Background
 As per our syllabus, we fourth year students have to
present our final year project in our desired field of
interest. It is a vital part of IOE syllabus in order to
make students competent to work in the actual field.
 We have chosen rural road development project
among the number of options available in
transportation project.
 We want to experience the working technique with
new innovative concept of ours while designing a road
in a sense of future demand that is structurally, eco-
friendly and atheistically designed.2
Intro
T
R
A
N
S
P
O
R
T
A
T
I
O
N
 Transportation plays a vital role in
basic infrastructure development in
mountainous country like Nepal.
 It is a social property.
 It is demand fulfilling demand.
3
Objectives and Scope
 To setup an alignment of a road as per the
environmental condition.
 To consider gradient, earthwork, road components
(drainage, retaining walls), geometric properties of the
road properly in the design.
 To prepare economical and stable road in rural areas.
 To link urban and rural areas with comfort, wide, safe,
smooth road.
4
Objectives and Scope
 For the overall development of country.
 To minimize the risk of loss of property and lives
by designing stable roads.
 To know the importance of team work.
 To design the road with innovative concept that is
structurally, atheistically and eco-friendly aspect.
5
Gantt chart
WORKING SCHEDULE
6
METHODOLOGY
 Planning
 Survey
 Preliminary Design
 Geometric Design
 Detailing
 Calculation
 Plotting
 Modeling
 Analysis
 Report Preparation
7
The work to be performed while
doing our project are listed as series
below:
Project PERT Chart
START
Pre synopsis
submission
Site
Selection
Reconnaissan
ce survey
11 th Nov , 2014
8
Survey and
data plot
Tests of soil
samples
Computation and
design
Traffic count
9
Project report
submission
Conclusion END
2015
10
ROAD SITE
Pang Gaun to Tika Bhairav (2.5km)
Location:
 Zone: Bagmati
 District: Lalitpur
 VDC: Pang Gaun
11
12
MAP STUDY
Location :- Where are things situated?
 A location can be specific for example, it can be
stated as coordinates of longitude and latitude or as a
distance from one place to another place.
eg. In our case, road site’s location is south east from
the valley.
 Latitudes/easting are imaginary lines running parallel
to the Equator.
 Longitudes(departures)/northing are imaginary lines
running parallel to the Prime Meridian.
13
MAP STUDY
14
Place :- What makes a place different from other
places? Differences might be defined in terms of
climate, physical features, or the people who live
there and their traditions.
Human-environment interaction :- What are the
relationships among people and places? How
have people changed the environment to better
suit their needs?
SOCIO-ECONOMIC
CONDITION
 The major caste in this area are newars, brahmin,
chhetri, sarkis, etc.
 Mainly the people are involved in agriculture.
 People are not well educated.
 The economic condition is poor.
Equipments used in geometric
survey
GPS (Global Positioning System)
 2 numbers
 Principle:
Satellites based allocation of a position by
latitude, departure and elevation.
16
Geometric design
17
 Profile
 Plan
 Cross section
18
fig. Plan (central alignment only)
Pavement design
 Traffic count
 CBR test
19
Traffic study
 A traffic study is an engineering investigation
to evaluate a transportation system.
 A study typically consists of collecting data,
projecting traffic volumes, and identifying the
improvements required for the transportation
system.
20
Traffic Count
 A traffic count is a count of traffic along a
particular road, either done electronically or by
people counting by the side of the road.
 Traffic counts can be used by local councils to
identify which routes are used most, and to either
improve that road or provide an alternative if
there is an excessive amount of traffic.
Traffic Count
Leaving the valley Entering the valley
22
bike car/jeep bus
Truck
( unloaded)
Truck
(loaded)
Heavy
(tipper) tandem
19 5 2 1 8 1 0
11 2 4 1 3 1 0
8 2 3 4 13 2 1
9 3 1 1 12 0 0
bike car/jeep bus
Truck
( unloaded)
Truck
(loaded)
Heavy
(tipper) tandem
15 2 4 5 3 0 0
7 4 1 6 0 0 0
11 1 1 2 0 0 0
6 3 6 12 0 0 0
minutes
15
other 15
other 15
other 15
39 10 12 25 3 0 0 47 12 10 7 36 4 1total
Therefore,
Total traffic volume= 206 vehicles per hour
23
CBR test
24
CBR test
25
26
CB
R
= CBR [%]
p = measured pressure for site soils [N/mm²]
ps
= pressure to achieve equal penetration on standard
soil [N/mm²]
27
CBR VALUE SUBGRADE STRENGTH
3% and less Poor
3% - 5% Normal
5% - 15% Good
CONCLUSION
 Geometric analysis of different roads has become
evitable in today’s world. So, we are quite interested
in indulging us in this research as we have interest
towards this subject. Further in Nepal, geometric
analysis of roads are to be done and for this we want
to prepare ourselves.
 We believe that after the completion of this project we
are not only capable of geometrically analyzing
existing as well as newly prepared roads but also can
put forward our suggestions to ensure or increase the
safety, strength and durability of the roads.
28
design references
 Rural Road Standard, DOLIDAR
 Pavement Design Guidelines, DOR
29
Thank
You!!!
30

More Related Content

What's hot

Floods
FloodsFloods
O & d survey
O & d survey O & d survey
O & d survey
KACHHOT BHAVESH
 
O and d study
O and d studyO and d study
O and d study
meetmksvs
 
Highway planning
Highway planningHighway planning
Highway planning
AKANSHA GURELE
 
Cordon line survey
Cordon line surveyCordon line survey
Cordon line survey
Nilgabs1
 
Modal split analysis
Modal split analysis Modal split analysis
Modal split analysis
ashahit
 
Chapter 3&4
Chapter 3&4Chapter 3&4
Chapter 3&4
EWIT
 
Traffic Volume Studies
Traffic Volume StudiesTraffic Volume Studies
Traffic Volume Studies
Md Tanvir Alam
 
Land-use transport planning
Land-use transport planning Land-use transport planning
Land-use transport planning
Bhavik A Shah
 
Hyetograph and hydrograph analysis
Hyetograph and hydrograph analysisHyetograph and hydrograph analysis
Hyetograph and hydrograph analysis
vivek gami
 
Traffic study project for final year CIVIL engineering
Traffic study project for final year CIVIL engineeringTraffic study project for final year CIVIL engineering
Traffic study project for final year CIVIL engineering
MohammadOsamaJafry
 
Stream Gauging
Stream GaugingStream Gauging
Stream Gauging
Sunny Agarwal
 
Flood estimation
Flood estimation Flood estimation
Flood estimation
RAJ BAIRWA
 
Poulation forecasting
Poulation forecastingPoulation forecasting
Poulation forecasting
Dr. Pallavi Badry
 
Capacity and LOS of Multi-Lane HIghways
Capacity and LOS of Multi-Lane HIghwaysCapacity and LOS of Multi-Lane HIghways
Capacity and LOS of Multi-Lane HIghways
Raghupathi Kandiboina
 
Seal coat,prime coat and tack coat
Seal coat,prime coat and tack coatSeal coat,prime coat and tack coat
Seal coat,prime coat and tack coat
MuhammadArif856
 
Unit 1
Unit 1Unit 1
Parking study
Parking studyParking study
Parking study
Ghanashyam Prajapati
 
3-Trip Generation-Distribution ( Transportation and Traffic Engineering Dr. S...
3-Trip Generation-Distribution ( Transportation and Traffic Engineering Dr. S...3-Trip Generation-Distribution ( Transportation and Traffic Engineering Dr. S...
3-Trip Generation-Distribution ( Transportation and Traffic Engineering Dr. S...
Hossam Shafiq I
 
Soil stabilisation (1)
Soil stabilisation (1)Soil stabilisation (1)
Soil stabilisation (1)
Safiullah Khan
 

What's hot (20)

Floods
FloodsFloods
Floods
 
O & d survey
O & d survey O & d survey
O & d survey
 
O and d study
O and d studyO and d study
O and d study
 
Highway planning
Highway planningHighway planning
Highway planning
 
Cordon line survey
Cordon line surveyCordon line survey
Cordon line survey
 
Modal split analysis
Modal split analysis Modal split analysis
Modal split analysis
 
Chapter 3&4
Chapter 3&4Chapter 3&4
Chapter 3&4
 
Traffic Volume Studies
Traffic Volume StudiesTraffic Volume Studies
Traffic Volume Studies
 
Land-use transport planning
Land-use transport planning Land-use transport planning
Land-use transport planning
 
Hyetograph and hydrograph analysis
Hyetograph and hydrograph analysisHyetograph and hydrograph analysis
Hyetograph and hydrograph analysis
 
Traffic study project for final year CIVIL engineering
Traffic study project for final year CIVIL engineeringTraffic study project for final year CIVIL engineering
Traffic study project for final year CIVIL engineering
 
Stream Gauging
Stream GaugingStream Gauging
Stream Gauging
 
Flood estimation
Flood estimation Flood estimation
Flood estimation
 
Poulation forecasting
Poulation forecastingPoulation forecasting
Poulation forecasting
 
Capacity and LOS of Multi-Lane HIghways
Capacity and LOS of Multi-Lane HIghwaysCapacity and LOS of Multi-Lane HIghways
Capacity and LOS of Multi-Lane HIghways
 
Seal coat,prime coat and tack coat
Seal coat,prime coat and tack coatSeal coat,prime coat and tack coat
Seal coat,prime coat and tack coat
 
Unit 1
Unit 1Unit 1
Unit 1
 
Parking study
Parking studyParking study
Parking study
 
3-Trip Generation-Distribution ( Transportation and Traffic Engineering Dr. S...
3-Trip Generation-Distribution ( Transportation and Traffic Engineering Dr. S...3-Trip Generation-Distribution ( Transportation and Traffic Engineering Dr. S...
3-Trip Generation-Distribution ( Transportation and Traffic Engineering Dr. S...
 
Soil stabilisation (1)
Soil stabilisation (1)Soil stabilisation (1)
Soil stabilisation (1)
 

Viewers also liked

STOMP sample project presentation
STOMP sample project presentationSTOMP sample project presentation
STOMP sample project presentation
sburakharper
 
Sample project
Sample projectSample project
Sample project
Zoltan Bognar
 
Online quiz system
Online quiz systemOnline quiz system
Online quiz system
Satyaki Mitra
 
Project planning and feasibility study
Project planning and feasibility studyProject planning and feasibility study
Project planning and feasibility study
Mars Mfyam
 
The socio-economic burden of unsafe abortion for women and households in Zambia
The socio-economic burden of unsafe abortion for women and households in ZambiaThe socio-economic burden of unsafe abortion for women and households in Zambia
The socio-economic burden of unsafe abortion for women and households in Zambia
Pregnancy termination trajectories in Zambia: the socio-economic costs
 
Unsafe Abortion
Unsafe AbortionUnsafe Abortion
Unsafe Abortion
Mahfuz Chowdhury
 
Bankole (Guttmacher) - Unsafe Abortion
Bankole (Guttmacher) - Unsafe AbortionBankole (Guttmacher) - Unsafe Abortion
Bankole (Guttmacher) - Unsafe Abortion
guestc7da32
 
Determining the Mathematical ROI of a Project Management Office (PMO) Impleme...
Determining the Mathematical ROI of a Project Management Office (PMO) Impleme...Determining the Mathematical ROI of a Project Management Office (PMO) Impleme...
Determining the Mathematical ROI of a Project Management Office (PMO) Impleme...
Ricardo Viana Vargas
 
Thesis Defence for Doctor of Information Science
Thesis Defence for Doctor of Information ScienceThesis Defence for Doctor of Information Science
Thesis Defence for Doctor of Information Science
Yuma Inoue
 
Abortions and Post Abortion Care
Abortions and Post Abortion CareAbortions and Post Abortion Care
Abortions and Post Abortion Care
Mubarak Yusuf
 
How to Give a TED Worthy Presentation
How to Give a TED Worthy PresentationHow to Give a TED Worthy Presentation
How to Give a TED Worthy Presentation
Brooke Estin
 
Online Quiz System Project PPT
Online Quiz System Project PPTOnline Quiz System Project PPT
Online Quiz System Project PPT
Shanthan Reddy
 
Earthquake Resistant Designs
Earthquake Resistant DesignsEarthquake Resistant Designs
Earthquake Resistant Designs
JNTU
 
Web design proposal sample
Web design proposal sampleWeb design proposal sample
Web design proposal sample
Adviacent
 
Sample project abstract
Sample project abstractSample project abstract
Sample project abstract
klezeh
 
abortion ppt
abortion pptabortion ppt
abortion ppt
Ameenah
 
Project proposal
Project proposalProject proposal
Project proposal
Cheri Amour Calicdan
 
Sample Project Proposal Design Document
Sample Project Proposal Design DocumentSample Project Proposal Design Document
Sample Project Proposal Design Document
Arturo Pelayo
 
My Thesis Defense Presentation
My Thesis Defense PresentationMy Thesis Defense Presentation
My Thesis Defense Presentation
David Onoue
 
Project proposal
Project proposalProject proposal
Project proposal
Jayson Patalinghug
 

Viewers also liked (20)

STOMP sample project presentation
STOMP sample project presentationSTOMP sample project presentation
STOMP sample project presentation
 
Sample project
Sample projectSample project
Sample project
 
Online quiz system
Online quiz systemOnline quiz system
Online quiz system
 
Project planning and feasibility study
Project planning and feasibility studyProject planning and feasibility study
Project planning and feasibility study
 
The socio-economic burden of unsafe abortion for women and households in Zambia
The socio-economic burden of unsafe abortion for women and households in ZambiaThe socio-economic burden of unsafe abortion for women and households in Zambia
The socio-economic burden of unsafe abortion for women and households in Zambia
 
Unsafe Abortion
Unsafe AbortionUnsafe Abortion
Unsafe Abortion
 
Bankole (Guttmacher) - Unsafe Abortion
Bankole (Guttmacher) - Unsafe AbortionBankole (Guttmacher) - Unsafe Abortion
Bankole (Guttmacher) - Unsafe Abortion
 
Determining the Mathematical ROI of a Project Management Office (PMO) Impleme...
Determining the Mathematical ROI of a Project Management Office (PMO) Impleme...Determining the Mathematical ROI of a Project Management Office (PMO) Impleme...
Determining the Mathematical ROI of a Project Management Office (PMO) Impleme...
 
Thesis Defence for Doctor of Information Science
Thesis Defence for Doctor of Information ScienceThesis Defence for Doctor of Information Science
Thesis Defence for Doctor of Information Science
 
Abortions and Post Abortion Care
Abortions and Post Abortion CareAbortions and Post Abortion Care
Abortions and Post Abortion Care
 
How to Give a TED Worthy Presentation
How to Give a TED Worthy PresentationHow to Give a TED Worthy Presentation
How to Give a TED Worthy Presentation
 
Online Quiz System Project PPT
Online Quiz System Project PPTOnline Quiz System Project PPT
Online Quiz System Project PPT
 
Earthquake Resistant Designs
Earthquake Resistant DesignsEarthquake Resistant Designs
Earthquake Resistant Designs
 
Web design proposal sample
Web design proposal sampleWeb design proposal sample
Web design proposal sample
 
Sample project abstract
Sample project abstractSample project abstract
Sample project abstract
 
abortion ppt
abortion pptabortion ppt
abortion ppt
 
Project proposal
Project proposalProject proposal
Project proposal
 
Sample Project Proposal Design Document
Sample Project Proposal Design DocumentSample Project Proposal Design Document
Sample Project Proposal Design Document
 
My Thesis Defense Presentation
My Thesis Defense PresentationMy Thesis Defense Presentation
My Thesis Defense Presentation
 
Project proposal
Project proposalProject proposal
Project proposal
 

Similar to project work presentation on road feasibility study (need to be corrected but can be used as reference)

Impact of Transportation System on Land Use in CBD area of Pabna Municipality...
Impact of Transportation System on Land Use in CBD area of Pabna Municipality...Impact of Transportation System on Land Use in CBD area of Pabna Municipality...
Impact of Transportation System on Land Use in CBD area of Pabna Municipality...
Md. Merazul Islam Abir
 
Impact of Different Types of Land Use on Transportation System of Dhaka City ...
Impact of Different Types of Land Use on Transportation System of Dhaka City ...Impact of Different Types of Land Use on Transportation System of Dhaka City ...
Impact of Different Types of Land Use on Transportation System of Dhaka City ...
Shahadat Hossain Shakil
 
IRJET- Rural Road Design and Development
IRJET- Rural Road Design and DevelopmentIRJET- Rural Road Design and Development
IRJET- Rural Road Design and Development
IRJET Journal
 
Identification of Suitable Landfill Site using Geographical Information Syste...
Identification of Suitable Landfill Site using Geographical Information Syste...Identification of Suitable Landfill Site using Geographical Information Syste...
Identification of Suitable Landfill Site using Geographical Information Syste...
Trupti Lokhande
 
Rmtsp
RmtspRmtsp
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
IJERD Editor
 
Applications of GIS in Municipal Solid Waste Management
Applications of GIS in Municipal Solid Waste ManagementApplications of GIS in Municipal Solid Waste Management
Applications of GIS in Municipal Solid Waste Management
Vignesh Sekar
 
Land use planning
Land use planningLand use planning
Land use planning
Kushal Patel
 
SNEAPA 2013 Friday e2_gis
SNEAPA 2013 Friday e2_gisSNEAPA 2013 Friday e2_gis
Landscape design for multimodal transport corridors
Landscape design for multimodal transport corridorsLandscape design for multimodal transport corridors
Landscape design for multimodal transport corridors
Geeva Chandana
 
BIKE IT MAKATI
BIKE IT MAKATIBIKE IT MAKATI
BIKE IT MAKATI
Rodelon Ramos
 
Route optimization of solid waste transportation in part of Lucknow- Capital ...
Route optimization of solid waste transportation in part of Lucknow- Capital ...Route optimization of solid waste transportation in part of Lucknow- Capital ...
Route optimization of solid waste transportation in part of Lucknow- Capital ...
IRJET Journal
 
Mode choice between roadway and waterway
Mode choice between roadway and waterwayMode choice between roadway and waterway
Mode choice between roadway and waterway
Aglaia Connect
 
Northern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGM
Northern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGMNorthern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGM
Northern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGM
Place North West
 
Study is to perform roadway condition survey of link road between panthapath ...
Study is to perform roadway condition survey of link road between panthapath ...Study is to perform roadway condition survey of link road between panthapath ...
Study is to perform roadway condition survey of link road between panthapath ...
Khaza Ahmed Palash
 
Remote Sensing and GIS-Based Monitoring of Land Use Change in Nagpur District...
Remote Sensing and GIS-Based Monitoring of Land Use Change in Nagpur District...Remote Sensing and GIS-Based Monitoring of Land Use Change in Nagpur District...
Remote Sensing and GIS-Based Monitoring of Land Use Change in Nagpur District...
IRJET Journal
 
civil engineers project work .docx
civil engineers project work .docxcivil engineers project work .docx
civil engineers project work .docx
Vijay Kumar
 
roadway condition survey
roadway condition surveyroadway condition survey
roadway condition survey
mruemran
 
A Review of "Evaluation of the Need for Highway Redesign and Modernization."
A Review of "Evaluation of the Need for Highway Redesign and Modernization."A Review of "Evaluation of the Need for Highway Redesign and Modernization."
A Review of "Evaluation of the Need for Highway Redesign and Modernization."
IRJET Journal
 
Training report of road construction
Training report of road constructionTraining report of road construction
Training report of road construction
ManavSinghal8
 

Similar to project work presentation on road feasibility study (need to be corrected but can be used as reference) (20)

Impact of Transportation System on Land Use in CBD area of Pabna Municipality...
Impact of Transportation System on Land Use in CBD area of Pabna Municipality...Impact of Transportation System on Land Use in CBD area of Pabna Municipality...
Impact of Transportation System on Land Use in CBD area of Pabna Municipality...
 
Impact of Different Types of Land Use on Transportation System of Dhaka City ...
Impact of Different Types of Land Use on Transportation System of Dhaka City ...Impact of Different Types of Land Use on Transportation System of Dhaka City ...
Impact of Different Types of Land Use on Transportation System of Dhaka City ...
 
IRJET- Rural Road Design and Development
IRJET- Rural Road Design and DevelopmentIRJET- Rural Road Design and Development
IRJET- Rural Road Design and Development
 
Identification of Suitable Landfill Site using Geographical Information Syste...
Identification of Suitable Landfill Site using Geographical Information Syste...Identification of Suitable Landfill Site using Geographical Information Syste...
Identification of Suitable Landfill Site using Geographical Information Syste...
 
Rmtsp
RmtspRmtsp
Rmtsp
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
Applications of GIS in Municipal Solid Waste Management
Applications of GIS in Municipal Solid Waste ManagementApplications of GIS in Municipal Solid Waste Management
Applications of GIS in Municipal Solid Waste Management
 
Land use planning
Land use planningLand use planning
Land use planning
 
SNEAPA 2013 Friday e2_gis
SNEAPA 2013 Friday e2_gisSNEAPA 2013 Friday e2_gis
SNEAPA 2013 Friday e2_gis
 
Landscape design for multimodal transport corridors
Landscape design for multimodal transport corridorsLandscape design for multimodal transport corridors
Landscape design for multimodal transport corridors
 
BIKE IT MAKATI
BIKE IT MAKATIBIKE IT MAKATI
BIKE IT MAKATI
 
Route optimization of solid waste transportation in part of Lucknow- Capital ...
Route optimization of solid waste transportation in part of Lucknow- Capital ...Route optimization of solid waste transportation in part of Lucknow- Capital ...
Route optimization of solid waste transportation in part of Lucknow- Capital ...
 
Mode choice between roadway and waterway
Mode choice between roadway and waterwayMode choice between roadway and waterway
Mode choice between roadway and waterway
 
Northern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGM
Northern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGMNorthern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGM
Northern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGM
 
Study is to perform roadway condition survey of link road between panthapath ...
Study is to perform roadway condition survey of link road between panthapath ...Study is to perform roadway condition survey of link road between panthapath ...
Study is to perform roadway condition survey of link road between panthapath ...
 
Remote Sensing and GIS-Based Monitoring of Land Use Change in Nagpur District...
Remote Sensing and GIS-Based Monitoring of Land Use Change in Nagpur District...Remote Sensing and GIS-Based Monitoring of Land Use Change in Nagpur District...
Remote Sensing and GIS-Based Monitoring of Land Use Change in Nagpur District...
 
civil engineers project work .docx
civil engineers project work .docxcivil engineers project work .docx
civil engineers project work .docx
 
roadway condition survey
roadway condition surveyroadway condition survey
roadway condition survey
 
A Review of "Evaluation of the Need for Highway Redesign and Modernization."
A Review of "Evaluation of the Need for Highway Redesign and Modernization."A Review of "Evaluation of the Need for Highway Redesign and Modernization."
A Review of "Evaluation of the Need for Highway Redesign and Modernization."
 
Training report of road construction
Training report of road constructionTraining report of road construction
Training report of road construction
 

Recently uploaded

Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
sexytaniya455
 
🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...
🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...
🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...
aarusi sexy model
 
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
DharmaBanothu
 
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEERDELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
EMERSON EDUARDO RODRIGUES
 
TENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineeringTENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineering
SnehalChavan75
 
Call Girls Chennai +91-8824825030 Vip Call Girls Chennai
Call Girls Chennai +91-8824825030 Vip Call Girls ChennaiCall Girls Chennai +91-8824825030 Vip Call Girls Chennai
Call Girls Chennai +91-8824825030 Vip Call Girls Chennai
paraasingh12 #V08
 
Cricket management system ptoject report.pdf
Cricket management system ptoject report.pdfCricket management system ptoject report.pdf
Cricket management system ptoject report.pdf
Kamal Acharya
 
paper relate Chozhavendhan et al. 2020.pdf
paper relate Chozhavendhan et al. 2020.pdfpaper relate Chozhavendhan et al. 2020.pdf
paper relate Chozhavendhan et al. 2020.pdf
ShurooqTaib
 
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
DharmaBanothu
 
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort ServiceCuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
yakranividhrini
 
My Airframe Metallic Design Capability Studies..pdf
My Airframe Metallic Design Capability Studies..pdfMy Airframe Metallic Design Capability Studies..pdf
My Airframe Metallic Design Capability Studies..pdf
Geoffrey Wardle. MSc. MSc. Snr.MAIAA
 
Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine
 
CSP_Study - Notes (Paul McNeill) 2017.pdf
CSP_Study - Notes (Paul McNeill) 2017.pdfCSP_Study - Notes (Paul McNeill) 2017.pdf
CSP_Study - Notes (Paul McNeill) 2017.pdf
Ismail Sultan
 
Lateral load-resisting systems in buildings.pptx
Lateral load-resisting systems in buildings.pptxLateral load-resisting systems in buildings.pptx
Lateral load-resisting systems in buildings.pptx
DebendraDevKhanal1
 
Online train ticket booking system project.pdf
Online train ticket booking system project.pdfOnline train ticket booking system project.pdf
Online train ticket booking system project.pdf
Kamal Acharya
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
felixwold
 
Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)
Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)
Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)
Tsuyoshi Horigome
 
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
simrangupta87541
 
INTRODUCTION TO ARTIFICIAL INTELLIGENCE BASIC
INTRODUCTION TO ARTIFICIAL INTELLIGENCE BASICINTRODUCTION TO ARTIFICIAL INTELLIGENCE BASIC
INTRODUCTION TO ARTIFICIAL INTELLIGENCE BASIC
GOKULKANNANMMECLECTC
 
Intuit CRAFT demonstration presentation for sde
Intuit CRAFT demonstration presentation for sdeIntuit CRAFT demonstration presentation for sde
Intuit CRAFT demonstration presentation for sde
ShivangMishra54
 

Recently uploaded (20)

Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
 
🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...
🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...
🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...
 
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
 
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEERDELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
DELTA V MES EMERSON EDUARDO RODRIGUES ENGINEER
 
TENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineeringTENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineering
 
Call Girls Chennai +91-8824825030 Vip Call Girls Chennai
Call Girls Chennai +91-8824825030 Vip Call Girls ChennaiCall Girls Chennai +91-8824825030 Vip Call Girls Chennai
Call Girls Chennai +91-8824825030 Vip Call Girls Chennai
 
Cricket management system ptoject report.pdf
Cricket management system ptoject report.pdfCricket management system ptoject report.pdf
Cricket management system ptoject report.pdf
 
paper relate Chozhavendhan et al. 2020.pdf
paper relate Chozhavendhan et al. 2020.pdfpaper relate Chozhavendhan et al. 2020.pdf
paper relate Chozhavendhan et al. 2020.pdf
 
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
 
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort ServiceCuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
 
My Airframe Metallic Design Capability Studies..pdf
My Airframe Metallic Design Capability Studies..pdfMy Airframe Metallic Design Capability Studies..pdf
My Airframe Metallic Design Capability Studies..pdf
 
Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024
 
CSP_Study - Notes (Paul McNeill) 2017.pdf
CSP_Study - Notes (Paul McNeill) 2017.pdfCSP_Study - Notes (Paul McNeill) 2017.pdf
CSP_Study - Notes (Paul McNeill) 2017.pdf
 
Lateral load-resisting systems in buildings.pptx
Lateral load-resisting systems in buildings.pptxLateral load-resisting systems in buildings.pptx
Lateral load-resisting systems in buildings.pptx
 
Online train ticket booking system project.pdf
Online train ticket booking system project.pdfOnline train ticket booking system project.pdf
Online train ticket booking system project.pdf
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
 
Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)
Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)
Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)
 
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
 
INTRODUCTION TO ARTIFICIAL INTELLIGENCE BASIC
INTRODUCTION TO ARTIFICIAL INTELLIGENCE BASICINTRODUCTION TO ARTIFICIAL INTELLIGENCE BASIC
INTRODUCTION TO ARTIFICIAL INTELLIGENCE BASIC
 
Intuit CRAFT demonstration presentation for sde
Intuit CRAFT demonstration presentation for sdeIntuit CRAFT demonstration presentation for sde
Intuit CRAFT demonstration presentation for sde
 

project work presentation on road feasibility study (need to be corrected but can be used as reference)

  • 1. -Rakesh Sunari Magar(77) -Pawan Bhatta(65) -Nirajan Dahal(58) -Needesh Budhathoki(56) Prof. Dr. Padma Bahadur Shahi 1
  • 2. Background  As per our syllabus, we fourth year students have to present our final year project in our desired field of interest. It is a vital part of IOE syllabus in order to make students competent to work in the actual field.  We have chosen rural road development project among the number of options available in transportation project.  We want to experience the working technique with new innovative concept of ours while designing a road in a sense of future demand that is structurally, eco- friendly and atheistically designed.2
  • 3. Intro T R A N S P O R T A T I O N  Transportation plays a vital role in basic infrastructure development in mountainous country like Nepal.  It is a social property.  It is demand fulfilling demand. 3
  • 4. Objectives and Scope  To setup an alignment of a road as per the environmental condition.  To consider gradient, earthwork, road components (drainage, retaining walls), geometric properties of the road properly in the design.  To prepare economical and stable road in rural areas.  To link urban and rural areas with comfort, wide, safe, smooth road. 4
  • 5. Objectives and Scope  For the overall development of country.  To minimize the risk of loss of property and lives by designing stable roads.  To know the importance of team work.  To design the road with innovative concept that is structurally, atheistically and eco-friendly aspect. 5
  • 7. METHODOLOGY  Planning  Survey  Preliminary Design  Geometric Design  Detailing  Calculation  Plotting  Modeling  Analysis  Report Preparation 7 The work to be performed while doing our project are listed as series below:
  • 8. Project PERT Chart START Pre synopsis submission Site Selection Reconnaissan ce survey 11 th Nov , 2014 8
  • 9. Survey and data plot Tests of soil samples Computation and design Traffic count 9
  • 11. ROAD SITE Pang Gaun to Tika Bhairav (2.5km) Location:  Zone: Bagmati  District: Lalitpur  VDC: Pang Gaun 11
  • 12. 12
  • 13. MAP STUDY Location :- Where are things situated?  A location can be specific for example, it can be stated as coordinates of longitude and latitude or as a distance from one place to another place. eg. In our case, road site’s location is south east from the valley.  Latitudes/easting are imaginary lines running parallel to the Equator.  Longitudes(departures)/northing are imaginary lines running parallel to the Prime Meridian. 13
  • 14. MAP STUDY 14 Place :- What makes a place different from other places? Differences might be defined in terms of climate, physical features, or the people who live there and their traditions. Human-environment interaction :- What are the relationships among people and places? How have people changed the environment to better suit their needs?
  • 15. SOCIO-ECONOMIC CONDITION  The major caste in this area are newars, brahmin, chhetri, sarkis, etc.  Mainly the people are involved in agriculture.  People are not well educated.  The economic condition is poor.
  • 16. Equipments used in geometric survey GPS (Global Positioning System)  2 numbers  Principle: Satellites based allocation of a position by latitude, departure and elevation. 16
  • 17. Geometric design 17  Profile  Plan  Cross section
  • 18. 18 fig. Plan (central alignment only)
  • 19. Pavement design  Traffic count  CBR test 19
  • 20. Traffic study  A traffic study is an engineering investigation to evaluate a transportation system.  A study typically consists of collecting data, projecting traffic volumes, and identifying the improvements required for the transportation system. 20
  • 21. Traffic Count  A traffic count is a count of traffic along a particular road, either done electronically or by people counting by the side of the road.  Traffic counts can be used by local councils to identify which routes are used most, and to either improve that road or provide an alternative if there is an excessive amount of traffic.
  • 22. Traffic Count Leaving the valley Entering the valley 22 bike car/jeep bus Truck ( unloaded) Truck (loaded) Heavy (tipper) tandem 19 5 2 1 8 1 0 11 2 4 1 3 1 0 8 2 3 4 13 2 1 9 3 1 1 12 0 0 bike car/jeep bus Truck ( unloaded) Truck (loaded) Heavy (tipper) tandem 15 2 4 5 3 0 0 7 4 1 6 0 0 0 11 1 1 2 0 0 0 6 3 6 12 0 0 0 minutes 15 other 15 other 15 other 15 39 10 12 25 3 0 0 47 12 10 7 36 4 1total
  • 23. Therefore, Total traffic volume= 206 vehicles per hour 23
  • 26. 26 CB R = CBR [%] p = measured pressure for site soils [N/mm²] ps = pressure to achieve equal penetration on standard soil [N/mm²]
  • 27. 27 CBR VALUE SUBGRADE STRENGTH 3% and less Poor 3% - 5% Normal 5% - 15% Good
  • 28. CONCLUSION  Geometric analysis of different roads has become evitable in today’s world. So, we are quite interested in indulging us in this research as we have interest towards this subject. Further in Nepal, geometric analysis of roads are to be done and for this we want to prepare ourselves.  We believe that after the completion of this project we are not only capable of geometrically analyzing existing as well as newly prepared roads but also can put forward our suggestions to ensure or increase the safety, strength and durability of the roads. 28
  • 29. design references  Rural Road Standard, DOLIDAR  Pavement Design Guidelines, DOR 29