尊敬的 微信汇率:1円 ≈ 0.046166 元 支付宝汇率:1円 ≈ 0.046257元 [退出登录]
SlideShare a Scribd company logo
6/15/2024 1
PROGRAM EVALUATION
REVIEW TECHNIQUE(PERT)
and GANTT CHART
Ms. Jyoti Chand
MSc Nursing
Objectives
◦ to introduce programme evaluation review technique
◦ to describe purposes of PERT
◦ to enlist features of PERT
◦ to explain components of PERT
◦ to explain steps involved in PERT
◦ to enumerate advantages of PERT
◦ to elaborate limitations
6/15/2024 2
Introduction
◦ PERT is a method of analyzing the task involved in a given project,
especially the time needed to complete each task, and to identify the
minimum time needed to complete the project.
◦ In 1958, the project evaluation review technique was developed by Booz
Allen Hamilton, the US Navy to manage the Polaris submarine missile
program of their special projects office.
6/15/2024 3
Definition
◦ PERT is a work devised to complete the project work in time. It analyses
the actual work time required to complete a task.
6/15/2024 4
Purposes of PERT
◦ To minimize time and cost for completing a program.
◦ To minimize idle resources.
◦ To improve communication and coordination among different
management levels.
◦ To identify issues and obstacles.
◦ To monitor the work progress.
◦ To complete the project so as to minimize time.
6/15/2024 5
Features of PERT
◦ PERT is a task- oriented technique.
◦ It may contain hundreds or thousands of events.
◦ It identifies events.
◦ It identifies critical activities.
◦ It specifies the time required to complete each identified
event/task/activity.
◦ It calculate the minimum time for project completion.
◦ It allows uncertainty in the duration of tasks.
6/15/2024 6
6/15/2024 7
3 Parameters
1. Optimistic time
2. Most likely time
3. Pessimistic time
Cont…
◦ Optimistic time: It is the minimum possible time required to complete
the task anticipating that every event has occurred better than usually
expected.
◦ Most likely time: An estimate of time based on whether the time manager
thinks that it is necessary to complete the task.
◦ Pessimistic time: An estimate of time based on the assumption that some
problem may occur.
6/15/2024 8
Components of PERT model
◦ Predecessor event: It is an event that precedes some other event; it can
be single or multiple.
◦ Successor events: It is an event that immediately follows some other
events; it can have multiple successor events.
◦ Expected time or the very best time(TH): The accurate or the actual
time required to complete the task, it is the most reliable and valid time
estimated . It can be calculates using the following relation
TH= (O+4M + P)/6
6/15/2024 9
Cont…
◦ Float or slack time: it is an amount of time that can be floated without
causing delay in the total completion of the work.
◦ Critical Path: It is the longest possible & actual total time required to
complete the full task.
6/15/2024 10
Steps involved in PERT
◦ Identify the specific activities and milestones
◦ Determine the proper sequence of the activities
◦ Construct a network diagram
◦ Estimate the time required for each activity
◦ Determine the critical path
◦ Update the PERT chart as the project progresses.
6/15/2024 11
Identify the specific activities and milestones
◦ The activities are the tasks required to complete a project. The milestones
are the events making the beginning and the end of one or more activities.
◦ It is helpful to list the tasks in a table that in later steps can be expanded to
include information on sequence.
6/15/2024 12
Determine the proper sequence of the activities:
◦ this step may be combined with the activity identification step since the
activity sequence is evident for some tasks.
◦ Other tasks may required more analysis to determine the exact order in
which they must be performed.
6/15/2024 13
Construct a network diagram
◦ Using the activity sequence information, a network diagram can be drawn
showing the sequence of the serial and parallel activities.
◦ Each activity represents a node in the network, and the arrow represents
the relation between activities.
6/15/2024 14
Determine the critical path
◦ the critical path is determined by adding the times for the activities in each
sequence & determining the longest path in the project.
Update the PERT chart as the project progresses:
◦ make adjustments in the PERT chart as the project progresses. As the
project unfolds, the estimated times can be replaced with actual times.
6/15/2024 15
PERT FLOW CHART
6/15/2024 16
Cont…
◦ The circle indicates the starting and finishing time of the task.
◦ Each ARROW represents the task- time consuming elements.
◦ Alphabets indicate different TASK and time required to carry out the
activity by NUMBERS.
6/15/2024 17
Advantages
◦ It is simple, comprehensive and the most accessible tool for organizational
planning and management development, acquisition and installation of a
system.
◦ It is an essential means to improve communication and coordination
among different management levels.
◦ It is a helpful technique to identify various issues and problems during the
process.
6/15/2024 18
Cont…
◦ It provides grounds for monitoring the continuous and timely progress of
the project.
◦ It provides a base for evaluation and control system.
6/15/2024 19
Limitation
◦ Uncertainty is attached to the time estimate
◦ Amount of resources available is a significant restriction.
◦ All activities may not be progressing on schedule.
◦ Lack of trained staff to adopt PERT technique.
6/15/2024 20
Q) For small Nursing group project, find expected time &
Draw network?
Activity Optimistic
Time(0)
Most likely
time (M)
Pessimistic
time (P)
Expected
Time
1-2 6 9 18
2-3 3 7 17
2-4 4 10 16
2-5 2 6 16
3-5 5 10 21
4-5 6 11 22
5-6 4 7 16
6/15/2024 21
Solution:
6/15/2024 22
Activity Optimistic
Time(0)
Most likely
time (M)
Pessimistic
time (P)
Expected
Time
1-2 6 9 18 10
2-3 3 7 17 08
2-4 4 10 16 10
2-5 2 6 16 07
3-5 5 10 21 11
4-5 6 11 22 12
5-6 4 7 16 08
GANTT CHART
6/15/2024 23
Gantt chart
◦ An activity plan (Gantt chart) is a traditional method of planning that
depicts the sequence of tasks to be completed within the set time frame.
◦ It is a simple graphical representation of various activities performed in
the stipulated time framework or against the progression of time in the
form of a bar diagram.
6/15/2024 24
Cont…
◦ It was developed by Henry Gantt, a mechanical engineer, in 1910.
◦ It shows time relationships between the "events" of a program; these
events are goal oriented.
◦ The Gantt chart is a tool to assess the progress of the program. It shows
the relationship between tasks and time duration in the bar diagram to
accomplish a plan
6/15/2024 25
Definition
◦ A Gantt chart is a type of bar chart that illustrates a project schedule. This
chart lists the tasks to be performed on the vertical axis, and the time
intervals on the horizontal axis. The width of the horizontal bars in the
graphs shows the duration of each activity.
6/15/2024 26
HISTORICAL DEVELOPMENT
◦ 1896: Karol Adamiecki creates the first project management chart: the
Harmonogram, a precursor to the modern Gantt chart.
◦ 1931: Adamiecki publishes the Harmonogram.
◦ 1910-1915: Henry Gantt publishes his own project management system,
the gantt chart.
6/15/2024 27
Purposes
◦ To plan and provide a visual graphical illustration of schedule
tasks/activities.
◦ To track specific critical activity to observe carefully.
◦ To monitor and control program activities.
◦ For logistics of a project or program.
6/15/2024 28
Features of Gantt chart
◦ It gives a graphical illustration of a schedule.
◦ It is a time-oriented activity plan depicted in the graphical chart.
◦ It visualizes all activities of the project and total time of the project.
◦ It represents each event in a bar. Each bar represents the time duration of
that activity.
6/15/2024 29
Cont…
◦ Length of the bar also depicts its starting time and ending time. Each event
in a bar corresponds to other activity.
6/15/2024 30
PROCESS
Identify the
Purpose
Define the
Project
Timeline
Break the
Project Down
into
Manageable
Pieces
Create
Progress
Bars
Add
Milestone
Markers
6/15/2024 31
◦ Identify the Purpose: It is helpful to first decide whether this is a project
or a process, because diagramming a process might work better with a
flow chart.
◦ Define the Project Timeline: Decide how to divide the increments of
time for the duration of the project. Each one should have a start date, end
date.
6/15/2024 32
Break the Project Down into Manageable Pieces:
◦ Divide the project into major components, then tasks and subtasks.
Continue breaking them down until they are each straight forward tasks.
◦ They should be of short enough duration that timeframes can be
accurately estimated.
6/15/2024 33
Create Progress Bars:
◦ The next step is to create a progress bar for each task.
◦ A progress bar is simply a horizontal bar that should be in line with the
task name it represents and should begin beneath its start date and end
beneath its end date.
6/15/2024 34
◦ Add Milestone Markers: Choose a symbol to represent milestones, that
is, major events that either have a large part in the process or must be
completed before progress can continue. Place them on the chart beneath
the date or time when they occur.
6/15/2024 35
Construction of Gantt chart
6/15/2024 36
◦ A horizontal line (X-axis) is the time scale over which to complete a
program. The length of each task/event bar corresponds to the duration of
the task/event. Specify period in days, weeks or months, years, etc.
◦ A vertical axis/line depicts different activities of the project, e.g. A, B, C,
D. List the tasks sequentially/ chronologically. The event/taskbar depicts
the starting time and finishing time of that event/task.
6/15/2024 37
6/15/2024 38
6/15/2024 39
Uses of Gantt chart
To represent time and type of task of the project
To plan and schedule projects
To depict a sequence of the functions
To monitor the functioning of the project
To take immediate remedial action if delays.
6/15/2024 40
Advantages
◦ It is simple and easy to use.
◦ It represents activities on a scale.
◦ It expresses time of each event explicitly.
◦ It is easy to understand the starting and completion time of each
operation.
◦ It makes easy to calculate the total time of the program.
6/15/2024 41
Disadvantages
They can become extraordinarily complex.
The size of the bar does not indicate the amount of work
Difficult to see on one sheet of paper.
They need to be constantly updated.
6/15/2024 42
Difference between PERT chart and GANTT chart
6/15/2024 43
PERT CHART GANTT CHART
First developed and introduced by US Navy in
1950
First developed and introduced by Henry Gantt
in 1917
Each task associated with the project is
represented as flowchart in boxes or Network
diagrams
Each activity of the project is represented as a
bar in the Bar charts
Each box represents each task. Each task shows
the task duration. Arrows are used to represent
interdependencies of each task.
The position, length of the bar is a
representation of start, end and duration of the
activity.
Used for large and complex projects Employed for small projects
PERT chart focuses on the dependency of
relationship
GANTT chart focuses on the time required to
complete a task.
6/15/2024 44
Practice Exercise
Create a Gantt chart using the chart below:
Activity Predecessor Duration (days)
A - 2
B A 3
C B 4
D C 3
6/15/2024 45
Conclusion:
◦ PERT has been widely used in all types of management to carry out the
work efficiently. Both PERT and GANTT diagrams can simplify working
with projects, increase productivity, and make the workflow more
transparent for everyone. GANTT charts are used in nursing field to
represent mortality and morbidity rates and also indicates duty roaster.
6/15/2024 46
Application of Research
◦ The use of “Program Evaluation and Review Technique” (PERT) in the
design and control of a medical research project
Authors: Woolf C.R, Cass W., Mc Elroy, J.
◦ Abstract: Program Evaluation and Review Technique (PERT) was
developed in 1958 by the United States Navy in order to control a large
research and development project. This technique has now been applied
to a medical research project, “The Surgical Treatment of Emphysema, the
Selection of Patients and the Evaluation of Results” at the Toronto General
Hospital.
6/15/2024 47
Cont…
◦ In order to use PERT, the project is broken down into the individual tasks
that must be performed. A network is drawn showing the sequence of
activities from start to final completion, thus defining the work to be done.
◦ As each activity is completed, an IBM card is sent to the project director
who compares the actual completion date with the date on the schedule
report. In this way it is possible to determine whether the project is on
time, behind or ahead of schedule.
6/15/2024 48
Cont…
◦ Conclusion: The PERT technique has significantly helped to organize the
project and maintain progress toward its conclusion. It is suggested that
this technique can be used successfully in complex medical research work
6/15/2024 49
References:
◦ Vati J. “Principles and Practice of Nursing Management and Administration” Jaypee Brothers
Publications Ltd. Haryana 2013; 164-168
◦ Clement. I “ Management of Nursing Services and Education” Jaypee brothers Publications. Ltd.
New delhi; 107-108
◦ Roussel .L “ Management and leadership for Nurse Administrators” Jones & Bartlet Publications.
Ltd. 5 th Edition Haryana. 2017; 256-258
◦ Woolf CR, Cass W, McElroy J. The use of "Program Evaluation and Review Technique" (PERT) in the
design and control of a medical research project. Comput Biomed Res.2015 Oct;2(2):176-86. doi:
10.1016/0010-4809(68)90036-0.
◦ Dawson MR. A case study in Gantt charts as historiophoty: A century of psychology at the
University of Alberta. Hist Psychol. 2013 May;16(2):145-57. doi: 10.1037/a0031079.
6/15/2024 50
6/15/2024 51

More Related Content

Similar to PERT & GANTT Chart.pptx

Project Time Management
Project Time ManagementProject Time Management
Project Time Management
dyaksa hanindito
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
BetshaTizazu2
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
Dr. Divya Khandelwal
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
Anupama holla
 
Network Analysis- CPM ppt..pptx
Network Analysis- CPM  ppt..pptxNetwork Analysis- CPM  ppt..pptx
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
ahsanrabbani
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
TecnicoItca
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
Zara Bizan, P.E., MIEM
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javed
Waqar Ahmed
 
GANTT CHARTS.pptx
GANTT CHARTS.pptxGANTT CHARTS.pptx
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
S.Vijaya Bhaskar
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
AMIT PAYAL
 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.ppt
ssusere57332
 
Lecture -19 & 20.ppt.pdf
Lecture -19 & 20.ppt.pdfLecture -19 & 20.ppt.pdf
Lecture -19 & 20.ppt.pdf
narmeen11
 
S curves
S curvesS curves
S curves
Sagar Rana
 
Programme evaluation review technique
Programme evaluation review techniqueProgramme evaluation review technique
Programme evaluation review technique
saheli chakraborty
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
Yousef Abugosh, PMP, MA
 
Gantt chart
Gantt chartGantt chart
Gantt chart
Tanoj Patidar
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
TinotendaChivese
 
Nce603 mod unit2
Nce603 mod unit2Nce603 mod unit2
Nce603 mod unit2
MODASSAR ANSARI
 

Similar to PERT & GANTT Chart.pptx (20)

Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Network Analysis- CPM ppt..pptx
Network Analysis- CPM  ppt..pptxNetwork Analysis- CPM  ppt..pptx
Network Analysis- CPM ppt..pptx
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javed
 
GANTT CHARTS.pptx
GANTT CHARTS.pptxGANTT CHARTS.pptx
GANTT CHARTS.pptx
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.ppt
 
Lecture -19 & 20.ppt.pdf
Lecture -19 & 20.ppt.pdfLecture -19 & 20.ppt.pdf
Lecture -19 & 20.ppt.pdf
 
S curves
S curvesS curves
S curves
 
Programme evaluation review technique
Programme evaluation review techniqueProgramme evaluation review technique
Programme evaluation review technique
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
 
Gantt chart
Gantt chartGantt chart
Gantt chart
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
Nce603 mod unit2
Nce603 mod unit2Nce603 mod unit2
Nce603 mod unit2
 

More from Jyoti Chand

Martha Rogers Theory.pptx
Martha Rogers Theory.pptxMartha Rogers Theory.pptx
Martha Rogers Theory.pptx
Jyoti Chand
 
Application of computer in nursing.pptsx
Application of computer in nursing.pptsxApplication of computer in nursing.pptsx
Application of computer in nursing.pptsx
Jyoti Chand
 
Health belief model.pptx
Health belief model.pptxHealth belief model.pptx
Health belief model.pptx
Jyoti Chand
 
Budgeting.pptx
Budgeting.pptxBudgeting.pptx
Budgeting.pptx
Jyoti Chand
 
Historical development of community health.pptx
Historical development of community health.pptxHistorical development of community health.pptx
Historical development of community health.pptx
Jyoti Chand
 
Community resources for elderly.pptx
Community resources for elderly.pptxCommunity resources for elderly.pptx
Community resources for elderly.pptx
Jyoti Chand
 
Mid Term Appraisal & Types of Budget.pptx
Mid Term Appraisal &  Types of Budget.pptxMid Term Appraisal &  Types of Budget.pptx
Mid Term Appraisal & Types of Budget.pptx
Jyoti Chand
 
Family Planning.pptx
Family Planning.pptxFamily Planning.pptx
Family Planning.pptx
Jyoti Chand
 
Health Promotion and Levels of Prevention.pptx
Health Promotion and Levels of Prevention.pptxHealth Promotion and Levels of Prevention.pptx
Health Promotion and Levels of Prevention.pptx
Jyoti Chand
 
Measurement of health and disease.pptx..
Measurement of health and disease.pptx..Measurement of health and disease.pptx..
Measurement of health and disease.pptx..
Jyoti Chand
 
National Rural Health Mission(NRHM).pptx
National Rural Health Mission(NRHM).pptxNational Rural Health Mission(NRHM).pptx
National Rural Health Mission(NRHM).pptx
Jyoti Chand
 
Wound healing PPT
Wound healing PPTWound healing PPT
Wound healing PPT
Jyoti Chand
 

More from Jyoti Chand (12)

Martha Rogers Theory.pptx
Martha Rogers Theory.pptxMartha Rogers Theory.pptx
Martha Rogers Theory.pptx
 
Application of computer in nursing.pptsx
Application of computer in nursing.pptsxApplication of computer in nursing.pptsx
Application of computer in nursing.pptsx
 
Health belief model.pptx
Health belief model.pptxHealth belief model.pptx
Health belief model.pptx
 
Budgeting.pptx
Budgeting.pptxBudgeting.pptx
Budgeting.pptx
 
Historical development of community health.pptx
Historical development of community health.pptxHistorical development of community health.pptx
Historical development of community health.pptx
 
Community resources for elderly.pptx
Community resources for elderly.pptxCommunity resources for elderly.pptx
Community resources for elderly.pptx
 
Mid Term Appraisal & Types of Budget.pptx
Mid Term Appraisal &  Types of Budget.pptxMid Term Appraisal &  Types of Budget.pptx
Mid Term Appraisal & Types of Budget.pptx
 
Family Planning.pptx
Family Planning.pptxFamily Planning.pptx
Family Planning.pptx
 
Health Promotion and Levels of Prevention.pptx
Health Promotion and Levels of Prevention.pptxHealth Promotion and Levels of Prevention.pptx
Health Promotion and Levels of Prevention.pptx
 
Measurement of health and disease.pptx..
Measurement of health and disease.pptx..Measurement of health and disease.pptx..
Measurement of health and disease.pptx..
 
National Rural Health Mission(NRHM).pptx
National Rural Health Mission(NRHM).pptxNational Rural Health Mission(NRHM).pptx
National Rural Health Mission(NRHM).pptx
 
Wound healing PPT
Wound healing PPTWound healing PPT
Wound healing PPT
 

Recently uploaded

Diversity Quiz Prelims by Quiz Club, IIT Kanpur
Diversity Quiz Prelims by Quiz Club, IIT KanpurDiversity Quiz Prelims by Quiz Club, IIT Kanpur
Diversity Quiz Prelims by Quiz Club, IIT Kanpur
Quiz Club IIT Kanpur
 
Science-9-Lesson-1-The Bohr Model-NLC.pptx pptx
Science-9-Lesson-1-The Bohr Model-NLC.pptx pptxScience-9-Lesson-1-The Bohr Model-NLC.pptx pptx
Science-9-Lesson-1-The Bohr Model-NLC.pptx pptx
Catherine Dela Cruz
 
Keynote given on June 24 for MASSP at Grand Traverse City
Keynote given on June 24 for MASSP at Grand Traverse CityKeynote given on June 24 for MASSP at Grand Traverse City
Keynote given on June 24 for MASSP at Grand Traverse City
PJ Caposey
 
Diversity Quiz Finals by Quiz Club, IIT Kanpur
Diversity Quiz Finals by Quiz Club, IIT KanpurDiversity Quiz Finals by Quiz Club, IIT Kanpur
Diversity Quiz Finals by Quiz Club, IIT Kanpur
Quiz Club IIT Kanpur
 
Information and Communication Technology in Education
Information and Communication Technology in EducationInformation and Communication Technology in Education
Information and Communication Technology in Education
MJDuyan
 
220711130088 Sumi Basak Virtual University EPC 3.pptx
220711130088 Sumi Basak Virtual University EPC 3.pptx220711130088 Sumi Basak Virtual University EPC 3.pptx
220711130088 Sumi Basak Virtual University EPC 3.pptx
Kalna College
 
A Quiz on Drug Abuse Awareness by Quizzito
A Quiz on Drug Abuse Awareness by QuizzitoA Quiz on Drug Abuse Awareness by Quizzito
A Quiz on Drug Abuse Awareness by Quizzito
Quizzito The Quiz Society of Gargi College
 
8+8+8 Rule Of Time Management For Better Productivity
8+8+8 Rule Of Time Management For Better Productivity8+8+8 Rule Of Time Management For Better Productivity
8+8+8 Rule Of Time Management For Better Productivity
RuchiRathor2
 
What are the new features in the Fleet Odoo 17
What are the new features in the Fleet Odoo 17What are the new features in the Fleet Odoo 17
What are the new features in the Fleet Odoo 17
Celine George
 
INTRODUCTION TO HOSPITALS & AND ITS ORGANIZATION
INTRODUCTION TO HOSPITALS & AND ITS ORGANIZATION INTRODUCTION TO HOSPITALS & AND ITS ORGANIZATION
INTRODUCTION TO HOSPITALS & AND ITS ORGANIZATION
ShwetaGawande8
 
The Science of Learning: implications for modern teaching
The Science of Learning: implications for modern teachingThe Science of Learning: implications for modern teaching
The Science of Learning: implications for modern teaching
Derek Wenmoth
 
Contiguity Of Various Message Forms - Rupam Chandra.pptx
Contiguity Of Various Message Forms - Rupam Chandra.pptxContiguity Of Various Message Forms - Rupam Chandra.pptx
Contiguity Of Various Message Forms - Rupam Chandra.pptx
Kalna College
 
Decolonizing Universal Design for Learning
Decolonizing Universal Design for LearningDecolonizing Universal Design for Learning
Decolonizing Universal Design for Learning
Frederic Fovet
 
Opportunity scholarships and the schools that receive them
Opportunity scholarships and the schools that receive themOpportunity scholarships and the schools that receive them
Opportunity scholarships and the schools that receive them
EducationNC
 
IoT (Internet of Things) introduction Notes.pdf
IoT (Internet of Things) introduction Notes.pdfIoT (Internet of Things) introduction Notes.pdf
IoT (Internet of Things) introduction Notes.pdf
roshanranjit222
 
Ethiopia and Eritrea Eritrea's journey has been marked by resilience and dete...
Ethiopia and Eritrea Eritrea's journey has been marked by resilience and dete...Ethiopia and Eritrea Eritrea's journey has been marked by resilience and dete...
Ethiopia and Eritrea Eritrea's journey has been marked by resilience and dete...
biruktesfaye27
 
Non-Verbal Communication for Tech Professionals
Non-Verbal Communication for Tech ProfessionalsNon-Verbal Communication for Tech Professionals
Non-Verbal Communication for Tech Professionals
MattVassar1
 
The basics of sentences session 8pptx.pptx
The basics of sentences session 8pptx.pptxThe basics of sentences session 8pptx.pptx
The basics of sentences session 8pptx.pptx
heathfieldcps1
 
78 Microsoft-Publisher - Sirin Sultana Bora.pptx
78 Microsoft-Publisher - Sirin Sultana Bora.pptx78 Microsoft-Publisher - Sirin Sultana Bora.pptx
78 Microsoft-Publisher - Sirin Sultana Bora.pptx
Kalna College
 
Accounting for Restricted Grants When and How To Record Properly
Accounting for Restricted Grants  When and How To Record ProperlyAccounting for Restricted Grants  When and How To Record Properly
Accounting for Restricted Grants When and How To Record Properly
TechSoup
 

Recently uploaded (20)

Diversity Quiz Prelims by Quiz Club, IIT Kanpur
Diversity Quiz Prelims by Quiz Club, IIT KanpurDiversity Quiz Prelims by Quiz Club, IIT Kanpur
Diversity Quiz Prelims by Quiz Club, IIT Kanpur
 
Science-9-Lesson-1-The Bohr Model-NLC.pptx pptx
Science-9-Lesson-1-The Bohr Model-NLC.pptx pptxScience-9-Lesson-1-The Bohr Model-NLC.pptx pptx
Science-9-Lesson-1-The Bohr Model-NLC.pptx pptx
 
Keynote given on June 24 for MASSP at Grand Traverse City
Keynote given on June 24 for MASSP at Grand Traverse CityKeynote given on June 24 for MASSP at Grand Traverse City
Keynote given on June 24 for MASSP at Grand Traverse City
 
Diversity Quiz Finals by Quiz Club, IIT Kanpur
Diversity Quiz Finals by Quiz Club, IIT KanpurDiversity Quiz Finals by Quiz Club, IIT Kanpur
Diversity Quiz Finals by Quiz Club, IIT Kanpur
 
Information and Communication Technology in Education
Information and Communication Technology in EducationInformation and Communication Technology in Education
Information and Communication Technology in Education
 
220711130088 Sumi Basak Virtual University EPC 3.pptx
220711130088 Sumi Basak Virtual University EPC 3.pptx220711130088 Sumi Basak Virtual University EPC 3.pptx
220711130088 Sumi Basak Virtual University EPC 3.pptx
 
A Quiz on Drug Abuse Awareness by Quizzito
A Quiz on Drug Abuse Awareness by QuizzitoA Quiz on Drug Abuse Awareness by Quizzito
A Quiz on Drug Abuse Awareness by Quizzito
 
8+8+8 Rule Of Time Management For Better Productivity
8+8+8 Rule Of Time Management For Better Productivity8+8+8 Rule Of Time Management For Better Productivity
8+8+8 Rule Of Time Management For Better Productivity
 
What are the new features in the Fleet Odoo 17
What are the new features in the Fleet Odoo 17What are the new features in the Fleet Odoo 17
What are the new features in the Fleet Odoo 17
 
INTRODUCTION TO HOSPITALS & AND ITS ORGANIZATION
INTRODUCTION TO HOSPITALS & AND ITS ORGANIZATION INTRODUCTION TO HOSPITALS & AND ITS ORGANIZATION
INTRODUCTION TO HOSPITALS & AND ITS ORGANIZATION
 
The Science of Learning: implications for modern teaching
The Science of Learning: implications for modern teachingThe Science of Learning: implications for modern teaching
The Science of Learning: implications for modern teaching
 
Contiguity Of Various Message Forms - Rupam Chandra.pptx
Contiguity Of Various Message Forms - Rupam Chandra.pptxContiguity Of Various Message Forms - Rupam Chandra.pptx
Contiguity Of Various Message Forms - Rupam Chandra.pptx
 
Decolonizing Universal Design for Learning
Decolonizing Universal Design for LearningDecolonizing Universal Design for Learning
Decolonizing Universal Design for Learning
 
Opportunity scholarships and the schools that receive them
Opportunity scholarships and the schools that receive themOpportunity scholarships and the schools that receive them
Opportunity scholarships and the schools that receive them
 
IoT (Internet of Things) introduction Notes.pdf
IoT (Internet of Things) introduction Notes.pdfIoT (Internet of Things) introduction Notes.pdf
IoT (Internet of Things) introduction Notes.pdf
 
Ethiopia and Eritrea Eritrea's journey has been marked by resilience and dete...
Ethiopia and Eritrea Eritrea's journey has been marked by resilience and dete...Ethiopia and Eritrea Eritrea's journey has been marked by resilience and dete...
Ethiopia and Eritrea Eritrea's journey has been marked by resilience and dete...
 
Non-Verbal Communication for Tech Professionals
Non-Verbal Communication for Tech ProfessionalsNon-Verbal Communication for Tech Professionals
Non-Verbal Communication for Tech Professionals
 
The basics of sentences session 8pptx.pptx
The basics of sentences session 8pptx.pptxThe basics of sentences session 8pptx.pptx
The basics of sentences session 8pptx.pptx
 
78 Microsoft-Publisher - Sirin Sultana Bora.pptx
78 Microsoft-Publisher - Sirin Sultana Bora.pptx78 Microsoft-Publisher - Sirin Sultana Bora.pptx
78 Microsoft-Publisher - Sirin Sultana Bora.pptx
 
Accounting for Restricted Grants When and How To Record Properly
Accounting for Restricted Grants  When and How To Record ProperlyAccounting for Restricted Grants  When and How To Record Properly
Accounting for Restricted Grants When and How To Record Properly
 

PERT & GANTT Chart.pptx

  • 1. 6/15/2024 1 PROGRAM EVALUATION REVIEW TECHNIQUE(PERT) and GANTT CHART Ms. Jyoti Chand MSc Nursing
  • 2. Objectives ◦ to introduce programme evaluation review technique ◦ to describe purposes of PERT ◦ to enlist features of PERT ◦ to explain components of PERT ◦ to explain steps involved in PERT ◦ to enumerate advantages of PERT ◦ to elaborate limitations 6/15/2024 2
  • 3. Introduction ◦ PERT is a method of analyzing the task involved in a given project, especially the time needed to complete each task, and to identify the minimum time needed to complete the project. ◦ In 1958, the project evaluation review technique was developed by Booz Allen Hamilton, the US Navy to manage the Polaris submarine missile program of their special projects office. 6/15/2024 3
  • 4. Definition ◦ PERT is a work devised to complete the project work in time. It analyses the actual work time required to complete a task. 6/15/2024 4
  • 5. Purposes of PERT ◦ To minimize time and cost for completing a program. ◦ To minimize idle resources. ◦ To improve communication and coordination among different management levels. ◦ To identify issues and obstacles. ◦ To monitor the work progress. ◦ To complete the project so as to minimize time. 6/15/2024 5
  • 6. Features of PERT ◦ PERT is a task- oriented technique. ◦ It may contain hundreds or thousands of events. ◦ It identifies events. ◦ It identifies critical activities. ◦ It specifies the time required to complete each identified event/task/activity. ◦ It calculate the minimum time for project completion. ◦ It allows uncertainty in the duration of tasks. 6/15/2024 6
  • 7. 6/15/2024 7 3 Parameters 1. Optimistic time 2. Most likely time 3. Pessimistic time
  • 8. Cont… ◦ Optimistic time: It is the minimum possible time required to complete the task anticipating that every event has occurred better than usually expected. ◦ Most likely time: An estimate of time based on whether the time manager thinks that it is necessary to complete the task. ◦ Pessimistic time: An estimate of time based on the assumption that some problem may occur. 6/15/2024 8
  • 9. Components of PERT model ◦ Predecessor event: It is an event that precedes some other event; it can be single or multiple. ◦ Successor events: It is an event that immediately follows some other events; it can have multiple successor events. ◦ Expected time or the very best time(TH): The accurate or the actual time required to complete the task, it is the most reliable and valid time estimated . It can be calculates using the following relation TH= (O+4M + P)/6 6/15/2024 9
  • 10. Cont… ◦ Float or slack time: it is an amount of time that can be floated without causing delay in the total completion of the work. ◦ Critical Path: It is the longest possible & actual total time required to complete the full task. 6/15/2024 10
  • 11. Steps involved in PERT ◦ Identify the specific activities and milestones ◦ Determine the proper sequence of the activities ◦ Construct a network diagram ◦ Estimate the time required for each activity ◦ Determine the critical path ◦ Update the PERT chart as the project progresses. 6/15/2024 11
  • 12. Identify the specific activities and milestones ◦ The activities are the tasks required to complete a project. The milestones are the events making the beginning and the end of one or more activities. ◦ It is helpful to list the tasks in a table that in later steps can be expanded to include information on sequence. 6/15/2024 12
  • 13. Determine the proper sequence of the activities: ◦ this step may be combined with the activity identification step since the activity sequence is evident for some tasks. ◦ Other tasks may required more analysis to determine the exact order in which they must be performed. 6/15/2024 13
  • 14. Construct a network diagram ◦ Using the activity sequence information, a network diagram can be drawn showing the sequence of the serial and parallel activities. ◦ Each activity represents a node in the network, and the arrow represents the relation between activities. 6/15/2024 14
  • 15. Determine the critical path ◦ the critical path is determined by adding the times for the activities in each sequence & determining the longest path in the project. Update the PERT chart as the project progresses: ◦ make adjustments in the PERT chart as the project progresses. As the project unfolds, the estimated times can be replaced with actual times. 6/15/2024 15
  • 17. Cont… ◦ The circle indicates the starting and finishing time of the task. ◦ Each ARROW represents the task- time consuming elements. ◦ Alphabets indicate different TASK and time required to carry out the activity by NUMBERS. 6/15/2024 17
  • 18. Advantages ◦ It is simple, comprehensive and the most accessible tool for organizational planning and management development, acquisition and installation of a system. ◦ It is an essential means to improve communication and coordination among different management levels. ◦ It is a helpful technique to identify various issues and problems during the process. 6/15/2024 18
  • 19. Cont… ◦ It provides grounds for monitoring the continuous and timely progress of the project. ◦ It provides a base for evaluation and control system. 6/15/2024 19
  • 20. Limitation ◦ Uncertainty is attached to the time estimate ◦ Amount of resources available is a significant restriction. ◦ All activities may not be progressing on schedule. ◦ Lack of trained staff to adopt PERT technique. 6/15/2024 20
  • 21. Q) For small Nursing group project, find expected time & Draw network? Activity Optimistic Time(0) Most likely time (M) Pessimistic time (P) Expected Time 1-2 6 9 18 2-3 3 7 17 2-4 4 10 16 2-5 2 6 16 3-5 5 10 21 4-5 6 11 22 5-6 4 7 16 6/15/2024 21
  • 22. Solution: 6/15/2024 22 Activity Optimistic Time(0) Most likely time (M) Pessimistic time (P) Expected Time 1-2 6 9 18 10 2-3 3 7 17 08 2-4 4 10 16 10 2-5 2 6 16 07 3-5 5 10 21 11 4-5 6 11 22 12 5-6 4 7 16 08
  • 24. Gantt chart ◦ An activity plan (Gantt chart) is a traditional method of planning that depicts the sequence of tasks to be completed within the set time frame. ◦ It is a simple graphical representation of various activities performed in the stipulated time framework or against the progression of time in the form of a bar diagram. 6/15/2024 24
  • 25. Cont… ◦ It was developed by Henry Gantt, a mechanical engineer, in 1910. ◦ It shows time relationships between the "events" of a program; these events are goal oriented. ◦ The Gantt chart is a tool to assess the progress of the program. It shows the relationship between tasks and time duration in the bar diagram to accomplish a plan 6/15/2024 25
  • 26. Definition ◦ A Gantt chart is a type of bar chart that illustrates a project schedule. This chart lists the tasks to be performed on the vertical axis, and the time intervals on the horizontal axis. The width of the horizontal bars in the graphs shows the duration of each activity. 6/15/2024 26
  • 27. HISTORICAL DEVELOPMENT ◦ 1896: Karol Adamiecki creates the first project management chart: the Harmonogram, a precursor to the modern Gantt chart. ◦ 1931: Adamiecki publishes the Harmonogram. ◦ 1910-1915: Henry Gantt publishes his own project management system, the gantt chart. 6/15/2024 27
  • 28. Purposes ◦ To plan and provide a visual graphical illustration of schedule tasks/activities. ◦ To track specific critical activity to observe carefully. ◦ To monitor and control program activities. ◦ For logistics of a project or program. 6/15/2024 28
  • 29. Features of Gantt chart ◦ It gives a graphical illustration of a schedule. ◦ It is a time-oriented activity plan depicted in the graphical chart. ◦ It visualizes all activities of the project and total time of the project. ◦ It represents each event in a bar. Each bar represents the time duration of that activity. 6/15/2024 29
  • 30. Cont… ◦ Length of the bar also depicts its starting time and ending time. Each event in a bar corresponds to other activity. 6/15/2024 30
  • 31. PROCESS Identify the Purpose Define the Project Timeline Break the Project Down into Manageable Pieces Create Progress Bars Add Milestone Markers 6/15/2024 31
  • 32. ◦ Identify the Purpose: It is helpful to first decide whether this is a project or a process, because diagramming a process might work better with a flow chart. ◦ Define the Project Timeline: Decide how to divide the increments of time for the duration of the project. Each one should have a start date, end date. 6/15/2024 32
  • 33. Break the Project Down into Manageable Pieces: ◦ Divide the project into major components, then tasks and subtasks. Continue breaking them down until they are each straight forward tasks. ◦ They should be of short enough duration that timeframes can be accurately estimated. 6/15/2024 33
  • 34. Create Progress Bars: ◦ The next step is to create a progress bar for each task. ◦ A progress bar is simply a horizontal bar that should be in line with the task name it represents and should begin beneath its start date and end beneath its end date. 6/15/2024 34
  • 35. ◦ Add Milestone Markers: Choose a symbol to represent milestones, that is, major events that either have a large part in the process or must be completed before progress can continue. Place them on the chart beneath the date or time when they occur. 6/15/2024 35
  • 36. Construction of Gantt chart 6/15/2024 36
  • 37. ◦ A horizontal line (X-axis) is the time scale over which to complete a program. The length of each task/event bar corresponds to the duration of the task/event. Specify period in days, weeks or months, years, etc. ◦ A vertical axis/line depicts different activities of the project, e.g. A, B, C, D. List the tasks sequentially/ chronologically. The event/taskbar depicts the starting time and finishing time of that event/task. 6/15/2024 37
  • 40. Uses of Gantt chart To represent time and type of task of the project To plan and schedule projects To depict a sequence of the functions To monitor the functioning of the project To take immediate remedial action if delays. 6/15/2024 40
  • 41. Advantages ◦ It is simple and easy to use. ◦ It represents activities on a scale. ◦ It expresses time of each event explicitly. ◦ It is easy to understand the starting and completion time of each operation. ◦ It makes easy to calculate the total time of the program. 6/15/2024 41
  • 42. Disadvantages They can become extraordinarily complex. The size of the bar does not indicate the amount of work Difficult to see on one sheet of paper. They need to be constantly updated. 6/15/2024 42
  • 43. Difference between PERT chart and GANTT chart 6/15/2024 43
  • 44. PERT CHART GANTT CHART First developed and introduced by US Navy in 1950 First developed and introduced by Henry Gantt in 1917 Each task associated with the project is represented as flowchart in boxes or Network diagrams Each activity of the project is represented as a bar in the Bar charts Each box represents each task. Each task shows the task duration. Arrows are used to represent interdependencies of each task. The position, length of the bar is a representation of start, end and duration of the activity. Used for large and complex projects Employed for small projects PERT chart focuses on the dependency of relationship GANTT chart focuses on the time required to complete a task. 6/15/2024 44
  • 45. Practice Exercise Create a Gantt chart using the chart below: Activity Predecessor Duration (days) A - 2 B A 3 C B 4 D C 3 6/15/2024 45
  • 46. Conclusion: ◦ PERT has been widely used in all types of management to carry out the work efficiently. Both PERT and GANTT diagrams can simplify working with projects, increase productivity, and make the workflow more transparent for everyone. GANTT charts are used in nursing field to represent mortality and morbidity rates and also indicates duty roaster. 6/15/2024 46
  • 47. Application of Research ◦ The use of “Program Evaluation and Review Technique” (PERT) in the design and control of a medical research project Authors: Woolf C.R, Cass W., Mc Elroy, J. ◦ Abstract: Program Evaluation and Review Technique (PERT) was developed in 1958 by the United States Navy in order to control a large research and development project. This technique has now been applied to a medical research project, “The Surgical Treatment of Emphysema, the Selection of Patients and the Evaluation of Results” at the Toronto General Hospital. 6/15/2024 47
  • 48. Cont… ◦ In order to use PERT, the project is broken down into the individual tasks that must be performed. A network is drawn showing the sequence of activities from start to final completion, thus defining the work to be done. ◦ As each activity is completed, an IBM card is sent to the project director who compares the actual completion date with the date on the schedule report. In this way it is possible to determine whether the project is on time, behind or ahead of schedule. 6/15/2024 48
  • 49. Cont… ◦ Conclusion: The PERT technique has significantly helped to organize the project and maintain progress toward its conclusion. It is suggested that this technique can be used successfully in complex medical research work 6/15/2024 49
  • 50. References: ◦ Vati J. “Principles and Practice of Nursing Management and Administration” Jaypee Brothers Publications Ltd. Haryana 2013; 164-168 ◦ Clement. I “ Management of Nursing Services and Education” Jaypee brothers Publications. Ltd. New delhi; 107-108 ◦ Roussel .L “ Management and leadership for Nurse Administrators” Jones & Bartlet Publications. Ltd. 5 th Edition Haryana. 2017; 256-258 ◦ Woolf CR, Cass W, McElroy J. The use of "Program Evaluation and Review Technique" (PERT) in the design and control of a medical research project. Comput Biomed Res.2015 Oct;2(2):176-86. doi: 10.1016/0010-4809(68)90036-0. ◦ Dawson MR. A case study in Gantt charts as historiophoty: A century of psychology at the University of Alberta. Hist Psychol. 2013 May;16(2):145-57. doi: 10.1037/a0031079. 6/15/2024 50
  翻译: