尊敬的 微信汇率:1円 ≈ 0.046089 元 支付宝汇率:1円 ≈ 0.04618元 [退出登录]
SlideShare a Scribd company logo
Engineering Mangement




Program Evaluation Review
     Technique (PERT)
         Prepared by :
   Anas Tomeh               Fira Eid

         Prepared for :
         Dr. Reema Nassar
Objective of the presentation


• To understand the formula , the use and
  the benefits of Program , Evaluation ,and
  Review Technic (PERT) analysis .
What is the PERT ?



Program (Project) Evaluation and Review Technique (PERT): is
a project management tool used to schedule, organize, and
coordinate tasks within a project. It is basically a method to
analyse the tasks involved in completing a given
project, especially the time needed to complete each task, and
to identify the minimum time needed to complete the total
project.
When we use PERT ?



 • PERT is used when activity times are uncertain.
    – Determine the duration of the project .
    – Decision making under risk (“P” for probabilistic)
Determine the duration of the project


  • OPTIMISTIC TIME: Best time if everything goes perfectly
  • REALISTIC TIME: Most likely time
  • PESSIMISTIC TIME: A worst-case situation
                       B + 4M + P
    Expected Time = -------------------
                                6
Determine the duration of the project
  • Example:
  For excavation activity let :
  B = 12 days
  M = 18 days
  P = 60
  What is the expected time for this activity?

  Sol :


                           12 + 4(18) + 60
          Expected Time = -------------------------
                                 6
                        = 24 days
Determine the duration of the project
        Activity   Predecessor   Optimistic   Normal   Pessimistic       Te
                                    (B)        (m)        (P)        (B+4m+P)/6



          A           ---           2           4          6          4.00
          B           ---           3           5          9          5.33
          C            A            4           5          7          5.17
          D            A            4           6         10          6.33
          E          B, C           4           5          7          5.17
          F            D            3           4          8          4.50
          G            E            3           5          8          5.17
    f
Determine the duration of the project

                     D           F




           A




                     C
  Start                                     Finish




           B                 E          G
Determine the duration of the project
                        D                 F
                      D:6.33           D:4.5
                       ES:4           ES:10.33
                     EF:10.33         EF:14.83
             A
            D:4
            ES:0
            EF:4

                        C
                     D:5.17                                  Finish
   Start              ES:4
   ES:0                                                       D:0
                     EF:9.17                                ES:19.51
   EF:0
                                                            EF:19.51

              B                     E               G
           D:5.33                D:5.17           D:5.17
            ES:0                 ES:9.17         ES:14.34
           EF:5.33              EF:14.34         EF:19.51
Determine the duration of the project
                        D                     F
                     D:6.33                D:4.5
                      ES:4                ES:10.33
                    EF:10.33              EF:14.83
                     LS:8.68              LS:15.01
                    LF:15.01              LF:19.51
            A
           D:4
           ES:0
           EF:4
           LS:0
           LF:4
                       C
                    D:5.17
  Start                                                          Finish
                     ES:4
   D:0                                                             D:0
                    EF:9.17
  ES:0                                                          ES:19.51
                     LS:4
  EF:0                                                          EF:19.51
                    LF:9.17
  LS:0                                                          LS:19.51
  LF:0                                                          LF:19.51
             B                     E                    G
          D:5.33                D:5.17                D:5.17
           ES:0                 ES:9.17              ES:14.34
          EF:5.33              EF:14.34              EF:19.51
          LS:3.84               LS:9.17              LS:14.34
          LF:9.17              LF:14.34              LF:19.51
Determine the duration of the project

              Critical Path

   Critical Path: A-C-E-G
   • Path A-D-F           = 14.83 work days
   • Path A-C-E-G = 19.51 work days
   • Path B-E-G           = 15.67 work days
Determine the duration of the project

               Critical Path
           Activity     LF-EF         Total
              A           4-4           0

              B        9.17 – 5.33    3.84

              C        9.17 – 9.17      0

              D       15.01 – 10.33   4.68

              E       14.34 – 14.34     0

              F       19.51 – 14.83   4.68

              G       19.51 – 19.51     0
Assessing Risks


   • Risk is a measure of the probability (and
     consequences) of not completing a project
     on time.
   • A major responsibility of the project
     manager at the start of a project is to
     develop a risk-management plan.
   • A Risk-Management Plan identifies the
     key risks to a project’s success and
     prescribes ways to circumvent them.
Assessing Risks


  • With PERT’s three time-estimates, we get a mean
    (average) time and a variance for each activity and each
    path.
     – We also get a project mean time and variance.
  • In order to compute probabilities (assuming a normal
    distribution) we need the activity means and variances.
     – Most computer packages calculate this for you.
Assessing Risks
Path        Time (wks)                12
                                         I 27
                                      48 1563
A-I-K33         33
A-F-K28         28
                             A                                  K
A-C-G-J-K       67       0       12   12 F 22   Latest     63   69     Latest
B-D-H-J-K       69       2 1214       53 1063    start     63 6 69
                                                                       finish
B-E-J-K         43                               time                   time
                                         C
                                      12   22    22 G 57
                 Start                                                 Finish
                                      14 1024    24   59
                                                    35



                         0
                             B9       9
                                         D19     19
                                                    H 59   59
                                                                J 63
                         0 9 9        9 1019     19 4059   59 4 63




                                       9 E 33
                                      35 2459
Assessing Risks


• What is the probability that our sample project
  will finish in 69 weeks as scheduled?
   100%     (Why?)
   – Because we used CPM!
      • (This means we were certain of all of our activity times.)
   – If we weren’t certain, we should have used PERT
      • You can’t do risk analysis if you use CPM
Assessing Risks

  • Calculate standard deviation
     – Standard deviation- average deviation from the
       estimated time
        • SD=(TP-T0)/6
     – higher the SD is the greater amount of uncertainty
       exists

  • Calculate variance
     – reflects the spread of a value over a normal
       distribution
        • V=SD2
     – a large variance indicates great uncertainty, a small
       variance indicates a more accurate estimate
Assessing Risks


             What is the Probability of it taking 72 weeks?

  Critical       Critical Path = B - D - H - J – K = 69 weeks
  Path           T = 72 weeks        C = 69 weeks
  Varianc                                                  T–C
 e
  2 =  (variances of activities along critical path) =
                                                      z
                                                            2
 2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89


        z=    72 – 69
               11.89         Look up Z value in normal distribution table
        Z = 0.870                         Pz = .8078 or 80.78%
                                       (Probability of it taking 72 weeks)
Assessing Risks




   Look up the Z value (0.870) in the table of normal distribution.
   .8078 or 80.78% is the probability of the project taking up to 72 wks.
   Going over 72 weeks would be 100 – 80.78 = 19.22%
Assessing Risks



                                               Normal distribution:
              Length of critical               Mean = 69 weeks;
              path is 69 weeks                  = 3.45 weeks


       Probability of taking
       72 weeks is 0.8078                              Probability of
       or 80.78%                                      exceeding 72 weeks
                                                      is 0.1922 or 19.22%




                                     69   72
                           Project duration (weeks)
Assessing Risks

  • Assume a PERT project critical path takes 40 days, and that the
    variance of this path is 2.147
      – You wish to know the probability of the project going over 42 days.
  • Compute the standard deviation of the critical path. (Take the square
    root of the variance of 2.147) Std. Dev. = 1.465
      – POM/QM software gives you the variance of the critical path.
  • Compute the Z value: Z = (absolute time difference) / Std. Dev.
            In this example, Z = (42 days - 40 days) / 1.465 = 1.365
  • Look up the Z value of 1.365 in a Normal Distribution table to get the
    probability of the project taking 42 days.
  • Subtract it from 100% to get the probability of going over 42.
Assessing Risks




   Look up the Z value (1.365) in the table of normal distribution.
   (In this case you need to interpolate between the Z values of .9313 and .9147)
   .9139 or 91.39% is the probability of the project taking up to 42 days.
   Going over 42 days is thus 100 - 91.39 = 8.61%
Thank you for attention
  Any Questions ????

More Related Content

What's hot

Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Zulfiquer Ahmed Amin
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
saurabmi2
 
Gantt
GanttGantt
Gantt
Balaji P
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
Shivangi Saini
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysis
Harinadh Karimikonda
 
Monitoring and evaluation (2)
Monitoring and evaluation (2)Monitoring and evaluation (2)
Monitoring and evaluation (2)
Dr.RAJEEV KASHYAP
 
Project Monitoring and Evaluation
Project Monitoring and Evaluation Project Monitoring and Evaluation
Project Monitoring and Evaluation
Central University of Karnataka Kalaburagi
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project management
Jared C. Powell
 
Project management cycle
Project management  cycleProject management  cycle
Project management cycle
Megha BHardwaj
 
Project Auditing
Project AuditingProject Auditing
Project Auditing
Salih Islam
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
Mr. Ramesh Nayaka
 
project management concepts
project management conceptsproject management concepts
project management concepts
Aswin prakash i , Xantus Technologies
 
Project management and project life cycle
Project management and project life cycleProject management and project life cycle
Project management and project life cycle
Institute of Rural Management
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
MaRS Discovery District
 
Planning
PlanningPlanning
Planning
Joubert Dias
 
Gantt chart
Gantt chartGantt chart
Gantt chart
Tanoj Patidar
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
Abhishek Pachisia
 
Project appraisal for financial markets
Project appraisal for financial marketsProject appraisal for financial markets
Project appraisal for financial markets
karangoyal972
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
Ahmed Rami Elsherif, PMP, ITBMC
 

What's hot (20)

Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
 
Gantt
GanttGantt
Gantt
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysis
 
Monitoring and evaluation (2)
Monitoring and evaluation (2)Monitoring and evaluation (2)
Monitoring and evaluation (2)
 
Project Monitoring and Evaluation
Project Monitoring and Evaluation Project Monitoring and Evaluation
Project Monitoring and Evaluation
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project management
 
Project management cycle
Project management  cycleProject management  cycle
Project management cycle
 
Project Auditing
Project AuditingProject Auditing
Project Auditing
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
project management concepts
project management conceptsproject management concepts
project management concepts
 
Project management and project life cycle
Project management and project life cycleProject management and project life cycle
Project management and project life cycle
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Planning
PlanningPlanning
Planning
 
Gantt chart
Gantt chartGantt chart
Gantt chart
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 
Project appraisal for financial markets
Project appraisal for financial marketsProject appraisal for financial markets
Project appraisal for financial markets
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 

Similar to Program evaluation review technique (pert)

Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert Chart
Vinay Prajapati
 
Pert cpm
Pert cpmPert cpm
Pert cpm
Ann vasquez
 
Pert cpm
Pert cpmPert cpm
Pert cpm
Ann vasquez
 
Pert- program evaluation and review technique
Pert- program evaluation and review techniquePert- program evaluation and review technique
Pert- program evaluation and review technique
Vinci Viveka
 
شبكات الأعمال
شبكات الأعمال  شبكات الأعمال
شبكات الأعمال
Muhammad Hassan
 
PERT/CPM
PERT/CPMPERT/CPM
PERT/CPM
Farhanah Noah
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
Nikka Lopez
 
Rowing Selection usiSeat racing by Duncan Holland: Seat racing examples
Rowing Selection usiSeat racing by Duncan Holland: Seat racing examplesRowing Selection usiSeat racing by Duncan Holland: Seat racing examples
Rowing Selection usiSeat racing by Duncan Holland: Seat racing examples
Rebecca Caroe
 
CPM-PERT-Examples .pptx
CPM-PERT-Examples .pptxCPM-PERT-Examples .pptx
CPM-PERT-Examples .pptx
ssuser9b876d
 
Network diagram problems
Network diagram problemsNetwork diagram problems
Network diagram problems
Subhra Mishra
 

Similar to Program evaluation review technique (pert) (10)

Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert Chart
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Pert- program evaluation and review technique
Pert- program evaluation and review techniquePert- program evaluation and review technique
Pert- program evaluation and review technique
 
شبكات الأعمال
شبكات الأعمال  شبكات الأعمال
شبكات الأعمال
 
PERT/CPM
PERT/CPMPERT/CPM
PERT/CPM
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Rowing Selection usiSeat racing by Duncan Holland: Seat racing examples
Rowing Selection usiSeat racing by Duncan Holland: Seat racing examplesRowing Selection usiSeat racing by Duncan Holland: Seat racing examples
Rowing Selection usiSeat racing by Duncan Holland: Seat racing examples
 
CPM-PERT-Examples .pptx
CPM-PERT-Examples .pptxCPM-PERT-Examples .pptx
CPM-PERT-Examples .pptx
 
Network diagram problems
Network diagram problemsNetwork diagram problems
Network diagram problems
 

Recently uploaded

Erasmus + DISSEMINATION ACTIVITIES Croatia
Erasmus + DISSEMINATION ACTIVITIES CroatiaErasmus + DISSEMINATION ACTIVITIES Croatia
Erasmus + DISSEMINATION ACTIVITIES Croatia
whatchangedhowreflec
 
Cross-Cultural Leadership and Communication
Cross-Cultural Leadership and CommunicationCross-Cultural Leadership and Communication
Cross-Cultural Leadership and Communication
MattVassar1
 
bryophytes.pptx bsc botany honours second semester
bryophytes.pptx bsc botany honours  second semesterbryophytes.pptx bsc botany honours  second semester
bryophytes.pptx bsc botany honours second semester
Sarojini38
 
The Rise of the Digital Telecommunication Marketplace.pptx
The Rise of the Digital Telecommunication Marketplace.pptxThe Rise of the Digital Telecommunication Marketplace.pptx
The Rise of the Digital Telecommunication Marketplace.pptx
PriyaKumari928991
 
220711130100 udita Chakraborty Aims and objectives of national policy on inf...
220711130100 udita Chakraborty  Aims and objectives of national policy on inf...220711130100 udita Chakraborty  Aims and objectives of national policy on inf...
220711130100 udita Chakraborty Aims and objectives of national policy on inf...
Kalna College
 
A Quiz on Drug Abuse Awareness by Quizzito
A Quiz on Drug Abuse Awareness by QuizzitoA Quiz on Drug Abuse Awareness by Quizzito
A Quiz on Drug Abuse Awareness by Quizzito
Quizzito The Quiz Society of Gargi College
 
Post init hook in the odoo 17 ERP Module
Post init hook in the  odoo 17 ERP ModulePost init hook in the  odoo 17 ERP Module
Post init hook in the odoo 17 ERP Module
Celine George
 
Ethiopia and Eritrea Eritrea's journey has been marked by resilience and dete...
Ethiopia and Eritrea Eritrea's journey has been marked by resilience and dete...Ethiopia and Eritrea Eritrea's journey has been marked by resilience and dete...
Ethiopia and Eritrea Eritrea's journey has been marked by resilience and dete...
biruktesfaye27
 
How to Create User Notification in Odoo 17
How to Create User Notification in Odoo 17How to Create User Notification in Odoo 17
How to Create User Notification in Odoo 17
Celine George
 
Library news letter Kitengesa Uganda June 2024
Library news letter Kitengesa Uganda June 2024Library news letter Kitengesa Uganda June 2024
Library news letter Kitengesa Uganda June 2024
Friends of African Village Libraries
 
Diversity Quiz Finals by Quiz Club, IIT Kanpur
Diversity Quiz Finals by Quiz Club, IIT KanpurDiversity Quiz Finals by Quiz Club, IIT Kanpur
Diversity Quiz Finals by Quiz Club, IIT Kanpur
Quiz Club IIT Kanpur
 
220711130088 Sumi Basak Virtual University EPC 3.pptx
220711130088 Sumi Basak Virtual University EPC 3.pptx220711130088 Sumi Basak Virtual University EPC 3.pptx
220711130088 Sumi Basak Virtual University EPC 3.pptx
Kalna College
 
BỘ BÀI TẬP TEST THEO UNIT - FORM 2025 - TIẾNG ANH 12 GLOBAL SUCCESS - KÌ 1 (B...
BỘ BÀI TẬP TEST THEO UNIT - FORM 2025 - TIẾNG ANH 12 GLOBAL SUCCESS - KÌ 1 (B...BỘ BÀI TẬP TEST THEO UNIT - FORM 2025 - TIẾNG ANH 12 GLOBAL SUCCESS - KÌ 1 (B...
BỘ BÀI TẬP TEST THEO UNIT - FORM 2025 - TIẾNG ANH 12 GLOBAL SUCCESS - KÌ 1 (B...
Nguyen Thanh Tu Collection
 
Angle-or,,,,,-Pull-of-Muscleexercise therapy.pptx
Angle-or,,,,,-Pull-of-Muscleexercise therapy.pptxAngle-or,,,,,-Pull-of-Muscleexercise therapy.pptx
Angle-or,,,,,-Pull-of-Muscleexercise therapy.pptx
siddhimeena3
 
Hospital pharmacy and it's organization (1).pdf
Hospital pharmacy and it's organization (1).pdfHospital pharmacy and it's organization (1).pdf
Hospital pharmacy and it's organization (1).pdf
ShwetaGawande8
 
The basics of sentences session 8pptx.pptx
The basics of sentences session 8pptx.pptxThe basics of sentences session 8pptx.pptx
The basics of sentences session 8pptx.pptx
heathfieldcps1
 
How to Create a Stage or a Pipeline in Odoo 17 CRM
How to Create a Stage or a Pipeline in Odoo 17 CRMHow to Create a Stage or a Pipeline in Odoo 17 CRM
How to Create a Stage or a Pipeline in Odoo 17 CRM
Celine George
 
Diversity Quiz Prelims by Quiz Club, IIT Kanpur
Diversity Quiz Prelims by Quiz Club, IIT KanpurDiversity Quiz Prelims by Quiz Club, IIT Kanpur
Diversity Quiz Prelims by Quiz Club, IIT Kanpur
Quiz Club IIT Kanpur
 
How to stay relevant as a cyber professional: Skills, trends and career paths...
How to stay relevant as a cyber professional: Skills, trends and career paths...How to stay relevant as a cyber professional: Skills, trends and career paths...
How to stay relevant as a cyber professional: Skills, trends and career paths...
Infosec
 
Creating Images and Videos through AI.pptx
Creating Images and Videos through AI.pptxCreating Images and Videos through AI.pptx
Creating Images and Videos through AI.pptx
Forum of Blended Learning
 

Recently uploaded (20)

Erasmus + DISSEMINATION ACTIVITIES Croatia
Erasmus + DISSEMINATION ACTIVITIES CroatiaErasmus + DISSEMINATION ACTIVITIES Croatia
Erasmus + DISSEMINATION ACTIVITIES Croatia
 
Cross-Cultural Leadership and Communication
Cross-Cultural Leadership and CommunicationCross-Cultural Leadership and Communication
Cross-Cultural Leadership and Communication
 
bryophytes.pptx bsc botany honours second semester
bryophytes.pptx bsc botany honours  second semesterbryophytes.pptx bsc botany honours  second semester
bryophytes.pptx bsc botany honours second semester
 
The Rise of the Digital Telecommunication Marketplace.pptx
The Rise of the Digital Telecommunication Marketplace.pptxThe Rise of the Digital Telecommunication Marketplace.pptx
The Rise of the Digital Telecommunication Marketplace.pptx
 
220711130100 udita Chakraborty Aims and objectives of national policy on inf...
220711130100 udita Chakraborty  Aims and objectives of national policy on inf...220711130100 udita Chakraborty  Aims and objectives of national policy on inf...
220711130100 udita Chakraborty Aims and objectives of national policy on inf...
 
A Quiz on Drug Abuse Awareness by Quizzito
A Quiz on Drug Abuse Awareness by QuizzitoA Quiz on Drug Abuse Awareness by Quizzito
A Quiz on Drug Abuse Awareness by Quizzito
 
Post init hook in the odoo 17 ERP Module
Post init hook in the  odoo 17 ERP ModulePost init hook in the  odoo 17 ERP Module
Post init hook in the odoo 17 ERP Module
 
Ethiopia and Eritrea Eritrea's journey has been marked by resilience and dete...
Ethiopia and Eritrea Eritrea's journey has been marked by resilience and dete...Ethiopia and Eritrea Eritrea's journey has been marked by resilience and dete...
Ethiopia and Eritrea Eritrea's journey has been marked by resilience and dete...
 
How to Create User Notification in Odoo 17
How to Create User Notification in Odoo 17How to Create User Notification in Odoo 17
How to Create User Notification in Odoo 17
 
Library news letter Kitengesa Uganda June 2024
Library news letter Kitengesa Uganda June 2024Library news letter Kitengesa Uganda June 2024
Library news letter Kitengesa Uganda June 2024
 
Diversity Quiz Finals by Quiz Club, IIT Kanpur
Diversity Quiz Finals by Quiz Club, IIT KanpurDiversity Quiz Finals by Quiz Club, IIT Kanpur
Diversity Quiz Finals by Quiz Club, IIT Kanpur
 
220711130088 Sumi Basak Virtual University EPC 3.pptx
220711130088 Sumi Basak Virtual University EPC 3.pptx220711130088 Sumi Basak Virtual University EPC 3.pptx
220711130088 Sumi Basak Virtual University EPC 3.pptx
 
BỘ BÀI TẬP TEST THEO UNIT - FORM 2025 - TIẾNG ANH 12 GLOBAL SUCCESS - KÌ 1 (B...
BỘ BÀI TẬP TEST THEO UNIT - FORM 2025 - TIẾNG ANH 12 GLOBAL SUCCESS - KÌ 1 (B...BỘ BÀI TẬP TEST THEO UNIT - FORM 2025 - TIẾNG ANH 12 GLOBAL SUCCESS - KÌ 1 (B...
BỘ BÀI TẬP TEST THEO UNIT - FORM 2025 - TIẾNG ANH 12 GLOBAL SUCCESS - KÌ 1 (B...
 
Angle-or,,,,,-Pull-of-Muscleexercise therapy.pptx
Angle-or,,,,,-Pull-of-Muscleexercise therapy.pptxAngle-or,,,,,-Pull-of-Muscleexercise therapy.pptx
Angle-or,,,,,-Pull-of-Muscleexercise therapy.pptx
 
Hospital pharmacy and it's organization (1).pdf
Hospital pharmacy and it's organization (1).pdfHospital pharmacy and it's organization (1).pdf
Hospital pharmacy and it's organization (1).pdf
 
The basics of sentences session 8pptx.pptx
The basics of sentences session 8pptx.pptxThe basics of sentences session 8pptx.pptx
The basics of sentences session 8pptx.pptx
 
How to Create a Stage or a Pipeline in Odoo 17 CRM
How to Create a Stage or a Pipeline in Odoo 17 CRMHow to Create a Stage or a Pipeline in Odoo 17 CRM
How to Create a Stage or a Pipeline in Odoo 17 CRM
 
Diversity Quiz Prelims by Quiz Club, IIT Kanpur
Diversity Quiz Prelims by Quiz Club, IIT KanpurDiversity Quiz Prelims by Quiz Club, IIT Kanpur
Diversity Quiz Prelims by Quiz Club, IIT Kanpur
 
How to stay relevant as a cyber professional: Skills, trends and career paths...
How to stay relevant as a cyber professional: Skills, trends and career paths...How to stay relevant as a cyber professional: Skills, trends and career paths...
How to stay relevant as a cyber professional: Skills, trends and career paths...
 
Creating Images and Videos through AI.pptx
Creating Images and Videos through AI.pptxCreating Images and Videos through AI.pptx
Creating Images and Videos through AI.pptx
 

Program evaluation review technique (pert)

  • 1. Engineering Mangement Program Evaluation Review Technique (PERT) Prepared by : Anas Tomeh Fira Eid Prepared for : Dr. Reema Nassar
  • 2. Objective of the presentation • To understand the formula , the use and the benefits of Program , Evaluation ,and Review Technic (PERT) analysis .
  • 3. What is the PERT ? Program (Project) Evaluation and Review Technique (PERT): is a project management tool used to schedule, organize, and coordinate tasks within a project. It is basically a method to analyse the tasks involved in completing a given project, especially the time needed to complete each task, and to identify the minimum time needed to complete the total project.
  • 4. When we use PERT ? • PERT is used when activity times are uncertain. – Determine the duration of the project . – Decision making under risk (“P” for probabilistic)
  • 5. Determine the duration of the project • OPTIMISTIC TIME: Best time if everything goes perfectly • REALISTIC TIME: Most likely time • PESSIMISTIC TIME: A worst-case situation B + 4M + P Expected Time = ------------------- 6
  • 6. Determine the duration of the project • Example: For excavation activity let : B = 12 days M = 18 days P = 60 What is the expected time for this activity? Sol : 12 + 4(18) + 60 Expected Time = ------------------------- 6 = 24 days
  • 7. Determine the duration of the project Activity Predecessor Optimistic Normal Pessimistic Te (B) (m) (P) (B+4m+P)/6 A --- 2 4 6 4.00 B --- 3 5 9 5.33 C A 4 5 7 5.17 D A 4 6 10 6.33 E B, C 4 5 7 5.17 F D 3 4 8 4.50 G E 3 5 8 5.17 f
  • 8. Determine the duration of the project D F A C Start Finish B E G
  • 9. Determine the duration of the project D F D:6.33 D:4.5 ES:4 ES:10.33 EF:10.33 EF:14.83 A D:4 ES:0 EF:4 C D:5.17 Finish Start ES:4 ES:0 D:0 EF:9.17 ES:19.51 EF:0 EF:19.51 B E G D:5.33 D:5.17 D:5.17 ES:0 ES:9.17 ES:14.34 EF:5.33 EF:14.34 EF:19.51
  • 10. Determine the duration of the project D F D:6.33 D:4.5 ES:4 ES:10.33 EF:10.33 EF:14.83 LS:8.68 LS:15.01 LF:15.01 LF:19.51 A D:4 ES:0 EF:4 LS:0 LF:4 C D:5.17 Start Finish ES:4 D:0 D:0 EF:9.17 ES:0 ES:19.51 LS:4 EF:0 EF:19.51 LF:9.17 LS:0 LS:19.51 LF:0 LF:19.51 B E G D:5.33 D:5.17 D:5.17 ES:0 ES:9.17 ES:14.34 EF:5.33 EF:14.34 EF:19.51 LS:3.84 LS:9.17 LS:14.34 LF:9.17 LF:14.34 LF:19.51
  • 11. Determine the duration of the project Critical Path Critical Path: A-C-E-G • Path A-D-F = 14.83 work days • Path A-C-E-G = 19.51 work days • Path B-E-G = 15.67 work days
  • 12. Determine the duration of the project Critical Path Activity LF-EF Total A 4-4 0 B 9.17 – 5.33 3.84 C 9.17 – 9.17 0 D 15.01 – 10.33 4.68 E 14.34 – 14.34 0 F 19.51 – 14.83 4.68 G 19.51 – 19.51 0
  • 13. Assessing Risks • Risk is a measure of the probability (and consequences) of not completing a project on time. • A major responsibility of the project manager at the start of a project is to develop a risk-management plan. • A Risk-Management Plan identifies the key risks to a project’s success and prescribes ways to circumvent them.
  • 14. Assessing Risks • With PERT’s three time-estimates, we get a mean (average) time and a variance for each activity and each path. – We also get a project mean time and variance. • In order to compute probabilities (assuming a normal distribution) we need the activity means and variances. – Most computer packages calculate this for you.
  • 15. Assessing Risks Path Time (wks) 12 I 27 48 1563 A-I-K33 33 A-F-K28 28 A K A-C-G-J-K 67 0 12 12 F 22 Latest 63 69 Latest B-D-H-J-K 69 2 1214 53 1063 start 63 6 69 finish B-E-J-K 43 time time C 12 22 22 G 57 Start Finish 14 1024 24 59 35 0 B9 9 D19 19 H 59 59 J 63 0 9 9 9 1019 19 4059 59 4 63 9 E 33 35 2459
  • 16. Assessing Risks • What is the probability that our sample project will finish in 69 weeks as scheduled? 100% (Why?) – Because we used CPM! • (This means we were certain of all of our activity times.) – If we weren’t certain, we should have used PERT • You can’t do risk analysis if you use CPM
  • 17. Assessing Risks • Calculate standard deviation – Standard deviation- average deviation from the estimated time • SD=(TP-T0)/6 – higher the SD is the greater amount of uncertainty exists • Calculate variance – reflects the spread of a value over a normal distribution • V=SD2 – a large variance indicates great uncertainty, a small variance indicates a more accurate estimate
  • 18. Assessing Risks What is the Probability of it taking 72 weeks? Critical Critical Path = B - D - H - J – K = 69 weeks Path T = 72 weeks C = 69 weeks Varianc T–C e 2 =  (variances of activities along critical path) = z 2 2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89 z= 72 – 69 11.89 Look up Z value in normal distribution table Z = 0.870 Pz = .8078 or 80.78% (Probability of it taking 72 weeks)
  • 19. Assessing Risks Look up the Z value (0.870) in the table of normal distribution. .8078 or 80.78% is the probability of the project taking up to 72 wks. Going over 72 weeks would be 100 – 80.78 = 19.22%
  • 20. Assessing Risks Normal distribution: Length of critical Mean = 69 weeks; path is 69 weeks  = 3.45 weeks Probability of taking 72 weeks is 0.8078 Probability of or 80.78% exceeding 72 weeks is 0.1922 or 19.22% 69 72 Project duration (weeks)
  • 21. Assessing Risks • Assume a PERT project critical path takes 40 days, and that the variance of this path is 2.147 – You wish to know the probability of the project going over 42 days. • Compute the standard deviation of the critical path. (Take the square root of the variance of 2.147) Std. Dev. = 1.465 – POM/QM software gives you the variance of the critical path. • Compute the Z value: Z = (absolute time difference) / Std. Dev. In this example, Z = (42 days - 40 days) / 1.465 = 1.365 • Look up the Z value of 1.365 in a Normal Distribution table to get the probability of the project taking 42 days. • Subtract it from 100% to get the probability of going over 42.
  • 22. Assessing Risks Look up the Z value (1.365) in the table of normal distribution. (In this case you need to interpolate between the Z values of .9313 and .9147) .9139 or 91.39% is the probability of the project taking up to 42 days. Going over 42 days is thus 100 - 91.39 = 8.61%
  • 23. Thank you for attention Any Questions ????
  翻译: