尊敬的 微信汇率:1円 ≈ 0.046239 元 支付宝汇率:1円 ≈ 0.04633元 [退出登录]
SlideShare a Scribd company logo
W01.JNB.000682 Gokwe Water Tank
1 BENDING REINFORCEMENT CALCULATION
1.1 Moment diagram giving Max Sagging Moment:
See Elastic Beam design calculations Strip A (DL + LL)
1.1.1 Required reinforcement area for Max Sagging Moment:
Mmax = 416.1 kNm
fcu = 20Mpa; fy = 450Mpa
cover = 30mm
Thickness of the beam: 500mm
Assumed diameter of reinforcement: d = 32mm
deff = 500 – 30 – 32/2 = 454mm
k = Mmax / (b x deff
2
x fcu) = 0.1  (1m strip: b=1000mm)
y = 0.5 + √0.25 − 𝑘/0.9 = 0.87
z = y x deff = 395mm
As = Mmax / (0.87 x fy x z) = 2691 mm2
/m
Adopt Y25 @175mm c/c: As = 2810 mm2
/m’
1.1.2 Required reinforcement area for Additional Sagging Moment:
Mmax = 235 kNm
fcu = 20Mpa; fy = 450Mpa
cover = 30mm
Thickness of the beam: 500mm
Assumed diameter of reinforcement: d = 32mm
deff = 500 – 30 – 32/2 = 454mm
k = Mmax / (b x deff
2
x fcu) = 0.057  (1m strip: b=1000mm)
y = 0.5 + √0.25 − 𝑘/0.9 = 0.93
Max Sagging Moment
Additional Sagging
Moment
W01.JNB.000682 Gokwe Water Tank
z = y x deff = 422mm
As = Mmax / (0.87 x fy x z) = 1422 mm2
/m
Adopt Y20 @200mm c/c: As = 1570 mm2
/m
1.2 Moment diagram giving Max Hogging Moment:
See Elastic Beam design calculations Strip C (DL + WL)
1.2.1 Required reinforcement area for Max Hogging Moment:
Mmax = 52.82 kNm
fcu = 20Mpa; fy = 450Mpa
cover = 30mm
Thickness of the beam: 500mm
Assumed diameter of reinforcement: d = 32mm
deff = 500 – 30 – 32/2 = 454mm
k = Mmax / (b x deff
2
x fcu) = 0.013  (1m strip: b=1000mm)
y = 0.5 + √0.25 − 𝑘/0.9 = 0.985  Adopt y = 0.95
z = y x deff = 431mm
As = Mmax / (0.87 x fy x z) = 313 mm2
/m
Adopt Y12 @ 250mm c/c: As = 452 mm2
/m
Max Hogging Moment
W01.JNB.000682 Gokwe Water Tank
1.3 Reinforcement sketch
1.3.1 Bottom Reinforcing – B1
1.3.2 Bottom Reinforcing – B2
Y20 @ 200 Y20 @ 200 Y20 @ 200
Y20 @ 200Y20 @ 200
Y20 @ 200 Y20 @ 200 Y20 @ 200
Y20 @ 100
Y20 @ 200 Y20 @ 200 Y20 @ 200
Y20 @ 200Y20 @ 200
Y20 @ 200 Y20 @ 200 Y20 @ 200
Y20 @ 100
W01.JNB.000682 Gokwe Water Tank
1.3.3 Top Reinforcing – T1 & T2
Y12 @ 250 Y12 @ 250 Y12 @ 250
Y12 @ 250Y12 @ 250
Y12 @ 250 Y12 @ 250 Y12 @ 250
Y12 @ 250
W01.JNB.000682 Gokwe Water Tank
2 UPLIFT OF FOUNDATION DUE TO COLUMN & SOIL LOADING FROM
ABOVE
2.1 Strip A (1m Strip width)
2.1.1 Uniformly Distributed Load from Column & Soil
From the reactions output (pg 1 of the foundation design): F = 361.8 kN + 489 kN + 361.8 kN = 1212.6 kN
Length of strip A: L = 10 mm
Thus the uniformly distributed load from the 3 columns located on Strip A: UDLstrip A = F/L = 121.3 kN/m
The uniformly distributed load from the 0.5m layer soil ontop of the foundation: UDLsoil = 18 x 1 x 0.5 = 9 kN/m
2.1.2 Moment Diagram giving Max Hogging Moment
Refer to the Elastic Beam Design for Strip A: Uplift due to Column & Soil Loads from the Top (no soil underneath)
for the calculation of the moments.
2.1.3 Required reinforcement area for Hogging Moment:
Mmax = 33.55 kNm
fcu = 20Mpa; fy = 450Mpa
cover = 30mm
Thickness of the beam: 500mm
Assumed diameter of reinforcement: d = 20mm
Hogging Moments
form here due to
downward load of the 3
columns and the 0.5m
layer soil on top of the
foundation
Hogging
Moments
W01.JNB.000682 Gokwe Water Tank
deff = 500 – 30 – 20/2 = 460mm
k = Mmax / (b x deff
2
x fcu) = 0.008  (1m strip: b=1000mm)
y = 0.5 + √0.25 − 𝑘/0.9 = 0.99  Adopt y = 0.95
z = y x deff = 437mm
As = Mmax / (0.87 x fy x z) = 196 mm2
/m
Adopt Y10 @ 250mm c/c: As = 314 mm2
/m
2.2 Strip B (1m Strip width)
2.2.1 Uniformly Distributed Load from Column & Soil
From the reactions output (pg 1 of the foundation design): F = 375.8 kN + 489 kN + 375.8 kN = 1240.6 kN
Length of strip A: L = 12 mm
Thus the uniformly distributed load from the 3 columns located on Strip A: UDLstrip A = F/L = 103.4 kN/m
The uniformly distributed load from the 0.5m layer soil ontop of the foundation: UDLsoil = 18 x 1 x 0.5 = 9 kN/m
The uniformly distributed self-weight of the foundation slab = UDLself = 25 x 1 x 0.5 = 12.5 kN/m
2.2.2 Moment Diagram giving Max Hogging Moment
Refer to the Elastic Beam Design for Strip B: Uplift due to Column & Soil Loads from the Top (no soil underneath)
for the calculation of the moments.
Hogging Moments
form here due to
downward load of the 3
columns and the 0.5m
layer soil on top of the
foundation
Hogging
Moments
W01.JNB.000682 Gokwe Water Tank
2.2.3 Required reinforcement area for Hogging Moment:
Mmax = 59.6 kNm
fcu = 20Mpa; fy = 450Mpa
cover = 30mm
Thickness of the beam: 500mm
Assumed diameter of reinforcement: d = 20mm
deff = 500 – 30 – 20/2 = 460mm
k = Mmax / (b x deff
2
x fcu) = 0.014  (1m strip: b=1000mm)
y = 0.5 + √0.25 − 𝑘/0.9 = 0.98  Adopt y = 0.95
z = y x deff = 437mm
As = Mmax / (0.87 x fy x z) = 325 mm2
/m
Adopt Y12 @ 250mm c/c: As = 452 mm2
/m
2.3 Strip C (1m Strip width)
2.3.1 Uniformly Distributed Load from Column & Soil
From the reactions output (pg 1 of the foundation design): F = -77.3 kN +(-87.6) kN + (-77.3) kN = -242.2 kN
Length of strip A: L = 12 mm
Thus the uniformly distributed load from the 3 columns located on Strip A: UDLstrip A = F/L = -20.2 kN/m
The uniformly distributed load from the 0.5m layer soil ontop of the foundation: UDLsoil = 18 x 1 x 0.5 = 9 kN/m
2.3.2 Moment Diagram giving Max Hogging Moment
Refer to the Elastic Beam Design for Strip C: Uplift due to Column & Soil Loads from the Top (no soil underneath)
for the calculation of the moments.
Hogging Moments
form here due to the
dominant upward load
of the 3 columns
(caused by dominant
wind force.
W01.JNB.000682 Gokwe Water Tank
2.3.3 Required reinforcement area for Hogging Moment:
Mmax = 22.4 kNm
fcu = 20Mpa; fy = 450Mpa
cover = 30mm
Thickness of the beam: 500mm
Assumed diameter of reinforcement: d = 20mm
deff = 500 – 30 – 20/2 = 460mm
k = Mmax / (b x deff
2
x fcu) = 0.005  (1m strip: b=1000mm)
y = 0.5 + √0.25 − 𝑘/0.9 = 0.99  Adopt y = 0.95
z = y x deff = 437mm
As = Mmax / (0.87 x fy x z) = 131 mm2
/m
Adopt Y10 @ 250mm c/c: As = 314 mm2
/m
 Thus Y12 @ 250mm c/c will be sufficient
Hogging
Moments
W01.JNB.000682 Gokwe Water Tank
3 CONNECTION DESIGN
3.1 Detail 1 (Fixed Connection)
Beam 1 lies on top of the column (connected to the column with a column end plate) and beam 2 (notched)
connects into beam 1. Beams 3 & 4 will then be welded to the column.
3.1.1 Column End Plate
 The axial load of the beam  shear force in the connection
 The axial load in the column  axial load in the connection
 The moment in the beam or column (the biggest one in order to be conservative)  the moment in the
connection
See Attached beam-col connection design done in Prokon.
Beam 2 (Supported Beam)
Beam 1 (Supporting Beam)
Beam 3 & 4 (Walkway Supporting Beams)
FORCES & MOMENT IN THE CONNECTION:
 V = 21.8 kN
 Axial: P = 164.7 kN (Compression)
 M = 38.5 kNm
V
M
P
W01.JNB.000682 Gokwe Water Tank
3.1.2 Top Plate (to make the connection a fixed connection)
Detail 1 requires to be a fixed connection hence a top plate needs to be bolted to the top flanges of beam 1 and
beam 2 in order to fix the beam to beam connection. The concept shown below will be used for the top plate
design. A normal beam-col connection will be done in Prokon and the plate thickness and bolt sizes obtained
from that design will be used for the top plate thickness and bolt specs.
See the attached beam-col connection design for the calculation of the top plate thickness and bolt size.
3.1.3 Cleat Design
Beam 2 will notched at the top and bottom in order to fit into beam 1. Beam 2 will be bolted to an angle (both
sides) and then bolted to beam 1.
Beam 2
Beam 1
V
M
P
FORCES & MOMENT IN BEAM 2
(see beam element end forces table for connection 1)
 V = 71.23 kN
 Axial: P = 13.34 kN
 M = 39.77 kNm
Beam 2
Beam 1
W01.JNB.000682 Gokwe Water Tank
The following assumptions were made:
 M16 Bolts
 3 Bolts in a row
 90 x 90 x 8 Angles
 Cleat dimensions as follows:
Shear and Bearing Resistance of Bolts in Supported Beam
 Vr = 0.6ØnmAb0.7fuvr = 170 kN > V = 71.23 kN OK
 Br = 3Øtwdboltnfubr = 299 kN > V = 71.23 kN OK
Shear and Bearing Resistance of Bolts in Supporting Beam
 Vr = 0.6ØnmAb0.7fuvr = 170 kN > V = 71.23 kN OK
 Br = 3Øtwdboltnfubr = 599 kN > V = 71.23 kN OK
Shear and Bearing Resistance of Angle Cleats (2 angle cleats)
 Vr = 2(0.5ØLntfu) = 473 kN > V = 71.23 kN OK
 Br = Øtnafu = 289 kN > V = 71.23 kN OK
Tension in Bolts of Supported Beam
50
50
80
80
50 40
Øvr bolt = 0.8
Øbr bolt = 0.67
n = 3
m = 2
Ab = 201 mm2
fuvr = 420 x 10-3
tw = 6.9 mm
dbolt = 16 mm
fubr = 450 x 10-3
Øvr bolt = 0.8
Øbr bolt = 0.67
n = 6
m = 1
Ab = 201 mm2
fuvr = 420 x 10-3
tw = 6.9 mm
dbolt = 16 mm
fubr = 450 x 10-3
Øvr = 0.9
Øbr = 0.67
n = 3
a = 40
fu = 450 x 10-3
t = 8 mm
Ln = 200 – (3x18) = 146 mm
Øb = 0.8
Ab = 201
fu = 800 x 10-3
(Grade 8.8 Bolts
M = 39.77 kNm
Top bolt is in Tension
Bottom bolt is in Compression
160mm
W01.JNB.000682 Gokwe Water Tank
T = C = M/distance between top bolt and bottom bolt from the centre
T = C = 39.77 / 0.08m = 497 kN
Tu = P + T = 13.34 + 497 = 510.5 kN
there are 2 cleats (on either side of beam 2’s web)
Thus: Tu = 510.5 / 2 = 255 kN
Tr = 2(0.75ØbAbfu) = 192 kN < Tu = 255 kN NOT OK
Tr = 301 kN (with M20 bolts) > Tu = 255 kN OK
Combined Shear and Tension of Bolts
Vu / Vr + Tu / Tr = (71.23 / 170) + (255 / 301) = 1.27 < 1.4 OK
Tension and Shear Block Failure of Cleat
Tr + Vr = ØAntfu + 0.6ØAnvfy = 506 kN > Tu = 255 kN OK
Use M20 Bolts
Ø = 0.9
fu = 450 x 10-3
fy = 300 x 10-3
Ant = (160 – 1x18)(8) = 1136 mm2
Agv = (40)(8) = 320 mm2
Anv = (40 – 0.25(18))(8) = 284 mm2
Thus Use M20 Bolts for Detail 1: Cleat Connection
W01.JNB.000682 Gokwe Water Tank
3.2 Detail 2 (Pinned Connection)
Beam 1 lies on top of the column (connected to the column with a column end plate) and beam 2 (notched top
and bottom) connects into beam 1. Beam 3 will then be welded to the column or to beam 2.
3.2.1 Column End Plate
 The axial load of the beam  shear force in the connection
 The axial load in the column  axial load in the connection
 The moment in the beam or column (the biggest one in order to be conservative)  the moment in the
connection
See Attached beam-col connection design done in Prokon.
Beam 2 (Supported Beam)
Beam 1 (Supporting Beam)
Beam 3 (Walkway Supporting Beams)
FORCES & MOMENT IN THE CONNECTION:
 V = 33.78 kN
 Axial: P = 293.93 kN (Compression)
 M = 76 kNm
V
M
P
W01.JNB.000682 Gokwe Water Tank
3.2.2 Cleat Design
Beam 2 will notched at the top and bottom in order to fit into beam 1. Beam 2 will be bolted to an angle (both
sides) and then bolted to beam 1.
The following assumptions were made:
*Note: the same bolt sizes, bolts in a row and cleat dimensions were chosen on order to keep all the cleat
connections uniform so as to simplify operations on site.
 M16 Bolts
 3 Bolts in a row
 90 x 90 x 8 Angles
 Cleat dimensions as follows:
Shear and Bearing Resistance of Bolts in Supported Beam
 Vr = 0.6ØnmAb0.7fuvr = 170 kN > V = 50.5 kN OK
 Br = 3Øtwdboltnfubr = 299 kN > V = 50.5 kN OK
Shear and Bearing Resistance of Bolts in Supporting Beam
V
M
P
FORCES & MOMENT IN BEAM 2
(see beam element end forces table for connection 1)
 V = 50.5 kN
 Axial: P = 3.11 kN
 M = 0 kNm (beam 2 pinned to beam 1)
Beam 2 (Supported Beam)
Beam 1 (Supporting Beam)
50
50
80
80
50 40
Øvr bolt = 0.8
Øbr bolt = 0.67
n = 3
m = 2
Ab = 201 mm2
fuvr = 420 x 10-3
tw = 6.9 mm
dbolt = 16 mm
fubr = 450 x 10-3
Øvr bolt = 0.8
Øbr bolt = 0.67
n = 6
m = 1
Ab = 201 mm2
fuvr = 420 x 10-3
tw = 8 mm
dbolt = 16 mm
fubr = 450 x 10-3
W01.JNB.000682 Gokwe Water Tank
 Vr = 0.6ØnmAb0.7fuvr = 170 kN > V = 71.23 kN OK
 Br = 3Øtwdboltnfubr = 694 kN > V = 50.5 kN OK
Shear and Bearing Resistance of Angle Cleats (2 angle cleats)
 Vr = 2(0.5ØLntfu) = 473 kN > V = 50.5 kN OK
 Br = Øtnafu = 289 kN > V = 50.5 kN OK
Tension in Bolts of Supported Beam
Tu = P = 3.11 kN
there are 2 cleats (on either side of beam 2’s web)
Thus: Tu = 3.11 / 2 = 1.56 kN
Tr = 2(0.75ØbAbfu) = 192 kN < Tu = 1.56 kN OK
Combined Shear and Tension of Bolts
Vu / Vr + Tu / Tr = (50.5 / 170) + (1.56 / 192) = 0.31 < 1.4 OK
Tension and Shear Block Failure of Cleat
Tr + Vr = ØAntfu + 0.6ØAnvfy = 506 kN > Tu = 255 kN OK
Øvr = 0.9
Øbr = 0.67
n = 3
a = 40
fu = 450 x 10-3
t = 8 mm
Ln = 200 – (3x18) = 146 mm
Øb = 0.8
Ab = 201
fu = 800 x 10-3
(Grade 8.8 Bolts
P
160mm
Ø = 0.9
fu = 450 x 10-3
fy = 300 x 10-3
Ant = (160 – 1x18)(8) = 1136 mm2
Agv = (40)(8) = 320 mm2
Anv = (40 – 0.25(18))(8) = 284 mm2
W01.JNB.000682 Gokwe Water Tank
3.3 Detail 3 (Fixed Connection)
Beam 1 lies on top of the column (connected to the column with a column end plate) and beam 2 (notched)
connects into beam 1. Beams 3 will then be welded to the column or beam 2.
3.3.1 Column End Plate
 The axial load of the beam  shear force in the connection
 The axial load in the column  axial load in the connection
 The moment in the beam or column (the biggest one in order to be conservative)  the moment in the
connection
See Attached beam-col connection design done in Prokon.
Beam 2 (Supported Beam)
Beam 1 (Supporting Beam)
Beam 3 (Walkway Supporting Beam)
FORCES & MOMENT IN THE CONNECTION:
 V = 12.6 kN
 Axial: P = 508 kN (Compression)
 M = 74.6 kNm
V
M
P
W01.JNB.000682 Gokwe Water Tank
3.3.2 Top/Splice Plate (to make the connection a fixed connection)
Detail 3 requires to be a fixed connection hence a top plate needs to be bolted to the top flanges of beam 1 and
beam 2 in order to fix the beam to beam connection. The concept shown below will be used for the top plate
design. A normal beam-col connection will be done in Prokon and the plate thickness and bolt sizes obtained
from that design will be used for the top plate thickness and bolt specs.
See the attached beam-col connection design for the calculation of the top plate thickness and bolt size.
3.3.3 Cleat Design
Beam 2 will be notched at the top and bottom in order to fit into beam 1. Beam 2 will be bolted to an angle (both
sides) and then bolted to beam 1.
Beam 2
Beam 1
V
M
P
FORCES & MOMENT IN BEAM 2
(see beam element end forces table for connection 1)
 V = 260 kN
 Axial: P = 39 kN
 M = 112.73 kNm
Beam 2
Beam 1
W01.JNB.000682 Gokwe Water Tank
The following assumptions were made:
 M20 Bolts
 4 Bolts in a row
 90 x 90 x 8 Angles
 Cleat dimensions as follows:
Shear and Bearing Resistance of Bolts in Supported Beam
 Vr = 0.6ØnmAb0.7fuvr = 354.5 kN > V = 260 kN OK
 Br = 3Øtwdboltnfubr = 578 kN > V = 260 kN OK
Shear and Bearing Resistance of Bolts in Supporting Beam
 Vr = 0.6ØnmAb0.7fuvr = 354.5 kN > V = 260 kN OK
 Br = 3Øtwdboltnfubr = 1157 kN > V = 260 kN OK
Shear and Bearing Resistance of Angle Cleats (2 angle cleats)
 Vr = 2(0.5ØLntfu) = 686.9 kN > V = 260 kN OK
 Br = Øtnafu = 385.9 kN > V = 260 kN OK
Tension in Bolts of Supported Beam
45
70
70
70
50 40
Øvr bolt = 0.8
Øbr bolt = 0.67
n = 4
m = 2
Ab = 314 mm2
fuvr = 420 x 10-3
tw = 8 mm
dbolt = 20 mm
fubr = 450 x 10-3
Øvr bolt = 0.8
Øbr bolt = 0.67
n = 8
m = 1
Ab = 314 mm2
fuvr = 420 x 10-3
tw = 8 mm
dbolt = 20 mm
fubr = 450 x 10-3
Øvr = 0.9
Øbr = 0.67
n = 4
a = 40
fu = 450 x 10-3
t = 8 mm
Ln = 300 – (4x22) = 212 mm
Øb = 0.8
Ab = 314
fu = 800 x 10-3
(Grade 8.8 Bolts
M = 112.73 kNm
Top 2 bolts is in Tension
Bottom 2 bolts is in Compression
210mm
45
W01.JNB.000682 Gokwe Water Tank
T = C = M/distance between top bolt and bottom bolt from the centre
T = C = 112.73 / 0.105m = 1073.6 kN per bolt and 2 bolts per cleat are in tension
T = C = 1073.6 / 2 = 536.8 kN
Tu = P + T = 39 + 536.8 = 575.8 kN
there are 2 cleats (on either side of beam 2’s web)
Thus: Tu = 575.8 / 2 = 288 kN
Tr = 2(0.75ØbAbfu) = kN < Tu = 301 kN OK
Combined Shear and Tension of Bolts
Vu / Vr + Tu / Tr = (260 / 345.5) + (288 / 301) = 1.7 < 1.4 NOT OK  Please advise what to do
Tension and Shear Block Failure of Cleat
Tr + Vr = ØAntfu + 0.6ØAnvfy = 618 kN > Tu = 255 kN OK
Ø = 0.9
fu = 450 x 10-3
fy = 300 x 10-3
Ant = (210 – 1.5x22)(8) = 1416 mm2
Agv = (40)(8) = 320 mm2
Anv = (40 – 0.25(22))(8) = 276 mm2
W01.JNB.000682 Gokwe Water Tank
3.4 Detail 4 (Pinned Connection)
Beam 1 lies on top of the column (connected to the column with a column end plate) and beam 2 (notched)
connects into beam 1.
3.4.1 Column End Plate
 The axial load of the beam  shear force in the connection
 The axial load in the column  axial load in the connection
 The moment in the beam or column (the biggest one in order to be conservative)  the moment in the
connection
See Attached beam-col connection design done in Prokon.
Beam 1 (Supporting Beam)
Beam 2 (Supported Beam)
Beam 1 (Supporting Beam)
FORCES & MOMENT IN THE CONNECTION:
 V 33.57 kN
 Axial: P = 766.4 kN (Compression)
 M = 151.43 kNm
V
M
P
W01.JNB.000682 Gokwe Water Tank
3.4.2 End Plate Design
Beam 2 will be notched at the top and bottom in order to fit into beam 1. Beam 2 will be bolted to an angle (both
sides) and then bolted to beam 1.
The following assumptions were made:
 M20 Bolts
 3 Bolts in a row
 12mm End Plate
 End Plate dimensions as follows:
See attached excell sheet for end plate calculations.
V
M
P
FORCES & MOMENT IN BEAM 2
(see beam element end forces table for connection 1)
 V = 226.42 kN
 Axial: P = 38.33 kN
 M = 0 kNm (pinned connection)
Beam 2 (Supported Beam)
Beam 1 (Supporting Beam)
50 50
50
100
100
50
150
W01.JNB.000682 Gokwe Water Tank
3.5 Detail 5 (Pinned Connection)
Beam 1 land beam 2 (horizontal members) will be welded to and end plate and bolted to the column web and
flanges respectively.
3.5.1 End Plate Design
Beam 2 will be notched at the top and bottom in order to fit into beam 1. Beam 2 will be bolted to an angle (both
sides) and then bolted to beam 1.
The following assumptions were made:
 M16 Bolts
 2 Bolts in a row
 10mm End Plate
 End Plate dimensions as follows:
See attached excell sheet for end plate calculations.
Beam 1 (Horizontal Member)
Beam 2 (Horizontal Member)
V M
P
FORCES & MOMENT IN BEAM 2
(see beam element end forces table for connection 1)
 V = 0.3 kN
 Axial: P = 52 kN
 M = 0.65 kNm
Beam 2 (Horizontal Member)
Beam 1 (Horizontal Member)
50
150
50
40 4070
End Plate
W01.JNB.000682 Gokwe Water Tank
3.6 Detail 5 (Weld Check)
Beam 2 (walkway supporting beam) will be fully welded to beam 1 (secondary beam).
3.6.1 Weld Check
See attached excell sheet for weld check.
Beam 1 (Secondary Beam)
Beam 2 (Walkway Supporting Beam)
W01.JNB.000682 Gokwe Water Tank
3.7 Detail 6 (Corner Connection of Channels (walkway ringbeam))
PC 230 x 90 Channels
80 x 80 x 6 Angle
2 x M12 Bolts
W01.JNB.000682 Gokwe Water Tank
3.8 Detail 7 (Walkway Supporting Beams)
Beam 1 (secondary beams), beam 2 (secondary 2 beams) and beam 3 (primary beam) are all flush at the top.
The walkway supporting beams are not flush with beam 1, beam 2 and beam 3. Spacers will be used in order to
obtain an equal level for the mentis grid at the top.
Walkway
Supporting Beams
Primary Beam
Secondary 2
Beams
Secondary Beams
W01.JNB.000682 Gokwe Water Tank
3.9 Detail 8 (Mentis Grid Detail)
RS40 Rectagrid with 30x4.5 Nominal Bearer Bar Size

More Related Content

What's hot

PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAPPERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
Sumarno Feriyal
 
Shallow Foundations ( Combined, Strap, Raft foundation)
Shallow Foundations ( Combined, Strap, Raft foundation)Shallow Foundations ( Combined, Strap, Raft foundation)
Shallow Foundations ( Combined, Strap, Raft foundation)
Mohammed Zakaria
 
05-Strength of Double Angle Bolted Tension Members (Steel Structural Design &...
05-Strength of Double Angle Bolted Tension Members (Steel Structural Design &...05-Strength of Double Angle Bolted Tension Members (Steel Structural Design &...
05-Strength of Double Angle Bolted Tension Members (Steel Structural Design &...
Hossam Shafiq II
 
RC member analysis and design
RC member analysis and designRC member analysis and design
RC member analysis and design
Kingsley Aboagye
 
Brzev ch13 ism
Brzev ch13 ismBrzev ch13 ism
Brzev ch13 ism
sidneyprice
 
Design and Drawing of Reinforced concrete structures
Design and Drawing of Reinforced concrete structuresDesign and Drawing of Reinforced concrete structures
Design and Drawing of Reinforced concrete structures
SJ BASHA
 
Structural building by engineer abdikani farah ahmed(enggalaydh)
Structural building by engineer abdikani farah ahmed(enggalaydh)Structural building by engineer abdikani farah ahmed(enggalaydh)
Structural building by engineer abdikani farah ahmed(enggalaydh)
EngGalaydh Farah Axmed
 
Base ring analysis
Base ring analysisBase ring analysis
Base ring analysis
Amit Narayan Nitnaware
 
Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)
Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)
Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)
Dr.Costas Sachpazis
 
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
Hossam Shafiq II
 
17-Examples of Beams (Steel Structural Design & Prof. Shehab Mourad)
17-Examples of Beams (Steel Structural Design & Prof. Shehab Mourad)17-Examples of Beams (Steel Structural Design & Prof. Shehab Mourad)
17-Examples of Beams (Steel Structural Design & Prof. Shehab Mourad)
Hossam Shafiq II
 
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
Hossam Shafiq II
 
10346 07 08 examination paper
10346 07 08 examination paper10346 07 08 examination paper
10346 07 08 examination paper
Eddy Ching
 
Footing Design
Footing DesignFooting Design
Footing Design
Sagnik Bhattacharjee
 
Сalculation of the сentral node
Сalculation of the сentral nodeСalculation of the сentral node
Сalculation of the сentral node
Dmitriy Semenov
 
MERENCANAKAN BALOK BETON PRATEGANG
MERENCANAKAN BALOK BETON PRATEGANGMERENCANAKAN BALOK BETON PRATEGANG
MERENCANAKAN BALOK BETON PRATEGANG
Mira Pemayun
 
Exemplu de calcul şarpantă din lemn folosind programul WoodExpress
Exemplu de calcul şarpantă din lemn folosind programul WoodExpressExemplu de calcul şarpantă din lemn folosind programul WoodExpress
Exemplu de calcul şarpantă din lemn folosind programul WoodExpress
Ursachi Răzvan
 
Worked example extract_flat_slabs
Worked example extract_flat_slabsWorked example extract_flat_slabs
Worked example extract_flat_slabs
Luan Truong Van
 
Sachpazis: Two-way RC Slab Slab Analysis & Design (EN1992-1-1:2004) example
Sachpazis: Two-way RC Slab Slab Analysis & Design (EN1992-1-1:2004) exampleSachpazis: Two-way RC Slab Slab Analysis & Design (EN1992-1-1:2004) example
Sachpazis: Two-way RC Slab Slab Analysis & Design (EN1992-1-1:2004) example
Dr.Costas Sachpazis
 
19-Examples for Beam Column (Steel Structural Design & Prof. Shehab Mourad)
19-Examples for Beam Column (Steel Structural Design & Prof. Shehab Mourad)19-Examples for Beam Column (Steel Structural Design & Prof. Shehab Mourad)
19-Examples for Beam Column (Steel Structural Design & Prof. Shehab Mourad)
Hossam Shafiq II
 

What's hot (20)

PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAPPERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
 
Shallow Foundations ( Combined, Strap, Raft foundation)
Shallow Foundations ( Combined, Strap, Raft foundation)Shallow Foundations ( Combined, Strap, Raft foundation)
Shallow Foundations ( Combined, Strap, Raft foundation)
 
05-Strength of Double Angle Bolted Tension Members (Steel Structural Design &...
05-Strength of Double Angle Bolted Tension Members (Steel Structural Design &...05-Strength of Double Angle Bolted Tension Members (Steel Structural Design &...
05-Strength of Double Angle Bolted Tension Members (Steel Structural Design &...
 
RC member analysis and design
RC member analysis and designRC member analysis and design
RC member analysis and design
 
Brzev ch13 ism
Brzev ch13 ismBrzev ch13 ism
Brzev ch13 ism
 
Design and Drawing of Reinforced concrete structures
Design and Drawing of Reinforced concrete structuresDesign and Drawing of Reinforced concrete structures
Design and Drawing of Reinforced concrete structures
 
Structural building by engineer abdikani farah ahmed(enggalaydh)
Structural building by engineer abdikani farah ahmed(enggalaydh)Structural building by engineer abdikani farah ahmed(enggalaydh)
Structural building by engineer abdikani farah ahmed(enggalaydh)
 
Base ring analysis
Base ring analysisBase ring analysis
Base ring analysis
 
Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)
Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)
Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)
 
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
 
17-Examples of Beams (Steel Structural Design & Prof. Shehab Mourad)
17-Examples of Beams (Steel Structural Design & Prof. Shehab Mourad)17-Examples of Beams (Steel Structural Design & Prof. Shehab Mourad)
17-Examples of Beams (Steel Structural Design & Prof. Shehab Mourad)
 
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
 
10346 07 08 examination paper
10346 07 08 examination paper10346 07 08 examination paper
10346 07 08 examination paper
 
Footing Design
Footing DesignFooting Design
Footing Design
 
Сalculation of the сentral node
Сalculation of the сentral nodeСalculation of the сentral node
Сalculation of the сentral node
 
MERENCANAKAN BALOK BETON PRATEGANG
MERENCANAKAN BALOK BETON PRATEGANGMERENCANAKAN BALOK BETON PRATEGANG
MERENCANAKAN BALOK BETON PRATEGANG
 
Exemplu de calcul şarpantă din lemn folosind programul WoodExpress
Exemplu de calcul şarpantă din lemn folosind programul WoodExpressExemplu de calcul şarpantă din lemn folosind programul WoodExpress
Exemplu de calcul şarpantă din lemn folosind programul WoodExpress
 
Worked example extract_flat_slabs
Worked example extract_flat_slabsWorked example extract_flat_slabs
Worked example extract_flat_slabs
 
Sachpazis: Two-way RC Slab Slab Analysis & Design (EN1992-1-1:2004) example
Sachpazis: Two-way RC Slab Slab Analysis & Design (EN1992-1-1:2004) exampleSachpazis: Two-way RC Slab Slab Analysis & Design (EN1992-1-1:2004) example
Sachpazis: Two-way RC Slab Slab Analysis & Design (EN1992-1-1:2004) example
 
19-Examples for Beam Column (Steel Structural Design & Prof. Shehab Mourad)
19-Examples for Beam Column (Steel Structural Design & Prof. Shehab Mourad)19-Examples for Beam Column (Steel Structural Design & Prof. Shehab Mourad)
19-Examples for Beam Column (Steel Structural Design & Prof. Shehab Mourad)
 

Viewers also liked

Build fast cost comparison
Build fast cost comparisonBuild fast cost comparison
Build fast cost comparison
greenbuildproducts
 
Effort estimation
Effort estimationEffort estimation
Effort estimation
Hanokh Aloni
 
Guesstimate Methods and Examples
Guesstimate Methods and ExamplesGuesstimate Methods and Examples
Guesstimate Methods and Examples
Igor Kokcharov
 
RGPV EX7102 UNIT II
RGPV EX7102 UNIT IIRGPV EX7102 UNIT II
RGPV EX7102 UNIT II
Mani Deep Dutt
 
NTPC DADRI.
NTPC DADRI.NTPC DADRI.
NTPC DADRI.
Ankit Kumar
 
Oscar Alvarez. Presentation
Oscar Alvarez. PresentationOscar Alvarez. Presentation
Oscar Alvarez. Presentation
Oscar Alvarez
 
Gas Turbine
Gas TurbineGas Turbine
Earthwork Volume Calculation Methods
Earthwork Volume Calculation MethodsEarthwork Volume Calculation Methods
Earthwork Volume Calculation Methods
riyasood003
 
143137557 storage-tanks
143137557 storage-tanks143137557 storage-tanks
143137557 storage-tanks
bernard347
 
Concrete- Classification,Properties and Testing
Concrete- Classification,Properties and TestingConcrete- Classification,Properties and Testing
Concrete- Classification,Properties and Testing
Rishabh Lala
 
Gas turbine-power-plant[1]
Gas turbine-power-plant[1]Gas turbine-power-plant[1]
Gas turbine-power-plant[1]
Manish Sadhu
 
Gas turbine
Gas turbine Gas turbine
Gas turbine
Manu Khurana
 
Gas Turbine Theory - Principle of Operation and Construction
Gas Turbine Theory  - Principle of Operation and ConstructionGas Turbine Theory  - Principle of Operation and Construction
Gas Turbine Theory - Principle of Operation and Construction
Sahyog Shishodia
 
Gas Turbine Operation
Gas Turbine OperationGas Turbine Operation
Gas Turbine Operation
Malik M. N.
 
Gas Turbine PPT
Gas Turbine PPTGas Turbine PPT
Gas Turbine PPT
A M
 
Steam Turbines
Steam Turbines Steam Turbines
Steam Turbines
Amir Ayad
 
Gas turbine power plants
Gas turbine power plantsGas turbine power plants
Gas turbine power plants
Nishkam Dhiman
 
Gas turbine course
Gas turbine courseGas turbine course

Viewers also liked (18)

Build fast cost comparison
Build fast cost comparisonBuild fast cost comparison
Build fast cost comparison
 
Effort estimation
Effort estimationEffort estimation
Effort estimation
 
Guesstimate Methods and Examples
Guesstimate Methods and ExamplesGuesstimate Methods and Examples
Guesstimate Methods and Examples
 
RGPV EX7102 UNIT II
RGPV EX7102 UNIT IIRGPV EX7102 UNIT II
RGPV EX7102 UNIT II
 
NTPC DADRI.
NTPC DADRI.NTPC DADRI.
NTPC DADRI.
 
Oscar Alvarez. Presentation
Oscar Alvarez. PresentationOscar Alvarez. Presentation
Oscar Alvarez. Presentation
 
Gas Turbine
Gas TurbineGas Turbine
Gas Turbine
 
Earthwork Volume Calculation Methods
Earthwork Volume Calculation MethodsEarthwork Volume Calculation Methods
Earthwork Volume Calculation Methods
 
143137557 storage-tanks
143137557 storage-tanks143137557 storage-tanks
143137557 storage-tanks
 
Concrete- Classification,Properties and Testing
Concrete- Classification,Properties and TestingConcrete- Classification,Properties and Testing
Concrete- Classification,Properties and Testing
 
Gas turbine-power-plant[1]
Gas turbine-power-plant[1]Gas turbine-power-plant[1]
Gas turbine-power-plant[1]
 
Gas turbine
Gas turbine Gas turbine
Gas turbine
 
Gas Turbine Theory - Principle of Operation and Construction
Gas Turbine Theory  - Principle of Operation and ConstructionGas Turbine Theory  - Principle of Operation and Construction
Gas Turbine Theory - Principle of Operation and Construction
 
Gas Turbine Operation
Gas Turbine OperationGas Turbine Operation
Gas Turbine Operation
 
Gas Turbine PPT
Gas Turbine PPTGas Turbine PPT
Gas Turbine PPT
 
Steam Turbines
Steam Turbines Steam Turbines
Steam Turbines
 
Gas turbine power plants
Gas turbine power plantsGas turbine power plants
Gas turbine power plants
 
Gas turbine course
Gas turbine courseGas turbine course
Gas turbine course
 

Similar to Foundation Reinforcement Calcs & Connection Calcs

Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Dhaka University of Engineering & Technology, Gazipur
 
Chapter 12
Chapter 12Chapter 12
Chapter 12
Afgaab Cumar
 
CANTILEVER RETAINING WALL FOR CIVIL ENGINEER
CANTILEVER RETAINING WALL FOR CIVIL ENGINEERCANTILEVER RETAINING WALL FOR CIVIL ENGINEER
CANTILEVER RETAINING WALL FOR CIVIL ENGINEER
VICTOR A. KIPLAGAT
 
Design ppt
Design pptDesign ppt
Design ppt
tishu001
 
Analysis and Design of Residential building.pptx
Analysis and Design of Residential building.pptxAnalysis and Design of Residential building.pptx
Analysis and Design of Residential building.pptx
DP NITHIN
 
Structural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowStructural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknow
Anchit Agrawal
 
350 kl overhead water intze tank design
350 kl overhead water intze tank design350 kl overhead water intze tank design
350 kl overhead water intze tank design
Harish Mahavar
 
final internship ppt.pptx
final internship ppt.pptxfinal internship ppt.pptx
final internship ppt.pptx
KiranKr32
 
Footing design
Footing designFooting design
Footing design
Vikas Mehta
 
Guntry girder
Guntry girderGuntry girder
Guntry girder
kajol panchal
 
Design of footing
Design of footingDesign of footing
Design of footing
NripeshJha
 
Worked example extract_flat_slabs
Worked example extract_flat_slabsWorked example extract_flat_slabs
Worked example extract_flat_slabs
luantvconst
 
PLANNING,ANALYSIS,DESIGNING AND ESTIMATION OF CANTILEVER RESIDENTIAL BUILDING
PLANNING,ANALYSIS,DESIGNING AND ESTIMATION OF CANTILEVER RESIDENTIAL BUILDINGPLANNING,ANALYSIS,DESIGNING AND ESTIMATION OF CANTILEVER RESIDENTIAL BUILDING
PLANNING,ANALYSIS,DESIGNING AND ESTIMATION OF CANTILEVER RESIDENTIAL BUILDING
Seranjeevi Seranjeevi
 
Beams design and analysis
Beams design and analysisBeams design and analysis
Beams design and analysis
Aman Adam
 
Ref F2F Week 4 - Solution_unlocked.pdf
Ref F2F Week 4 - Solution_unlocked.pdfRef F2F Week 4 - Solution_unlocked.pdf
Ref F2F Week 4 - Solution_unlocked.pdf
Robin Arthur Flores
 
Structural Design
Structural DesignStructural Design
Structural Design
Vj NiroSh
 
Singly R.C. beam
Singly R.C. beam  Singly R.C. beam
Singly R.C. beam
Yash Patel
 
2 compression
2  compression2  compression
2 compression
Ahmed Gamal
 
Column Interaction Diagram construction
Column Interaction Diagram constructionColumn Interaction Diagram construction
Column Interaction Diagram construction
Pritesh Parmar
 
psad 1.pdf
psad 1.pdfpsad 1.pdf

Similar to Foundation Reinforcement Calcs & Connection Calcs (20)

Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
Chapter 12
Chapter 12Chapter 12
Chapter 12
 
CANTILEVER RETAINING WALL FOR CIVIL ENGINEER
CANTILEVER RETAINING WALL FOR CIVIL ENGINEERCANTILEVER RETAINING WALL FOR CIVIL ENGINEER
CANTILEVER RETAINING WALL FOR CIVIL ENGINEER
 
Design ppt
Design pptDesign ppt
Design ppt
 
Analysis and Design of Residential building.pptx
Analysis and Design of Residential building.pptxAnalysis and Design of Residential building.pptx
Analysis and Design of Residential building.pptx
 
Structural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowStructural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknow
 
350 kl overhead water intze tank design
350 kl overhead water intze tank design350 kl overhead water intze tank design
350 kl overhead water intze tank design
 
final internship ppt.pptx
final internship ppt.pptxfinal internship ppt.pptx
final internship ppt.pptx
 
Footing design
Footing designFooting design
Footing design
 
Guntry girder
Guntry girderGuntry girder
Guntry girder
 
Design of footing
Design of footingDesign of footing
Design of footing
 
Worked example extract_flat_slabs
Worked example extract_flat_slabsWorked example extract_flat_slabs
Worked example extract_flat_slabs
 
PLANNING,ANALYSIS,DESIGNING AND ESTIMATION OF CANTILEVER RESIDENTIAL BUILDING
PLANNING,ANALYSIS,DESIGNING AND ESTIMATION OF CANTILEVER RESIDENTIAL BUILDINGPLANNING,ANALYSIS,DESIGNING AND ESTIMATION OF CANTILEVER RESIDENTIAL BUILDING
PLANNING,ANALYSIS,DESIGNING AND ESTIMATION OF CANTILEVER RESIDENTIAL BUILDING
 
Beams design and analysis
Beams design and analysisBeams design and analysis
Beams design and analysis
 
Ref F2F Week 4 - Solution_unlocked.pdf
Ref F2F Week 4 - Solution_unlocked.pdfRef F2F Week 4 - Solution_unlocked.pdf
Ref F2F Week 4 - Solution_unlocked.pdf
 
Structural Design
Structural DesignStructural Design
Structural Design
 
Singly R.C. beam
Singly R.C. beam  Singly R.C. beam
Singly R.C. beam
 
2 compression
2  compression2  compression
2 compression
 
Column Interaction Diagram construction
Column Interaction Diagram constructionColumn Interaction Diagram construction
Column Interaction Diagram construction
 
psad 1.pdf
psad 1.pdfpsad 1.pdf
psad 1.pdf
 

Foundation Reinforcement Calcs & Connection Calcs

  • 1. W01.JNB.000682 Gokwe Water Tank 1 BENDING REINFORCEMENT CALCULATION 1.1 Moment diagram giving Max Sagging Moment: See Elastic Beam design calculations Strip A (DL + LL) 1.1.1 Required reinforcement area for Max Sagging Moment: Mmax = 416.1 kNm fcu = 20Mpa; fy = 450Mpa cover = 30mm Thickness of the beam: 500mm Assumed diameter of reinforcement: d = 32mm deff = 500 – 30 – 32/2 = 454mm k = Mmax / (b x deff 2 x fcu) = 0.1  (1m strip: b=1000mm) y = 0.5 + √0.25 − 𝑘/0.9 = 0.87 z = y x deff = 395mm As = Mmax / (0.87 x fy x z) = 2691 mm2 /m Adopt Y25 @175mm c/c: As = 2810 mm2 /m’ 1.1.2 Required reinforcement area for Additional Sagging Moment: Mmax = 235 kNm fcu = 20Mpa; fy = 450Mpa cover = 30mm Thickness of the beam: 500mm Assumed diameter of reinforcement: d = 32mm deff = 500 – 30 – 32/2 = 454mm k = Mmax / (b x deff 2 x fcu) = 0.057  (1m strip: b=1000mm) y = 0.5 + √0.25 − 𝑘/0.9 = 0.93 Max Sagging Moment Additional Sagging Moment
  • 2. W01.JNB.000682 Gokwe Water Tank z = y x deff = 422mm As = Mmax / (0.87 x fy x z) = 1422 mm2 /m Adopt Y20 @200mm c/c: As = 1570 mm2 /m 1.2 Moment diagram giving Max Hogging Moment: See Elastic Beam design calculations Strip C (DL + WL) 1.2.1 Required reinforcement area for Max Hogging Moment: Mmax = 52.82 kNm fcu = 20Mpa; fy = 450Mpa cover = 30mm Thickness of the beam: 500mm Assumed diameter of reinforcement: d = 32mm deff = 500 – 30 – 32/2 = 454mm k = Mmax / (b x deff 2 x fcu) = 0.013  (1m strip: b=1000mm) y = 0.5 + √0.25 − 𝑘/0.9 = 0.985  Adopt y = 0.95 z = y x deff = 431mm As = Mmax / (0.87 x fy x z) = 313 mm2 /m Adopt Y12 @ 250mm c/c: As = 452 mm2 /m Max Hogging Moment
  • 3. W01.JNB.000682 Gokwe Water Tank 1.3 Reinforcement sketch 1.3.1 Bottom Reinforcing – B1 1.3.2 Bottom Reinforcing – B2 Y20 @ 200 Y20 @ 200 Y20 @ 200 Y20 @ 200Y20 @ 200 Y20 @ 200 Y20 @ 200 Y20 @ 200 Y20 @ 100 Y20 @ 200 Y20 @ 200 Y20 @ 200 Y20 @ 200Y20 @ 200 Y20 @ 200 Y20 @ 200 Y20 @ 200 Y20 @ 100
  • 4. W01.JNB.000682 Gokwe Water Tank 1.3.3 Top Reinforcing – T1 & T2 Y12 @ 250 Y12 @ 250 Y12 @ 250 Y12 @ 250Y12 @ 250 Y12 @ 250 Y12 @ 250 Y12 @ 250 Y12 @ 250
  • 5. W01.JNB.000682 Gokwe Water Tank 2 UPLIFT OF FOUNDATION DUE TO COLUMN & SOIL LOADING FROM ABOVE 2.1 Strip A (1m Strip width) 2.1.1 Uniformly Distributed Load from Column & Soil From the reactions output (pg 1 of the foundation design): F = 361.8 kN + 489 kN + 361.8 kN = 1212.6 kN Length of strip A: L = 10 mm Thus the uniformly distributed load from the 3 columns located on Strip A: UDLstrip A = F/L = 121.3 kN/m The uniformly distributed load from the 0.5m layer soil ontop of the foundation: UDLsoil = 18 x 1 x 0.5 = 9 kN/m 2.1.2 Moment Diagram giving Max Hogging Moment Refer to the Elastic Beam Design for Strip A: Uplift due to Column & Soil Loads from the Top (no soil underneath) for the calculation of the moments. 2.1.3 Required reinforcement area for Hogging Moment: Mmax = 33.55 kNm fcu = 20Mpa; fy = 450Mpa cover = 30mm Thickness of the beam: 500mm Assumed diameter of reinforcement: d = 20mm Hogging Moments form here due to downward load of the 3 columns and the 0.5m layer soil on top of the foundation Hogging Moments
  • 6. W01.JNB.000682 Gokwe Water Tank deff = 500 – 30 – 20/2 = 460mm k = Mmax / (b x deff 2 x fcu) = 0.008  (1m strip: b=1000mm) y = 0.5 + √0.25 − 𝑘/0.9 = 0.99  Adopt y = 0.95 z = y x deff = 437mm As = Mmax / (0.87 x fy x z) = 196 mm2 /m Adopt Y10 @ 250mm c/c: As = 314 mm2 /m 2.2 Strip B (1m Strip width) 2.2.1 Uniformly Distributed Load from Column & Soil From the reactions output (pg 1 of the foundation design): F = 375.8 kN + 489 kN + 375.8 kN = 1240.6 kN Length of strip A: L = 12 mm Thus the uniformly distributed load from the 3 columns located on Strip A: UDLstrip A = F/L = 103.4 kN/m The uniformly distributed load from the 0.5m layer soil ontop of the foundation: UDLsoil = 18 x 1 x 0.5 = 9 kN/m The uniformly distributed self-weight of the foundation slab = UDLself = 25 x 1 x 0.5 = 12.5 kN/m 2.2.2 Moment Diagram giving Max Hogging Moment Refer to the Elastic Beam Design for Strip B: Uplift due to Column & Soil Loads from the Top (no soil underneath) for the calculation of the moments. Hogging Moments form here due to downward load of the 3 columns and the 0.5m layer soil on top of the foundation Hogging Moments
  • 7. W01.JNB.000682 Gokwe Water Tank 2.2.3 Required reinforcement area for Hogging Moment: Mmax = 59.6 kNm fcu = 20Mpa; fy = 450Mpa cover = 30mm Thickness of the beam: 500mm Assumed diameter of reinforcement: d = 20mm deff = 500 – 30 – 20/2 = 460mm k = Mmax / (b x deff 2 x fcu) = 0.014  (1m strip: b=1000mm) y = 0.5 + √0.25 − 𝑘/0.9 = 0.98  Adopt y = 0.95 z = y x deff = 437mm As = Mmax / (0.87 x fy x z) = 325 mm2 /m Adopt Y12 @ 250mm c/c: As = 452 mm2 /m 2.3 Strip C (1m Strip width) 2.3.1 Uniformly Distributed Load from Column & Soil From the reactions output (pg 1 of the foundation design): F = -77.3 kN +(-87.6) kN + (-77.3) kN = -242.2 kN Length of strip A: L = 12 mm Thus the uniformly distributed load from the 3 columns located on Strip A: UDLstrip A = F/L = -20.2 kN/m The uniformly distributed load from the 0.5m layer soil ontop of the foundation: UDLsoil = 18 x 1 x 0.5 = 9 kN/m 2.3.2 Moment Diagram giving Max Hogging Moment Refer to the Elastic Beam Design for Strip C: Uplift due to Column & Soil Loads from the Top (no soil underneath) for the calculation of the moments. Hogging Moments form here due to the dominant upward load of the 3 columns (caused by dominant wind force.
  • 8. W01.JNB.000682 Gokwe Water Tank 2.3.3 Required reinforcement area for Hogging Moment: Mmax = 22.4 kNm fcu = 20Mpa; fy = 450Mpa cover = 30mm Thickness of the beam: 500mm Assumed diameter of reinforcement: d = 20mm deff = 500 – 30 – 20/2 = 460mm k = Mmax / (b x deff 2 x fcu) = 0.005  (1m strip: b=1000mm) y = 0.5 + √0.25 − 𝑘/0.9 = 0.99  Adopt y = 0.95 z = y x deff = 437mm As = Mmax / (0.87 x fy x z) = 131 mm2 /m Adopt Y10 @ 250mm c/c: As = 314 mm2 /m  Thus Y12 @ 250mm c/c will be sufficient Hogging Moments
  • 9. W01.JNB.000682 Gokwe Water Tank 3 CONNECTION DESIGN 3.1 Detail 1 (Fixed Connection) Beam 1 lies on top of the column (connected to the column with a column end plate) and beam 2 (notched) connects into beam 1. Beams 3 & 4 will then be welded to the column. 3.1.1 Column End Plate  The axial load of the beam  shear force in the connection  The axial load in the column  axial load in the connection  The moment in the beam or column (the biggest one in order to be conservative)  the moment in the connection See Attached beam-col connection design done in Prokon. Beam 2 (Supported Beam) Beam 1 (Supporting Beam) Beam 3 & 4 (Walkway Supporting Beams) FORCES & MOMENT IN THE CONNECTION:  V = 21.8 kN  Axial: P = 164.7 kN (Compression)  M = 38.5 kNm V M P
  • 10. W01.JNB.000682 Gokwe Water Tank 3.1.2 Top Plate (to make the connection a fixed connection) Detail 1 requires to be a fixed connection hence a top plate needs to be bolted to the top flanges of beam 1 and beam 2 in order to fix the beam to beam connection. The concept shown below will be used for the top plate design. A normal beam-col connection will be done in Prokon and the plate thickness and bolt sizes obtained from that design will be used for the top plate thickness and bolt specs. See the attached beam-col connection design for the calculation of the top plate thickness and bolt size. 3.1.3 Cleat Design Beam 2 will notched at the top and bottom in order to fit into beam 1. Beam 2 will be bolted to an angle (both sides) and then bolted to beam 1. Beam 2 Beam 1 V M P FORCES & MOMENT IN BEAM 2 (see beam element end forces table for connection 1)  V = 71.23 kN  Axial: P = 13.34 kN  M = 39.77 kNm Beam 2 Beam 1
  • 11. W01.JNB.000682 Gokwe Water Tank The following assumptions were made:  M16 Bolts  3 Bolts in a row  90 x 90 x 8 Angles  Cleat dimensions as follows: Shear and Bearing Resistance of Bolts in Supported Beam  Vr = 0.6ØnmAb0.7fuvr = 170 kN > V = 71.23 kN OK  Br = 3Øtwdboltnfubr = 299 kN > V = 71.23 kN OK Shear and Bearing Resistance of Bolts in Supporting Beam  Vr = 0.6ØnmAb0.7fuvr = 170 kN > V = 71.23 kN OK  Br = 3Øtwdboltnfubr = 599 kN > V = 71.23 kN OK Shear and Bearing Resistance of Angle Cleats (2 angle cleats)  Vr = 2(0.5ØLntfu) = 473 kN > V = 71.23 kN OK  Br = Øtnafu = 289 kN > V = 71.23 kN OK Tension in Bolts of Supported Beam 50 50 80 80 50 40 Øvr bolt = 0.8 Øbr bolt = 0.67 n = 3 m = 2 Ab = 201 mm2 fuvr = 420 x 10-3 tw = 6.9 mm dbolt = 16 mm fubr = 450 x 10-3 Øvr bolt = 0.8 Øbr bolt = 0.67 n = 6 m = 1 Ab = 201 mm2 fuvr = 420 x 10-3 tw = 6.9 mm dbolt = 16 mm fubr = 450 x 10-3 Øvr = 0.9 Øbr = 0.67 n = 3 a = 40 fu = 450 x 10-3 t = 8 mm Ln = 200 – (3x18) = 146 mm Øb = 0.8 Ab = 201 fu = 800 x 10-3 (Grade 8.8 Bolts M = 39.77 kNm Top bolt is in Tension Bottom bolt is in Compression 160mm
  • 12. W01.JNB.000682 Gokwe Water Tank T = C = M/distance between top bolt and bottom bolt from the centre T = C = 39.77 / 0.08m = 497 kN Tu = P + T = 13.34 + 497 = 510.5 kN there are 2 cleats (on either side of beam 2’s web) Thus: Tu = 510.5 / 2 = 255 kN Tr = 2(0.75ØbAbfu) = 192 kN < Tu = 255 kN NOT OK Tr = 301 kN (with M20 bolts) > Tu = 255 kN OK Combined Shear and Tension of Bolts Vu / Vr + Tu / Tr = (71.23 / 170) + (255 / 301) = 1.27 < 1.4 OK Tension and Shear Block Failure of Cleat Tr + Vr = ØAntfu + 0.6ØAnvfy = 506 kN > Tu = 255 kN OK Use M20 Bolts Ø = 0.9 fu = 450 x 10-3 fy = 300 x 10-3 Ant = (160 – 1x18)(8) = 1136 mm2 Agv = (40)(8) = 320 mm2 Anv = (40 – 0.25(18))(8) = 284 mm2 Thus Use M20 Bolts for Detail 1: Cleat Connection
  • 13. W01.JNB.000682 Gokwe Water Tank 3.2 Detail 2 (Pinned Connection) Beam 1 lies on top of the column (connected to the column with a column end plate) and beam 2 (notched top and bottom) connects into beam 1. Beam 3 will then be welded to the column or to beam 2. 3.2.1 Column End Plate  The axial load of the beam  shear force in the connection  The axial load in the column  axial load in the connection  The moment in the beam or column (the biggest one in order to be conservative)  the moment in the connection See Attached beam-col connection design done in Prokon. Beam 2 (Supported Beam) Beam 1 (Supporting Beam) Beam 3 (Walkway Supporting Beams) FORCES & MOMENT IN THE CONNECTION:  V = 33.78 kN  Axial: P = 293.93 kN (Compression)  M = 76 kNm V M P
  • 14. W01.JNB.000682 Gokwe Water Tank 3.2.2 Cleat Design Beam 2 will notched at the top and bottom in order to fit into beam 1. Beam 2 will be bolted to an angle (both sides) and then bolted to beam 1. The following assumptions were made: *Note: the same bolt sizes, bolts in a row and cleat dimensions were chosen on order to keep all the cleat connections uniform so as to simplify operations on site.  M16 Bolts  3 Bolts in a row  90 x 90 x 8 Angles  Cleat dimensions as follows: Shear and Bearing Resistance of Bolts in Supported Beam  Vr = 0.6ØnmAb0.7fuvr = 170 kN > V = 50.5 kN OK  Br = 3Øtwdboltnfubr = 299 kN > V = 50.5 kN OK Shear and Bearing Resistance of Bolts in Supporting Beam V M P FORCES & MOMENT IN BEAM 2 (see beam element end forces table for connection 1)  V = 50.5 kN  Axial: P = 3.11 kN  M = 0 kNm (beam 2 pinned to beam 1) Beam 2 (Supported Beam) Beam 1 (Supporting Beam) 50 50 80 80 50 40 Øvr bolt = 0.8 Øbr bolt = 0.67 n = 3 m = 2 Ab = 201 mm2 fuvr = 420 x 10-3 tw = 6.9 mm dbolt = 16 mm fubr = 450 x 10-3 Øvr bolt = 0.8 Øbr bolt = 0.67 n = 6 m = 1 Ab = 201 mm2 fuvr = 420 x 10-3 tw = 8 mm dbolt = 16 mm fubr = 450 x 10-3
  • 15. W01.JNB.000682 Gokwe Water Tank  Vr = 0.6ØnmAb0.7fuvr = 170 kN > V = 71.23 kN OK  Br = 3Øtwdboltnfubr = 694 kN > V = 50.5 kN OK Shear and Bearing Resistance of Angle Cleats (2 angle cleats)  Vr = 2(0.5ØLntfu) = 473 kN > V = 50.5 kN OK  Br = Øtnafu = 289 kN > V = 50.5 kN OK Tension in Bolts of Supported Beam Tu = P = 3.11 kN there are 2 cleats (on either side of beam 2’s web) Thus: Tu = 3.11 / 2 = 1.56 kN Tr = 2(0.75ØbAbfu) = 192 kN < Tu = 1.56 kN OK Combined Shear and Tension of Bolts Vu / Vr + Tu / Tr = (50.5 / 170) + (1.56 / 192) = 0.31 < 1.4 OK Tension and Shear Block Failure of Cleat Tr + Vr = ØAntfu + 0.6ØAnvfy = 506 kN > Tu = 255 kN OK Øvr = 0.9 Øbr = 0.67 n = 3 a = 40 fu = 450 x 10-3 t = 8 mm Ln = 200 – (3x18) = 146 mm Øb = 0.8 Ab = 201 fu = 800 x 10-3 (Grade 8.8 Bolts P 160mm Ø = 0.9 fu = 450 x 10-3 fy = 300 x 10-3 Ant = (160 – 1x18)(8) = 1136 mm2 Agv = (40)(8) = 320 mm2 Anv = (40 – 0.25(18))(8) = 284 mm2
  • 16. W01.JNB.000682 Gokwe Water Tank 3.3 Detail 3 (Fixed Connection) Beam 1 lies on top of the column (connected to the column with a column end plate) and beam 2 (notched) connects into beam 1. Beams 3 will then be welded to the column or beam 2. 3.3.1 Column End Plate  The axial load of the beam  shear force in the connection  The axial load in the column  axial load in the connection  The moment in the beam or column (the biggest one in order to be conservative)  the moment in the connection See Attached beam-col connection design done in Prokon. Beam 2 (Supported Beam) Beam 1 (Supporting Beam) Beam 3 (Walkway Supporting Beam) FORCES & MOMENT IN THE CONNECTION:  V = 12.6 kN  Axial: P = 508 kN (Compression)  M = 74.6 kNm V M P
  • 17. W01.JNB.000682 Gokwe Water Tank 3.3.2 Top/Splice Plate (to make the connection a fixed connection) Detail 3 requires to be a fixed connection hence a top plate needs to be bolted to the top flanges of beam 1 and beam 2 in order to fix the beam to beam connection. The concept shown below will be used for the top plate design. A normal beam-col connection will be done in Prokon and the plate thickness and bolt sizes obtained from that design will be used for the top plate thickness and bolt specs. See the attached beam-col connection design for the calculation of the top plate thickness and bolt size. 3.3.3 Cleat Design Beam 2 will be notched at the top and bottom in order to fit into beam 1. Beam 2 will be bolted to an angle (both sides) and then bolted to beam 1. Beam 2 Beam 1 V M P FORCES & MOMENT IN BEAM 2 (see beam element end forces table for connection 1)  V = 260 kN  Axial: P = 39 kN  M = 112.73 kNm Beam 2 Beam 1
  • 18. W01.JNB.000682 Gokwe Water Tank The following assumptions were made:  M20 Bolts  4 Bolts in a row  90 x 90 x 8 Angles  Cleat dimensions as follows: Shear and Bearing Resistance of Bolts in Supported Beam  Vr = 0.6ØnmAb0.7fuvr = 354.5 kN > V = 260 kN OK  Br = 3Øtwdboltnfubr = 578 kN > V = 260 kN OK Shear and Bearing Resistance of Bolts in Supporting Beam  Vr = 0.6ØnmAb0.7fuvr = 354.5 kN > V = 260 kN OK  Br = 3Øtwdboltnfubr = 1157 kN > V = 260 kN OK Shear and Bearing Resistance of Angle Cleats (2 angle cleats)  Vr = 2(0.5ØLntfu) = 686.9 kN > V = 260 kN OK  Br = Øtnafu = 385.9 kN > V = 260 kN OK Tension in Bolts of Supported Beam 45 70 70 70 50 40 Øvr bolt = 0.8 Øbr bolt = 0.67 n = 4 m = 2 Ab = 314 mm2 fuvr = 420 x 10-3 tw = 8 mm dbolt = 20 mm fubr = 450 x 10-3 Øvr bolt = 0.8 Øbr bolt = 0.67 n = 8 m = 1 Ab = 314 mm2 fuvr = 420 x 10-3 tw = 8 mm dbolt = 20 mm fubr = 450 x 10-3 Øvr = 0.9 Øbr = 0.67 n = 4 a = 40 fu = 450 x 10-3 t = 8 mm Ln = 300 – (4x22) = 212 mm Øb = 0.8 Ab = 314 fu = 800 x 10-3 (Grade 8.8 Bolts M = 112.73 kNm Top 2 bolts is in Tension Bottom 2 bolts is in Compression 210mm 45
  • 19. W01.JNB.000682 Gokwe Water Tank T = C = M/distance between top bolt and bottom bolt from the centre T = C = 112.73 / 0.105m = 1073.6 kN per bolt and 2 bolts per cleat are in tension T = C = 1073.6 / 2 = 536.8 kN Tu = P + T = 39 + 536.8 = 575.8 kN there are 2 cleats (on either side of beam 2’s web) Thus: Tu = 575.8 / 2 = 288 kN Tr = 2(0.75ØbAbfu) = kN < Tu = 301 kN OK Combined Shear and Tension of Bolts Vu / Vr + Tu / Tr = (260 / 345.5) + (288 / 301) = 1.7 < 1.4 NOT OK  Please advise what to do Tension and Shear Block Failure of Cleat Tr + Vr = ØAntfu + 0.6ØAnvfy = 618 kN > Tu = 255 kN OK Ø = 0.9 fu = 450 x 10-3 fy = 300 x 10-3 Ant = (210 – 1.5x22)(8) = 1416 mm2 Agv = (40)(8) = 320 mm2 Anv = (40 – 0.25(22))(8) = 276 mm2
  • 20. W01.JNB.000682 Gokwe Water Tank 3.4 Detail 4 (Pinned Connection) Beam 1 lies on top of the column (connected to the column with a column end plate) and beam 2 (notched) connects into beam 1. 3.4.1 Column End Plate  The axial load of the beam  shear force in the connection  The axial load in the column  axial load in the connection  The moment in the beam or column (the biggest one in order to be conservative)  the moment in the connection See Attached beam-col connection design done in Prokon. Beam 1 (Supporting Beam) Beam 2 (Supported Beam) Beam 1 (Supporting Beam) FORCES & MOMENT IN THE CONNECTION:  V 33.57 kN  Axial: P = 766.4 kN (Compression)  M = 151.43 kNm V M P
  • 21. W01.JNB.000682 Gokwe Water Tank 3.4.2 End Plate Design Beam 2 will be notched at the top and bottom in order to fit into beam 1. Beam 2 will be bolted to an angle (both sides) and then bolted to beam 1. The following assumptions were made:  M20 Bolts  3 Bolts in a row  12mm End Plate  End Plate dimensions as follows: See attached excell sheet for end plate calculations. V M P FORCES & MOMENT IN BEAM 2 (see beam element end forces table for connection 1)  V = 226.42 kN  Axial: P = 38.33 kN  M = 0 kNm (pinned connection) Beam 2 (Supported Beam) Beam 1 (Supporting Beam) 50 50 50 100 100 50 150
  • 22. W01.JNB.000682 Gokwe Water Tank 3.5 Detail 5 (Pinned Connection) Beam 1 land beam 2 (horizontal members) will be welded to and end plate and bolted to the column web and flanges respectively. 3.5.1 End Plate Design Beam 2 will be notched at the top and bottom in order to fit into beam 1. Beam 2 will be bolted to an angle (both sides) and then bolted to beam 1. The following assumptions were made:  M16 Bolts  2 Bolts in a row  10mm End Plate  End Plate dimensions as follows: See attached excell sheet for end plate calculations. Beam 1 (Horizontal Member) Beam 2 (Horizontal Member) V M P FORCES & MOMENT IN BEAM 2 (see beam element end forces table for connection 1)  V = 0.3 kN  Axial: P = 52 kN  M = 0.65 kNm Beam 2 (Horizontal Member) Beam 1 (Horizontal Member) 50 150 50 40 4070 End Plate
  • 23. W01.JNB.000682 Gokwe Water Tank 3.6 Detail 5 (Weld Check) Beam 2 (walkway supporting beam) will be fully welded to beam 1 (secondary beam). 3.6.1 Weld Check See attached excell sheet for weld check. Beam 1 (Secondary Beam) Beam 2 (Walkway Supporting Beam)
  • 24. W01.JNB.000682 Gokwe Water Tank 3.7 Detail 6 (Corner Connection of Channels (walkway ringbeam)) PC 230 x 90 Channels 80 x 80 x 6 Angle 2 x M12 Bolts
  • 25. W01.JNB.000682 Gokwe Water Tank 3.8 Detail 7 (Walkway Supporting Beams) Beam 1 (secondary beams), beam 2 (secondary 2 beams) and beam 3 (primary beam) are all flush at the top. The walkway supporting beams are not flush with beam 1, beam 2 and beam 3. Spacers will be used in order to obtain an equal level for the mentis grid at the top. Walkway Supporting Beams Primary Beam Secondary 2 Beams Secondary Beams
  • 26. W01.JNB.000682 Gokwe Water Tank 3.9 Detail 8 (Mentis Grid Detail) RS40 Rectagrid with 30x4.5 Nominal Bearer Bar Size
  翻译: