尊敬的 微信汇率:1円 ≈ 0.046078 元 支付宝汇率:1円 ≈ 0.046168元 [退出登录]
SlideShare a Scribd company logo
Prepared By
Prof. Ashish Makwana
Civil Engg. Dept.
Prof. Ashish Makwana 1
PRESENTATION
OUTLINE…
• Resource Allocation
• Resource Allocation: Procedure
• Resource Levelling
• Resource Smoothing
• Scheduling
Prof. Ashish Makwana 2
RESOURCE ALLOCATION
• The various activities of the project are scheduled
in such a way that the requirement of various
resources is more or less uniform all along the
project duration.
• The main purpose of resources allocation is to
rearrange the activities of network in such a
manner that the project can be completed with
available resources, with minimum increase in cost
and without delaying the completion period.
Prof. Ashish Makwana 3
RESOURCE ALLOCATION:
PROCEDURE
1. Prepare - Network, Time duration, Critical path
2. Time scaled version of Network
3. Determined - Cumulative requirements of various
resources
4. Prepare – Histograms
5. Resource levelling – done by delaying some of the
non-critical activities
Prof. Ashish Makwana 4
RESOURCE LEVELLING
• Carry out when – (i) demand for a particular
resources exceeds its availability
• (ii) Requirement of Masons and Labours both,
because it is very difficult to arrange this much
persons on a day to day basis
• Done – by delaying some of the non-critical
activities which have float / adjusting the start time
of non-critical activities
• Activity adjustment – during process, max.
requirement does not exceed the limit of available
resources
Prof. Ashish Makwana 5
RESOURCE SMOOTHING
• Done – shifting of activities by their available floats,
so that a uniform demand for the resources are
generated.
• Project Time – not change in any case
Prof. Ashish Makwana 6
SCHEDULING
• Meaning – Process of preparing the work plan to a
time frame indicating the start and completion of
each activity
• Preparation – labour, material, machinery, money
• Useful – Actual progress of each activity compared
to planned programmes for corrective actions and
then speed up the work
Prof. Ashish Makwana 7
1 2 3 4 5
Bricks Nos. 4500 4000 5500 3000 2600
Sand Cum 20 20 35 25 15
Aggregate Cum 20 35 30 25 30
Cement bags Nos. 110 100 115 120 130
Steel Quintal 0 2 10 2 0
Weeks
UnitsMaterial
Prepared by______________Name of work______________
Date_________________
Material Schedule
Prof. Ashish Makwana 8
Labour Schedule
1 2 3 4 5
Carpenters 1 1 1 1 1
Welders 0 0 0 1 1
Mixers
Operator
0 0 1 0 0
Masons 1 1 2 2 1
Bar benders 0 2 1 0 0
Labours 3 3 10 6 3
Name of work______________
Manpower
(Labour)
Weeks
Prepared by______________
Date_________________
Prof. Ashish Makwana 9
Equipment Schedule
1 2 3 4 5
Concrete
Mixer
0 0 1 0 0
Vibrator 0 0 1 0 0
Welding set 0 0 1 1 1
Truck 0 1 1 0.5 0.5
Equipment
for erecting
trusses
0 0 0 1 0
Name of work______________ Prepared by______________
Date_________________
Equipment
Weeks
Prof. Ashish Makwana 10
THANK YOU
Prof. Ashish Makwana 11

More Related Content

What's hot

Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...
A Makwana
 
Job layout per
Job layout perJob layout per
Job layout per
raj balar
 
Construction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdfConstruction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdf
MeleseMengistu
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
srinivas2036
 
Lump Sum Contract
Lump Sum ContractLump Sum Contract
Lump Sum Contract
efinancemanagement.com
 
Earthwork and excavation
Earthwork  and  excavationEarthwork  and  excavation
Earthwork and excavation
Krishna Spoorthy Rachamalla
 
Construction Material Management
Construction Material ManagementConstruction Material Management
Construction Material Management
Priya Ramaraj
 
Estimation introduction - Estimation, Costing and Valuation (ECV)
Estimation introduction - Estimation, Costing and Valuation (ECV)Estimation introduction - Estimation, Costing and Valuation (ECV)
Estimation introduction - Estimation, Costing and Valuation (ECV)
Shanmugasundaram N
 
What is construction management & its Benefits?
What is construction management & its Benefits?What is construction management & its Benefits?
What is construction management & its Benefits?
maria_singh
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture)
Muhammad Aljalali
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
student
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
guestdb5e498
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
akashpadole
 
Rate analysis
Rate analysisRate analysis
Rate analysis
DhavalMithaiwala
 
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B M
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B MModule-1:Introduction to Construction Management by Dr. Vinay Kumar B M
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B M
VIDYA VIKAS INSTITUTE OF ENGINEERING AND TECHNOLOGY
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
Kabilan Kabi
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
rathodjaydeep2
 
Well foundations
Well foundationsWell foundations
Well foundations
ganesh6561
 
Chapter 4.3 well foundation-final-ppt
Chapter 4.3   well foundation-final-pptChapter 4.3   well foundation-final-ppt
Chapter 4.3 well foundation-final-ppt
DYPCET
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
srinivas2036
 

What's hot (20)

Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...
 
Job layout per
Job layout perJob layout per
Job layout per
 
Construction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdfConstruction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdf
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Lump Sum Contract
Lump Sum ContractLump Sum Contract
Lump Sum Contract
 
Earthwork and excavation
Earthwork  and  excavationEarthwork  and  excavation
Earthwork and excavation
 
Construction Material Management
Construction Material ManagementConstruction Material Management
Construction Material Management
 
Estimation introduction - Estimation, Costing and Valuation (ECV)
Estimation introduction - Estimation, Costing and Valuation (ECV)Estimation introduction - Estimation, Costing and Valuation (ECV)
Estimation introduction - Estimation, Costing and Valuation (ECV)
 
What is construction management & its Benefits?
What is construction management & its Benefits?What is construction management & its Benefits?
What is construction management & its Benefits?
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture)
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
Rate analysis
Rate analysisRate analysis
Rate analysis
 
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B M
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B MModule-1:Introduction to Construction Management by Dr. Vinay Kumar B M
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B M
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
 
Well foundations
Well foundationsWell foundations
Well foundations
 
Chapter 4.3 well foundation-final-ppt
Chapter 4.3   well foundation-final-pptChapter 4.3   well foundation-final-ppt
Chapter 4.3 well foundation-final-ppt
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 

Similar to Resources allocation and resources scheduling_Construction Management

Construction planning_Construction Management (2180611) (Semester-8), Civil E...
Construction planning_Construction Management (2180611) (Semester-8), Civil E...Construction planning_Construction Management (2180611) (Semester-8), Civil E...
Construction planning_Construction Management (2180611) (Semester-8), Civil E...
A Makwana
 
Scheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptScheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.ppt
TecnicoItca
 
Chap008.ppt
Chap008.pptChap008.ppt
Chap008.ppt
LucasMogaka
 
Anjali pgdm2-1504-resource planning
Anjali pgdm2-1504-resource planningAnjali pgdm2-1504-resource planning
Anjali pgdm2-1504-resource planning
Anjali Mehta
 
Lecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxLecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptx
TecnicoItca
 
Scheduling resources and costs is a crucial aspect of project management that...
Scheduling resources and costs is a crucial aspect of project management that...Scheduling resources and costs is a crucial aspect of project management that...
Scheduling resources and costs is a crucial aspect of project management that...
THULASIMANOHARAN2
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
Raj J Das
 
Allocating Resources To The Project
Allocating Resources To The ProjectAllocating Resources To The Project
Allocating Resources To The Project
Jeff Brooks
 
10.resources measurement and its utilization
10.resources measurement and its utilization10.resources measurement and its utilization
10.resources measurement and its utilization
Selva Prakash
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
Sagar Kaptan
 
EpM
EpMEpM
PM-Chapter8-1.pptx
PM-Chapter8-1.pptxPM-Chapter8-1.pptx
PM-Chapter8-1.pptx
TecnicoItca
 
ITFT - Project Management
ITFT - Project ManagementITFT - Project Management
ITFT - Project Management
Pooja
 
Pete day resume 8 2010
Pete day resume 8 2010Pete day resume 8 2010
Pete day resume 8 2010
Pete Day
 
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Shrikant Kate
 
Ls2419601967
Ls2419601967Ls2419601967
Ls2419601967
IJERA Editor
 
Chapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptChapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.ppt
TecnicoItca
 
Industrial Engineering (Method Study and Work study)
Industrial Engineering (Method Study and Work study)Industrial Engineering (Method Study and Work study)
Industrial Engineering (Method Study and Work study)
Vishal Shinde
 
Resource Planning
Resource PlanningResource Planning
Resource Planning
Wajahat Ali
 
Lec8 maintenance planning and scheduling1
Lec8 maintenance planning and scheduling1Lec8 maintenance planning and scheduling1
Lec8 maintenance planning and scheduling1
Maxwell Odira
 

Similar to Resources allocation and resources scheduling_Construction Management (20)

Construction planning_Construction Management (2180611) (Semester-8), Civil E...
Construction planning_Construction Management (2180611) (Semester-8), Civil E...Construction planning_Construction Management (2180611) (Semester-8), Civil E...
Construction planning_Construction Management (2180611) (Semester-8), Civil E...
 
Scheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptScheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.ppt
 
Chap008.ppt
Chap008.pptChap008.ppt
Chap008.ppt
 
Anjali pgdm2-1504-resource planning
Anjali pgdm2-1504-resource planningAnjali pgdm2-1504-resource planning
Anjali pgdm2-1504-resource planning
 
Lecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxLecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptx
 
Scheduling resources and costs is a crucial aspect of project management that...
Scheduling resources and costs is a crucial aspect of project management that...Scheduling resources and costs is a crucial aspect of project management that...
Scheduling resources and costs is a crucial aspect of project management that...
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
 
Allocating Resources To The Project
Allocating Resources To The ProjectAllocating Resources To The Project
Allocating Resources To The Project
 
10.resources measurement and its utilization
10.resources measurement and its utilization10.resources measurement and its utilization
10.resources measurement and its utilization
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
EpM
EpMEpM
EpM
 
PM-Chapter8-1.pptx
PM-Chapter8-1.pptxPM-Chapter8-1.pptx
PM-Chapter8-1.pptx
 
ITFT - Project Management
ITFT - Project ManagementITFT - Project Management
ITFT - Project Management
 
Pete day resume 8 2010
Pete day resume 8 2010Pete day resume 8 2010
Pete day resume 8 2010
 
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
 
Ls2419601967
Ls2419601967Ls2419601967
Ls2419601967
 
Chapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.pptChapter-8-Post-Mid.ppt
Chapter-8-Post-Mid.ppt
 
Industrial Engineering (Method Study and Work study)
Industrial Engineering (Method Study and Work study)Industrial Engineering (Method Study and Work study)
Industrial Engineering (Method Study and Work study)
 
Resource Planning
Resource PlanningResource Planning
Resource Planning
 
Lec8 maintenance planning and scheduling1
Lec8 maintenance planning and scheduling1Lec8 maintenance planning and scheduling1
Lec8 maintenance planning and scheduling1
 

More from A Makwana

Attributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewAttributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a review
A Makwana
 
A Review on Thin-shell Structures: Advances and Trends
A Review on Thin-shell Structures: Advances and TrendsA Review on Thin-shell Structures: Advances and Trends
A Review on Thin-shell Structures: Advances and Trends
A Makwana
 
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
A Makwana
 
Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)
A Makwana
 
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
A Makwana
 
Economical Concrete
Economical ConcreteEconomical Concrete
Economical Concrete
A Makwana
 
Bacterial Concrete
Bacterial ConcreteBacterial Concrete
Bacterial Concrete
A Makwana
 
Risk in PPP Projects
Risk in PPP ProjectsRisk in PPP Projects
Risk in PPP Projects
A Makwana
 
Eco-Friendly Mortar
Eco-Friendly MortarEco-Friendly Mortar
Eco-Friendly Mortar
A Makwana
 
Risk Management: High Rise Construction
Risk Management: High Rise ConstructionRisk Management: High Rise Construction
Risk Management: High Rise Construction
A Makwana
 
Infrastructure Engineering & Management
Infrastructure Engineering & ManagementInfrastructure Engineering & Management
Infrastructure Engineering & Management
A Makwana
 
Utilization of Industrial Waste in Pervious Concrete
Utilization of Industrial Waste in Pervious ConcreteUtilization of Industrial Waste in Pervious Concrete
Utilization of Industrial Waste in Pervious Concrete
A Makwana
 
Application of Graphs through MS Excel & MATLAB for Research work
Application of Graphs through MS Excel & MATLAB for Research workApplication of Graphs through MS Excel & MATLAB for Research work
Application of Graphs through MS Excel & MATLAB for Research work
A Makwana
 
Ready Mixed Concrete Selection through Management Approach
Ready Mixed Concrete Selection through Management ApproachReady Mixed Concrete Selection through Management Approach
Ready Mixed Concrete Selection through Management Approach
A Makwana
 
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
A Makwana
 
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUESEXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
A Makwana
 
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACHDEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
A Makwana
 
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRYANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
A Makwana
 
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLDINTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
A Makwana
 
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
A Makwana
 

More from A Makwana (20)

Attributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewAttributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a review
 
A Review on Thin-shell Structures: Advances and Trends
A Review on Thin-shell Structures: Advances and TrendsA Review on Thin-shell Structures: Advances and Trends
A Review on Thin-shell Structures: Advances and Trends
 
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
 
Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)
 
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
 
Economical Concrete
Economical ConcreteEconomical Concrete
Economical Concrete
 
Bacterial Concrete
Bacterial ConcreteBacterial Concrete
Bacterial Concrete
 
Risk in PPP Projects
Risk in PPP ProjectsRisk in PPP Projects
Risk in PPP Projects
 
Eco-Friendly Mortar
Eco-Friendly MortarEco-Friendly Mortar
Eco-Friendly Mortar
 
Risk Management: High Rise Construction
Risk Management: High Rise ConstructionRisk Management: High Rise Construction
Risk Management: High Rise Construction
 
Infrastructure Engineering & Management
Infrastructure Engineering & ManagementInfrastructure Engineering & Management
Infrastructure Engineering & Management
 
Utilization of Industrial Waste in Pervious Concrete
Utilization of Industrial Waste in Pervious ConcreteUtilization of Industrial Waste in Pervious Concrete
Utilization of Industrial Waste in Pervious Concrete
 
Application of Graphs through MS Excel & MATLAB for Research work
Application of Graphs through MS Excel & MATLAB for Research workApplication of Graphs through MS Excel & MATLAB for Research work
Application of Graphs through MS Excel & MATLAB for Research work
 
Ready Mixed Concrete Selection through Management Approach
Ready Mixed Concrete Selection through Management ApproachReady Mixed Concrete Selection through Management Approach
Ready Mixed Concrete Selection through Management Approach
 
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
 
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUESEXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
 
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACHDEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
 
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRYANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
 
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLDINTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
 
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
 

Recently uploaded

My Aerospace Design and Structures Career Engineering LinkedIn version Presen...
My Aerospace Design and Structures Career Engineering LinkedIn version Presen...My Aerospace Design and Structures Career Engineering LinkedIn version Presen...
My Aerospace Design and Structures Career Engineering LinkedIn version Presen...
Geoffrey Wardle. MSc. MSc. Snr.MAIAA
 
Literature review for prompt engineering of ChatGPT.pptx
Literature review for prompt engineering of ChatGPT.pptxLiterature review for prompt engineering of ChatGPT.pptx
Literature review for prompt engineering of ChatGPT.pptx
LokerXu2
 
🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...
🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...
🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...
AK47
 
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
sexytaniya455
 
❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...
❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...
❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...
hotchicksescort
 
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
nainakaoornoida
 
AN INTRODUCTION OF AI & SEARCHING TECHIQUES
AN INTRODUCTION OF AI & SEARCHING TECHIQUESAN INTRODUCTION OF AI & SEARCHING TECHIQUES
AN INTRODUCTION OF AI & SEARCHING TECHIQUES
drshikhapandey2022
 
Basic principle and types Static Relays ppt
Basic principle and  types  Static Relays pptBasic principle and  types  Static Relays ppt
Basic principle and types Static Relays ppt
Sri Ramakrishna Institute of Technology
 
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdfSELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
Pallavi Sharma
 
Data Communication and Computer Networks Management System Project Report.pdf
Data Communication and Computer Networks Management System Project Report.pdfData Communication and Computer Networks Management System Project Report.pdf
Data Communication and Computer Networks Management System Project Report.pdf
Kamal Acharya
 
ESCORT SERVICE FULL ENJOY - @9711199012, Mayur Vihar CALL GIRLS SERVICE Delhi
ESCORT SERVICE FULL ENJOY - @9711199012, Mayur Vihar CALL GIRLS SERVICE DelhiESCORT SERVICE FULL ENJOY - @9711199012, Mayur Vihar CALL GIRLS SERVICE Delhi
ESCORT SERVICE FULL ENJOY - @9711199012, Mayur Vihar CALL GIRLS SERVICE Delhi
AK47
 
TENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineeringTENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineering
SnehalChavan75
 
The Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC Conduit
The Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC ConduitThe Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC Conduit
The Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC Conduit
Guangdong Ctube Industry Co., Ltd.
 
Call Girls Madurai 8824825030 Escort In Madurai service 24X7
Call Girls Madurai 8824825030 Escort In Madurai service 24X7Call Girls Madurai 8824825030 Escort In Madurai service 24X7
Call Girls Madurai 8824825030 Escort In Madurai service 24X7
Poonam Singh
 
Cricket management system ptoject report.pdf
Cricket management system ptoject report.pdfCricket management system ptoject report.pdf
Cricket management system ptoject report.pdf
Kamal Acharya
 
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
AK47
 
Call Girls In Lucknow 🔥 +91-7014168258🔥High Profile Call Girl Lucknow
Call Girls In Lucknow 🔥 +91-7014168258🔥High Profile Call Girl LucknowCall Girls In Lucknow 🔥 +91-7014168258🔥High Profile Call Girl Lucknow
Call Girls In Lucknow 🔥 +91-7014168258🔥High Profile Call Girl Lucknow
yogita singh$A17
 
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
sonamrawat5631
 
SPICE PARK JUL2024 ( 6,866 SPICE Models )
SPICE PARK JUL2024 ( 6,866 SPICE Models )SPICE PARK JUL2024 ( 6,866 SPICE Models )
SPICE PARK JUL2024 ( 6,866 SPICE Models )
Tsuyoshi Horigome
 
Kandivali Call Girls ☑ +91-9967584737 ☑ Available Hot Girls Aunty Book Now
Kandivali Call Girls ☑ +91-9967584737 ☑ Available Hot Girls Aunty Book NowKandivali Call Girls ☑ +91-9967584737 ☑ Available Hot Girls Aunty Book Now
Kandivali Call Girls ☑ +91-9967584737 ☑ Available Hot Girls Aunty Book Now
SONALI Batra $A12
 

Recently uploaded (20)

My Aerospace Design and Structures Career Engineering LinkedIn version Presen...
My Aerospace Design and Structures Career Engineering LinkedIn version Presen...My Aerospace Design and Structures Career Engineering LinkedIn version Presen...
My Aerospace Design and Structures Career Engineering LinkedIn version Presen...
 
Literature review for prompt engineering of ChatGPT.pptx
Literature review for prompt engineering of ChatGPT.pptxLiterature review for prompt engineering of ChatGPT.pptx
Literature review for prompt engineering of ChatGPT.pptx
 
🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...
🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...
🔥Independent Call Girls In Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Esco...
 
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
Call Girls Nagpur 8824825030 Escort In Nagpur service 24X7
 
❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...
❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...
❣Unsatisfied Bhabhi Call Girls Surat 💯Call Us 🔝 7014168258 🔝💃Independent Sura...
 
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
 
AN INTRODUCTION OF AI & SEARCHING TECHIQUES
AN INTRODUCTION OF AI & SEARCHING TECHIQUESAN INTRODUCTION OF AI & SEARCHING TECHIQUES
AN INTRODUCTION OF AI & SEARCHING TECHIQUES
 
Basic principle and types Static Relays ppt
Basic principle and  types  Static Relays pptBasic principle and  types  Static Relays ppt
Basic principle and types Static Relays ppt
 
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdfSELENIUM CONF -PALLAVI SHARMA - 2024.pdf
SELENIUM CONF -PALLAVI SHARMA - 2024.pdf
 
Data Communication and Computer Networks Management System Project Report.pdf
Data Communication and Computer Networks Management System Project Report.pdfData Communication and Computer Networks Management System Project Report.pdf
Data Communication and Computer Networks Management System Project Report.pdf
 
ESCORT SERVICE FULL ENJOY - @9711199012, Mayur Vihar CALL GIRLS SERVICE Delhi
ESCORT SERVICE FULL ENJOY - @9711199012, Mayur Vihar CALL GIRLS SERVICE DelhiESCORT SERVICE FULL ENJOY - @9711199012, Mayur Vihar CALL GIRLS SERVICE Delhi
ESCORT SERVICE FULL ENJOY - @9711199012, Mayur Vihar CALL GIRLS SERVICE Delhi
 
TENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineeringTENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineering
 
The Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC Conduit
The Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC ConduitThe Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC Conduit
The Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC Conduit
 
Call Girls Madurai 8824825030 Escort In Madurai service 24X7
Call Girls Madurai 8824825030 Escort In Madurai service 24X7Call Girls Madurai 8824825030 Escort In Madurai service 24X7
Call Girls Madurai 8824825030 Escort In Madurai service 24X7
 
Cricket management system ptoject report.pdf
Cricket management system ptoject report.pdfCricket management system ptoject report.pdf
Cricket management system ptoject report.pdf
 
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
🔥Photo Call Girls Lucknow 💯Call Us 🔝 6350257716 🔝💃Independent Lucknow Escorts...
 
Call Girls In Lucknow 🔥 +91-7014168258🔥High Profile Call Girl Lucknow
Call Girls In Lucknow 🔥 +91-7014168258🔥High Profile Call Girl LucknowCall Girls In Lucknow 🔥 +91-7014168258🔥High Profile Call Girl Lucknow
Call Girls In Lucknow 🔥 +91-7014168258🔥High Profile Call Girl Lucknow
 
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
 
SPICE PARK JUL2024 ( 6,866 SPICE Models )
SPICE PARK JUL2024 ( 6,866 SPICE Models )SPICE PARK JUL2024 ( 6,866 SPICE Models )
SPICE PARK JUL2024 ( 6,866 SPICE Models )
 
Kandivali Call Girls ☑ +91-9967584737 ☑ Available Hot Girls Aunty Book Now
Kandivali Call Girls ☑ +91-9967584737 ☑ Available Hot Girls Aunty Book NowKandivali Call Girls ☑ +91-9967584737 ☑ Available Hot Girls Aunty Book Now
Kandivali Call Girls ☑ +91-9967584737 ☑ Available Hot Girls Aunty Book Now
 

Resources allocation and resources scheduling_Construction Management

  • 1. Prepared By Prof. Ashish Makwana Civil Engg. Dept. Prof. Ashish Makwana 1
  • 2. PRESENTATION OUTLINE… • Resource Allocation • Resource Allocation: Procedure • Resource Levelling • Resource Smoothing • Scheduling Prof. Ashish Makwana 2
  • 3. RESOURCE ALLOCATION • The various activities of the project are scheduled in such a way that the requirement of various resources is more or less uniform all along the project duration. • The main purpose of resources allocation is to rearrange the activities of network in such a manner that the project can be completed with available resources, with minimum increase in cost and without delaying the completion period. Prof. Ashish Makwana 3
  • 4. RESOURCE ALLOCATION: PROCEDURE 1. Prepare - Network, Time duration, Critical path 2. Time scaled version of Network 3. Determined - Cumulative requirements of various resources 4. Prepare – Histograms 5. Resource levelling – done by delaying some of the non-critical activities Prof. Ashish Makwana 4
  • 5. RESOURCE LEVELLING • Carry out when – (i) demand for a particular resources exceeds its availability • (ii) Requirement of Masons and Labours both, because it is very difficult to arrange this much persons on a day to day basis • Done – by delaying some of the non-critical activities which have float / adjusting the start time of non-critical activities • Activity adjustment – during process, max. requirement does not exceed the limit of available resources Prof. Ashish Makwana 5
  • 6. RESOURCE SMOOTHING • Done – shifting of activities by their available floats, so that a uniform demand for the resources are generated. • Project Time – not change in any case Prof. Ashish Makwana 6
  • 7. SCHEDULING • Meaning – Process of preparing the work plan to a time frame indicating the start and completion of each activity • Preparation – labour, material, machinery, money • Useful – Actual progress of each activity compared to planned programmes for corrective actions and then speed up the work Prof. Ashish Makwana 7
  • 8. 1 2 3 4 5 Bricks Nos. 4500 4000 5500 3000 2600 Sand Cum 20 20 35 25 15 Aggregate Cum 20 35 30 25 30 Cement bags Nos. 110 100 115 120 130 Steel Quintal 0 2 10 2 0 Weeks UnitsMaterial Prepared by______________Name of work______________ Date_________________ Material Schedule Prof. Ashish Makwana 8
  • 9. Labour Schedule 1 2 3 4 5 Carpenters 1 1 1 1 1 Welders 0 0 0 1 1 Mixers Operator 0 0 1 0 0 Masons 1 1 2 2 1 Bar benders 0 2 1 0 0 Labours 3 3 10 6 3 Name of work______________ Manpower (Labour) Weeks Prepared by______________ Date_________________ Prof. Ashish Makwana 9
  • 10. Equipment Schedule 1 2 3 4 5 Concrete Mixer 0 0 1 0 0 Vibrator 0 0 1 0 0 Welding set 0 0 1 1 1 Truck 0 1 1 0.5 0.5 Equipment for erecting trusses 0 0 0 1 0 Name of work______________ Prepared by______________ Date_________________ Equipment Weeks Prof. Ashish Makwana 10
  翻译: