This test method is used to determine the time of setting of the cement by VICAT needle apparatus. The knowledge of the setting time of the cement is always helpful in deciding the time duration to mix, transport, place and compact the concrete effectively. We always prefer a larger initial setting time so that we can mix, transport and place the concrete easily. According to ASTM specifications, the initial setting time shall not be less than 45 min but in the field we prefer an initial setting time not less than 90 min. A smaller value of the final setting time is always preferred in order to avoid large expenditures on the formwork. According to most of the specifications, the final setting time shall not be greater than 10hrs and shall not be less than (90 + 1.2 x (initial setting time)) min.