尊敬的 微信汇率:1円 ≈ 0.046239 元 支付宝汇率:1円 ≈ 0.04633元 [退出登录]
SlideShare a Scribd company logo
Presented to: Dr. Josefina B. Bitonio
Professor
Presented by:
Rolinda B. Valdez
DM 211Project Development and Management
 Process whereby “project inputs are
converted to project outputs”. Maybe
looked at as:
 Putting in action the activities of the
project.
 Putting into practice what was proposed in
the project proposal into the actual project
 Management of the project or executing
the project intentions
Ernesto A. Franco 2010
Project Implementation Phase
Project Activation
 This means making arrangements to have the
project started. It involves coordination and
allocation of resources to make project
operational.
Project Operation
This is practical management of a project. Here,
project inputs are transformed into outputs to
achieve immediate objectives.
www.reading.ac.uk/ssc January 15,2014
Project Implementation Plan (PIP)
• If PIP not carried out
during the project design
process and embodied in
the project documents,
it is carried out at the
project activation stage.
4
Project implementation plan includes:
5
The following methods may be used to
answer the above questions:
1. Gantt chart
2. Critical Path Method (CPM) or Net work analysis
3. Project Evaluation and Review Techniques (PERT)
4. Simple formats
What is a GANTT Chart?
• The Gantt chart is also
referred to as the progress
chart.
• It is a chart showing the
timing of project activities
using horizontal bars.
• It is one of the techniques
of project scheduling, which
depicts the frequency of
activities and determines
the period of time for
implementation. 6
How to determine a GANTT chart
• Determine the parts or
implementation phases of the
project and the sequence in which
the associated activities shall be
carried out
• Then estimate the amount of time
required for each activity
• List the activities that can be carried
out at the same time and identify
those to be carried out sequentially
7
How to construct a GANTT chart?
• Time represented on the horizontal axis, and
activities on the vertical axis.
• Bars are entered to indicate the time period
allocated for each activity and the state of
progress at any particular point in time.
8
Project Activity Time Listing
9
Activity
earliest time
Activity
latest time
Activity
code
Activity
Description
Activity
duration
Start Finish Start Finish
Progress
remark
Example: Maize farming project
Activity
• Marketing
• Threshing
• Harvesting
• Weeding
• Planting
• Preparing seedbed
J F M A M J J A S O N D
Time period/ months
10
The Simple Format
11
ACTIVITY STARTING
DATE
ENDING
DATE
COST RESPONSIBLE
PERSON
REMARKS
- Preparing seed bed
- Planning
- Weeding
- Harvesting
- Storage
- Threshing
- Marketing
Project Activity Time Listing
12
Activity
earliest time
Activity
latest time
Activity
code
Activity
Description
Activity
duration
Start Finish Start Finish
Progress
remark
Approaches to Project Implementation
Top- down Approach
 Implementation mainly done by agencies from outside the
community with limited involvement by the beneficiaries.
Bottom-up Approach
 Beneficiaries implement the project. Outside agencies may
provide the financial resources and technical assistance
Collaborative Participatory Approach
 Both top-down and bottom-up approaches to project
implementation are applied in the process.
www.reading.ac.uk/ssc January 15,2014
Project Implementation Plan
It includes:
a. Project implementation schedule
 What activities can produce expected
project outputs?
 What is the sequence of these
activities?
 What is the time frames for these
activities?
 Who will be responsible for carrying
out each activity?
www.reading.ac.uk/ssc January 15,2014
Project Implementation plan (cont.)
b) The role of the implementing agency
 Specific responsibilities of the key staff during the project implementation
and monitoring are outlined.
c) Beneficiary participation
 Involvement of the beneficiaries in planning and implementation and what is
expected is spelt out.
d) Organizational structure and staffing
Consider the following:
> project structure for purposes of management
> qualifications and skills for the staff
> job descriptions and specifications for the staff
> technical assistance if needed
www.reading.ac.uk/ssc January 15,2014
Project Implementation Plan (cont.)
e) Financial management
looks at: funds management
accounting period
financial reports & statements
f) Reporting system
> Who will report?
> Whom to report?
> When to report?
 Standard design and reporting format is needed
g) Sustainability
Project should be sustained beyond the life of funding – especially if it
is a grant.
Project should not exhaust the available resources like raw materials
and labor.
Project Implementation Plan (cont.)
h) Time control and remedial action
Supervisors must be particular in:
 Time control measures
 Time scheduling
 Time extension and postponement
 Damages for non-completion
 Defect or warranty period
i) Project implementation schedule and Supervision
This includes set of checks and balances to ensure that the time
schedule is being adhered to.
Characteristics of A Good Project Manager
Project Manager should:
 Know the project and its objectives
 Have working knowledge in several fields
 Be able to understand general managerial problems
 Have active interest in training and developing
subordinates
 Be able to delegate some tasks to subordinates
 Know the systematic process for managing projects
 Be able to answer the following questions:
> What is the project for?
> Why it is required?
> Whom does it serve?
> How is it justified?
> How is it going to be used?
www.reading.ac.uk/ssc January 15,2014
Factors Affecting
Project
Implementation
Factors Affecting Project Implementation
Factors that lead to SUCCESS of
projects
• Political Commitment
• Simplicity of Design
• Careful Preparation
• Good Management
• Involvement of
beneficiaries/ community
Factors / Problems that lead to
FAILURE of Projects
• Financial problems
• Management Problems
• Technical problems
• Political Problems
Factors Affecting Project Implementation (
Cont.)Typical Implementation Problems
 Poor scheduling of projects leading to delays in
implementation
 Misallocation of funds
 Delay / lack of counterpart funding
 Lack of accountability and transparency
 Bureaucracy in decision- making
 Selfishness/ favoritism by some project managers
 Weak monitoring systems
 Natural calamities
 Lack of teamwork
 Lack of incentives for implementers
 Policy changes
www.reading.ac.uk/ssc
January 15,2014
Ensuring proper compliance of loan requirements
> loan funds may not be withdrawn to meet project expenditures immediately after the loan has
been approved, but must wait until it has “become effective”. The loan agreement provides that
the borrower must comply with the conditions for loan effectiveness within a specified period.
Recruitment of Consultants
Steps in recruiting consultants:
>call for expression of interest
>finalize terms of reference
>request for proposals
>evaluate technical / financial proposals
>negotiate / sign the consulting services contract
>issue the notice to proceed
 There should be Operations Manual that sets out policies, practices, and procedures for
recruiting and using consultants.
DB e-Handbook on Project Implementation
Managing Project Implementation
Managing Project Implementation ( cont.)
• Procurement plans
It identifies the:
 Contracts for goods, works, and consultant services to carry out the project
 Proposed method of procurement for contracts that are permitted under the
financing agreement
 Procurement Process
It involves:
 Bid packaging
 Prequalification (turnkey contracts)
 Preparation of bid documents
 Bid opening
 Bid evaluation
 Contract award
Project Implementation Structure
Should emphasize the following:
 Establish a measurement system
Measure results of work schedule progress, budget,
compliance with technical specifications, and resource
requirements
Report the results
Predict results of deviations
Implement action to correct deviations
Continue to review procedures
Monitor and evaluate performance
The achievement of project objectives requires both
an appropriate organization structure and selection of
best staff for the work.
The project organization should provide:
> functional managers
> flexible use of staff
> operation and maintenance of a core
project team
> simultaneous operation of the functional
organization and the project
Managing
Project
Implementation
The project manager undertakes the following for
implementing the project:
 Preparing for project implementation
1. set up the project office
2. organize the project management staff
3. allocate duties and responsibilities to staff
4. establish information and accounting systems
5. commence the project activities
 Organizing the Project Management Office
PMO should be at the project site or in the nearest
place that has accommodation ,utilities, transport and
communication.
 Recruiting and training personnel
Qualified staffs still needs orientation or training
courses to improve skills and should be assigned to
the PMO full-time during project implementation
 Defining and Assigning PMO staff and
Responsibilities
Functions, responsibilities, job description of each
staff should be clearly defined in order to
make wise decisions and to function well.
cont.
 Establishing a project record system
Project manager must set up and activate project records and
administrative files.
 Obtaining funds required for the initial works
Project manager should ensure that funds are available for
immediate disbursement before undertaking any work that will entail a
financial commitment
 Recruiting and Supervising the work of Consultants
Project manager is responsible to the channels of communication
between the PMO, EA and other project participants.
Cont.
 Supervising Construction of works or installation of
Equipment
> frequent on site inspection
>check contractors compliance with technical
specifications
>review and approve equipment operations
>monitor and compare actual progress of work
compared with the schedule
 Executing Project Covenants
>”undertakings” should be carried out in an efficient and
timely manner
cont.
 Controlling cost
To execute a project within budget and to focus
attention on potential cost problems in time to take
corrective or cost-minimizing actions.
 Controlling Project changes
Should formulate specific procedures for reviewing
and approving changes in the project.
Proposed changes must be studied carefully
considering its implications, costs, schedule and
expected project benefits
Cont.
Project Monitoring and Control
The project manager should continue
to:
 Monitor the progress of project activities
 Review the plan, design of the project at
various stages
 Make extensive use of project control and
accounting systems
 Measure progress and performance
 Track equipment and materials
 Closely monitor the cost
 Prepare project progress reports
>must be detailed enough to identify
and address problems being encountered
Project Commissioning and Completion
• Transferring responsibility for
project operations upon project
completion
• Providing advice and training to
operations staff
• Closing out project team and
project systems including
reassignment of team members,
records and files completions,
reports and completion of work
authorizations
Project Evaluation
Post project evaluation may cover a variety of
key items such as:
Beneficiary impact
Financial compliance
Legal covenants
Actual achievements versus planned objectives
Targets utilizing a variety of methods
Reports
Audits
ADB e-Handbook on Project Implementation
Project Recycling
 Output diffusion which may lead to
policy/program and project
improvements
 Decision to expand, duplicate, abort or
institutionalize
project within the organization
permanently
 Identification of linkages or spillover
investments
 Preparation of follow up investment
proposals
References:
Book
Management in the Philippine Setting
by Ernesto A. Franco
National Book Store pp.85-87
WEB
www.adb.org January 15,2014
eHandbook on Project Implementation
 www.reading.ac.uk/ssc February 10,2014
 www.mhwest.com/downloads/Project_Expansion_Gr
eg_Willis
Thank You

More Related Content

What's hot

project management
project managementproject management
project management
Sanchita Siromoni
 
Project management tools and techniques
Project management tools and techniquesProject management tools and techniques
Project management tools and techniques
Tata Dinyuy
 
PROJECT PLANNING AND MANAGEMENT
PROJECT PLANNING AND MANAGEMENTPROJECT PLANNING AND MANAGEMENT
PROJECT PLANNING AND MANAGEMENT
Abraham Ncunge
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
Slav Karaslavov
 
Project Management
Project ManagementProject Management
Project Management
Mark Roman
 
Project Planning and Development
Project Planning and DevelopmentProject Planning and Development
Project Planning and Development
Jo Balucanag - Bitonio
 
Project implementation
Project implementationProject implementation
Project implementation
Bishnu Deo Yadav
 
Project management cycle
Project management  cycleProject management  cycle
Project management cycle
Megha BHardwaj
 
Project Planning
Project PlanningProject Planning
Project Planning
Srinivasan Rengasamy
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
Jeremy Jay V. Lim, MBB, PMP
 
Project organisation structure
Project organisation structureProject organisation structure
Project organisation structure
sachin kumar sharma
 
PMBOK(Project Management Body of Knowledge)
PMBOK(Project Management Body of Knowledge)PMBOK(Project Management Body of Knowledge)
PMBOK(Project Management Body of Knowledge)
Mohammad Mohammadi
 
Project planning
Project planning Project planning
Project planning
Dipnarayan Thakur
 
Project Monitoring & Evaluation
Project Monitoring & EvaluationProject Monitoring & Evaluation
Project Monitoring & Evaluation
Srinivasan Rengasamy
 
2. project initiation
2. project initiation2. project initiation
2. project initiation
Mad Jutt
 
Project Manangement Introduction
Project Manangement IntroductionProject Manangement Introduction
Project Manangement Introduction
asim78
 
Logical framework
Logical frameworkLogical framework
Logical framework
Md. Ayatullah Khan
 
Project Development
Project Development Project Development
Project Development
Jo Balucanag - Bitonio
 
Ppt on project appraisal
Ppt on project appraisalPpt on project appraisal
Ppt on project appraisal
Hachnayen
 
Lecture 1. general introduction to project management
Lecture 1. general introduction to project management Lecture 1. general introduction to project management
Lecture 1. general introduction to project management
Dania Abdel-aziz
 

What's hot (20)

project management
project managementproject management
project management
 
Project management tools and techniques
Project management tools and techniquesProject management tools and techniques
Project management tools and techniques
 
PROJECT PLANNING AND MANAGEMENT
PROJECT PLANNING AND MANAGEMENTPROJECT PLANNING AND MANAGEMENT
PROJECT PLANNING AND MANAGEMENT
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Project Management
Project ManagementProject Management
Project Management
 
Project Planning and Development
Project Planning and DevelopmentProject Planning and Development
Project Planning and Development
 
Project implementation
Project implementationProject implementation
Project implementation
 
Project management cycle
Project management  cycleProject management  cycle
Project management cycle
 
Project Planning
Project PlanningProject Planning
Project Planning
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
Project organisation structure
Project organisation structureProject organisation structure
Project organisation structure
 
PMBOK(Project Management Body of Knowledge)
PMBOK(Project Management Body of Knowledge)PMBOK(Project Management Body of Knowledge)
PMBOK(Project Management Body of Knowledge)
 
Project planning
Project planning Project planning
Project planning
 
Project Monitoring & Evaluation
Project Monitoring & EvaluationProject Monitoring & Evaluation
Project Monitoring & Evaluation
 
2. project initiation
2. project initiation2. project initiation
2. project initiation
 
Project Manangement Introduction
Project Manangement IntroductionProject Manangement Introduction
Project Manangement Introduction
 
Logical framework
Logical frameworkLogical framework
Logical framework
 
Project Development
Project Development Project Development
Project Development
 
Ppt on project appraisal
Ppt on project appraisalPpt on project appraisal
Ppt on project appraisal
 
Lecture 1. general introduction to project management
Lecture 1. general introduction to project management Lecture 1. general introduction to project management
Lecture 1. general introduction to project management
 

Similar to Project Implementation

Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptx
HarsimratDeo1
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptx
HarsimratDeo1
 
SPM Unit 1.pptx
SPM Unit 1.pptxSPM Unit 1.pptx
SPM Unit 1.pptx
HarshitBisen4
 
Project implimentation
Project implimentationProject implimentation
Project implimentation
Mazhar Poohlah
 
Project management revised
Project management revisedProject management revised
Project management revised
Jubayer Alam Shoikat
 
Project management for technologies MGT410
Project management for technologies   MGT410Project management for technologies   MGT410
Project management for technologies MGT410
Saqib Imran
 
executing process group.pdf
executing process group.pdfexecuting process group.pdf
executing process group.pdf
CommunicationElectro
 
PME- CH 1.pptx
PME- CH 1.pptxPME- CH 1.pptx
PME- CH 1.pptx
ermiasalex30
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
PRIYANSHU KUMAR
 
Project management
Project managementProject management
Project management
Malik Khalid Mehmood
 
Smart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelySmart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectively
Chetan Khanzode
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
Rasan Samarasinghe
 
Project management
Project managementProject management
Project management
Sanjana Bharadwaj
 
PA- 210-G5-Preparing of Project Proposal and other Related needs for the Impl...
PA- 210-G5-Preparing of Project Proposal and other Related needs for the Impl...PA- 210-G5-Preparing of Project Proposal and other Related needs for the Impl...
PA- 210-G5-Preparing of Project Proposal and other Related needs for the Impl...
MarivicPenarubia1
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1
Imoh Etuk
 
assignment on project planning
assignment on project planningassignment on project planning
assignment on project planning
ShantiProconLLPSiteE
 
Unit2 Project phases.pptx
Unit2 Project phases.pptxUnit2 Project phases.pptx
Unit2 Project phases.pptx
AtulBhagwat6
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
Carla Fair-Wright
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business plan
farouq umar
 
Project Management Introduction
Project Management IntroductionProject Management Introduction

Similar to Project Implementation (20)

Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptx
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptx
 
SPM Unit 1.pptx
SPM Unit 1.pptxSPM Unit 1.pptx
SPM Unit 1.pptx
 
Project implimentation
Project implimentationProject implimentation
Project implimentation
 
Project management revised
Project management revisedProject management revised
Project management revised
 
Project management for technologies MGT410
Project management for technologies   MGT410Project management for technologies   MGT410
Project management for technologies MGT410
 
executing process group.pdf
executing process group.pdfexecuting process group.pdf
executing process group.pdf
 
PME- CH 1.pptx
PME- CH 1.pptxPME- CH 1.pptx
PME- CH 1.pptx
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Project management
Project managementProject management
Project management
 
Smart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelySmart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectively
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
Project management
Project managementProject management
Project management
 
PA- 210-G5-Preparing of Project Proposal and other Related needs for the Impl...
PA- 210-G5-Preparing of Project Proposal and other Related needs for the Impl...PA- 210-G5-Preparing of Project Proposal and other Related needs for the Impl...
PA- 210-G5-Preparing of Project Proposal and other Related needs for the Impl...
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1
 
assignment on project planning
assignment on project planningassignment on project planning
assignment on project planning
 
Unit2 Project phases.pptx
Unit2 Project phases.pptxUnit2 Project phases.pptx
Unit2 Project phases.pptx
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business plan
 
Project Management Introduction
Project Management IntroductionProject Management Introduction
Project Management Introduction
 

More from Jo Balucanag - Bitonio

Defining Urban, Urbanization & Urbanism
Defining Urban, Urbanization &  UrbanismDefining Urban, Urbanization &  Urbanism
Defining Urban, Urbanization & Urbanism
Jo Balucanag - Bitonio
 
Lecture on Rural Development Feb 24.pptx
Lecture on Rural Development Feb 24.pptxLecture on Rural Development Feb 24.pptx
Lecture on Rural Development Feb 24.pptx
Jo Balucanag - Bitonio
 
Lecture Presentation on Project Proposal
Lecture Presentation on Project ProposalLecture Presentation on Project Proposal
Lecture Presentation on Project Proposal
Jo Balucanag - Bitonio
 
MPA Lecture on Stakeholder Analysis.pptx
MPA Lecture on Stakeholder Analysis.pptxMPA Lecture on Stakeholder Analysis.pptx
MPA Lecture on Stakeholder Analysis.pptx
Jo Balucanag - Bitonio
 
LEC DEVELOPMENT ISSUES AND CONCERNS.pptx
LEC DEVELOPMENT ISSUES AND CONCERNS.pptxLEC DEVELOPMENT ISSUES AND CONCERNS.pptx
LEC DEVELOPMENT ISSUES AND CONCERNS.pptx
Jo Balucanag - Bitonio
 
Human beings Cause & Consequence of Devt
Human beings Cause & Consequence of DevtHuman beings Cause & Consequence of Devt
Human beings Cause & Consequence of Devt
Jo Balucanag - Bitonio
 
MPA 211: Lecture on WORK ETHICS. pptx
MPA 211:  Lecture  on  WORK ETHICS. pptxMPA 211:  Lecture  on  WORK ETHICS. pptx
MPA 211: Lecture on WORK ETHICS. pptx
Jo Balucanag - Bitonio
 
MPA 212 Lec Training and Development.pdf
MPA 212 Lec Training and Development.pdfMPA 212 Lec Training and Development.pdf
MPA 212 Lec Training and Development.pdf
Jo Balucanag - Bitonio
 
MPA 213 : LECTURE ON SOCIAL-DEVELOPMENT.
MPA 213 : LECTURE ON SOCIAL-DEVELOPMENT.MPA 213 : LECTURE ON SOCIAL-DEVELOPMENT.
MPA 213 : LECTURE ON SOCIAL-DEVELOPMENT.
Jo Balucanag - Bitonio
 
Urban & Metro Admin and Governancges.pdf
Urban & Metro Admin and Governancges.pdfUrban & Metro Admin and Governancges.pdf
Urban & Metro Admin and Governancges.pdf
Jo Balucanag - Bitonio
 
MPA 210 Lecture : Planning & Budgeting
MPA 210  Lecture :  Planning & BudgetingMPA 210  Lecture :  Planning & Budgeting
MPA 210 Lecture : Planning & Budgeting
Jo Balucanag - Bitonio
 
SPMS LECTURE :PERFORMANCE AND EVALUATION
SPMS LECTURE :PERFORMANCE AND EVALUATIONSPMS LECTURE :PERFORMANCE AND EVALUATION
SPMS LECTURE :PERFORMANCE AND EVALUATION
Jo Balucanag - Bitonio
 
Lecture Maintenance & Development of HR.
Lecture Maintenance & Development of HR.Lecture Maintenance & Development of HR.
Lecture Maintenance & Development of HR.
Jo Balucanag - Bitonio
 
Job Analysis, Job Design and Evaluation
Job Analysis, Job Design and  EvaluationJob Analysis, Job Design and  Evaluation
Job Analysis, Job Design and Evaluation
Jo Balucanag - Bitonio
 
MPA 212 Lecture :COPING WITH STRESS.pptx
MPA 212 Lecture :COPING WITH STRESS.pptxMPA 212 Lecture :COPING WITH STRESS.pptx
MPA 212 Lecture :COPING WITH STRESS.pptx
Jo Balucanag - Bitonio
 
MPA 212 Lecture : COACHING AND MENTORING
MPA 212 Lecture : COACHING AND MENTORINGMPA 212 Lecture : COACHING AND MENTORING
MPA 212 Lecture : COACHING AND MENTORING
Jo Balucanag - Bitonio
 
Lec Volatility, Uncertainty, Complexity
Lec  Volatility, Uncertainty, ComplexityLec  Volatility, Uncertainty, Complexity
Lec Volatility, Uncertainty, Complexity
Jo Balucanag - Bitonio
 
HRMD Lec Managing Ethically and Globally
HRMD Lec Managing Ethically and GloballyHRMD Lec Managing Ethically and Globally
HRMD Lec Managing Ethically and Globally
Jo Balucanag - Bitonio
 
Lec : Human Resources - Self Confidence
Lec :  Human Resources - Self ConfidenceLec :  Human Resources - Self Confidence
Lec : Human Resources - Self Confidence
Jo Balucanag - Bitonio
 
Lecture : Adaptive Organizational Design
Lecture : Adaptive Organizational DesignLecture : Adaptive Organizational Design
Lecture : Adaptive Organizational Design
Jo Balucanag - Bitonio
 

More from Jo Balucanag - Bitonio (20)

Defining Urban, Urbanization & Urbanism
Defining Urban, Urbanization &  UrbanismDefining Urban, Urbanization &  Urbanism
Defining Urban, Urbanization & Urbanism
 
Lecture on Rural Development Feb 24.pptx
Lecture on Rural Development Feb 24.pptxLecture on Rural Development Feb 24.pptx
Lecture on Rural Development Feb 24.pptx
 
Lecture Presentation on Project Proposal
Lecture Presentation on Project ProposalLecture Presentation on Project Proposal
Lecture Presentation on Project Proposal
 
MPA Lecture on Stakeholder Analysis.pptx
MPA Lecture on Stakeholder Analysis.pptxMPA Lecture on Stakeholder Analysis.pptx
MPA Lecture on Stakeholder Analysis.pptx
 
LEC DEVELOPMENT ISSUES AND CONCERNS.pptx
LEC DEVELOPMENT ISSUES AND CONCERNS.pptxLEC DEVELOPMENT ISSUES AND CONCERNS.pptx
LEC DEVELOPMENT ISSUES AND CONCERNS.pptx
 
Human beings Cause & Consequence of Devt
Human beings Cause & Consequence of DevtHuman beings Cause & Consequence of Devt
Human beings Cause & Consequence of Devt
 
MPA 211: Lecture on WORK ETHICS. pptx
MPA 211:  Lecture  on  WORK ETHICS. pptxMPA 211:  Lecture  on  WORK ETHICS. pptx
MPA 211: Lecture on WORK ETHICS. pptx
 
MPA 212 Lec Training and Development.pdf
MPA 212 Lec Training and Development.pdfMPA 212 Lec Training and Development.pdf
MPA 212 Lec Training and Development.pdf
 
MPA 213 : LECTURE ON SOCIAL-DEVELOPMENT.
MPA 213 : LECTURE ON SOCIAL-DEVELOPMENT.MPA 213 : LECTURE ON SOCIAL-DEVELOPMENT.
MPA 213 : LECTURE ON SOCIAL-DEVELOPMENT.
 
Urban & Metro Admin and Governancges.pdf
Urban & Metro Admin and Governancges.pdfUrban & Metro Admin and Governancges.pdf
Urban & Metro Admin and Governancges.pdf
 
MPA 210 Lecture : Planning & Budgeting
MPA 210  Lecture :  Planning & BudgetingMPA 210  Lecture :  Planning & Budgeting
MPA 210 Lecture : Planning & Budgeting
 
SPMS LECTURE :PERFORMANCE AND EVALUATION
SPMS LECTURE :PERFORMANCE AND EVALUATIONSPMS LECTURE :PERFORMANCE AND EVALUATION
SPMS LECTURE :PERFORMANCE AND EVALUATION
 
Lecture Maintenance & Development of HR.
Lecture Maintenance & Development of HR.Lecture Maintenance & Development of HR.
Lecture Maintenance & Development of HR.
 
Job Analysis, Job Design and Evaluation
Job Analysis, Job Design and  EvaluationJob Analysis, Job Design and  Evaluation
Job Analysis, Job Design and Evaluation
 
MPA 212 Lecture :COPING WITH STRESS.pptx
MPA 212 Lecture :COPING WITH STRESS.pptxMPA 212 Lecture :COPING WITH STRESS.pptx
MPA 212 Lecture :COPING WITH STRESS.pptx
 
MPA 212 Lecture : COACHING AND MENTORING
MPA 212 Lecture : COACHING AND MENTORINGMPA 212 Lecture : COACHING AND MENTORING
MPA 212 Lecture : COACHING AND MENTORING
 
Lec Volatility, Uncertainty, Complexity
Lec  Volatility, Uncertainty, ComplexityLec  Volatility, Uncertainty, Complexity
Lec Volatility, Uncertainty, Complexity
 
HRMD Lec Managing Ethically and Globally
HRMD Lec Managing Ethically and GloballyHRMD Lec Managing Ethically and Globally
HRMD Lec Managing Ethically and Globally
 
Lec : Human Resources - Self Confidence
Lec :  Human Resources - Self ConfidenceLec :  Human Resources - Self Confidence
Lec : Human Resources - Self Confidence
 
Lecture : Adaptive Organizational Design
Lecture : Adaptive Organizational DesignLecture : Adaptive Organizational Design
Lecture : Adaptive Organizational Design
 

Recently uploaded

一比一原版(毕业证)一桥大学毕业证如何办理
一比一原版(毕业证)一桥大学毕业证如何办理一比一原版(毕业证)一桥大学毕业证如何办理
一比一原版(毕业证)一桥大学毕业证如何办理
taqyea
 
Progress Report - Qualcomm AI Workshop - AI available - everywhereAI summit 1...
Progress Report - Qualcomm AI Workshop - AI available - everywhereAI summit 1...Progress Report - Qualcomm AI Workshop - AI available - everywhereAI summit 1...
Progress Report - Qualcomm AI Workshop - AI available - everywhereAI summit 1...
Holger Mueller
 
Kalyan Chart Satta Matka Dpboss Kalyan Matka Results
Kalyan Chart Satta Matka Dpboss Kalyan Matka ResultsKalyan Chart Satta Matka Dpboss Kalyan Matka Results
Kalyan Chart Satta Matka Dpboss Kalyan Matka Results
Satta Matka Dpboss Kalyan Matka Results
 
Revolutionizing Surface Protection Xlcoatings Nano Based Solutions
Revolutionizing Surface Protection Xlcoatings Nano Based SolutionsRevolutionizing Surface Protection Xlcoatings Nano Based Solutions
Revolutionizing Surface Protection Xlcoatings Nano Based Solutions
Excel coatings
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Call Girls Chandigarh👉9024918724👉Agency 💞Profile Escorts in Chandigarh Availa...
Call Girls Chandigarh👉9024918724👉Agency 💞Profile Escorts in Chandigarh Availa...Call Girls Chandigarh👉9024918724👉Agency 💞Profile Escorts in Chandigarh Availa...
Call Girls Chandigarh👉9024918724👉Agency 💞Profile Escorts in Chandigarh Availa...
nitachopra
 
Kanban Coaching Exchange with Dave White - Sample SDR Report
Kanban Coaching Exchange with Dave White - Sample SDR ReportKanban Coaching Exchange with Dave White - Sample SDR Report
Kanban Coaching Exchange with Dave White - Sample SDR Report
Helen Meek
 
Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...
Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...
Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...
Adani case
 
DPboss Indian Satta Matta Matka Result Fix Matka Number
DPboss Indian Satta Matta Matka Result Fix Matka NumberDPboss Indian Satta Matta Matka Result Fix Matka Number
DPboss Indian Satta Matta Matka Result Fix Matka Number
Satta Matka
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
Adani case
 
Kanban Coaching Exchange with Dave White - Example SDR Report
Kanban Coaching Exchange with Dave White - Example SDR ReportKanban Coaching Exchange with Dave White - Example SDR Report
Kanban Coaching Exchange with Dave White - Example SDR Report
Helen Meek
 
➒➌➎➏➑➐➋➑➐➐ Satta Matta Matka Dpboss Matka Guessing Kalyan panel Chart
➒➌➎➏➑➐➋➑➐➐ Satta Matta Matka Dpboss Matka Guessing Kalyan panel Chart➒➌➎➏➑➐➋➑➐➐ Satta Matta Matka Dpboss Matka Guessing Kalyan panel Chart
➒➌➎➏➑➐➋➑➐➐ Satta Matta Matka Dpboss Matka Guessing Kalyan panel Chart
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
Truck Loading Conveyor Manufacturers Chennai
Truck Loading Conveyor Manufacturers ChennaiTruck Loading Conveyor Manufacturers Chennai
Truck Loading Conveyor Manufacturers Chennai
ConveyorSystem
 
一比一原版(UU毕业证)犹他大学毕业证如何办理
一比一原版(UU毕业证)犹他大学毕业证如何办理一比一原版(UU毕业证)犹他大学毕业证如何办理
一比一原版(UU毕业证)犹他大学毕业证如何办理
taqyea
 
Satta Matka Kalyan Matka Satta Matka Guessing
Satta Matka Kalyan Matka Satta Matka GuessingSatta Matka Kalyan Matka Satta Matka Guessing
Satta Matka Kalyan Matka Satta Matka Guessing
DP Boss Satta Matka Kalyan Matka
 
L'indice de performance des ports à conteneurs de l'année 2023
L'indice de performance des ports à conteneurs de l'année 2023L'indice de performance des ports à conteneurs de l'année 2023
L'indice de performance des ports à conteneurs de l'année 2023
SPATPortToamasina
 
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
Intelligent Small Boat Security Solution - June 2024
Intelligent Small Boat Security Solution - June 2024Intelligent Small Boat Security Solution - June 2024
Intelligent Small Boat Security Solution - June 2024
Hector Del Castillo, CPM, CPMM
 

Recently uploaded (20)

一比一原版(毕业证)一桥大学毕业证如何办理
一比一原版(毕业证)一桥大学毕业证如何办理一比一原版(毕业证)一桥大学毕业证如何办理
一比一原版(毕业证)一桥大学毕业证如何办理
 
Progress Report - Qualcomm AI Workshop - AI available - everywhereAI summit 1...
Progress Report - Qualcomm AI Workshop - AI available - everywhereAI summit 1...Progress Report - Qualcomm AI Workshop - AI available - everywhereAI summit 1...
Progress Report - Qualcomm AI Workshop - AI available - everywhereAI summit 1...
 
Kalyan Chart Satta Matka Dpboss Kalyan Matka Results
Kalyan Chart Satta Matka Dpboss Kalyan Matka ResultsKalyan Chart Satta Matka Dpboss Kalyan Matka Results
Kalyan Chart Satta Matka Dpboss Kalyan Matka Results
 
Revolutionizing Surface Protection Xlcoatings Nano Based Solutions
Revolutionizing Surface Protection Xlcoatings Nano Based SolutionsRevolutionizing Surface Protection Xlcoatings Nano Based Solutions
Revolutionizing Surface Protection Xlcoatings Nano Based Solutions
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
Call Girls Chandigarh👉9024918724👉Agency 💞Profile Escorts in Chandigarh Availa...
Call Girls Chandigarh👉9024918724👉Agency 💞Profile Escorts in Chandigarh Availa...Call Girls Chandigarh👉9024918724👉Agency 💞Profile Escorts in Chandigarh Availa...
Call Girls Chandigarh👉9024918724👉Agency 💞Profile Escorts in Chandigarh Availa...
 
Kanban Coaching Exchange with Dave White - Sample SDR Report
Kanban Coaching Exchange with Dave White - Sample SDR ReportKanban Coaching Exchange with Dave White - Sample SDR Report
Kanban Coaching Exchange with Dave White - Sample SDR Report
 
Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...
Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...
Adani Group Requests For Additional Land For Its Dharavi Redevelopment Projec...
 
DPboss Indian Satta Matta Matka Result Fix Matka Number
DPboss Indian Satta Matta Matka Result Fix Matka NumberDPboss Indian Satta Matta Matka Result Fix Matka Number
DPboss Indian Satta Matta Matka Result Fix Matka Number
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
Adani Group's Active Interest In Increasing Its Presence in the Cement Manufa...
 
Kanban Coaching Exchange with Dave White - Example SDR Report
Kanban Coaching Exchange with Dave White - Example SDR ReportKanban Coaching Exchange with Dave White - Example SDR Report
Kanban Coaching Exchange with Dave White - Example SDR Report
 
➒➌➎➏➑➐➋➑➐➐ Satta Matta Matka Dpboss Matka Guessing Kalyan panel Chart
➒➌➎➏➑➐➋➑➐➐ Satta Matta Matka Dpboss Matka Guessing Kalyan panel Chart➒➌➎➏➑➐➋➑➐➐ Satta Matta Matka Dpboss Matka Guessing Kalyan panel Chart
➒➌➎➏➑➐➋➑➐➐ Satta Matta Matka Dpboss Matka Guessing Kalyan panel Chart
 
Truck Loading Conveyor Manufacturers Chennai
Truck Loading Conveyor Manufacturers ChennaiTruck Loading Conveyor Manufacturers Chennai
Truck Loading Conveyor Manufacturers Chennai
 
一比一原版(UU毕业证)犹他大学毕业证如何办理
一比一原版(UU毕业证)犹他大学毕业证如何办理一比一原版(UU毕业证)犹他大学毕业证如何办理
一比一原版(UU毕业证)犹他大学毕业证如何办理
 
Satta Matka Kalyan Matka Satta Matka Guessing
Satta Matka Kalyan Matka Satta Matka GuessingSatta Matka Kalyan Matka Satta Matka Guessing
Satta Matka Kalyan Matka Satta Matka Guessing
 
L'indice de performance des ports à conteneurs de l'année 2023
L'indice de performance des ports à conteneurs de l'année 2023L'indice de performance des ports à conteneurs de l'année 2023
L'indice de performance des ports à conteneurs de l'année 2023
 
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
➒➌➎➏➑➐➋➑➐➐ Satta Matka Dpboss Matka Guessing Indian Matka
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
Intelligent Small Boat Security Solution - June 2024
Intelligent Small Boat Security Solution - June 2024Intelligent Small Boat Security Solution - June 2024
Intelligent Small Boat Security Solution - June 2024
 

Project Implementation

  • 1. Presented to: Dr. Josefina B. Bitonio Professor Presented by: Rolinda B. Valdez DM 211Project Development and Management
  • 2.  Process whereby “project inputs are converted to project outputs”. Maybe looked at as:  Putting in action the activities of the project.  Putting into practice what was proposed in the project proposal into the actual project  Management of the project or executing the project intentions Ernesto A. Franco 2010
  • 3. Project Implementation Phase Project Activation  This means making arrangements to have the project started. It involves coordination and allocation of resources to make project operational. Project Operation This is practical management of a project. Here, project inputs are transformed into outputs to achieve immediate objectives. www.reading.ac.uk/ssc January 15,2014
  • 4. Project Implementation Plan (PIP) • If PIP not carried out during the project design process and embodied in the project documents, it is carried out at the project activation stage. 4
  • 5. Project implementation plan includes: 5 The following methods may be used to answer the above questions: 1. Gantt chart 2. Critical Path Method (CPM) or Net work analysis 3. Project Evaluation and Review Techniques (PERT) 4. Simple formats
  • 6. What is a GANTT Chart? • The Gantt chart is also referred to as the progress chart. • It is a chart showing the timing of project activities using horizontal bars. • It is one of the techniques of project scheduling, which depicts the frequency of activities and determines the period of time for implementation. 6
  • 7. How to determine a GANTT chart • Determine the parts or implementation phases of the project and the sequence in which the associated activities shall be carried out • Then estimate the amount of time required for each activity • List the activities that can be carried out at the same time and identify those to be carried out sequentially 7
  • 8. How to construct a GANTT chart? • Time represented on the horizontal axis, and activities on the vertical axis. • Bars are entered to indicate the time period allocated for each activity and the state of progress at any particular point in time. 8
  • 9. Project Activity Time Listing 9 Activity earliest time Activity latest time Activity code Activity Description Activity duration Start Finish Start Finish Progress remark
  • 10. Example: Maize farming project Activity • Marketing • Threshing • Harvesting • Weeding • Planting • Preparing seedbed J F M A M J J A S O N D Time period/ months 10
  • 11. The Simple Format 11 ACTIVITY STARTING DATE ENDING DATE COST RESPONSIBLE PERSON REMARKS - Preparing seed bed - Planning - Weeding - Harvesting - Storage - Threshing - Marketing
  • 12. Project Activity Time Listing 12 Activity earliest time Activity latest time Activity code Activity Description Activity duration Start Finish Start Finish Progress remark
  • 13. Approaches to Project Implementation Top- down Approach  Implementation mainly done by agencies from outside the community with limited involvement by the beneficiaries. Bottom-up Approach  Beneficiaries implement the project. Outside agencies may provide the financial resources and technical assistance Collaborative Participatory Approach  Both top-down and bottom-up approaches to project implementation are applied in the process. www.reading.ac.uk/ssc January 15,2014
  • 14. Project Implementation Plan It includes: a. Project implementation schedule  What activities can produce expected project outputs?  What is the sequence of these activities?  What is the time frames for these activities?  Who will be responsible for carrying out each activity? www.reading.ac.uk/ssc January 15,2014
  • 15. Project Implementation plan (cont.) b) The role of the implementing agency  Specific responsibilities of the key staff during the project implementation and monitoring are outlined. c) Beneficiary participation  Involvement of the beneficiaries in planning and implementation and what is expected is spelt out. d) Organizational structure and staffing Consider the following: > project structure for purposes of management > qualifications and skills for the staff > job descriptions and specifications for the staff > technical assistance if needed www.reading.ac.uk/ssc January 15,2014
  • 16. Project Implementation Plan (cont.) e) Financial management looks at: funds management accounting period financial reports & statements f) Reporting system > Who will report? > Whom to report? > When to report?  Standard design and reporting format is needed g) Sustainability Project should be sustained beyond the life of funding – especially if it is a grant. Project should not exhaust the available resources like raw materials and labor.
  • 17. Project Implementation Plan (cont.) h) Time control and remedial action Supervisors must be particular in:  Time control measures  Time scheduling  Time extension and postponement  Damages for non-completion  Defect or warranty period i) Project implementation schedule and Supervision This includes set of checks and balances to ensure that the time schedule is being adhered to.
  • 18. Characteristics of A Good Project Manager Project Manager should:  Know the project and its objectives  Have working knowledge in several fields  Be able to understand general managerial problems  Have active interest in training and developing subordinates  Be able to delegate some tasks to subordinates  Know the systematic process for managing projects  Be able to answer the following questions: > What is the project for? > Why it is required? > Whom does it serve? > How is it justified? > How is it going to be used? www.reading.ac.uk/ssc January 15,2014
  • 20. Factors Affecting Project Implementation Factors that lead to SUCCESS of projects • Political Commitment • Simplicity of Design • Careful Preparation • Good Management • Involvement of beneficiaries/ community Factors / Problems that lead to FAILURE of Projects • Financial problems • Management Problems • Technical problems • Political Problems
  • 21. Factors Affecting Project Implementation ( Cont.)Typical Implementation Problems  Poor scheduling of projects leading to delays in implementation  Misallocation of funds  Delay / lack of counterpart funding  Lack of accountability and transparency  Bureaucracy in decision- making  Selfishness/ favoritism by some project managers  Weak monitoring systems  Natural calamities  Lack of teamwork  Lack of incentives for implementers  Policy changes www.reading.ac.uk/ssc January 15,2014
  • 22. Ensuring proper compliance of loan requirements > loan funds may not be withdrawn to meet project expenditures immediately after the loan has been approved, but must wait until it has “become effective”. The loan agreement provides that the borrower must comply with the conditions for loan effectiveness within a specified period. Recruitment of Consultants Steps in recruiting consultants: >call for expression of interest >finalize terms of reference >request for proposals >evaluate technical / financial proposals >negotiate / sign the consulting services contract >issue the notice to proceed  There should be Operations Manual that sets out policies, practices, and procedures for recruiting and using consultants. DB e-Handbook on Project Implementation Managing Project Implementation
  • 23. Managing Project Implementation ( cont.) • Procurement plans It identifies the:  Contracts for goods, works, and consultant services to carry out the project  Proposed method of procurement for contracts that are permitted under the financing agreement  Procurement Process It involves:  Bid packaging  Prequalification (turnkey contracts)  Preparation of bid documents  Bid opening  Bid evaluation  Contract award
  • 24. Project Implementation Structure Should emphasize the following:  Establish a measurement system Measure results of work schedule progress, budget, compliance with technical specifications, and resource requirements Report the results Predict results of deviations Implement action to correct deviations Continue to review procedures Monitor and evaluate performance The achievement of project objectives requires both an appropriate organization structure and selection of best staff for the work. The project organization should provide: > functional managers > flexible use of staff > operation and maintenance of a core project team > simultaneous operation of the functional organization and the project
  • 25. Managing Project Implementation The project manager undertakes the following for implementing the project:  Preparing for project implementation 1. set up the project office 2. organize the project management staff 3. allocate duties and responsibilities to staff 4. establish information and accounting systems 5. commence the project activities  Organizing the Project Management Office PMO should be at the project site or in the nearest place that has accommodation ,utilities, transport and communication.  Recruiting and training personnel Qualified staffs still needs orientation or training courses to improve skills and should be assigned to the PMO full-time during project implementation  Defining and Assigning PMO staff and Responsibilities Functions, responsibilities, job description of each staff should be clearly defined in order to make wise decisions and to function well.
  • 26. cont.  Establishing a project record system Project manager must set up and activate project records and administrative files.  Obtaining funds required for the initial works Project manager should ensure that funds are available for immediate disbursement before undertaking any work that will entail a financial commitment  Recruiting and Supervising the work of Consultants Project manager is responsible to the channels of communication between the PMO, EA and other project participants.
  • 27. Cont.  Supervising Construction of works or installation of Equipment > frequent on site inspection >check contractors compliance with technical specifications >review and approve equipment operations >monitor and compare actual progress of work compared with the schedule  Executing Project Covenants >”undertakings” should be carried out in an efficient and timely manner
  • 28. cont.  Controlling cost To execute a project within budget and to focus attention on potential cost problems in time to take corrective or cost-minimizing actions.  Controlling Project changes Should formulate specific procedures for reviewing and approving changes in the project. Proposed changes must be studied carefully considering its implications, costs, schedule and expected project benefits
  • 29. Cont. Project Monitoring and Control The project manager should continue to:  Monitor the progress of project activities  Review the plan, design of the project at various stages  Make extensive use of project control and accounting systems  Measure progress and performance  Track equipment and materials  Closely monitor the cost  Prepare project progress reports >must be detailed enough to identify and address problems being encountered
  • 30. Project Commissioning and Completion • Transferring responsibility for project operations upon project completion • Providing advice and training to operations staff • Closing out project team and project systems including reassignment of team members, records and files completions, reports and completion of work authorizations
  • 31. Project Evaluation Post project evaluation may cover a variety of key items such as: Beneficiary impact Financial compliance Legal covenants Actual achievements versus planned objectives Targets utilizing a variety of methods Reports Audits ADB e-Handbook on Project Implementation
  • 32. Project Recycling  Output diffusion which may lead to policy/program and project improvements  Decision to expand, duplicate, abort or institutionalize project within the organization permanently  Identification of linkages or spillover investments  Preparation of follow up investment proposals
  • 33. References: Book Management in the Philippine Setting by Ernesto A. Franco National Book Store pp.85-87 WEB www.adb.org January 15,2014 eHandbook on Project Implementation  www.reading.ac.uk/ssc February 10,2014  www.mhwest.com/downloads/Project_Expansion_Gr eg_Willis
  翻译: