尊敬的 微信汇率:1円 ≈ 0.046078 元 支付宝汇率:1円 ≈ 0.046168元 [退出登录]
SlideShare a Scribd company logo
Estimation, Specifications & Contracts Earthworks Lecture .5
1
Dr. Muthanna Adil Najm Northern Technical University
Earthworks for various engineering projects
Earthworks, in general, may be encountered in any civil engineering
project.
In building and small projects, the quantities of earthworks can be
calculated easily as have been shown in previous subjects and solved examples,
whereas other kinds of projects, such as roads, canals, bridges, tunnels, dams
and others, involve a huge quantities of earthworks, the calculations of which
may be somewhat complex due to random changes or variations in the natural
ground level.
DEFINITIONS
Lead: it is the average horizontal straight practical distance through which the
excavated soil is carried from the sources to the place of spreading or
dumping. Usually the work site is divided into areas or blocks and haul
distance is calculated from the centre of each block to the destination
location. When the haul distance is too long the transport must be
calculated separately.
Lift: It is the average vertical distance (height) above which the soil has to be
lifted from the source. ‫الرفع‬ ‫مسافة‬
Quantity survey: the process of calculating the quantity of materials required to
build a project.
Mass Excavation: the requirement to excavate substantial volume of material,
usually at considerable depth or over a large area.
Structural excavation: excavation undertaken in support of structural element
construction, usually involve removing materials
from a limited area.
Estimation, Specifications & Contracts Earthworks Lecture .5
2
Dr. Muthanna Adil Najm Northern Technical University
Plan view: a construction drawing representing the horizontal alignment of the
work.
Profile view: a construction drawing depicting a vertical plane cut through the
centerline of the work . it shows the vertical relationship of the
ground surface and the finished work.
Cross section view: a construction drawing depicting a vertical section of
earthwork at right angles to the centerline of the work.
Cross sections: earthwork drawings cheated by combining the project design
with field measurements of existing conditions.
Stripping: the upper layer of organic material that must be removed before
beginning an excavation or embedment. ‫القشط‬ ‫أو‬ ‫التعرية‬
Mass diagram: It is a graph showing the accumulation of cut and fill with
distance from a starting, or origin, or reference point. Cut is
usually considered positive & fill negative. Mass diagram is
very useful for determining the quantities of earthworks,
computing hall distances and specifying the proper types of
equipment to perform the works.
(refer to attached details and examples – photo copy from Peurifoy)
.‫االنتفاخ‬ ‫نسبة‬ ‫اعتبار‬ ‫يتم‬percent swell‫في‬‫(عادة‬ ‫القطع‬ ‫مناطق‬20)%‫التقلص‬ ‫وعامل‬percent
shrinkage‫الدفن‬ ‫مناطق‬ ‫في‬‫(عادة‬10)%‫أو‬ ‫الحفريات‬ ‫حجم‬ ‫الحتساب‬‫المرصوصة‬ ‫المدفونة‬ ‫التربة‬
‫التوالي‬ ‫على‬.
)%( ‫االنتفاخ‬ ‫نسبة‬=‫بة‬‫ر‬‫الت‬ ‫حجم‬) ‫رخوة‬ ( ‫الحفر‬ ‫بعد‬–( ‫الطبيعي‬ ‫حجمها‬Bank(×100
( ‫الطبيعي‬ ‫حجمها‬B)
‫نسبة‬‫التقلص‬)%(=‫بة‬‫ر‬‫الت‬ ‫حجم‬‫الرص‬ ‫قبل‬–‫حجمها‬‫الرص‬ ‫بعد‬(compacted)×100
‫بة‬‫ر‬‫الت‬ ‫حجم‬‫الرص‬ ‫قبل‬
Estimation, Specifications & Contracts Earthworks Lecture .5
3
Dr. Muthanna Adil Najm Northern Technical University
‫في‬ ‫نقلها‬ ‫مطلوب‬ ‫اد‬‫و‬‫م‬ ‫توجد‬ ‫ال‬ ‫انه‬ ‫يعني‬ ‫فهذا‬ ،ً‫ا‬‫أفقي‬ ‫محطتين‬ ‫بين‬ ‫الكميات‬ ‫مخطط‬ ‫كان‬ ‫إذا‬
‫(أي‬ ‫نة‬‫ز‬‫ا‬‫و‬‫مت‬ ‫لكنها‬ ‫ء‬‫الجز‬ ‫هذا‬ ‫ضمن‬ ‫إمالء‬‫و‬ ‫قطع‬ ‫هناك‬ ‫ن‬‫يكو‬ ‫قد‬ ‫اقع‬‫و‬‫ال‬ ‫في‬ .‫ع‬‫المشرو‬ ‫من‬ ‫ء‬‫الجز‬ ‫هذا‬
‫من‬ ‫إمالء‬‫و‬ ‫جانب‬ ‫من‬ ‫قطع‬ ‫على‬ ‫يشتمل‬ ‫العمل‬ ‫كان‬ ‫إذا‬‫و‬ .)‫اإلمالء‬ ‫كمية‬ ‫يبا‬‫ر‬‫تق‬ ‫تساوي‬ ‫القطع‬ ‫كمية‬
‫من‬ ‫نقلها‬ ‫يمكن‬ ‫القطع‬ ‫كميات‬ ‫الن‬ ‫اء‬‫و‬‫االست‬ ‫إلى‬ ‫يميل‬ ‫أو‬ ‫ع‬‫ينز‬ ‫الكميات‬ ‫منحني‬ ‫فان‬ ،‫آخر‬ ‫جانب‬
"‫"العرضي‬ ‫النقل‬ ‫تسمى‬ ‫العملية‬ ‫وهذه‬ ،‫ى‬‫أخر‬ ‫إلى‬ ‫محطة‬ ‫من‬ ‫وليس‬ ‫آخر‬ ‫إلى‬ ‫جانب‬cross hall.
‫فالمنحنى‬ ،‫المحطات‬ ‫بين‬ ‫الحجوم‬ ‫يادة‬‫ز‬ ‫مع‬ ‫يزداد‬ ‫الكميات‬ ‫منحنى‬ ‫انحدار‬ ‫أو‬ ‫ميل‬ ‫إن‬
‫إلى‬ ‫يشير‬ ‫الصاعد‬‫إلى‬ ‫المنحنى‬ ‫يصل‬ .‫إمالئيات‬ ‫أعمال‬ ‫على‬ ‫يدل‬ ‫النازل‬ ‫المنحنى‬ ‫بينما‬ ‫قطع‬ ‫وجود‬
‫ويبدأ‬ ‫اإلمالء‬ ‫ينتهي‬ ‫حيث‬ ‫الدنيا‬ ‫المناطق‬ ‫الى‬‫و‬ ،‫اإلمالء‬ ‫ويبدأ‬ ‫القطع‬ ‫ينتهي‬ ‫حيث‬ ‫الذروة‬ ‫مناطق‬
.‫القطع‬
‫وفي‬ ،‫معينة‬ ‫نقاط‬ ‫في‬ ‫الكميات‬ ‫منحنى‬ ‫سيقطع‬ ‫فانه‬ ‫المرجع‬ ‫نقطة‬ ‫من‬ ً‫ا‬‫أفقي‬ ً‫ا‬‫خط‬ ‫رسمنا‬ ‫لو‬
‫ع‬‫مجمو‬ ‫إن‬ .‫التقاطع‬ ‫نقاط‬ ‫بين‬ )ً‫ا‬‫يب‬‫ر‬‫تق‬ ‫تتساوى‬ ‫(أي‬ ‫ن‬‫از‬‫و‬‫ستت‬ ‫اإلمالء‬‫و‬ ‫القطع‬ ‫كميات‬ ‫فان‬ ‫الحالة‬ ‫هذه‬
‫بمعدل‬ ‫يات‬‫ر‬‫للحف‬ ‫الكلية‬ ‫الكمية‬ ‫ضرب‬ ‫حاصل‬ ‫من‬ ‫حسابها‬ ‫يمكن‬ ‫الكلية‬ ‫النقل‬ ‫مسافة‬ ‫حصيلة‬ ‫أو‬
‫مساف‬‫النقل‬ ‫ة‬average haul distance‫كما‬ ‫تحديده‬ ‫فيمكن‬ ‫اإلمالء‬ ‫أو‬ ‫القطع‬ ‫كميات‬ ‫مركز‬ ‫أما‬ .
:‫يلي‬
1-‫نة‬‫ز‬‫ا‬‫و‬‫الم‬ ‫خط‬ ‫إلى‬ ‫الذروة‬ ‫نقطة‬ ‫من‬ ً‫ا‬‫عمودي‬ ً‫ا‬‫خط‬ ‫نرسم‬balancing line.
2-‫نقطتين‬ ‫في‬ ‫الكميات‬ ‫منحنى‬ ‫ويقطع‬ ‫أعاله‬ ‫المرسوم‬ ‫الخط‬ ‫بمنتصف‬ ‫يمر‬ ‫أفقيا‬ ً‫ا‬‫خط‬ ‫نرسم‬
‫النقاط‬ ‫(الحظ‬ .‫متقابلتين‬.)‫التقاطع‬ ‫نقطتي‬ ‫تقابل‬ ‫التي‬ ‫المحطات‬ ‫أو‬
Estimation, Specifications & Contracts Earthworks Lecture .5
4
Dr. Muthanna Adil Najm Northern Technical University
3-‫القطع‬ ‫كميات‬ ‫مركز‬ ‫تمثل‬ ‫المنحنى‬ ‫من‬ ‫الصاعد‬ ‫ء‬‫الجز‬ ‫في‬ ‫اقعة‬‫و‬‫ال‬ ‫المحطة‬ ‫أو‬ ‫النقطة‬ ‫إن‬
‫فتمثل‬ ‫المحطتين‬ ‫هاتين‬ ‫بين‬ ‫المسافة‬ ‫أما‬ .‫االمالئيات‬ ‫مركز‬ ‫هي‬ ‫النازل‬ ‫ء‬‫الجز‬ ‫في‬ ‫اقعة‬‫و‬‫ال‬ ‫المحطة‬‫و‬
‫ء‬‫الجز‬ ‫لهذا‬ ‫النقل‬ ‫مسافة‬haul distance.
‫إن‬‫انجاز‬ ‫معدل‬ ‫تقدير‬‫أعمال‬‫دقيقة‬ ‫ة‬‫ر‬‫بصو‬ ‫الحفر‬‫أم‬‫ر‬‫في‬ ‫تؤثر‬ ‫امل‬‫و‬‫ع‬ ‫عدة‬ ‫لوجود‬ ‫صعب‬
‫المعدل‬ ‫هذا‬،‫ويمكن‬‫ها‬‫إيجاز‬: ‫هي‬ ‫امل‬‫و‬‫الع‬ ‫من‬ ‫بمجموعتين‬-
sJob factor:‫المياه‬‫و‬ ‫الرطوبة‬ ‫مستوى‬ ،‫بة‬‫ر‬‫الت‬ ‫ع‬‫نو‬ : ‫منها‬ ‫الموقع‬‫و‬ ‫العمل‬ ‫بظروف‬ ‫تتعلق‬ ‫امل‬‫و‬‫ع‬
‫نقل‬ ‫ومسافة‬ ‫العمل‬ ‫حجم‬ ‫المعدات‬‫و‬ ‫العمال‬ ‫حركة‬ ‫ية‬‫ر‬‫ح‬ ،‫المناخية‬ ‫الظروف‬ ،‫الجوفية‬
Fill (m3
)
Cut (m3
)
Balance points
Haul distance
cut center of mass
fill center of mass
Estimation, Specifications & Contracts Earthworks Lecture .5
5
Dr. Muthanna Adil Najm Northern Technical University
‫بة‬‫ر‬‫الت‬‫وظروف‬ ‫ة‬‫ر‬‫المحفو‬‫يق‬‫ر‬‫الط‬. ‫الخ‬ ...‫إن‬‫مفروضة‬ ‫كلها‬ ‫هذه‬ ‫العمل‬ ‫ظروف‬
‫ال‬‫و‬ ‫المنفذة‬ ‫الجهة‬ ‫على‬.‫ها‬‫تغيير‬ ‫يمكنها‬
Management factors‫امل‬‫و‬‫ع‬ :‫ة‬‫ر‬‫اإلدا‬‫المعنوية‬ ‫ح‬‫الرو‬ ‫على‬ ‫الحفاظ‬‫و‬ ،‫العمل‬ ‫تنظيم‬ ‫وتتضمن‬
‫المناسبة‬ ‫ق‬‫الطر‬‫و‬ ‫العدد‬‫و‬ ‫المعدات‬ ‫استخدام‬‫و‬ ‫اختيار‬‫و‬ ‫للعمال‬ ‫العالية‬
‫العن‬ ،‫للعمل‬.‫ها‬‫وغير‬ ‫االنجاز‬ ‫معدالت‬ ‫على‬ ‫الحفاظ‬‫و‬ ‫بالمعدات‬ ‫اية‬‫كل‬
‫حسن‬ ‫على‬ ‫تعتمد‬ ‫امل‬‫و‬‫الع‬ ‫هذه‬‫ة‬‫ر‬‫إدا‬‫ة‬‫ر‬‫السيط‬ ‫ويمكن‬ ‫المنفذة‬ ‫الجهة‬
.‫عليها‬
‫مبادئ‬‫الترابية‬ ‫األعمال‬ ‫حساب‬Principles of Earthworks
Calculation
.‫ذلك‬ ‫خالف‬ ‫ذكر‬ ‫إن‬ ‫إال‬ ،‫المكعب‬ ‫بالمتر‬ ‫عادة‬ ‫ابية‬‫ر‬‫الت‬ ‫األعمال‬ ‫كميات‬ ‫تقاس‬
.‫منفصلة‬ ‫ة‬‫ر‬‫بصو‬ ‫تحسب‬ ‫أن‬ ‫يجب‬ ‫بة‬‫ر‬‫الت‬ ‫من‬ ‫مختلفة‬ ‫اع‬‫و‬‫ألن‬ ‫ابية‬‫ر‬‫الت‬ ‫األعمال‬
.‫لذلك‬ ‫مناسبة‬ ‫يقة‬‫ر‬‫ط‬ ‫وتستخدم‬ ‫بعناية‬ ‫قياسها‬ ‫بعد‬ ‫ابية‬‫ر‬‫الت‬ ‫الكميات‬ ‫تحسب‬
‫أعمال‬‫اإل‬.‫ة‬‫ر‬‫الفق‬ ‫في‬ ‫شمل‬ُ‫ت‬ ‫أن‬ ‫يجب‬ ‫التسوية‬‫و‬ ‫كساء‬
‫تحد‬ ‫يجب‬ ‫وهنا‬ ‫ابية‬‫ر‬‫الت‬ ‫الكميات‬ ‫ونقل‬ ‫فع‬‫ر‬ ‫تتضمن‬ ‫أن‬ ‫يجب‬ ‫ابية‬‫ر‬‫الت‬ ‫الكميات‬ ‫حسابات‬‫يد‬
.‫عملية‬ ‫لكل‬ ‫النقل‬ ‫مسافة‬
Estimation, Specifications & Contracts Earthworks Lecture .5
6
Dr. Muthanna Adil Najm Northern Technical University
‫الترابية‬ ‫الكميات‬ ‫حساب‬ ‫طرق‬Earth Computation Methods
‫اع‬‫ط‬‫الق‬ ‫أو‬ ‫ار‬‫ف‬‫الح‬ ‫ااطق‬‫ن‬‫م‬ ‫في‬ ‫ات‬‫و‬‫القن‬‫و‬ ‫الحديدية‬ ‫السكك‬‫و‬ ‫ات‬‫ر‬‫السيا‬ ‫ق‬‫لطر‬ ‫العرضي‬ ‫المقطع‬ ‫إن‬
cutting‫االء‬‫ا‬‫م‬‫اإل‬‫و‬filling‫اة‬‫ا‬‫ئ‬‫التعب‬‫و‬banking‫ارف‬‫ا‬‫ح‬‫من‬ ‫ابه‬‫ا‬‫ح‬ ‫اكل‬‫ا‬‫ش‬‫ب‬ ‫اادة‬‫ا‬‫ع‬ ‫ن‬‫او‬‫ا‬‫ك‬‫ي‬trapezoidal،
:‫يلي‬ ‫كما‬ ‫الشكل‬ ‫لهذا‬ ‫القطع‬ ‫مساحة‬ ‫حساب‬ ‫ويمكن‬
Area = ABCEF +AABF + AEDC
= bh + 0.5h.sh + 0.5 h.ah
Area= h [b + (ah + sh)/2] -----------------------------(1)
‫عندما‬s=a(‫أي‬:‫على‬ ‫نحصل‬ )‫للجانبين‬ ‫متساو‬ ‫االنحدار‬
Area= h (b + sh) = hb + sh2
---------------------------(2)
:‫أهمها‬‫و‬ ‫ابية‬‫ر‬‫الت‬ ‫األعمال‬ ‫كمية‬ ‫لحساب‬ ‫مستخدمة‬ ‫ق‬‫طر‬ ‫عدة‬ ‫هناك‬-
‫المساحات‬ ‫معدل‬ ‫طريقة‬Average end area method-I
‫ء‬‫الجز‬ ‫طول‬ ‫في‬ ‫ويضرب‬ ‫القطاع‬ ‫أو‬ ‫ء‬‫الجز‬ ‫في‬‫ر‬‫ط‬ ‫عند‬ ‫العرضي‬ ‫المقطع‬ ‫مساحة‬ ‫معدل‬ ‫حسب‬ُ‫ي‬
.‫الحجم‬ ‫على‬ ‫للحصول‬
‫صيغة‬‫معادلة‬ ‫أو‬‫الوسطي‬ ‫المقطع‬on FormulaMid Secti-II
A
B
F E D
C
a:1s:1
b
b ahsh
a:1s:1
h
Estimation, Specifications & Contracts Earthworks Lecture .5
7
Dr. Muthanna Adil Najm Northern Technical University
‫ت‬‫عند‬ ‫تفاع‬‫ر‬‫اال‬ ‫معدل‬ ‫عتمد‬ُ‫ي‬ ‫وهنا‬ ،‫ء‬‫الجز‬ ‫منتصف‬ ‫أو‬ ‫وسط‬ ‫عند‬ ‫المقطع‬ ‫مساحة‬ ‫حسب‬‫فين‬‫ر‬‫الط‬
.‫المساحة‬ ‫لحساب‬
‫تفاع‬‫ر‬‫اال‬ ‫معدل‬H = (h1+h2)/2
Where H: mean depth
h1,h2: depth at start & end points.
‫الموشور‬ ‫معادلة‬ormula methodPrismoidal f-III
‫ء‬‫جز‬ ‫لكل‬ ‫الحجم‬ ‫لحساب‬ ‫التالية‬ ‫الصيغة‬ ‫تستخدم‬ ‫حيث‬
V= L/6 (A1+A2+4Am)-------------------------(3)
Where A1, A2: areas at end points
Am: mid section area
L: length or distance between the adjacent stations (A1, A2)
Example: Calculate the quantity of earthworks for the 150 m long cutting,
12m wide at crest and whose side slope is 2.0:1. The centre
heights at every 30 m intervals are 0.5m 0.75m, 1.0m, 1.25m,
1.5m. Try solving by all above described methods.
Solution:
A – average area method
Quantity
m3
Length
M
Mean
area (m2
)
Area at station
bh + sh2
Depth
h(m)
Station
or
chained
12x0.5+2x0.5x0.5= 6.50.50
249.3308.3125
12x0.75+2x0.752
= 10.1250.751
Estimation, Specifications & Contracts Earthworks Lecture .5
8
Dr. Muthanna Adil Najm Northern Technical University
Quantity
m3
Length
M
Mean
area (m2
)
Area at station
bh + sh2
Depth
h(m)
Station
or
chained
361.83012.0625
12x1+2x12
= 1412
481.83016.0625
12x1.25+2x1.252
= 18.121.253
609.383020.3125
12x1.5+2x1.52
= 22.51.54
1702.26Total quantity =
B- Mid–Section Method
Quantity
(m3
)
Distance
(m)
Area bh+sh2
(m2
)Mean
Depth (m)
Depth
(m)
Station
0.50
248.43012(.625)+2(.625)2
=8.2810.625
0.751
360.93012(.875)+2(.875)2
=12.030.875
1.02
480.93016.031.125
1.253
608.43020.281.375
Estimation, Specifications & Contracts Earthworks Lecture .5
9
Dr. Muthanna Adil Najm Northern Technical University
1698.6m3
Total =1.54
C- For odd number of stations eq. (3) may be modified to obtain the
following formula:
V = L/3 (1st
Area + last Area + 4 x even areas + 2x odd areas)
Using this formula we can obtain the following (see areas in a):-
V = L/3 {A1+A5+4 (A2+A4)+2 (A3)}
= 30/3 {6.5+2205+4 (10.125+18.125)+2 (14)}
V = 1700 m3
Example: The ground levels at various chainage along line of a proposed
channel are as under, see the cross-section where some design
parameters are shown. The chain is s50m long.
222221220219218217216215Chainage
210.00209.65209.90210.35211.10211.50211.05210.30G.L. (m)
209.15209.20209.25209.30209.35209.40209.45209.50C.L. (m)
227226225224223Chainage
211.30211.60211.20210.90210.25G.L. (m)
208.90208.95209.00209.05209.10C.L. (m)
Estimation, Specifications & Contracts Earthworks Lecture .5
10
Dr. Muthanna Adil Najm Northern Technical University
Solution: use mid – section formula.
Acutting = bh + sh2
= 4h + 0.5 h2
Afilling = bh + sh2
= 2.5 (k-h) + 1 (k-h)2
+ 2 (k-h) + 1 (k-h)2
= 4.5 (k-h) + 2 (k-h)2
= 4.5 (4-h) + 2 (4-h)2
(1) (2) (3) (2) - (3) (5) (6) (7) (8) (9) (10)
Qty.
Filling
(m3)
Area
Filling
(m2)
K–hmean
(m)
Qty.
cutting
(m3)
Area
Cutting
(m2)
hmean
(m)
h
(m)
C. L.
(m)
G. L
(m)
Running
Distance
(m)
Chainage
0.80209.50210.300215
141428.282.82765.521.20
1.60209.45211.0550216
94618.932.154569.121.85
2.10209.40211.50100217
89417.892.07479.59.591.93
1.75209.35211.10150218
126125.222.63296.581.4
1.05209.30210.35200219
170134.033.15188.53.770.85
0.65209.25209.90250220
196639.333.45117.52.350.55
0.45209.20209.65300221
2.5
1:2h
1:2
4.00
K = 4.0
1:1 1:1
2.0
H=k-hH=k-h
1:1
Estimation, Specifications & Contracts Earthworks Lecture .5
11
Dr. Muthanna Adil Najm Northern Technical University
Qty.
Filling
(m3)
Area
Filling
(m2)
K–hmean
(m)
Qty.
cutting
(m3)
Area
Cutting
(m2)
hmean
(m)
h
(m)
C. L.
(m)
G. L
(m)
Running
Distance
(m)
Chainage
187637.523.35140.52.810.65
0.85209.15210.00350222
157531.53.02254.501.00
1.15209.10210.25400223
118723.752.5356.57.131.50
1.85209.05210.90450224
83116.631.97509.510.192.03
2.20209.00211.20500225
60012.01.5763412.682.43
2.65208.95211.60550226
54710.941.47666.513.332.53
2.40208.90211.30600227
147984378.5Total
Example: Estimate the cost of excavating and backfilling a trench 1.5 m
wide, 1.2 m deep and 150 m long. Assume the team consists of
one foreman and a number of laborers to perform the job
within five labor days ( each equivalent to 8 working hours).
The job involves the following operations:
- Loosening earth with a pick ( 0.35m3
/hr-laborer)
- Shoveling earth from trench ( 0.475 m3
/ hr-lab.)
- Backfilling trench ( 1.5 m3
/ hr-lab.)
Wages : 30000 I.D. /day for the foreman; 15000 I.D. /day for laborer.
Solution:
V = 1.5 ×1.2 ×150 = 270m3
270 270 270
Estimation, Specifications & Contracts Earthworks Lecture .5
12
Dr. Muthanna Adil Najm Northern Technical University
No. of (laborer - days) required = ---------- + ---------- + -------------
8×0.35 8×0.475 8×1. 5
= 96.43 + 71.05 +22.5 = 190 laborer- days
no. of laborers required to perform the job within 5 days=190/5= 38 laborers
Cost = ( 1×30.000 + 38×15.000) ×5 = 3.000.000 I.D.
Cost per 1m3
= 3.000.000 / 270 = 11111 I.D./m3
Cost per 1m length = 3.000.000 / 150 = 20.000 I.D./m.
Example: Resolve the previous example using wheel type trenching
machine to perform the first two operations . i.e. backfilling by
laborers. Assume the average speed of trenching 6.25m 1hr.
Average cost of renting & operating the machine is = 35.000
I.D. /hr.
Solution : we need the trenching machine to operate for
150m. / 6.25m /hr. = 24hrs. or 24 / 8 = 3 days
Cost of machine : 24×3.500 = 840.000 I.D.
For backfilling we need 22.5 (say 24) days-laborer
no. of laborers to do backfilling within 3 days:
24 / 3 = 8 laborers
So we need a team of 8 laborers & one foreman for 3 days.
The cost (wages) is: (8×15.000 + 1×30.000)×3 = 450.000 I.D.
Total per job = 840.000+450.000=1.290.000 I.D.
Cost per m3 = 1.290.000 / 270 = 4780 I.D/m3
Cost per m length = 1.290.000 / 150= 8600 I.D./1m of term
Estimation, Specifications & Contracts Earthworks Lecture .5
13
Dr. Muthanna Adil Najm Northern Technical University
Example: Estimate the cost of materials required for installing solid
sheeting for 100 m of trench 2.1 m deep . use 4 cm × 25cm lumber 2.4 m
long for sheeting with two horizontal rows of 10cm × 15 cm wales on
each side of the trench for the full length of the trench. Assume that the
sheeting can be used 4 times and the wales ten times. Price = 520 000
I.D/m3
.
Solution:
Vsh. = 0.04×2.4×100×2 = 19.2m3
V Wales = 0.1 ×0.15×100×2×2 = 6m3
Csh = 19.2×520000 / 4 = 2496000
Cw.= 6×520000 / 10 = 312000 I.D.
total 2808000 I.D.
‫اي‬ ‫الحالة‬ ‫هذه‬ ‫مالحظة‬Solid Sheeting‫ال‬ ‫في‬ ‫خاصة‬ ‫حالة‬ ‫هي‬‫ا‬Shoring‫ن‬‫تكو‬ ‫حيث‬
‫اح‬‫و‬‫األل‬.‫متالصقة‬ ‫وليست‬ ‫محددة‬ ‫مسافات‬ ‫على‬

More Related Content

What's hot

Application of taguchi method in the optimization of boring parameters 2
Application of taguchi method in the optimization of boring parameters 2Application of taguchi method in the optimization of boring parameters 2
Application of taguchi method in the optimization of boring parameters 2
IAEME Publication
 
Enhancing the Submersible Pump Rotor Performance by Taguchi Optimization Tech...
Enhancing the Submersible Pump Rotor Performance by Taguchi Optimization Tech...Enhancing the Submersible Pump Rotor Performance by Taguchi Optimization Tech...
Enhancing the Submersible Pump Rotor Performance by Taguchi Optimization Tech...
IRJET Journal
 
IRJET- Planning, Analyzing and Design of High Rise Building using Etabs
IRJET- Planning, Analyzing and Design of High Rise Building using EtabsIRJET- Planning, Analyzing and Design of High Rise Building using Etabs
IRJET- Planning, Analyzing and Design of High Rise Building using Etabs
IRJET Journal
 
Optimization of surface roughness in high speed end milling operation using
Optimization of surface roughness in  high speed end milling operation usingOptimization of surface roughness in  high speed end milling operation using
Optimization of surface roughness in high speed end milling operation using
IAEME Publication
 
Study of Surface Roughness measurement in turning of EN 18 steel
Study of Surface Roughness measurement in turning of EN 18 steelStudy of Surface Roughness measurement in turning of EN 18 steel
Study of Surface Roughness measurement in turning of EN 18 steel
IRJET Journal
 
Bar Graph Method in Engineering management
Bar Graph Method in Engineering management Bar Graph Method in Engineering management
Bar Graph Method in Engineering management
Nzar Braim
 
QUANTITY SURVEY FOR BUILDING ESTIMATION
QUANTITY SURVEY FOR BUILDING ESTIMATIONQUANTITY SURVEY FOR BUILDING ESTIMATION
QUANTITY SURVEY FOR BUILDING ESTIMATION
M Usoof
 
Optimization of input parameters of cnc turning operation for the given comp
Optimization of input parameters of cnc turning operation for the given compOptimization of input parameters of cnc turning operation for the given comp
Optimization of input parameters of cnc turning operation for the given comp
IAEME Publication
 
Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...
IJERA Editor
 
Experimental Investigation and Parametric Analysis of Surface Roughness in C...
Experimental Investigation and Parametric Analysis of Surface  Roughness in C...Experimental Investigation and Parametric Analysis of Surface  Roughness in C...
Experimental Investigation and Parametric Analysis of Surface Roughness in C...
IJMER
 
EXPERIMENTAL STUDY OF TURNING OPERATION AND OPTIMIZATION OF MRR AND SURFACE R...
EXPERIMENTAL STUDY OF TURNING OPERATION AND OPTIMIZATION OF MRR AND SURFACE R...EXPERIMENTAL STUDY OF TURNING OPERATION AND OPTIMIZATION OF MRR AND SURFACE R...
EXPERIMENTAL STUDY OF TURNING OPERATION AND OPTIMIZATION OF MRR AND SURFACE R...
AM Publications
 
Usage of N2 Method for the Performance Evaluation of Plan Asymmetric Structures
Usage of N2 Method for the Performance Evaluation of Plan Asymmetric StructuresUsage of N2 Method for the Performance Evaluation of Plan Asymmetric Structures
Usage of N2 Method for the Performance Evaluation of Plan Asymmetric Structures
IRJET Journal
 
IRJET- Analysis of Cutting Process Parameter During Turning of EN 31 for Mini...
IRJET- Analysis of Cutting Process Parameter During Turning of EN 31 for Mini...IRJET- Analysis of Cutting Process Parameter During Turning of EN 31 for Mini...
IRJET- Analysis of Cutting Process Parameter During Turning of EN 31 for Mini...
IRJET Journal
 
IRJET- Research Review on Multi-Objective Optimization of Machining Parameter...
IRJET- Research Review on Multi-Objective Optimization of Machining Parameter...IRJET- Research Review on Multi-Objective Optimization of Machining Parameter...
IRJET- Research Review on Multi-Objective Optimization of Machining Parameter...
IRJET Journal
 
Facility layout
Facility layoutFacility layout
Facility layout
Đán Lê
 
Facility layout
Facility layoutFacility layout
Facility layout
Maria Ceejee
 
IRJET- Comparative Study on Analysis and Design of Regular Configuration of B...
IRJET- Comparative Study on Analysis and Design of Regular Configuration of B...IRJET- Comparative Study on Analysis and Design of Regular Configuration of B...
IRJET- Comparative Study on Analysis and Design of Regular Configuration of B...
IRJET Journal
 
At03302720279
At03302720279At03302720279
At03302720279
ijceronline
 
Parametric optimisation by using response surface
Parametric optimisation by using response surfaceParametric optimisation by using response surface
Parametric optimisation by using response surface
prj_publication
 

What's hot (19)

Application of taguchi method in the optimization of boring parameters 2
Application of taguchi method in the optimization of boring parameters 2Application of taguchi method in the optimization of boring parameters 2
Application of taguchi method in the optimization of boring parameters 2
 
Enhancing the Submersible Pump Rotor Performance by Taguchi Optimization Tech...
Enhancing the Submersible Pump Rotor Performance by Taguchi Optimization Tech...Enhancing the Submersible Pump Rotor Performance by Taguchi Optimization Tech...
Enhancing the Submersible Pump Rotor Performance by Taguchi Optimization Tech...
 
IRJET- Planning, Analyzing and Design of High Rise Building using Etabs
IRJET- Planning, Analyzing and Design of High Rise Building using EtabsIRJET- Planning, Analyzing and Design of High Rise Building using Etabs
IRJET- Planning, Analyzing and Design of High Rise Building using Etabs
 
Optimization of surface roughness in high speed end milling operation using
Optimization of surface roughness in  high speed end milling operation usingOptimization of surface roughness in  high speed end milling operation using
Optimization of surface roughness in high speed end milling operation using
 
Study of Surface Roughness measurement in turning of EN 18 steel
Study of Surface Roughness measurement in turning of EN 18 steelStudy of Surface Roughness measurement in turning of EN 18 steel
Study of Surface Roughness measurement in turning of EN 18 steel
 
Bar Graph Method in Engineering management
Bar Graph Method in Engineering management Bar Graph Method in Engineering management
Bar Graph Method in Engineering management
 
QUANTITY SURVEY FOR BUILDING ESTIMATION
QUANTITY SURVEY FOR BUILDING ESTIMATIONQUANTITY SURVEY FOR BUILDING ESTIMATION
QUANTITY SURVEY FOR BUILDING ESTIMATION
 
Optimization of input parameters of cnc turning operation for the given comp
Optimization of input parameters of cnc turning operation for the given compOptimization of input parameters of cnc turning operation for the given comp
Optimization of input parameters of cnc turning operation for the given comp
 
Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...
 
Experimental Investigation and Parametric Analysis of Surface Roughness in C...
Experimental Investigation and Parametric Analysis of Surface  Roughness in C...Experimental Investigation and Parametric Analysis of Surface  Roughness in C...
Experimental Investigation and Parametric Analysis of Surface Roughness in C...
 
EXPERIMENTAL STUDY OF TURNING OPERATION AND OPTIMIZATION OF MRR AND SURFACE R...
EXPERIMENTAL STUDY OF TURNING OPERATION AND OPTIMIZATION OF MRR AND SURFACE R...EXPERIMENTAL STUDY OF TURNING OPERATION AND OPTIMIZATION OF MRR AND SURFACE R...
EXPERIMENTAL STUDY OF TURNING OPERATION AND OPTIMIZATION OF MRR AND SURFACE R...
 
Usage of N2 Method for the Performance Evaluation of Plan Asymmetric Structures
Usage of N2 Method for the Performance Evaluation of Plan Asymmetric StructuresUsage of N2 Method for the Performance Evaluation of Plan Asymmetric Structures
Usage of N2 Method for the Performance Evaluation of Plan Asymmetric Structures
 
IRJET- Analysis of Cutting Process Parameter During Turning of EN 31 for Mini...
IRJET- Analysis of Cutting Process Parameter During Turning of EN 31 for Mini...IRJET- Analysis of Cutting Process Parameter During Turning of EN 31 for Mini...
IRJET- Analysis of Cutting Process Parameter During Turning of EN 31 for Mini...
 
IRJET- Research Review on Multi-Objective Optimization of Machining Parameter...
IRJET- Research Review on Multi-Objective Optimization of Machining Parameter...IRJET- Research Review on Multi-Objective Optimization of Machining Parameter...
IRJET- Research Review on Multi-Objective Optimization of Machining Parameter...
 
Facility layout
Facility layoutFacility layout
Facility layout
 
Facility layout
Facility layoutFacility layout
Facility layout
 
IRJET- Comparative Study on Analysis and Design of Regular Configuration of B...
IRJET- Comparative Study on Analysis and Design of Regular Configuration of B...IRJET- Comparative Study on Analysis and Design of Regular Configuration of B...
IRJET- Comparative Study on Analysis and Design of Regular Configuration of B...
 
At03302720279
At03302720279At03302720279
At03302720279
 
Parametric optimisation by using response surface
Parametric optimisation by using response surfaceParametric optimisation by using response surface
Parametric optimisation by using response surface
 

Similar to Lec.5 earthworks for various engineering projects

Mass Haul Diagrams in Optimization of Earthwork Computations
Mass Haul Diagrams in Optimization of Earthwork ComputationsMass Haul Diagrams in Optimization of Earthwork Computations
Mass Haul Diagrams in Optimization of Earthwork Computations
ijtsrd
 
L1 Planning for Earthwork Construction
L1 Planning for Earthwork ConstructionL1 Planning for Earthwork Construction
L1 Planning for Earthwork Construction
Don W. Lewis
 
Balancing Diagram ppt
Balancing Diagram pptBalancing Diagram ppt
Balancing Diagram ppt
ArunKumar6667
 
Part 9, Volume.pdf
Part 9, Volume.pdfPart 9, Volume.pdf
Part 9, Volume.pdf
BAGARAGAZARomuald1
 
Area & volume 2
Area & volume  2Area & volume  2
Area & volume 2
Mital Damani
 
Conduct cadastral Survey work and apply earth work estimation.pptx
Conduct cadastral Survey work and apply earth work estimation.pptxConduct cadastral Survey work and apply earth work estimation.pptx
Conduct cadastral Survey work and apply earth work estimation.pptx
Behailuzenebe1
 
Chapter 4 earth work and quantities new
Chapter 4 earth work and quantities newChapter 4 earth work and quantities new
Chapter 4 earth work and quantities new
BashaFayissa1
 
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil EngineeringQuantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Aabid Ansar
 
Fw2
Fw2Fw2
PROJECTS ON SURVEYING
PROJECTS ON SURVEYINGPROJECTS ON SURVEYING
PROJECTS ON SURVEYING
Naga Praveen Nadakuditi
 
Design-Proposal-Gillespie
Design-Proposal-GillespieDesign-Proposal-Gillespie
Design-Proposal-Gillespie
Cameron Gillespie
 
Field work 1 (1)
Field work 1 (1)Field work 1 (1)
Field work 1 (1)
Chee Lee
 
Estimation of Heat Flux on A Launch Vehicle Fin at Hypersonic Mach Numbers --...
Estimation of Heat Flux on A Launch Vehicle Fin at Hypersonic Mach Numbers --...Estimation of Heat Flux on A Launch Vehicle Fin at Hypersonic Mach Numbers --...
Estimation of Heat Flux on A Launch Vehicle Fin at Hypersonic Mach Numbers --...
Abhishek Jain
 
Engineering surveying-ii
Engineering surveying-iiEngineering surveying-ii
Engineering surveying-ii
Marvin Ken
 
CFD and Artificial Neural Networks Analysis of Plane Sudden Expansion Flows
CFD and Artificial Neural Networks Analysis of Plane Sudden Expansion FlowsCFD and Artificial Neural Networks Analysis of Plane Sudden Expansion Flows
CFD and Artificial Neural Networks Analysis of Plane Sudden Expansion Flows
CSCJournals
 
unit-3.ppt
unit-3.pptunit-3.ppt
unit-3.ppt
Srini Vasan
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for building
Himani762003
 
IntroductionTopological sorting is a common operation performed .docx
IntroductionTopological sorting is a common operation performed .docxIntroductionTopological sorting is a common operation performed .docx
IntroductionTopological sorting is a common operation performed .docx
mariuse18nolet
 
Final course project report
Final course project reportFinal course project report
Final course project report
Kaggwa Abdul
 
Ecv
EcvEcv

Similar to Lec.5 earthworks for various engineering projects (20)

Mass Haul Diagrams in Optimization of Earthwork Computations
Mass Haul Diagrams in Optimization of Earthwork ComputationsMass Haul Diagrams in Optimization of Earthwork Computations
Mass Haul Diagrams in Optimization of Earthwork Computations
 
L1 Planning for Earthwork Construction
L1 Planning for Earthwork ConstructionL1 Planning for Earthwork Construction
L1 Planning for Earthwork Construction
 
Balancing Diagram ppt
Balancing Diagram pptBalancing Diagram ppt
Balancing Diagram ppt
 
Part 9, Volume.pdf
Part 9, Volume.pdfPart 9, Volume.pdf
Part 9, Volume.pdf
 
Area & volume 2
Area & volume  2Area & volume  2
Area & volume 2
 
Conduct cadastral Survey work and apply earth work estimation.pptx
Conduct cadastral Survey work and apply earth work estimation.pptxConduct cadastral Survey work and apply earth work estimation.pptx
Conduct cadastral Survey work and apply earth work estimation.pptx
 
Chapter 4 earth work and quantities new
Chapter 4 earth work and quantities newChapter 4 earth work and quantities new
Chapter 4 earth work and quantities new
 
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil EngineeringQuantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
 
Fw2
Fw2Fw2
Fw2
 
PROJECTS ON SURVEYING
PROJECTS ON SURVEYINGPROJECTS ON SURVEYING
PROJECTS ON SURVEYING
 
Design-Proposal-Gillespie
Design-Proposal-GillespieDesign-Proposal-Gillespie
Design-Proposal-Gillespie
 
Field work 1 (1)
Field work 1 (1)Field work 1 (1)
Field work 1 (1)
 
Estimation of Heat Flux on A Launch Vehicle Fin at Hypersonic Mach Numbers --...
Estimation of Heat Flux on A Launch Vehicle Fin at Hypersonic Mach Numbers --...Estimation of Heat Flux on A Launch Vehicle Fin at Hypersonic Mach Numbers --...
Estimation of Heat Flux on A Launch Vehicle Fin at Hypersonic Mach Numbers --...
 
Engineering surveying-ii
Engineering surveying-iiEngineering surveying-ii
Engineering surveying-ii
 
CFD and Artificial Neural Networks Analysis of Plane Sudden Expansion Flows
CFD and Artificial Neural Networks Analysis of Plane Sudden Expansion FlowsCFD and Artificial Neural Networks Analysis of Plane Sudden Expansion Flows
CFD and Artificial Neural Networks Analysis of Plane Sudden Expansion Flows
 
unit-3.ppt
unit-3.pptunit-3.ppt
unit-3.ppt
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for building
 
IntroductionTopological sorting is a common operation performed .docx
IntroductionTopological sorting is a common operation performed .docxIntroductionTopological sorting is a common operation performed .docx
IntroductionTopological sorting is a common operation performed .docx
 
Final course project report
Final course project reportFinal course project report
Final course project report
 
Ecv
EcvEcv
Ecv
 

More from Muthanna Abbu

Lec.4 Excavation and fill works of wall footings
Lec.4 Excavation and fill works of wall footingsLec.4 Excavation and fill works of wall footings
Lec.4 Excavation and fill works of wall footings
Muthanna Abbu
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
Muthanna Abbu
 
Lec.2 statically determinate structures & statically indeterminate struct...
Lec.2 statically determinate structures & statically indeterminate struct...Lec.2 statically determinate structures & statically indeterminate struct...
Lec.2 statically determinate structures & statically indeterminate struct...
Muthanna Abbu
 
Lec.1 introduction to the theory of structures. types of structures, loads,
Lec.1   introduction to the theory of structures. types of structures, loads,Lec.1   introduction to the theory of structures. types of structures, loads,
Lec.1 introduction to the theory of structures. types of structures, loads,
Muthanna Abbu
 
Lec.9 strength design method doubly reinforced beams
Lec.9   strength design method doubly reinforced beamsLec.9   strength design method doubly reinforced beams
Lec.9 strength design method doubly reinforced beams
Muthanna Abbu
 
Lec.8 strength design method t beams
Lec.8   strength design method t beamsLec.8   strength design method t beams
Lec.8 strength design method t beams
Muthanna Abbu
 
Lec.7 strength design method rectangular sections 3
Lec.7   strength design method rectangular sections  3Lec.7   strength design method rectangular sections  3
Lec.7 strength design method rectangular sections 3
Muthanna Abbu
 
Lec.6 strength design method rectangular sections 2
Lec.6   strength design method rectangular sections  2Lec.6   strength design method rectangular sections  2
Lec.6 strength design method rectangular sections 2
Muthanna Abbu
 
Lec.5 strength design method rectangular sections 1
Lec.5   strength design method rectangular sections  1Lec.5   strength design method rectangular sections  1
Lec.5 strength design method rectangular sections 1
Muthanna Abbu
 
Lec.4 working stress 2
Lec.4   working stress 2Lec.4   working stress 2
Lec.4 working stress 2
Muthanna Abbu
 
Lec.3 working stress 1
Lec.3   working stress 1Lec.3   working stress 1
Lec.3 working stress 1
Muthanna Abbu
 
Lec.2 materials
Lec.2   materialsLec.2   materials
Lec.2 materials
Muthanna Abbu
 
Lec.1 introduction
Lec.1   introductionLec.1   introduction
Lec.1 introduction
Muthanna Abbu
 
Theory of Structures Syllabus
Theory of Structures SyllabusTheory of Structures Syllabus
Theory of Structures Syllabus
Muthanna Abbu
 
Analysis & Design of reinforced concrete structures (1) Syllabus
Analysis & Design of reinforced concrete structures (1) SyllabusAnalysis & Design of reinforced concrete structures (1) Syllabus
Analysis & Design of reinforced concrete structures (1) Syllabus
Muthanna Abbu
 
Analysis & Design of reinforced concrete structures (2) Syllabus
Analysis & Design of reinforced concrete structures (2) SyllabusAnalysis & Design of reinforced concrete structures (2) Syllabus
Analysis & Design of reinforced concrete structures (2) Syllabus
Muthanna Abbu
 
Design of Steel Structures Syllabus
Design of Steel Structures SyllabusDesign of Steel Structures Syllabus
Design of Steel Structures Syllabus
Muthanna Abbu
 
Computer Applications 2 Syllabus
Computer Applications 2 SyllabusComputer Applications 2 Syllabus
Computer Applications 2 Syllabus
Muthanna Abbu
 
هندسة المطارات والسكك 4
هندسة المطارات والسكك 4هندسة المطارات والسكك 4
هندسة المطارات والسكك 4
Muthanna Abbu
 
هندسة المطارات والسكك 3
هندسة المطارات والسكك 3هندسة المطارات والسكك 3
هندسة المطارات والسكك 3
Muthanna Abbu
 

More from Muthanna Abbu (20)

Lec.4 Excavation and fill works of wall footings
Lec.4 Excavation and fill works of wall footingsLec.4 Excavation and fill works of wall footings
Lec.4 Excavation and fill works of wall footings
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
 
Lec.2 statically determinate structures & statically indeterminate struct...
Lec.2 statically determinate structures & statically indeterminate struct...Lec.2 statically determinate structures & statically indeterminate struct...
Lec.2 statically determinate structures & statically indeterminate struct...
 
Lec.1 introduction to the theory of structures. types of structures, loads,
Lec.1   introduction to the theory of structures. types of structures, loads,Lec.1   introduction to the theory of structures. types of structures, loads,
Lec.1 introduction to the theory of structures. types of structures, loads,
 
Lec.9 strength design method doubly reinforced beams
Lec.9   strength design method doubly reinforced beamsLec.9   strength design method doubly reinforced beams
Lec.9 strength design method doubly reinforced beams
 
Lec.8 strength design method t beams
Lec.8   strength design method t beamsLec.8   strength design method t beams
Lec.8 strength design method t beams
 
Lec.7 strength design method rectangular sections 3
Lec.7   strength design method rectangular sections  3Lec.7   strength design method rectangular sections  3
Lec.7 strength design method rectangular sections 3
 
Lec.6 strength design method rectangular sections 2
Lec.6   strength design method rectangular sections  2Lec.6   strength design method rectangular sections  2
Lec.6 strength design method rectangular sections 2
 
Lec.5 strength design method rectangular sections 1
Lec.5   strength design method rectangular sections  1Lec.5   strength design method rectangular sections  1
Lec.5 strength design method rectangular sections 1
 
Lec.4 working stress 2
Lec.4   working stress 2Lec.4   working stress 2
Lec.4 working stress 2
 
Lec.3 working stress 1
Lec.3   working stress 1Lec.3   working stress 1
Lec.3 working stress 1
 
Lec.2 materials
Lec.2   materialsLec.2   materials
Lec.2 materials
 
Lec.1 introduction
Lec.1   introductionLec.1   introduction
Lec.1 introduction
 
Theory of Structures Syllabus
Theory of Structures SyllabusTheory of Structures Syllabus
Theory of Structures Syllabus
 
Analysis & Design of reinforced concrete structures (1) Syllabus
Analysis & Design of reinforced concrete structures (1) SyllabusAnalysis & Design of reinforced concrete structures (1) Syllabus
Analysis & Design of reinforced concrete structures (1) Syllabus
 
Analysis & Design of reinforced concrete structures (2) Syllabus
Analysis & Design of reinforced concrete structures (2) SyllabusAnalysis & Design of reinforced concrete structures (2) Syllabus
Analysis & Design of reinforced concrete structures (2) Syllabus
 
Design of Steel Structures Syllabus
Design of Steel Structures SyllabusDesign of Steel Structures Syllabus
Design of Steel Structures Syllabus
 
Computer Applications 2 Syllabus
Computer Applications 2 SyllabusComputer Applications 2 Syllabus
Computer Applications 2 Syllabus
 
هندسة المطارات والسكك 4
هندسة المطارات والسكك 4هندسة المطارات والسكك 4
هندسة المطارات والسكك 4
 
هندسة المطارات والسكك 3
هندسة المطارات والسكك 3هندسة المطارات والسكك 3
هندسة المطارات والسكك 3
 

Recently uploaded

My Airframe Metallic Design Capability Studies..pdf
My Airframe Metallic Design Capability Studies..pdfMy Airframe Metallic Design Capability Studies..pdf
My Airframe Metallic Design Capability Studies..pdf
Geoffrey Wardle. MSc. MSc. Snr.MAIAA
 
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
nainakaoornoida
 
Sri Guru Hargobind Ji - Bandi Chor Guru.pdf
Sri Guru Hargobind Ji - Bandi Chor Guru.pdfSri Guru Hargobind Ji - Bandi Chor Guru.pdf
Sri Guru Hargobind Ji - Bandi Chor Guru.pdf
Balvir Singh
 
💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...
💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...
💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...
rupa singh
 
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdfSELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
Pallavi Sharma
 
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
sonamrawat5631
 
Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...
Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...
Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...
Banerescorts
 
🚺ANJALI MEHTA High Profile Call Girls Ahmedabad 💯Call Us 🔝 9352988975 🔝💃Top C...
🚺ANJALI MEHTA High Profile Call Girls Ahmedabad 💯Call Us 🔝 9352988975 🔝💃Top C...🚺ANJALI MEHTA High Profile Call Girls Ahmedabad 💯Call Us 🔝 9352988975 🔝💃Top C...
🚺ANJALI MEHTA High Profile Call Girls Ahmedabad 💯Call Us 🔝 9352988975 🔝💃Top C...
dulbh kashyap
 
The Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC Conduit
The Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC ConduitThe Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC Conduit
The Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC Conduit
Guangdong Ctube Industry Co., Ltd.
 
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
simrangupta87541
 
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort ServiceCuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
yakranividhrini
 
Standards Method of Detailing Structural Concrete.pdf
Standards Method of Detailing Structural Concrete.pdfStandards Method of Detailing Structural Concrete.pdf
Standards Method of Detailing Structural Concrete.pdf
baoancons14
 
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call GirlCall Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
sapna sharmap11
 
Cricket management system ptoject report.pdf
Cricket management system ptoject report.pdfCricket management system ptoject report.pdf
Cricket management system ptoject report.pdf
Kamal Acharya
 
TENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineeringTENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineering
SnehalChavan75
 
ESCORT SERVICE FULL ENJOY - @9711199012, Mayur Vihar CALL GIRLS SERVICE Delhi
ESCORT SERVICE FULL ENJOY - @9711199012, Mayur Vihar CALL GIRLS SERVICE DelhiESCORT SERVICE FULL ENJOY - @9711199012, Mayur Vihar CALL GIRLS SERVICE Delhi
ESCORT SERVICE FULL ENJOY - @9711199012, Mayur Vihar CALL GIRLS SERVICE Delhi
AK47
 
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptxMODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
NaveenNaveen726446
 
anatomy of space vehicle and aerospace structures.pptx
anatomy of space vehicle and aerospace structures.pptxanatomy of space vehicle and aerospace structures.pptx
anatomy of space vehicle and aerospace structures.pptx
ssusercf1619
 
My Aerospace Design and Structures Career Engineering LinkedIn version Presen...
My Aerospace Design and Structures Career Engineering LinkedIn version Presen...My Aerospace Design and Structures Career Engineering LinkedIn version Presen...
My Aerospace Design and Structures Career Engineering LinkedIn version Presen...
Geoffrey Wardle. MSc. MSc. Snr.MAIAA
 
Call Girls Madurai 8824825030 Escort In Madurai service 24X7
Call Girls Madurai 8824825030 Escort In Madurai service 24X7Call Girls Madurai 8824825030 Escort In Madurai service 24X7
Call Girls Madurai 8824825030 Escort In Madurai service 24X7
Poonam Singh
 

Recently uploaded (20)

My Airframe Metallic Design Capability Studies..pdf
My Airframe Metallic Design Capability Studies..pdfMy Airframe Metallic Design Capability Studies..pdf
My Airframe Metallic Design Capability Studies..pdf
 
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
 
Sri Guru Hargobind Ji - Bandi Chor Guru.pdf
Sri Guru Hargobind Ji - Bandi Chor Guru.pdfSri Guru Hargobind Ji - Bandi Chor Guru.pdf
Sri Guru Hargobind Ji - Bandi Chor Guru.pdf
 
💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...
💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...
💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...
 
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdfSELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
 
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
 
Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...
Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...
Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...
 
🚺ANJALI MEHTA High Profile Call Girls Ahmedabad 💯Call Us 🔝 9352988975 🔝💃Top C...
🚺ANJALI MEHTA High Profile Call Girls Ahmedabad 💯Call Us 🔝 9352988975 🔝💃Top C...🚺ANJALI MEHTA High Profile Call Girls Ahmedabad 💯Call Us 🔝 9352988975 🔝💃Top C...
🚺ANJALI MEHTA High Profile Call Girls Ahmedabad 💯Call Us 🔝 9352988975 🔝💃Top C...
 
The Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC Conduit
The Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC ConduitThe Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC Conduit
The Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC Conduit
 
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
Mahipalpur Call Girls Delhi 🔥 9711199012 ❄- Pick Your Dream Call Girls with 1...
 
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort ServiceCuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
Cuttack Call Girls 💯Call Us 🔝 7374876321 🔝 💃 Independent Female Escort Service
 
Standards Method of Detailing Structural Concrete.pdf
Standards Method of Detailing Structural Concrete.pdfStandards Method of Detailing Structural Concrete.pdf
Standards Method of Detailing Structural Concrete.pdf
 
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call GirlCall Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
 
Cricket management system ptoject report.pdf
Cricket management system ptoject report.pdfCricket management system ptoject report.pdf
Cricket management system ptoject report.pdf
 
TENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineeringTENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineering
 
ESCORT SERVICE FULL ENJOY - @9711199012, Mayur Vihar CALL GIRLS SERVICE Delhi
ESCORT SERVICE FULL ENJOY - @9711199012, Mayur Vihar CALL GIRLS SERVICE DelhiESCORT SERVICE FULL ENJOY - @9711199012, Mayur Vihar CALL GIRLS SERVICE Delhi
ESCORT SERVICE FULL ENJOY - @9711199012, Mayur Vihar CALL GIRLS SERVICE Delhi
 
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptxMODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
 
anatomy of space vehicle and aerospace structures.pptx
anatomy of space vehicle and aerospace structures.pptxanatomy of space vehicle and aerospace structures.pptx
anatomy of space vehicle and aerospace structures.pptx
 
My Aerospace Design and Structures Career Engineering LinkedIn version Presen...
My Aerospace Design and Structures Career Engineering LinkedIn version Presen...My Aerospace Design and Structures Career Engineering LinkedIn version Presen...
My Aerospace Design and Structures Career Engineering LinkedIn version Presen...
 
Call Girls Madurai 8824825030 Escort In Madurai service 24X7
Call Girls Madurai 8824825030 Escort In Madurai service 24X7Call Girls Madurai 8824825030 Escort In Madurai service 24X7
Call Girls Madurai 8824825030 Escort In Madurai service 24X7
 

Lec.5 earthworks for various engineering projects

  • 1. Estimation, Specifications & Contracts Earthworks Lecture .5 1 Dr. Muthanna Adil Najm Northern Technical University Earthworks for various engineering projects Earthworks, in general, may be encountered in any civil engineering project. In building and small projects, the quantities of earthworks can be calculated easily as have been shown in previous subjects and solved examples, whereas other kinds of projects, such as roads, canals, bridges, tunnels, dams and others, involve a huge quantities of earthworks, the calculations of which may be somewhat complex due to random changes or variations in the natural ground level. DEFINITIONS Lead: it is the average horizontal straight practical distance through which the excavated soil is carried from the sources to the place of spreading or dumping. Usually the work site is divided into areas or blocks and haul distance is calculated from the centre of each block to the destination location. When the haul distance is too long the transport must be calculated separately. Lift: It is the average vertical distance (height) above which the soil has to be lifted from the source. ‫الرفع‬ ‫مسافة‬ Quantity survey: the process of calculating the quantity of materials required to build a project. Mass Excavation: the requirement to excavate substantial volume of material, usually at considerable depth or over a large area. Structural excavation: excavation undertaken in support of structural element construction, usually involve removing materials from a limited area.
  • 2. Estimation, Specifications & Contracts Earthworks Lecture .5 2 Dr. Muthanna Adil Najm Northern Technical University Plan view: a construction drawing representing the horizontal alignment of the work. Profile view: a construction drawing depicting a vertical plane cut through the centerline of the work . it shows the vertical relationship of the ground surface and the finished work. Cross section view: a construction drawing depicting a vertical section of earthwork at right angles to the centerline of the work. Cross sections: earthwork drawings cheated by combining the project design with field measurements of existing conditions. Stripping: the upper layer of organic material that must be removed before beginning an excavation or embedment. ‫القشط‬ ‫أو‬ ‫التعرية‬ Mass diagram: It is a graph showing the accumulation of cut and fill with distance from a starting, or origin, or reference point. Cut is usually considered positive & fill negative. Mass diagram is very useful for determining the quantities of earthworks, computing hall distances and specifying the proper types of equipment to perform the works. (refer to attached details and examples – photo copy from Peurifoy) .‫االنتفاخ‬ ‫نسبة‬ ‫اعتبار‬ ‫يتم‬percent swell‫في‬‫(عادة‬ ‫القطع‬ ‫مناطق‬20)%‫التقلص‬ ‫وعامل‬percent shrinkage‫الدفن‬ ‫مناطق‬ ‫في‬‫(عادة‬10)%‫أو‬ ‫الحفريات‬ ‫حجم‬ ‫الحتساب‬‫المرصوصة‬ ‫المدفونة‬ ‫التربة‬ ‫التوالي‬ ‫على‬. )%( ‫االنتفاخ‬ ‫نسبة‬=‫بة‬‫ر‬‫الت‬ ‫حجم‬) ‫رخوة‬ ( ‫الحفر‬ ‫بعد‬–( ‫الطبيعي‬ ‫حجمها‬Bank(×100 ( ‫الطبيعي‬ ‫حجمها‬B) ‫نسبة‬‫التقلص‬)%(=‫بة‬‫ر‬‫الت‬ ‫حجم‬‫الرص‬ ‫قبل‬–‫حجمها‬‫الرص‬ ‫بعد‬(compacted)×100 ‫بة‬‫ر‬‫الت‬ ‫حجم‬‫الرص‬ ‫قبل‬
  • 3. Estimation, Specifications & Contracts Earthworks Lecture .5 3 Dr. Muthanna Adil Najm Northern Technical University ‫في‬ ‫نقلها‬ ‫مطلوب‬ ‫اد‬‫و‬‫م‬ ‫توجد‬ ‫ال‬ ‫انه‬ ‫يعني‬ ‫فهذا‬ ،ً‫ا‬‫أفقي‬ ‫محطتين‬ ‫بين‬ ‫الكميات‬ ‫مخطط‬ ‫كان‬ ‫إذا‬ ‫(أي‬ ‫نة‬‫ز‬‫ا‬‫و‬‫مت‬ ‫لكنها‬ ‫ء‬‫الجز‬ ‫هذا‬ ‫ضمن‬ ‫إمالء‬‫و‬ ‫قطع‬ ‫هناك‬ ‫ن‬‫يكو‬ ‫قد‬ ‫اقع‬‫و‬‫ال‬ ‫في‬ .‫ع‬‫المشرو‬ ‫من‬ ‫ء‬‫الجز‬ ‫هذا‬ ‫من‬ ‫إمالء‬‫و‬ ‫جانب‬ ‫من‬ ‫قطع‬ ‫على‬ ‫يشتمل‬ ‫العمل‬ ‫كان‬ ‫إذا‬‫و‬ .)‫اإلمالء‬ ‫كمية‬ ‫يبا‬‫ر‬‫تق‬ ‫تساوي‬ ‫القطع‬ ‫كمية‬ ‫من‬ ‫نقلها‬ ‫يمكن‬ ‫القطع‬ ‫كميات‬ ‫الن‬ ‫اء‬‫و‬‫االست‬ ‫إلى‬ ‫يميل‬ ‫أو‬ ‫ع‬‫ينز‬ ‫الكميات‬ ‫منحني‬ ‫فان‬ ،‫آخر‬ ‫جانب‬ "‫"العرضي‬ ‫النقل‬ ‫تسمى‬ ‫العملية‬ ‫وهذه‬ ،‫ى‬‫أخر‬ ‫إلى‬ ‫محطة‬ ‫من‬ ‫وليس‬ ‫آخر‬ ‫إلى‬ ‫جانب‬cross hall. ‫فالمنحنى‬ ،‫المحطات‬ ‫بين‬ ‫الحجوم‬ ‫يادة‬‫ز‬ ‫مع‬ ‫يزداد‬ ‫الكميات‬ ‫منحنى‬ ‫انحدار‬ ‫أو‬ ‫ميل‬ ‫إن‬ ‫إلى‬ ‫يشير‬ ‫الصاعد‬‫إلى‬ ‫المنحنى‬ ‫يصل‬ .‫إمالئيات‬ ‫أعمال‬ ‫على‬ ‫يدل‬ ‫النازل‬ ‫المنحنى‬ ‫بينما‬ ‫قطع‬ ‫وجود‬ ‫ويبدأ‬ ‫اإلمالء‬ ‫ينتهي‬ ‫حيث‬ ‫الدنيا‬ ‫المناطق‬ ‫الى‬‫و‬ ،‫اإلمالء‬ ‫ويبدأ‬ ‫القطع‬ ‫ينتهي‬ ‫حيث‬ ‫الذروة‬ ‫مناطق‬ .‫القطع‬ ‫وفي‬ ،‫معينة‬ ‫نقاط‬ ‫في‬ ‫الكميات‬ ‫منحنى‬ ‫سيقطع‬ ‫فانه‬ ‫المرجع‬ ‫نقطة‬ ‫من‬ ً‫ا‬‫أفقي‬ ً‫ا‬‫خط‬ ‫رسمنا‬ ‫لو‬ ‫ع‬‫مجمو‬ ‫إن‬ .‫التقاطع‬ ‫نقاط‬ ‫بين‬ )ً‫ا‬‫يب‬‫ر‬‫تق‬ ‫تتساوى‬ ‫(أي‬ ‫ن‬‫از‬‫و‬‫ستت‬ ‫اإلمالء‬‫و‬ ‫القطع‬ ‫كميات‬ ‫فان‬ ‫الحالة‬ ‫هذه‬ ‫بمعدل‬ ‫يات‬‫ر‬‫للحف‬ ‫الكلية‬ ‫الكمية‬ ‫ضرب‬ ‫حاصل‬ ‫من‬ ‫حسابها‬ ‫يمكن‬ ‫الكلية‬ ‫النقل‬ ‫مسافة‬ ‫حصيلة‬ ‫أو‬ ‫مساف‬‫النقل‬ ‫ة‬average haul distance‫كما‬ ‫تحديده‬ ‫فيمكن‬ ‫اإلمالء‬ ‫أو‬ ‫القطع‬ ‫كميات‬ ‫مركز‬ ‫أما‬ . :‫يلي‬ 1-‫نة‬‫ز‬‫ا‬‫و‬‫الم‬ ‫خط‬ ‫إلى‬ ‫الذروة‬ ‫نقطة‬ ‫من‬ ً‫ا‬‫عمودي‬ ً‫ا‬‫خط‬ ‫نرسم‬balancing line. 2-‫نقطتين‬ ‫في‬ ‫الكميات‬ ‫منحنى‬ ‫ويقطع‬ ‫أعاله‬ ‫المرسوم‬ ‫الخط‬ ‫بمنتصف‬ ‫يمر‬ ‫أفقيا‬ ً‫ا‬‫خط‬ ‫نرسم‬ ‫النقاط‬ ‫(الحظ‬ .‫متقابلتين‬.)‫التقاطع‬ ‫نقطتي‬ ‫تقابل‬ ‫التي‬ ‫المحطات‬ ‫أو‬
  • 4. Estimation, Specifications & Contracts Earthworks Lecture .5 4 Dr. Muthanna Adil Najm Northern Technical University 3-‫القطع‬ ‫كميات‬ ‫مركز‬ ‫تمثل‬ ‫المنحنى‬ ‫من‬ ‫الصاعد‬ ‫ء‬‫الجز‬ ‫في‬ ‫اقعة‬‫و‬‫ال‬ ‫المحطة‬ ‫أو‬ ‫النقطة‬ ‫إن‬ ‫فتمثل‬ ‫المحطتين‬ ‫هاتين‬ ‫بين‬ ‫المسافة‬ ‫أما‬ .‫االمالئيات‬ ‫مركز‬ ‫هي‬ ‫النازل‬ ‫ء‬‫الجز‬ ‫في‬ ‫اقعة‬‫و‬‫ال‬ ‫المحطة‬‫و‬ ‫ء‬‫الجز‬ ‫لهذا‬ ‫النقل‬ ‫مسافة‬haul distance. ‫إن‬‫انجاز‬ ‫معدل‬ ‫تقدير‬‫أعمال‬‫دقيقة‬ ‫ة‬‫ر‬‫بصو‬ ‫الحفر‬‫أم‬‫ر‬‫في‬ ‫تؤثر‬ ‫امل‬‫و‬‫ع‬ ‫عدة‬ ‫لوجود‬ ‫صعب‬ ‫المعدل‬ ‫هذا‬،‫ويمكن‬‫ها‬‫إيجاز‬: ‫هي‬ ‫امل‬‫و‬‫الع‬ ‫من‬ ‫بمجموعتين‬- sJob factor:‫المياه‬‫و‬ ‫الرطوبة‬ ‫مستوى‬ ،‫بة‬‫ر‬‫الت‬ ‫ع‬‫نو‬ : ‫منها‬ ‫الموقع‬‫و‬ ‫العمل‬ ‫بظروف‬ ‫تتعلق‬ ‫امل‬‫و‬‫ع‬ ‫نقل‬ ‫ومسافة‬ ‫العمل‬ ‫حجم‬ ‫المعدات‬‫و‬ ‫العمال‬ ‫حركة‬ ‫ية‬‫ر‬‫ح‬ ،‫المناخية‬ ‫الظروف‬ ،‫الجوفية‬ Fill (m3 ) Cut (m3 ) Balance points Haul distance cut center of mass fill center of mass
  • 5. Estimation, Specifications & Contracts Earthworks Lecture .5 5 Dr. Muthanna Adil Najm Northern Technical University ‫بة‬‫ر‬‫الت‬‫وظروف‬ ‫ة‬‫ر‬‫المحفو‬‫يق‬‫ر‬‫الط‬. ‫الخ‬ ...‫إن‬‫مفروضة‬ ‫كلها‬ ‫هذه‬ ‫العمل‬ ‫ظروف‬ ‫ال‬‫و‬ ‫المنفذة‬ ‫الجهة‬ ‫على‬.‫ها‬‫تغيير‬ ‫يمكنها‬ Management factors‫امل‬‫و‬‫ع‬ :‫ة‬‫ر‬‫اإلدا‬‫المعنوية‬ ‫ح‬‫الرو‬ ‫على‬ ‫الحفاظ‬‫و‬ ،‫العمل‬ ‫تنظيم‬ ‫وتتضمن‬ ‫المناسبة‬ ‫ق‬‫الطر‬‫و‬ ‫العدد‬‫و‬ ‫المعدات‬ ‫استخدام‬‫و‬ ‫اختيار‬‫و‬ ‫للعمال‬ ‫العالية‬ ‫العن‬ ،‫للعمل‬.‫ها‬‫وغير‬ ‫االنجاز‬ ‫معدالت‬ ‫على‬ ‫الحفاظ‬‫و‬ ‫بالمعدات‬ ‫اية‬‫كل‬ ‫حسن‬ ‫على‬ ‫تعتمد‬ ‫امل‬‫و‬‫الع‬ ‫هذه‬‫ة‬‫ر‬‫إدا‬‫ة‬‫ر‬‫السيط‬ ‫ويمكن‬ ‫المنفذة‬ ‫الجهة‬ .‫عليها‬ ‫مبادئ‬‫الترابية‬ ‫األعمال‬ ‫حساب‬Principles of Earthworks Calculation .‫ذلك‬ ‫خالف‬ ‫ذكر‬ ‫إن‬ ‫إال‬ ،‫المكعب‬ ‫بالمتر‬ ‫عادة‬ ‫ابية‬‫ر‬‫الت‬ ‫األعمال‬ ‫كميات‬ ‫تقاس‬ .‫منفصلة‬ ‫ة‬‫ر‬‫بصو‬ ‫تحسب‬ ‫أن‬ ‫يجب‬ ‫بة‬‫ر‬‫الت‬ ‫من‬ ‫مختلفة‬ ‫اع‬‫و‬‫ألن‬ ‫ابية‬‫ر‬‫الت‬ ‫األعمال‬ .‫لذلك‬ ‫مناسبة‬ ‫يقة‬‫ر‬‫ط‬ ‫وتستخدم‬ ‫بعناية‬ ‫قياسها‬ ‫بعد‬ ‫ابية‬‫ر‬‫الت‬ ‫الكميات‬ ‫تحسب‬ ‫أعمال‬‫اإل‬.‫ة‬‫ر‬‫الفق‬ ‫في‬ ‫شمل‬ُ‫ت‬ ‫أن‬ ‫يجب‬ ‫التسوية‬‫و‬ ‫كساء‬ ‫تحد‬ ‫يجب‬ ‫وهنا‬ ‫ابية‬‫ر‬‫الت‬ ‫الكميات‬ ‫ونقل‬ ‫فع‬‫ر‬ ‫تتضمن‬ ‫أن‬ ‫يجب‬ ‫ابية‬‫ر‬‫الت‬ ‫الكميات‬ ‫حسابات‬‫يد‬ .‫عملية‬ ‫لكل‬ ‫النقل‬ ‫مسافة‬
  • 6. Estimation, Specifications & Contracts Earthworks Lecture .5 6 Dr. Muthanna Adil Najm Northern Technical University ‫الترابية‬ ‫الكميات‬ ‫حساب‬ ‫طرق‬Earth Computation Methods ‫اع‬‫ط‬‫الق‬ ‫أو‬ ‫ار‬‫ف‬‫الح‬ ‫ااطق‬‫ن‬‫م‬ ‫في‬ ‫ات‬‫و‬‫القن‬‫و‬ ‫الحديدية‬ ‫السكك‬‫و‬ ‫ات‬‫ر‬‫السيا‬ ‫ق‬‫لطر‬ ‫العرضي‬ ‫المقطع‬ ‫إن‬ cutting‫االء‬‫ا‬‫م‬‫اإل‬‫و‬filling‫اة‬‫ا‬‫ئ‬‫التعب‬‫و‬banking‫ارف‬‫ا‬‫ح‬‫من‬ ‫ابه‬‫ا‬‫ح‬ ‫اكل‬‫ا‬‫ش‬‫ب‬ ‫اادة‬‫ا‬‫ع‬ ‫ن‬‫او‬‫ا‬‫ك‬‫ي‬trapezoidal، :‫يلي‬ ‫كما‬ ‫الشكل‬ ‫لهذا‬ ‫القطع‬ ‫مساحة‬ ‫حساب‬ ‫ويمكن‬ Area = ABCEF +AABF + AEDC = bh + 0.5h.sh + 0.5 h.ah Area= h [b + (ah + sh)/2] -----------------------------(1) ‫عندما‬s=a(‫أي‬:‫على‬ ‫نحصل‬ )‫للجانبين‬ ‫متساو‬ ‫االنحدار‬ Area= h (b + sh) = hb + sh2 ---------------------------(2) :‫أهمها‬‫و‬ ‫ابية‬‫ر‬‫الت‬ ‫األعمال‬ ‫كمية‬ ‫لحساب‬ ‫مستخدمة‬ ‫ق‬‫طر‬ ‫عدة‬ ‫هناك‬- ‫المساحات‬ ‫معدل‬ ‫طريقة‬Average end area method-I ‫ء‬‫الجز‬ ‫طول‬ ‫في‬ ‫ويضرب‬ ‫القطاع‬ ‫أو‬ ‫ء‬‫الجز‬ ‫في‬‫ر‬‫ط‬ ‫عند‬ ‫العرضي‬ ‫المقطع‬ ‫مساحة‬ ‫معدل‬ ‫حسب‬ُ‫ي‬ .‫الحجم‬ ‫على‬ ‫للحصول‬ ‫صيغة‬‫معادلة‬ ‫أو‬‫الوسطي‬ ‫المقطع‬on FormulaMid Secti-II A B F E D C a:1s:1 b b ahsh a:1s:1 h
  • 7. Estimation, Specifications & Contracts Earthworks Lecture .5 7 Dr. Muthanna Adil Najm Northern Technical University ‫ت‬‫عند‬ ‫تفاع‬‫ر‬‫اال‬ ‫معدل‬ ‫عتمد‬ُ‫ي‬ ‫وهنا‬ ،‫ء‬‫الجز‬ ‫منتصف‬ ‫أو‬ ‫وسط‬ ‫عند‬ ‫المقطع‬ ‫مساحة‬ ‫حسب‬‫فين‬‫ر‬‫الط‬ .‫المساحة‬ ‫لحساب‬ ‫تفاع‬‫ر‬‫اال‬ ‫معدل‬H = (h1+h2)/2 Where H: mean depth h1,h2: depth at start & end points. ‫الموشور‬ ‫معادلة‬ormula methodPrismoidal f-III ‫ء‬‫جز‬ ‫لكل‬ ‫الحجم‬ ‫لحساب‬ ‫التالية‬ ‫الصيغة‬ ‫تستخدم‬ ‫حيث‬ V= L/6 (A1+A2+4Am)-------------------------(3) Where A1, A2: areas at end points Am: mid section area L: length or distance between the adjacent stations (A1, A2) Example: Calculate the quantity of earthworks for the 150 m long cutting, 12m wide at crest and whose side slope is 2.0:1. The centre heights at every 30 m intervals are 0.5m 0.75m, 1.0m, 1.25m, 1.5m. Try solving by all above described methods. Solution: A – average area method Quantity m3 Length M Mean area (m2 ) Area at station bh + sh2 Depth h(m) Station or chained 12x0.5+2x0.5x0.5= 6.50.50 249.3308.3125 12x0.75+2x0.752 = 10.1250.751
  • 8. Estimation, Specifications & Contracts Earthworks Lecture .5 8 Dr. Muthanna Adil Najm Northern Technical University Quantity m3 Length M Mean area (m2 ) Area at station bh + sh2 Depth h(m) Station or chained 361.83012.0625 12x1+2x12 = 1412 481.83016.0625 12x1.25+2x1.252 = 18.121.253 609.383020.3125 12x1.5+2x1.52 = 22.51.54 1702.26Total quantity = B- Mid–Section Method Quantity (m3 ) Distance (m) Area bh+sh2 (m2 )Mean Depth (m) Depth (m) Station 0.50 248.43012(.625)+2(.625)2 =8.2810.625 0.751 360.93012(.875)+2(.875)2 =12.030.875 1.02 480.93016.031.125 1.253 608.43020.281.375
  • 9. Estimation, Specifications & Contracts Earthworks Lecture .5 9 Dr. Muthanna Adil Najm Northern Technical University 1698.6m3 Total =1.54 C- For odd number of stations eq. (3) may be modified to obtain the following formula: V = L/3 (1st Area + last Area + 4 x even areas + 2x odd areas) Using this formula we can obtain the following (see areas in a):- V = L/3 {A1+A5+4 (A2+A4)+2 (A3)} = 30/3 {6.5+2205+4 (10.125+18.125)+2 (14)} V = 1700 m3 Example: The ground levels at various chainage along line of a proposed channel are as under, see the cross-section where some design parameters are shown. The chain is s50m long. 222221220219218217216215Chainage 210.00209.65209.90210.35211.10211.50211.05210.30G.L. (m) 209.15209.20209.25209.30209.35209.40209.45209.50C.L. (m) 227226225224223Chainage 211.30211.60211.20210.90210.25G.L. (m) 208.90208.95209.00209.05209.10C.L. (m)
  • 10. Estimation, Specifications & Contracts Earthworks Lecture .5 10 Dr. Muthanna Adil Najm Northern Technical University Solution: use mid – section formula. Acutting = bh + sh2 = 4h + 0.5 h2 Afilling = bh + sh2 = 2.5 (k-h) + 1 (k-h)2 + 2 (k-h) + 1 (k-h)2 = 4.5 (k-h) + 2 (k-h)2 = 4.5 (4-h) + 2 (4-h)2 (1) (2) (3) (2) - (3) (5) (6) (7) (8) (9) (10) Qty. Filling (m3) Area Filling (m2) K–hmean (m) Qty. cutting (m3) Area Cutting (m2) hmean (m) h (m) C. L. (m) G. L (m) Running Distance (m) Chainage 0.80209.50210.300215 141428.282.82765.521.20 1.60209.45211.0550216 94618.932.154569.121.85 2.10209.40211.50100217 89417.892.07479.59.591.93 1.75209.35211.10150218 126125.222.63296.581.4 1.05209.30210.35200219 170134.033.15188.53.770.85 0.65209.25209.90250220 196639.333.45117.52.350.55 0.45209.20209.65300221 2.5 1:2h 1:2 4.00 K = 4.0 1:1 1:1 2.0 H=k-hH=k-h 1:1
  • 11. Estimation, Specifications & Contracts Earthworks Lecture .5 11 Dr. Muthanna Adil Najm Northern Technical University Qty. Filling (m3) Area Filling (m2) K–hmean (m) Qty. cutting (m3) Area Cutting (m2) hmean (m) h (m) C. L. (m) G. L (m) Running Distance (m) Chainage 187637.523.35140.52.810.65 0.85209.15210.00350222 157531.53.02254.501.00 1.15209.10210.25400223 118723.752.5356.57.131.50 1.85209.05210.90450224 83116.631.97509.510.192.03 2.20209.00211.20500225 60012.01.5763412.682.43 2.65208.95211.60550226 54710.941.47666.513.332.53 2.40208.90211.30600227 147984378.5Total Example: Estimate the cost of excavating and backfilling a trench 1.5 m wide, 1.2 m deep and 150 m long. Assume the team consists of one foreman and a number of laborers to perform the job within five labor days ( each equivalent to 8 working hours). The job involves the following operations: - Loosening earth with a pick ( 0.35m3 /hr-laborer) - Shoveling earth from trench ( 0.475 m3 / hr-lab.) - Backfilling trench ( 1.5 m3 / hr-lab.) Wages : 30000 I.D. /day for the foreman; 15000 I.D. /day for laborer. Solution: V = 1.5 ×1.2 ×150 = 270m3 270 270 270
  • 12. Estimation, Specifications & Contracts Earthworks Lecture .5 12 Dr. Muthanna Adil Najm Northern Technical University No. of (laborer - days) required = ---------- + ---------- + ------------- 8×0.35 8×0.475 8×1. 5 = 96.43 + 71.05 +22.5 = 190 laborer- days no. of laborers required to perform the job within 5 days=190/5= 38 laborers Cost = ( 1×30.000 + 38×15.000) ×5 = 3.000.000 I.D. Cost per 1m3 = 3.000.000 / 270 = 11111 I.D./m3 Cost per 1m length = 3.000.000 / 150 = 20.000 I.D./m. Example: Resolve the previous example using wheel type trenching machine to perform the first two operations . i.e. backfilling by laborers. Assume the average speed of trenching 6.25m 1hr. Average cost of renting & operating the machine is = 35.000 I.D. /hr. Solution : we need the trenching machine to operate for 150m. / 6.25m /hr. = 24hrs. or 24 / 8 = 3 days Cost of machine : 24×3.500 = 840.000 I.D. For backfilling we need 22.5 (say 24) days-laborer no. of laborers to do backfilling within 3 days: 24 / 3 = 8 laborers So we need a team of 8 laborers & one foreman for 3 days. The cost (wages) is: (8×15.000 + 1×30.000)×3 = 450.000 I.D. Total per job = 840.000+450.000=1.290.000 I.D. Cost per m3 = 1.290.000 / 270 = 4780 I.D/m3 Cost per m length = 1.290.000 / 150= 8600 I.D./1m of term
  • 13. Estimation, Specifications & Contracts Earthworks Lecture .5 13 Dr. Muthanna Adil Najm Northern Technical University Example: Estimate the cost of materials required for installing solid sheeting for 100 m of trench 2.1 m deep . use 4 cm × 25cm lumber 2.4 m long for sheeting with two horizontal rows of 10cm × 15 cm wales on each side of the trench for the full length of the trench. Assume that the sheeting can be used 4 times and the wales ten times. Price = 520 000 I.D/m3 . Solution: Vsh. = 0.04×2.4×100×2 = 19.2m3 V Wales = 0.1 ×0.15×100×2×2 = 6m3 Csh = 19.2×520000 / 4 = 2496000 Cw.= 6×520000 / 10 = 312000 I.D. total 2808000 I.D. ‫اي‬ ‫الحالة‬ ‫هذه‬ ‫مالحظة‬Solid Sheeting‫ال‬ ‫في‬ ‫خاصة‬ ‫حالة‬ ‫هي‬‫ا‬Shoring‫ن‬‫تكو‬ ‫حيث‬ ‫اح‬‫و‬‫األل‬.‫متالصقة‬ ‫وليست‬ ‫محددة‬ ‫مسافات‬ ‫على‬
  翻译: