLEARANCE
A no of conditions determine the kind of building that may be erected on a plot of ground.
These conditions determine where on the plot it may be located. There are also convenants that
are legally binding regulations. These may be setting height of building, prohibit utility of
buildings or ban rooftop network towers etc.
Zoning laws regulate the setback and other factors that play into equation of house location a lot.
Septic tanks also require special considerations and a certificate of occupancy is also required for
some loaning and legal processes.
2.2 Surveying and Layout
Survey is the first step done in any construction site so as to get the required level of surface. It
is also used in level transferrin during construction of retaining wall.
Generally at site survey is carried out by following two instruments.
Total Station A total station is an electronic/optical instrument used in modern
surveying and building construction. The total station is an electronic theodolite
(transit) integrated with an electronic distance meter (EDM) to read slope distances
15. 15
from the instrument to a particular point. By this instrument we can measure Angle,
Distance, Coordinate and also Data Processing.
Advantages: The following are some of the major advantages of using total station over
the conventional surveying instruments
1. Field work is carried out very fast.
2. Accuracy of measurement is high.
3. Manual errors involved in reading and recording are eliminated.
4. Calculation of coordinates is very fast and accurate. Even corrections for
temperature and pressure are automatically made.
5. Computers can be employed for map making and plotting contour and cross-sections.
Contour intervals and scales can be changed in no time.
B-Auto level- It is a leveling instrument which was on site checking the elevations of various
points.
Auto level is a modified form of dumpy level. We used auto level to transfer the level of ground
to retaining wall and setting thickness of slab in which first of all marking was made to fix the
level of particular elevations then casting of slab was performed.
Transferring of surface level to retaining wall
1 Set the auto level at the building floor level.
2 Level the instrument.
3 Take the staff reading at point also on floor level surface.
4 Locate the staff on the formwork of retaining wall and adjust the staff in such a way so
that reading of staff is same as staff reading in step 3.
2.3 EXCAVATION
Excavation work on the site was being done by the JCB Machines and excavated soil was
transferred using dumpers.
16. 16
Following measures should be prevented while excavations work.
1 There should be proper timbering while excavation for basement area.
2 Dewatering should be done before construction work.
3 During rainy season excavation work should be avoided.
Excavation of soil for construction of retaining wall.
2.4 FOUNDATION
Footings are strips of concrete or filled concrete blocks placed under foundation wall. Gravel or
crushed stone footings may also be used. The purpose of footing is to transfer the loads safely
in the ground.
Generally in high rise buildings three types of footings are provided
Isolated Footing
An isolated footing is used to support the load on a single column. It is usually either square or
rectangular in plan. It represents the simplest, most economical type and most widely used
footing. Whenever possible, square footings are provided so as to reduce the bending moments
and shearing forces at their critical sections. Isolated footings are used in case of light column
loads, when columns are not closely spaced. An isolated footing must, therefore, be provided by
17. 17
two sets of reinforcement bars placed on top of the other near the bottom of the footing. In case
of property line restrictions, footings may be designed for eccentric loading or combined footing
is used as an alternative to isolated footing.
Combined footing
Whenever a column is to be provided near the edge of property and it may not be permissible to
extend the footing beyond a certain limit. In such a case, the load on the footing will be
eccentric and hence this will result in uneven distribution of load to the supporting soil. Hence,
an alternative design would be to provide a common footing to the edge column and to an
interior column close to it. Combined footings under two or more columns are used under
closely spaced, heavily loaded interior columns where individual footings, if they were
provided, would be either very close to each other, or overlap each other. This footing is called
“combined footing”.
A view of Isolated and Combined footings at construction site
ISOLATED FOOTINGS COMBINED FOOTINGS
Raft footing or Mat footing-
This is a footing that covers the entire area under the structure. This footing is used when very
heavy loads of building are to be transmitted to the underlying soil having very low and
18. 18
differential bearing capacities. Due to its rigidity, it minimizes differential settlement. There are
several types of raft foundation in use. The most common types are; the flat slab and the slab-
beam types
Raft footings are provided in following cases
When the ground water table is high, rafts are often placed over piles to control
buoyancy.
When isolated footings for column overlap on each other.
When total area of footing slab is more than50% of total area.
Where underground flooring is required this type of footing is provided and it serves
as footing as well as floor.
2.5 CONCRETING
After shuttering and scaffolding concreting should be done.
During concreting following equipment’s are used
Concrete mixer.
Mounted concrete pump.
Concrete vibrators (e.g. Needle vibrator, plate/ surface vibrator etc.).
During concreting work following instructions should be followed
There should be proper compaction of poured concrete.
There should be spacers to provide cover to reinforcement.
There should be proper curing of concrete construction
2.6 Wall Construction
In framed structure generally brick walls are constructed for partition purpose and half brick
walls are made. But at the site no wall was constructed with brick because it was a high rise
building. All the walls were constructed as RCC wall because these acts as a shear wall and
provide horizontal stability to building and reduces the deflection.
19. 19
Workers at site during forming work for RCC wall construction
2.7 Beam and Columns
In framed structure fixed type beams are constructed. In such type of beams proper
reinforcement should be done for positive as well as negative bending moments.
In such type of structures short columns are constructed with minimum
eccentricity. In square or rectangular shaped columns min. 4 no’s of 12 mm
diameter bars must be used and spacing should not be more than as per code
IS 456:2000.
20. 20
2.8 Slab
Slabs are of following types-
One way slab
In one way slab load transfer occurs only in one direction. For one way slab aspect ratio should
be more than or equal to 2. In one way slab reinforcement calculated is provided only in shorter
direction and in other direction distribution steel is provided.
21. 21
Two way slab
In two way slab load transfer occurs in both the directions. For two way slab aspect ratio
should be less than 2. In two way slab reinforcement is provided in both shorter and longer
directions and at the supports negative reinforcement is also provided.
22. 22
CHAPTER-3 Material & Equipment
3.1MATERIALS USED FOR CONSTRUCTION AT SITE
At the construction site following materials were being used
3.1.1 Cement
The function of cement is to combine with water and to form cement paste. This paste first sets
i.e. it becomes firms and then hardens due to chemical reaction, called hydration, between the
cement and water. On setting & hardening, the cement binds the aggregate together into a stone
like hard mass & thus provides strength, durability & water-tighten to the concrete. Quality of
cement is based on grade of cement. The grades of cement are as-
33 Grade
43 Grades
53 Grades
At the site Portland cement of 53 grades (ULTRATECH CEMENT) was used.
The initial setting time of cement = 30 minutes (1/2 hr.)
The final setting time of cement = 10 hrs.
3.1.2 Aggregate
Aggregates are small pieces of broken stones in irregular size and shapes.
Neat cement is very rarely used in construction works since it is liable to shrink too much and
become cracks on setting. Moreover, it will be costly to use neat cement in construction work.
Therefore cement is mixed with some inert strong & durable hard materials.
They also reduce the cost of concrete because they are comparative much cheaper as cement.
Types of aggregates:
Fine aggregate (sand)
The aggregate, which pass through 4.75 mm, I.S. sieve and entirely retain on 75 micron
(.075mm) I.S. sieve is known as fine aggregate.
23. 23
Function of fine aggregate
The function of using fine aggregate in a concrete mix is to fill up the voids existing in the coarse
aggregate and to obtain a dense and strong concrete with less quantity of cement and increase the
workability of the concrete mix.
Coarse aggregate
The aggregate, which pass through 75 mm I.S. sieve and entirely retain on 4.75 I.S.
sieve is known as coarse aggregates.
At construction site aggregate used are as follows
Coarse aggregate of 20mm size.
Coarse aggregate of 12.5 mm size (As per concrete mix design).
Fine aggregate in form of coarse sand.
3.1.3 REINFORCEMENT
8 mm dia lateral ties 20mm dia longitudional bars
24. 24
Steel Bars in Retaining Wall Steel Bars Placed at Site
The material that develops a good bond with concrete in order to increase its strength is
called reinforcement. Steel bars are highly strong in tension, shear, bending moment,
torsion and compression.
Function of reinforcement
Reinforcement working as a tension member because concrete is strong in compression and
week in tension so reinforcement resists the tensile stresses in the concrete members. At the
site contractor using the high strength steel bars and T.M.T. (Thermo Mechanically Treated)
bars of diameter 8 mm, 10 mm, 16 mm, 20 mm & 32 mm as per requirement of design.
At construction site 8 mm, 10 mm, 16 mm, 20 mm & 32 mm (T.M.T.) reinforcement bars
were being used.
The bars were of grade Fe415 for 8mm and Fe500 for other diameter bars.
The bars were of brand TATA TISCON.
The main reason of using steel bars in RCC is that, the coefficients of thermal
expansion of steel bars and concrete is of approximately equal value.
25. 25
3.1.4 Fly ash
At the site, a small amount of fly ash was also being used which is produced by burning of
coal in thermal power plants.
The main advantages of using fly ash in building construction are as follows-
It is free of cost.
Its consumption reduces environmental pollution.
It has a fair quality of bonding properties.
3.1.5 Admixtures
Admixtures are generally used to affect workability of concrete mix and to reduce water
content. Admixtures also increases the target mean strength of concrete
At the site HYPERPLAST PC- 711 (MADE BY- DON CHEMICALS) admixture was
being used to increase workability and to reduce quantity of water in concrete mix.
Types of admixtures-
Accelerators
Retarders
Water reducers/plasticizers/superplasticizers
Air entraining agents
Bonding admixtures
26. 26
3.1.6 Other materials
Stone dust
Plywood
3.2 EQUIPMENTS USED
3.2.1. Concrete pump
3.2.2. Rotary mixer for transporting R.M.C.
3.2.3. Crane
3.2.4. Boom pump (used in construction of retaining wall where transportation of
R.M.C. was very difficult because of excavation work)
3.2.5. Ready Mix Concrete plant
29. 29
CHAPTER-4 Quality Control
Quality control is the part of quality management that ensures products and service comply
with requirements. It is a work method that facilitates the measurement of the quality
characteristics of a unit, compares them with the established standards, and analyses the
differences between the results obtained and the desired results in order to make decisions
which will correct any differences.
Technical specifications define the type of controls that must be carried out to ensure the
construction works are carried out correctly. They include not only products materials, but
also the execution and completion of the works.
Causes for poor quality These can be summarized as ignorance, poor materials, poor
design, poor detailing, poor workmanship, improper quantity of cement, improper
concrete mix, excess water, inadequate compaction, substandard forms, inadequate
curing, inadequate cover, poor construction practices, poor supervision and above all
lack of technical knowledge.
4.1 QUALITY CONTROL IN CONCRETE WORKS
Since concrete keeps a very important place in modern building construction works, so it
is necessary to test and inspection of concrete work at site.
Following points should be kept in mind while concreting.
There should proper compacting of poured concrete because every 1% void
reduce the strength of concrete by 20%.
There should be proper curing of concrete work for at least 7 to 10days because it helps in
gaining the strength.
Level of formwork should be same throughout the building while casting the slab
There should be a lab to test the properties of Green Concrete like slump, initial
setting time etc.
30. 30
There should be proper portioning of materials while preparing R.M.C.
4.1.1Quality control works in concreting at site
Needle vibrator was being used for compaction.
RMC plant was being operated for concrete mixing.
A lab was established for testing.
4.2 QUALITY CONTROL IN REINFOREMENT
The reinforcement should be provided at designed spacing.
Steel bars of designed grade should be used.
Steel bars should be placed at dry places to prevent them from corrosion.
For quality assurance of steel a test report was also given to company by TATA
STEEL LIMITED.
31. 31
CHAPTER-4 Contribution
5.1 REINFORCEMENT PLACEMENT AND CASTING OF SLAB
At there I was involved while placement of reinforcement bar for monolithic
construction of concrete slab with beam.
Reinforcement in the slab with alternate bent up bars provided at supports in order to
provide negative reinforcement at support in two way slab
32. 32
Reinforcement in the slab at site
.
In concreting, concrete pump, needle vibrator etc. were used
33. 33
5.2 IN THE CONSTRUCTION OF RETAINING WALL
In the retaining wall two sided reinforcement was provided with 16mm steel bars
with 200mm c/c spacing.
The retaining wall was constructed without shear key.
RETAINING WALL AFTER
CONSTRUCTION
A VIEW OF REINFORCEMENT IN
RETAINING
WALL
5.3 IN THE CONSTRUCTION OF SHEAR WALL
At the site all the walls were provided with two sided reinforcement and constructed by
concrete which may work as shear wall during earthquake or wind blow. In general
buildings lift pit acts as shear wall and reduces horizontal deflection of building during
horizontal loading.
34. 34
LIFT PIT SERVES AS SHEAR WALL
A VIEW OF REINFORCEMENT IN
RCC WALL
5.4 PALCING OF REINFORCEMENT IN A COLUMN
LATERAL TIES WITH 135* BEND
35. 35
Lateral ties 8mm dia provided@150mm c/c in a column
Longitudional steel bars of 20mm dia provided in a column