尊敬的 微信汇率:1円 ≈ 0.046078 元 支付宝汇率:1円 ≈ 0.046168元 [退出登录]
SlideShare a Scribd company logo
PresentedBy:
Shah Khushbu K.
Content
Time planning
 Time planning is the process of developing a work programme .
 It implies programming of the chosen work plan on a calendar date basis and
provides the base against which all progress measured.
Time planning process
 In construction all projects are time bound. The project time objectives are
correlated.
 It is the time factor which determines the project cost. Time is the essence of all
construction contracts.
 Time delays attract penalties while early completion can earn rewards.
 However, inspire of one’s best efforts to complete a project on time, changes from
the original estimated project time plan do occur sometimes.
 There may be many reasons, both foreseen and unforeseen, for non-completion of
a project on time. However, the absence of a project time plan almost makes
certain that a project cannot be completed on schedule without incurring extra cost.
 A plan, prepared well before the commencement of construction in a project, cam
be instrumental in formulating directions, coordinating function, setting targets,
forecasting resources, budgeting-cost, controlling performance and motivating
people.
 It is for these reasons that the project planning starts with time planning as the first
Step.
Stages of Time planning:-
1. Project work breakdown
2. Modelling and analyzing networks
3. Scheduling work programs.
Project work breakdown
 This means breaking down the scope of project work into its
constituent sub projects, tasks, work packages and activities.
 It involves splitting of the project works into its manageable constituents
arranged in a hierarchical order till desired level.
 The work breakdown levels are categorized into :
 Sub projects
 Tasks
 Work packages
 Activity
 operations
 These levels depends upon the plan type, the nature, and complexity of the
project and the expected degree of control.
 The work breakdown levels for various types of plans are below the fig.
 It may be noted that the levels classification is a broad concept and, at times,
overlapping of the levels may become unavoidable.
Summary plan
Corporate
management
Sub project
Project master
plan
Project
management
tasks
Task plan
Managerial
levels
Work
packages
Monthly work
programme
Supervisor
levels
activity
Project
plan
hierarchy
Project
control
levels
Work
break
down
levels
Work-breakdown levels
Modelling and analyzing networks
 Project networks analysis is a generic term that cover all network techniques
use for planning, scheduling and controlling of projects.
 The three commonly use techniques in this family are :
1) Critical path method (CPM)
2) Program evolution and review technique (PERT)
3) Precedence network analysis (PNA)
 The common features of this techniques are that they make use of
network model for depicting time plan of the project, apply critical path
concept for determining project duration and identifying critical activity.
 Each technique has a distinct model and its field of application varies.
Network Analysis Procedures
 The modeling and analysis of a network involves the following steps:
 Defining scope of network
 Determining activities
 Developing network logic diagram
 Structuring model
 Incorporating activates duration
 Numbering activity
 Computing critical path
 Validating network
Criteria For Selection Network Techniques
 CPM is best suited for developing sub project or sub network having activities
with single time duration.
 PERT is useful for sub projects involving uncertatinies.it is a probabilistic
approach of three times and used for assenting activity duration.
 PNA is a most commonly used technique for time planning of construction sub
projects and projects.
Scheduling work programs
Object of scheduling:-
 Scheduling means putting the plan on calendar basis.
 A project network shows the sequence and interdependences of activities, their
time durations and their earliest and latest completion time but this need to be
scheduled to determining commencement and terminations dates of each
activity, using optimum resources or working within resource constraints.
Scheduling Procedure:-
 Scheduling methodology varies with the planning technique and the nature of task.
 Simple projects can be schedule using bar chart methodology, Line of Balance
technique is widely accepted for scheduling repetitive works projects.
 Network scheduling methodology is suitable for all types of projects. There are
many other scheduling s ultimately schedules are best presented in the bar chart
form fir case of comprehension and communication.
 The scheduling procedures, depending upon the type of project can be broadly
divided into two categories:
1. Scheduling non repetitive network based projects
2. Scheduling repetitive project using line of balance technique
Procedure for scheduling Network based plan:-
 Outline scheduling constraints
 Design scheduling calendar
 List activities in order of sensitivity
 Draw earliest start time schedule
 Determines resource optimisation criteria
 Schedule critical activities
 Schedule non-critical activities
 Validate time objectives
 Schedule other resources
 Scheduling within resources constraints
 Scheduling repetitive works projects.
Work scheduling methodology:-
 Bar chart
 Network plan
 Line of Balance
Purpose of work scheduling:-
 It simplifies the project plan.
 It validates the time objectives.
 It optimizes the resources employed.
 It forecasting the input resources, and predicts the output.
 It evaluates the implications of scheduling constraints.
Resource Planning
 Construction Project refers to a high stake endeavor aiming at time bound
predetermined performance objective. Unless matching resources are planned and
procured, no activity can be executed according to a prefixed time schedule.
 Project managers must take complex decisions under different scheduling needs
(such as smooth resource utilization profiles and resource constraints) and under
conditions of uncertainty that sometimes extend beyond task durations.
 The present study deals with resource scheduling for a fast track project with
constrained durations.
 The study has been carried out in two phases. In the first phase, with the aid of
PRIMAVERA software project schedule for various activities for the construction
of a commercial building was prepared. Subsequently, requirements of resources
were attributed to the activities based on Standard Schedule Rates (CPWD). The
requisite data has been collected from the detailed drawings and prevailing site
conditions.
 In the second phase, a Resource Constrained Analysis was carried out by
Resource Levelling for various activities by decreasing resources with increased
duration to study the time-cost implications.
Resource planning process
Forecasting Input and Output:-
 A forecast is a predication of what is anticipated in future. It represents current
thinking about the future outcome. It is based on various assumptions and
judgments.
 The assumptions made at the time of forecasting are based on the currently
available information which may or may not hold good in future.
 The input and output forecast includes the data wise requirements of project
manpower, major materials, costly equipment, production costs, sales or earned
value of work done and the expected income.
 Resource forecasts are generally depicted graphically with time represented along
abscissa and the resources along the ordinate axis to determine the date wise and
cumulative requirements pattern.
 The resulting graphical pattern for most of the cumulative forecast is that of ‘S’
shaped curve.
 Inputs and output forecast aids in conceptualization of the project. It indicates the
quantum of resources required for executing is project and the output expected.
 The pattern of input resources form the base for evaluating such needs as
workers accommodation materials storage, equipment work load and project
funding pattern.
Four M for Resource planning
Manpower:
 Manpower is one of the main factors in the successful execution of projects. No
amount of automation or machinery can replace the manpower needed for
completion of a project.
 It cannot be treated like a commodity and cannot be dismissed or re-employed at
will. Technical hands once employed are normally continued till their requirement
ceases.
 The idle labour time is paid for and the strikes and breakdown of work are kept in
view by the management .The task these affect labour productivity.
 The non availability of suitable skilled labour is generally a limiting factor. The
labour turnover, sickness and absenteeism further aggravate the problem.
 The working hours, overtime and other incentives have to be considered while
deciding the manpower schedule. The management-labour agreements and the
governing labour laws considerably, affect labour employment.
 A schedule cannot take care off all the variables but these can be reduced
considerably, by working out a uniform trade category-wise manpower
requirements schedule, or by fixing a pattern depending upon the manpower
availability and working conditions.
Machinery:
 The availability of machinery is normally, a limiting factor. For Example, in an
activity involving excavation, the schedule may specify a requirement of two dozers,
but one may actually be availability or allotted.
 This would entail a recasting of the whole schedule. In such circumstances, various
alternatives like delay-penalty costs, cost of time crashing and the cost of
procurement or hiring of additional machinery have to be weighed before making
the final decision.
 The aim of machinery-and equipment scheduling should be to find out the minimum
duration schedule in which The employment of equipment and machinery is
systematically and uniformly distributed based on its availability or allotment.
Material:
 No project can ever be started without materials. Construction materials are
increasingly becoming scarce, and their procurement is a time consuming process.
 One method could be, to stock materials well before they are required so as to
ensure timely supply, but the stock inventory costs money. Generally the inventory
should be zero before the commencement and after the completion of the project.
 To go a step forward, this rule should be made applicable to each activity. But for
certain materials, the procurements action can be based on the guiding principle that
materials inventory must be kept to the minimum. In case of materials in short,
supply the schedule may have to be based on availability constraints.
Money:
 Money is the core of all the projects activities. The project management aims at
economics and the contractor works for earning profit. The proper management of
money results in savings while its improper use proves ruinous.
 In the LST schedule, the large production costs gets staggered over a longer period
of time, thus reducing investments. This LST schedule may prove attractive to a
builder because of least investments. Therefore, a builder’s schedule, would
generally aim to execute those jobs earlier which are more profitable, involve least
investment and benefits his cash flow.
 On the other hand, the client would aim at phasing of construction for early
completion. The network schedule must balance these conflicting requirements.
 It is used to assign the available resources in an economic way. It is
part of resource management. In project management, resource
allocation is the scheduling of activities and the resources required by
those activities while taking into consideration both the resource
availability and the project time.
Resource Allocation
Resource allocation graph algorithm
 This technique is used to maintain the utilization of project resources
at particular limits. For example, if Resource ABC is assigned to a
project activity, when the project is being executed in a functional
organization and the resource is available for only 5 hours in a day.
Then, resource smoothing technique will be employed to allocate the
resources according to the specific limits.
Resource Smoothening
 Resource levelling is a technique in project management that overlooks resource
allocation and resolves possible conflict arising from over-allocation. When
project managers undertake a project, they need to plan their resources
accordingly.
 This will benefit the organization without having to face conflicts and not being
able to deliver on time. Resource levelling is considered one of the key
elements to resource management in the organization.
 An organization starts to face problems if resources are not allocated properly
i.e., some resource may be over-allocated whilst others will be under-allocated.
Both will bring about a financial risk to the organization.
Resource Levelling
Resource levelling Techniques
 Critical path is a common type of technique used by project managers when it
comes to resource levelling. The critical path represents for both the longest and
shortest time duration paths in the network diagram to complete the project.
 However, apart from the widely used critical path concept, project managers use
fast tracking and crashing if things get out of hand.
o Fast tracking: This performs critical path tasks. This buys time. The
prominent feature of this technique is that although the work is completed for
the moment, possibility of rework is higher.
o Crashing: This refers to assigning resources in addition to existing resources
to get work done faster, associated with additional cost such as labor,
equipment, etc.
 It is a software that will help us optimize our day to day operations.
 It give us access to all our data, including: expenses, project, time tracking,
contract, customers.
 It also helps with the organization and management of our company; while
facility control, it gives us the ability tom accesses our project at any time
from any were on any devices.
Management Software
List of Management Software Needs of management software
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE

More Related Content

What's hot

Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
Aditi Garg
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1
Ahmad Basim Hamza
 
CPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryCPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction Indistry
Michael Pink
 
construction project planing
 construction project planing construction project planing
construction project planing
SANJEEV Wazir
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
Vîñõđ Kůmåř
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
mohamed elashri
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
Baker Khader Abdallah, PMP
 
6 time PMBOK
6 time PMBOK6 time PMBOK
6 time PMBOK
Waseem Siddique
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
rielaantonio
 
project time management
 project time management project time management
project time management
Hira Atiq
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Tùng Trần Thanh
 
Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...
ijtsrd
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling
Reema
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
SHAZEBALIKHAN1
 
06 project time management
06  project time management06  project time management
06 project time management
Ala Ibrahim
 
Project time management
Project time managementProject time management
Project time management
Jack Pumpuni Frimpong-Manso
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
Golam Bitonsir
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
dyaksa hanindito
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a Project
Meryem Yıldız
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
Procept Associates
 

What's hot (20)

Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1
 
CPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryCPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction Indistry
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
6 time PMBOK
6 time PMBOK6 time PMBOK
6 time PMBOK
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
project time management
 project time management project time management
project time management
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
 
Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
06 project time management
06  project time management06  project time management
06 project time management
 
Project time management
Project time managementProject time management
Project time management
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a Project
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 

Similar to TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE

Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
Golam Bitonsir
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
Golam Bitonsir
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
behailuzerihun1
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
behailuzerihun1
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdf
Surashmie Kaalmegh
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & Techniques
SHAZEBALIKHAN1
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects
Somashekar S.M
 
Network Analysis- CPM ppt..pptx
Network Analysis- CPM  ppt..pptxNetwork Analysis- CPM  ppt..pptx
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
guestc8140fe
 
Good scheduling practice
Good scheduling practiceGood scheduling practice
Good scheduling practice
krunalchem
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3
POOJA UDAYAN
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.ppt
DejeneTsegaye6
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
Lii Van
 
Stopping the insanity
Stopping the insanityStopping the insanity
Stopping the insanity
Renzo Streglio
 
Project typed
Project typedProject typed
Project typed
Rahul
 
Ch23-Software Engineering 9
Ch23-Software Engineering 9Ch23-Software Engineering 9
Ch23-Software Engineering 9
Ian Sommerville
 
Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdf
ssuserc0e4e0
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
MuhammadAmanAzam
 
SE18_Lec 13_ Project Planning
SE18_Lec 13_ Project PlanningSE18_Lec 13_ Project Planning
SE18_Lec 13_ Project Planning
Amr E. Mohamed
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
srinivas2036
 

Similar to TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE (20)

Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdf
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & Techniques
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects
 
Network Analysis- CPM ppt..pptx
Network Analysis- CPM  ppt..pptxNetwork Analysis- CPM  ppt..pptx
Network Analysis- CPM ppt..pptx
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
 
Good scheduling practice
Good scheduling practiceGood scheduling practice
Good scheduling practice
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.ppt
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
Stopping the insanity
Stopping the insanityStopping the insanity
Stopping the insanity
 
Project typed
Project typedProject typed
Project typed
 
Ch23-Software Engineering 9
Ch23-Software Engineering 9Ch23-Software Engineering 9
Ch23-Software Engineering 9
 
Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdf
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
 
SE18_Lec 13_ Project Planning
SE18_Lec 13_ Project PlanningSE18_Lec 13_ Project Planning
SE18_Lec 13_ Project Planning
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 

More from KHUSHBU SHAH

PLANE TABLE SURVEY
PLANE TABLE SURVEYPLANE TABLE SURVEY
PLANE TABLE SURVEY
KHUSHBU SHAH
 
DEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKDEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORK
KHUSHBU SHAH
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge Engineering
KHUSHBU SHAH
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway track
KHUSHBU SHAH
 
Chapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yardsChapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yards
KHUSHBU SHAH
 
Chapter 5 Introduction to railway
Chapter 5 Introduction to railwayChapter 5 Introduction to railway
Chapter 5 Introduction to railway
KHUSHBU SHAH
 
Chapter 4 Drainge and maintenance of road
Chapter 4 Drainge and maintenance of roadChapter 4 Drainge and maintenance of road
Chapter 4 Drainge and maintenance of road
KHUSHBU SHAH
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometrics
KHUSHBU SHAH
 
Chapter 1 Introduction to road
Chapter 1 Introduction to roadChapter 1 Introduction to road
Chapter 1 Introduction to road
KHUSHBU SHAH
 
Equipment management
Equipment managementEquipment management
Equipment management
KHUSHBU SHAH
 
Labour management
Labour managementLabour management
Labour management
KHUSHBU SHAH
 
Material management
Material managementMaterial management
Material management
KHUSHBU SHAH
 
Chapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipmentsChapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipments
KHUSHBU SHAH
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
KHUSHBU SHAH
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavations
KHUSHBU SHAH
 
Chapter 3 caisson
Chapter 3 caissonChapter 3 caisson
Chapter 3 caisson
KHUSHBU SHAH
 
Chapter 2 coffer-dam
Chapter 2 coffer-damChapter 2 coffer-dam
Chapter 2 coffer-dam
KHUSHBU SHAH
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
KHUSHBU SHAH
 
Chapter 13 green building
Chapter 13 green buildingChapter 13 green building
Chapter 13 green building
KHUSHBU SHAH
 
Chapter 12 special treatments
Chapter 12 special treatmentsChapter 12 special treatments
Chapter 12 special treatments
KHUSHBU SHAH
 

More from KHUSHBU SHAH (20)

PLANE TABLE SURVEY
PLANE TABLE SURVEYPLANE TABLE SURVEY
PLANE TABLE SURVEY
 
DEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKDEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORK
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge Engineering
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway track
 
Chapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yardsChapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yards
 
Chapter 5 Introduction to railway
Chapter 5 Introduction to railwayChapter 5 Introduction to railway
Chapter 5 Introduction to railway
 
Chapter 4 Drainge and maintenance of road
Chapter 4 Drainge and maintenance of roadChapter 4 Drainge and maintenance of road
Chapter 4 Drainge and maintenance of road
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometrics
 
Chapter 1 Introduction to road
Chapter 1 Introduction to roadChapter 1 Introduction to road
Chapter 1 Introduction to road
 
Equipment management
Equipment managementEquipment management
Equipment management
 
Labour management
Labour managementLabour management
Labour management
 
Material management
Material managementMaterial management
Material management
 
Chapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipmentsChapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipments
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavations
 
Chapter 3 caisson
Chapter 3 caissonChapter 3 caisson
Chapter 3 caisson
 
Chapter 2 coffer-dam
Chapter 2 coffer-damChapter 2 coffer-dam
Chapter 2 coffer-dam
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
 
Chapter 13 green building
Chapter 13 green buildingChapter 13 green building
Chapter 13 green building
 
Chapter 12 special treatments
Chapter 12 special treatmentsChapter 12 special treatments
Chapter 12 special treatments
 

Recently uploaded

Basic principle and types Static Relays ppt
Basic principle and  types  Static Relays pptBasic principle and  types  Static Relays ppt
Basic principle and types Static Relays ppt
Sri Ramakrishna Institute of Technology
 
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
sonamrawat5631
 
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call GirlCall Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
sapna sharmap11
 
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
DharmaBanothu
 
anatomy of space vehicle and aerospace structures.pptx
anatomy of space vehicle and aerospace structures.pptxanatomy of space vehicle and aerospace structures.pptx
anatomy of space vehicle and aerospace structures.pptx
ssusercf1619
 
🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...
🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...
🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...
AK47
 
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
AK47
 
High Profile Call Girls Ahmedabad 🔥 7737669865 🔥 Real Fun With Sexual Girl Av...
High Profile Call Girls Ahmedabad 🔥 7737669865 🔥 Real Fun With Sexual Girl Av...High Profile Call Girls Ahmedabad 🔥 7737669865 🔥 Real Fun With Sexual Girl Av...
High Profile Call Girls Ahmedabad 🔥 7737669865 🔥 Real Fun With Sexual Girl Av...
Ak47 Ak47
 
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptxMODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
NaveenNaveen726446
 
Covid Management System Project Report.pdf
Covid Management System Project Report.pdfCovid Management System Project Report.pdf
Covid Management System Project Report.pdf
Kamal Acharya
 
💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...
💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...
💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...
rupa singh
 
Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...
Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...
Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...
Banerescorts
 
SPICE PARK JUL2024 ( 6,866 SPICE Models )
SPICE PARK JUL2024 ( 6,866 SPICE Models )SPICE PARK JUL2024 ( 6,866 SPICE Models )
SPICE PARK JUL2024 ( 6,866 SPICE Models )
Tsuyoshi Horigome
 
❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...
❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...
❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...
hotchicksescort
 
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
sexytaniya455
 
College Call Girls Kolkata 🔥 7014168258 🔥 Real Fun With Sexual Girl Available...
College Call Girls Kolkata 🔥 7014168258 🔥 Real Fun With Sexual Girl Available...College Call Girls Kolkata 🔥 7014168258 🔥 Real Fun With Sexual Girl Available...
College Call Girls Kolkata 🔥 7014168258 🔥 Real Fun With Sexual Girl Available...
Ak47
 
一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理
一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理
一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理
nonods
 
Call Girls In Lucknow 🔥 +91-7014168258🔥High Profile Call Girl Lucknow
Call Girls In Lucknow 🔥 +91-7014168258🔥High Profile Call Girl LucknowCall Girls In Lucknow 🔥 +91-7014168258🔥High Profile Call Girl Lucknow
Call Girls In Lucknow 🔥 +91-7014168258🔥High Profile Call Girl Lucknow
yogita singh$A17
 
Cricket management system ptoject report.pdf
Cricket management system ptoject report.pdfCricket management system ptoject report.pdf
Cricket management system ptoject report.pdf
Kamal Acharya
 
Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine
 

Recently uploaded (20)

Basic principle and types Static Relays ppt
Basic principle and  types  Static Relays pptBasic principle and  types  Static Relays ppt
Basic principle and types Static Relays ppt
 
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
 
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call GirlCall Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
 
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
An In-Depth Exploration of Natural Language Processing: Evolution, Applicatio...
 
anatomy of space vehicle and aerospace structures.pptx
anatomy of space vehicle and aerospace structures.pptxanatomy of space vehicle and aerospace structures.pptx
anatomy of space vehicle and aerospace structures.pptx
 
🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...
🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...
🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...
 
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
 
High Profile Call Girls Ahmedabad 🔥 7737669865 🔥 Real Fun With Sexual Girl Av...
High Profile Call Girls Ahmedabad 🔥 7737669865 🔥 Real Fun With Sexual Girl Av...High Profile Call Girls Ahmedabad 🔥 7737669865 🔥 Real Fun With Sexual Girl Av...
High Profile Call Girls Ahmedabad 🔥 7737669865 🔥 Real Fun With Sexual Girl Av...
 
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptxMODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
MODULE 5 BIOLOGY FOR ENGINEERS TRENDS IN BIO ENGINEERING.pptx
 
Covid Management System Project Report.pdf
Covid Management System Project Report.pdfCovid Management System Project Report.pdf
Covid Management System Project Report.pdf
 
💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...
💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...
💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...
 
Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...
Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...
Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...
 
SPICE PARK JUL2024 ( 6,866 SPICE Models )
SPICE PARK JUL2024 ( 6,866 SPICE Models )SPICE PARK JUL2024 ( 6,866 SPICE Models )
SPICE PARK JUL2024 ( 6,866 SPICE Models )
 
❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...
❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...
❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...
 
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
 
College Call Girls Kolkata 🔥 7014168258 🔥 Real Fun With Sexual Girl Available...
College Call Girls Kolkata 🔥 7014168258 🔥 Real Fun With Sexual Girl Available...College Call Girls Kolkata 🔥 7014168258 🔥 Real Fun With Sexual Girl Available...
College Call Girls Kolkata 🔥 7014168258 🔥 Real Fun With Sexual Girl Available...
 
一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理
一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理
一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理
 
Call Girls In Lucknow 🔥 +91-7014168258🔥High Profile Call Girl Lucknow
Call Girls In Lucknow 🔥 +91-7014168258🔥High Profile Call Girl LucknowCall Girls In Lucknow 🔥 +91-7014168258🔥High Profile Call Girl Lucknow
Call Girls In Lucknow 🔥 +91-7014168258🔥High Profile Call Girl Lucknow
 
Cricket management system ptoject report.pdf
Cricket management system ptoject report.pdfCricket management system ptoject report.pdf
Cricket management system ptoject report.pdf
 
Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024Better Builder Magazine, Issue 49 / Spring 2024
Better Builder Magazine, Issue 49 / Spring 2024
 

TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE

  • 3. Time planning  Time planning is the process of developing a work programme .  It implies programming of the chosen work plan on a calendar date basis and provides the base against which all progress measured.
  • 4. Time planning process  In construction all projects are time bound. The project time objectives are correlated.  It is the time factor which determines the project cost. Time is the essence of all construction contracts.  Time delays attract penalties while early completion can earn rewards.  However, inspire of one’s best efforts to complete a project on time, changes from the original estimated project time plan do occur sometimes.
  • 5.  There may be many reasons, both foreseen and unforeseen, for non-completion of a project on time. However, the absence of a project time plan almost makes certain that a project cannot be completed on schedule without incurring extra cost.  A plan, prepared well before the commencement of construction in a project, cam be instrumental in formulating directions, coordinating function, setting targets, forecasting resources, budgeting-cost, controlling performance and motivating people.  It is for these reasons that the project planning starts with time planning as the first Step.
  • 6. Stages of Time planning:- 1. Project work breakdown 2. Modelling and analyzing networks 3. Scheduling work programs.
  • 7. Project work breakdown  This means breaking down the scope of project work into its constituent sub projects, tasks, work packages and activities.
  • 8.  It involves splitting of the project works into its manageable constituents arranged in a hierarchical order till desired level.  The work breakdown levels are categorized into :  Sub projects  Tasks  Work packages  Activity  operations
  • 9.  These levels depends upon the plan type, the nature, and complexity of the project and the expected degree of control.  The work breakdown levels for various types of plans are below the fig.  It may be noted that the levels classification is a broad concept and, at times, overlapping of the levels may become unavoidable.
  • 10. Summary plan Corporate management Sub project Project master plan Project management tasks Task plan Managerial levels Work packages Monthly work programme Supervisor levels activity Project plan hierarchy Project control levels Work break down levels Work-breakdown levels
  • 11. Modelling and analyzing networks  Project networks analysis is a generic term that cover all network techniques use for planning, scheduling and controlling of projects.  The three commonly use techniques in this family are : 1) Critical path method (CPM) 2) Program evolution and review technique (PERT) 3) Precedence network analysis (PNA)
  • 12.  The common features of this techniques are that they make use of network model for depicting time plan of the project, apply critical path concept for determining project duration and identifying critical activity.  Each technique has a distinct model and its field of application varies.
  • 13. Network Analysis Procedures  The modeling and analysis of a network involves the following steps:  Defining scope of network  Determining activities  Developing network logic diagram  Structuring model  Incorporating activates duration  Numbering activity  Computing critical path  Validating network
  • 14. Criteria For Selection Network Techniques  CPM is best suited for developing sub project or sub network having activities with single time duration.  PERT is useful for sub projects involving uncertatinies.it is a probabilistic approach of three times and used for assenting activity duration.  PNA is a most commonly used technique for time planning of construction sub projects and projects.
  • 15. Scheduling work programs Object of scheduling:-  Scheduling means putting the plan on calendar basis.  A project network shows the sequence and interdependences of activities, their time durations and their earliest and latest completion time but this need to be scheduled to determining commencement and terminations dates of each activity, using optimum resources or working within resource constraints.
  • 16. Scheduling Procedure:-  Scheduling methodology varies with the planning technique and the nature of task.  Simple projects can be schedule using bar chart methodology, Line of Balance technique is widely accepted for scheduling repetitive works projects.  Network scheduling methodology is suitable for all types of projects. There are many other scheduling s ultimately schedules are best presented in the bar chart form fir case of comprehension and communication.  The scheduling procedures, depending upon the type of project can be broadly divided into two categories: 1. Scheduling non repetitive network based projects 2. Scheduling repetitive project using line of balance technique
  • 17. Procedure for scheduling Network based plan:-  Outline scheduling constraints  Design scheduling calendar  List activities in order of sensitivity  Draw earliest start time schedule  Determines resource optimisation criteria  Schedule critical activities  Schedule non-critical activities  Validate time objectives  Schedule other resources  Scheduling within resources constraints  Scheduling repetitive works projects.
  • 18. Work scheduling methodology:-  Bar chart  Network plan  Line of Balance
  • 19. Purpose of work scheduling:-  It simplifies the project plan.  It validates the time objectives.  It optimizes the resources employed.  It forecasting the input resources, and predicts the output.  It evaluates the implications of scheduling constraints.
  • 20. Resource Planning  Construction Project refers to a high stake endeavor aiming at time bound predetermined performance objective. Unless matching resources are planned and procured, no activity can be executed according to a prefixed time schedule.  Project managers must take complex decisions under different scheduling needs (such as smooth resource utilization profiles and resource constraints) and under conditions of uncertainty that sometimes extend beyond task durations.  The present study deals with resource scheduling for a fast track project with constrained durations.
  • 21.  The study has been carried out in two phases. In the first phase, with the aid of PRIMAVERA software project schedule for various activities for the construction of a commercial building was prepared. Subsequently, requirements of resources were attributed to the activities based on Standard Schedule Rates (CPWD). The requisite data has been collected from the detailed drawings and prevailing site conditions.  In the second phase, a Resource Constrained Analysis was carried out by Resource Levelling for various activities by decreasing resources with increased duration to study the time-cost implications.
  • 22. Resource planning process Forecasting Input and Output:-  A forecast is a predication of what is anticipated in future. It represents current thinking about the future outcome. It is based on various assumptions and judgments.  The assumptions made at the time of forecasting are based on the currently available information which may or may not hold good in future.  The input and output forecast includes the data wise requirements of project manpower, major materials, costly equipment, production costs, sales or earned value of work done and the expected income.
  • 23.  Resource forecasts are generally depicted graphically with time represented along abscissa and the resources along the ordinate axis to determine the date wise and cumulative requirements pattern.  The resulting graphical pattern for most of the cumulative forecast is that of ‘S’ shaped curve.  Inputs and output forecast aids in conceptualization of the project. It indicates the quantum of resources required for executing is project and the output expected.  The pattern of input resources form the base for evaluating such needs as workers accommodation materials storage, equipment work load and project funding pattern.
  • 24. Four M for Resource planning Manpower:  Manpower is one of the main factors in the successful execution of projects. No amount of automation or machinery can replace the manpower needed for completion of a project.  It cannot be treated like a commodity and cannot be dismissed or re-employed at will. Technical hands once employed are normally continued till their requirement ceases.  The idle labour time is paid for and the strikes and breakdown of work are kept in view by the management .The task these affect labour productivity.
  • 25.  The non availability of suitable skilled labour is generally a limiting factor. The labour turnover, sickness and absenteeism further aggravate the problem.  The working hours, overtime and other incentives have to be considered while deciding the manpower schedule. The management-labour agreements and the governing labour laws considerably, affect labour employment.  A schedule cannot take care off all the variables but these can be reduced considerably, by working out a uniform trade category-wise manpower requirements schedule, or by fixing a pattern depending upon the manpower availability and working conditions.
  • 26. Machinery:  The availability of machinery is normally, a limiting factor. For Example, in an activity involving excavation, the schedule may specify a requirement of two dozers, but one may actually be availability or allotted.  This would entail a recasting of the whole schedule. In such circumstances, various alternatives like delay-penalty costs, cost of time crashing and the cost of procurement or hiring of additional machinery have to be weighed before making the final decision.  The aim of machinery-and equipment scheduling should be to find out the minimum duration schedule in which The employment of equipment and machinery is systematically and uniformly distributed based on its availability or allotment.
  • 27. Material:  No project can ever be started without materials. Construction materials are increasingly becoming scarce, and their procurement is a time consuming process.  One method could be, to stock materials well before they are required so as to ensure timely supply, but the stock inventory costs money. Generally the inventory should be zero before the commencement and after the completion of the project.  To go a step forward, this rule should be made applicable to each activity. But for certain materials, the procurements action can be based on the guiding principle that materials inventory must be kept to the minimum. In case of materials in short, supply the schedule may have to be based on availability constraints.
  • 28. Money:  Money is the core of all the projects activities. The project management aims at economics and the contractor works for earning profit. The proper management of money results in savings while its improper use proves ruinous.  In the LST schedule, the large production costs gets staggered over a longer period of time, thus reducing investments. This LST schedule may prove attractive to a builder because of least investments. Therefore, a builder’s schedule, would generally aim to execute those jobs earlier which are more profitable, involve least investment and benefits his cash flow.  On the other hand, the client would aim at phasing of construction for early completion. The network schedule must balance these conflicting requirements.
  • 29.  It is used to assign the available resources in an economic way. It is part of resource management. In project management, resource allocation is the scheduling of activities and the resources required by those activities while taking into consideration both the resource availability and the project time. Resource Allocation
  • 31.  This technique is used to maintain the utilization of project resources at particular limits. For example, if Resource ABC is assigned to a project activity, when the project is being executed in a functional organization and the resource is available for only 5 hours in a day. Then, resource smoothing technique will be employed to allocate the resources according to the specific limits. Resource Smoothening
  • 32.  Resource levelling is a technique in project management that overlooks resource allocation and resolves possible conflict arising from over-allocation. When project managers undertake a project, they need to plan their resources accordingly.  This will benefit the organization without having to face conflicts and not being able to deliver on time. Resource levelling is considered one of the key elements to resource management in the organization.  An organization starts to face problems if resources are not allocated properly i.e., some resource may be over-allocated whilst others will be under-allocated. Both will bring about a financial risk to the organization. Resource Levelling
  • 33. Resource levelling Techniques  Critical path is a common type of technique used by project managers when it comes to resource levelling. The critical path represents for both the longest and shortest time duration paths in the network diagram to complete the project.  However, apart from the widely used critical path concept, project managers use fast tracking and crashing if things get out of hand. o Fast tracking: This performs critical path tasks. This buys time. The prominent feature of this technique is that although the work is completed for the moment, possibility of rework is higher. o Crashing: This refers to assigning resources in addition to existing resources to get work done faster, associated with additional cost such as labor, equipment, etc.
  • 34.
  • 35.  It is a software that will help us optimize our day to day operations.  It give us access to all our data, including: expenses, project, time tracking, contract, customers.  It also helps with the organization and management of our company; while facility control, it gives us the ability tom accesses our project at any time from any were on any devices. Management Software
  • 36. List of Management Software Needs of management software
  翻译: