尊敬的 微信汇率:1円 ≈ 0.046078 元 支付宝汇率:1円 ≈ 0.046168元 [退出登录]
SlideShare a Scribd company logo
HOW TO PREPARE
THE RECOVERY /
REVISED
SCHEDULE
Rev.2
By. Engr. Abdulhay Mohamed Ghanem
Sr. Planning Engineer at Abdullah A. Alkodari Co.
Purpose of this document :
Purpose of this document is to explain
recovery/revised schedule properly by using
Who should read this document
This document is for who is concern about
schedulers, projects controllers and projects managers
The guys who will read and utilize
Primavera software like global changes, export
effect on schedule updating and this equation
BL Start). i.e A%C = (DD – BLST) / (
this document.
Let us start with preparation of
Firstly we have to know what is the meaning of recovery schedule? . We can simply say that the recovery
schedule is a new baseline schedule to rectify any occurred delay to the
whether by using crashing technique or fast track technique.
My example in this document, I am
schedule you have to make sure of the following:
1- No activities are out of sequence.
2- No activities with unsatisfied relation.
3- Remaining early start of all in progress activities is one day after data date
Regarding point no. 3, I will explain why we should fulfill
which will be applied.
4- Detach the baseline and separate the
If the updated schedule has an assigned baseline you shall remove that baseline.
is to explain and help how to use Primavera software to create a
recovery/revised schedule properly by using Primavera tools.
document:
who is concern about Primavera and project management such planners,
projects controllers and projects managers.
utilize this document should be conversant the following tools and options in
global changes, export and import in excel format, percent
effect on schedule updating and this equation Activity % complete = (Data date –
BLST) / (BLF – BLST), Which will be used to conclude the used
Let us start with preparation of recovery schedule.
Firstly we have to know what is the meaning of recovery schedule? . We can simply say that the recovery
schedule is a new baseline schedule to rectify any occurred delay to the project to meet contractual end
whether by using crashing technique or fast track technique.
example in this document, I am using percent complete type physical, before prepare your recovery
have to make sure of the following:
are out of sequence.
satisfied relation.
Remaining early start of all in progress activities is one day after data date
Regarding point no. 3, I will explain why we should fulfill this condition during explain the global changes
and separate the current progress.
If the updated schedule has an assigned baseline you shall remove that baseline.
Data Date is 31.May.15
rimavera software to create a
rimavera and project management such planners,
should be conversant the following tools and options in
percent complete type and its
BL start) / (BL finish –
Which will be used to conclude the used equation in
schedule.
Firstly we have to know what is the meaning of recovery schedule? . We can simply say that the recovery
project to meet contractual end
prepare your recovery
Remaining early start of all in progress activities is one day after data date not more.
lain the global changes
If the updated schedule has an assigned baseline you shall remove that baseline.
Data Date is 31.May.15
Tip: If this message appeared to you.
It means you have to release the old baseline from assigning to the current project.
assign baselines and change to current pro
If this message appeared to you.
means you have to release the old baseline from assigning to the current project.
and change to current project in mentioned tow positions, and then you can delete.
means you have to release the old baseline from assigning to the current project. From project –
ject in mentioned tow positions, and then you can delete.
5- Delete finish constraint of the project.
In projects layout, select dates label then remove date in cell of must finish by.(highlight it then press delete)
6- Press F9 to run scheduling–
scheduling options).
Delete finish constraint of the project.
layout, select dates label then remove date in cell of must finish by.(highlight it then press delete)
– Using retained logic option before scheduling progressed activities (From
layout, select dates label then remove date in cell of must finish by.(highlight it then press delete)
option before scheduling progressed activities (From
Now you can adjust the remaining duration
in progress activities and the relations of not started activities to prepare a proper recovery schedule
accordance with view of PM & CM and site
Tip: If you are using duration type fix duration and units,
you are using duration type fix duration and unit/time you will find your budgeted
planned in your baseline schedule before creating the recovery sc
end of this document how to solve.
Now we will apply the following global change to the current project as follow
a- Original duration of
b- Planned start date and planned finish date to be equal actual date for completed
activities.
Now you can adjust the remaining duration (remember I am using physical type for percent complete type)
in progress activities and the relations of not started activities to prepare a proper recovery schedule
accordance with view of PM & CM and site requirement to close the project on contractual end
ion type fix duration and units, you will find your budgeted total cost still the same. If
you are using duration type fix duration and unit/time you will find your budgeted total cost is more than you
planned in your baseline schedule before creating the recovery schedule. To solve this issue I will explain at the
is document how to solve.
Now we will apply the following global change to the current project as following:
nal duration of completed activities. (Original should = actual)
Planned start date and planned finish date to be equal actual date for completed
(remember I am using physical type for percent complete type) of
in progress activities and the relations of not started activities to prepare a proper recovery schedule in
requirement to close the project on contractual end.
you will find your budgeted total cost still the same. If
total cost is more than you
solve this issue I will explain at the
. (Original should = actual)
Planned start date and planned finish date to be equal actual date for completed
C- Original duration of in progress activities. (
d - Planned start date to be equal actual date for in progress activities.
After complete all steps. Did you asked yourself why
PV of the new recovery baseline? And how we can adjust it to make EV = PV =
67,528,929.48 SAR in my example?
you glanced to the snapshot below
Original duration of in progress activities. (Original = actual + remaining ).
Planned start date to be equal actual date for in progress activities.
After complete all steps. Did you asked yourself why EV at Data date
PV of the new recovery baseline? And how we can adjust it to make EV = PV =
SAR in my example?(remember I am using percent complete type physical)
you glanced to the snapshot below
actual + remaining ).
Planned start date to be equal actual date for in progress activities.
date (31.May.15) not equal
PV of the new recovery baseline? And how we can adjust it to make EV = PV =
(remember I am using percent complete type physical). If
In our example I used budgeted values
to the others two options it will not affect on the result as shown in previous snapshot.
From - admin - admin preferences
In our example I used budgeted values with current dates (Default option) even you change it
to the others two options it will not affect on the result as shown in previous snapshot.
admin preferences
(Default option) even you change it
to the others two options it will not affect on the result as shown in previous snapshot.
What if you are using
bingeing in your baseline schedule before
previous global changes
default to at completion values with current dates
1- EV = PV but not equal
2- The activities percent complete will be changed as well to values more than the actual
activities % complete
Note: in this example,
same data date is 68,876,923.16
Snapshot No.1
What if you are using percent complete type duration?. if you are using this type from
bingeing in your baseline schedule before creating the recovery baseline,
previous global changes then you changed the option of earned value calculation from
default to at completion values with current dates you will find the following:
EV = PV but not equal 68,876,923.16 SAR
The activities percent complete will be changed as well to values more than the actual
activities % complete at site. Please compare between snapshot No.1 and No.2.
in this example, we are using percent complete type duration the earned value at the
68,876,923.16 SAR
using this type from
creating the recovery baseline, then you applied all
then you changed the option of earned value calculation from
will find the following:
The activities percent complete will be changed as well to values more than the actual
at site. Please compare between snapshot No.1 and No.2.
we are using percent complete type duration the earned value at the
Note: The variance between PL and EV in snapshot No. 2
available.
With return to previous example (Physical), and the familiar equation of
– BL start) / (BL finish – BL start)
deferent formula. (Ghanem Equation
Let us see how I concluded this equation
A%C = (DD – BLST) / (BLF
Also OD = ED + RD
Where OD = Original duration of the activity.
ED = Elapsed duration of in progress activity.
RD = Remaining duration of in progress activity.
Then A%C = (DD – BLST) / (ED + RD)
A%C = ED / (ED + RD)
Where ED = DD – BLST for in progress activity.
A%C X ED + A%C X R
A%C X RD = ED – A%C X ED
RD = (ED / A%C) – ED
RD = ED ((1 / A%C)
While ED = DD –
Then DD – BLST = RD / ((1 / A%C)
Then BLST = DD
Snapshot No.2
The variance between PL and EV in snapshot No. 2 due to condition No.3 in page No.
example (Physical), and the familiar equation of Activity % complete = (Data date
BL start) which I will use it to adjust EV = PL = 67,528,929.48
Ghanem Equation)
BLST = DD – (RD / ((1 / A%C) – 1)))
Let us see how I concluded this equation
BLST) / (BLF-BLST) whereas BLF – BLST = OD
Where OD = Original duration of the activity.
ED = Elapsed duration of in progress activity.
RD = Remaining duration of in progress activity.
BLST) / (ED + RD)
A%C = ED / (ED + RD)
BLST for in progress activity.
A%C X ED + A%C X RD = ED
A%C X ED
ED
RD = ED ((1 / A%C) – 1)
– BLST and ED = RD / ((1 / A%C) – 1)
BLST = RD / ((1 / A%C) – 1)
BLST = DD – (RD / ((1 / A%C) – 1)))
due to condition No.3 in page No. 2 is not
Activity % complete = (Data date
67,528,929.48 SAR but in
1)))
BLST = OD
Note: DD, A%C and RD are fixed to fulfill the requirement of a proper recovery baseline
schedule.
If you filtered the completed a
problem will arise (EV not equal PV).
issue.
Export an excel sheet contain the following to work out
from Enterprise menu
DD, A%C and RD are fixed to fulfill the requirement of a proper recovery baseline
If you filtered the completed activities you will find EV = PV. while in progress activities,
problem will arise (EV not equal PV). therefore we will use the previous formula to solve this
Export an excel sheet contain the following to work out the formula. Before exporting, create
from Enterprise menu – user defined fields tow new fields as shown.
DD, A%C and RD are fixed to fulfill the requirement of a proper recovery baseline
V. while in progress activities, the
previous formula to solve this
. Before exporting, create
With reference to third
condition not available the new original duration
vise is correct. So, this availability of this condition is very important to work out formula
third condition in page No.2, if you look to the following you will find
condition not available the new original duration will be less than the actual + remaining while
this availability of this condition is very important to work out formula
Condition is not
available so 67+30
not equal 103
In Primavera Actual
Duration of in progress
activity is the elapsed
duration (ED)
condition in page No.2, if you look to the following you will find if the
will be less than the actual + remaining while
this availability of this condition is very important to work out formula.
In Primavera Actual
Duration of in progress
activity is the elapsed
Let us complete exporting operationLet us complete exporting operation
Condition is available
so 67+30 = 97
Only in progress
activity
n progress
Then add comma from option DataThen add comma from option Data – Text to columns
Copy – Past values
Apply this global change to calculate the new actual start date.Apply this global change to calculate the new actual start date.
Data Date
Delete operation area then
save then import to
Priamvera
Delete operation area then
Then apply this global change to make actual start equal to New Act st.
The result will be as shown below.
Reuse global change No. C & D
Then apply this global change to make actual start equal to New Act st.
The result will be as shown below.
to adjust the original duration, the result will be as the following:
Note
Then apply this global change to make actual start equal to New Act st.
result will be as the following:
Now EV = PV with variance 122,608
Put the contractual end (Must finish by)
Wait for Rev.3
In rev.3 I will talk exhaustively about revised schedule,
schedule and how to use excel sheet
apply some changes on that base line schedule
type of the activities.
122,608 SAR (variance = 0.18% of earned value can be neglected)
(Must finish by), maintain, assign your new created recovery
about revised schedule, How to save actual dates to
and how to use excel sheet to transfer data from updated schedule to ba
apply some changes on that base line schedule as mentioned in page No. 5 about
0.18% of earned value can be neglected)
your new created recovery, enjoy.
How to save actual dates to submit as built
to transfer data from updated schedule to baseline schedule after
as mentioned in page No. 5 about modifying duration
My contacts informaiton
Skype account : en_ghanem
Email : Abdelhay.Ghanem@gmail.com
Mobile Phone : +966-546810855 , +966-593068907

More Related Content

What's hot

Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
Tim Lloyd
 
Delay analysis final
Delay analysis finalDelay analysis final
Delay analysis final
Mahmoud Awwad, PMP, MCIOB
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
The Vertex Companies, LLC
 
Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01
Muhammad Mujahid PMP®, PSP®, SP®, APMC®
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
Farhan Moosa
 
Project management using Primavera 6.x by Karim Ragab
Project management using Primavera 6.x by Karim RagabProject management using Primavera 6.x by Karim Ragab
Project management using Primavera 6.x by Karim Ragab
Karim Ragab
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
Michael Pink
 
Claims
ClaimsClaims
Claims
Mike Debiak
 
Primavera p6 18.8 planning and scheduling guide r3
Primavera p6 18.8 planning and  scheduling guide r3Primavera p6 18.8 planning and  scheduling guide r3
Primavera p6 18.8 planning and scheduling guide r3
Matiwos Tsegaye
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
Chris Carson
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Primavera p6 advanced project planning
Primavera p6 advanced project planningPrimavera p6 advanced project planning
Primavera p6 advanced project planning
Amit Kumar Senapati, PMP®
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
Nithin Dev
 
Schedule Design AACE
Schedule Design AACESchedule Design AACE
Schedule Design AACE
Chris Carson
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
Vimal Daluwatta
 
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامسأسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
M Maged Hegazy, LLM, MBA, CCP, P3O
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
Kabilan Kabi
 
Understanding p6 dates
Understanding p6 datesUnderstanding p6 dates
Understanding p6 dates
krunalplanning
 
Fast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.pptFast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.ppt
Jo Balucanag - Bitonio
 

What's hot (20)

Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
Delay analysis final
Delay analysis finalDelay analysis final
Delay analysis final
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Project management using Primavera 6.x by Karim Ragab
Project management using Primavera 6.x by Karim RagabProject management using Primavera 6.x by Karim Ragab
Project management using Primavera 6.x by Karim Ragab
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Claims
ClaimsClaims
Claims
 
Primavera p6 18.8 planning and scheduling guide r3
Primavera p6 18.8 planning and  scheduling guide r3Primavera p6 18.8 planning and  scheduling guide r3
Primavera p6 18.8 planning and scheduling guide r3
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
Primavera p6 advanced project planning
Primavera p6 advanced project planningPrimavera p6 advanced project planning
Primavera p6 advanced project planning
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Schedule Design AACE
Schedule Design AACESchedule Design AACE
Schedule Design AACE
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامسأسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
Understanding p6 dates
Understanding p6 datesUnderstanding p6 dates
Understanding p6 dates
 
Fast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.pptFast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.ppt
 

Viewers also liked

Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
katrin enders
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Project Controls Expo
 
Pdf primavera tutorial
Pdf primavera tutorialPdf primavera tutorial
Pdf primavera tutorial
Ketut Swandana
 
The analysis and valuation of disruption
The analysis and valuation of disruptionThe analysis and valuation of disruption
The analysis and valuation of disruption
Dr Ezzat Mansour
 
P6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsP6 Version 7 Tricks and Traps
P6 Version 7 Tricks and Traps
InSync Conference
 
Comparative Study of ACH and ECH
Comparative Study of ACH and ECHComparative Study of ACH and ECH
Comparative Study of ACH and ECH
Kamran Akram
 
Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2
danieljohn810
 
WASPAG Presentation on ICH - Final Version
WASPAG Presentation on ICH - Final VersionWASPAG Presentation on ICH - Final Version
WASPAG Presentation on ICH - Final Version
Ishmael Yamson
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Charlie Jackson
 
Strategic Planning first entry - that everybody should know
Strategic Planning first entry - that everybody should knowStrategic Planning first entry - that everybody should know
Strategic Planning first entry - that everybody should know
Abdullah Ahmed, PMP, RMP
 
Activity Duration Types Explained with example in Primavera
Activity Duration Types Explained with example in PrimaveraActivity Duration Types Explained with example in Primavera
Activity Duration Types Explained with example in Primavera
CADD Centre Software Solutions Private Limited
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
Chris Carson
 
What's New in Primavera P6 16.2
What's New in Primavera P6 16.2What's New in Primavera P6 16.2
What's New in Primavera P6 16.2
Plan Academy - Online Primavera P6 Training
 
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
CADD Centre Software Solutions Private Limited
 
THE IMPORTANCE OF FDI IN THE MACEDONIAN ECONOMY - MBA магистерски студии
THE IMPORTANCE OF FDI IN THE MACEDONIAN ECONOMY - MBA магистерски студииTHE IMPORTANCE OF FDI IN THE MACEDONIAN ECONOMY - MBA магистерски студии
THE IMPORTANCE OF FDI IN THE MACEDONIAN ECONOMY - MBA магистерски студии
Faculty of Economics Ljubljana in Skopje
 
Chapter 1 (overview of derivatives)
Chapter 1 (overview of derivatives)Chapter 1 (overview of derivatives)
Chapter 1 (overview of derivatives)
Syafil Kahfi
 
7. curriculum vitae
7. curriculum vitae7. curriculum vitae
7. curriculum vitae
Mohammed Soliman
 

Viewers also liked (17)

Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
Pdf primavera tutorial
Pdf primavera tutorialPdf primavera tutorial
Pdf primavera tutorial
 
The analysis and valuation of disruption
The analysis and valuation of disruptionThe analysis and valuation of disruption
The analysis and valuation of disruption
 
P6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsP6 Version 7 Tricks and Traps
P6 Version 7 Tricks and Traps
 
Comparative Study of ACH and ECH
Comparative Study of ACH and ECHComparative Study of ACH and ECH
Comparative Study of ACH and ECH
 
Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2
 
WASPAG Presentation on ICH - Final Version
WASPAG Presentation on ICH - Final VersionWASPAG Presentation on ICH - Final Version
WASPAG Presentation on ICH - Final Version
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
Strategic Planning first entry - that everybody should know
Strategic Planning first entry - that everybody should knowStrategic Planning first entry - that everybody should know
Strategic Planning first entry - that everybody should know
 
Activity Duration Types Explained with example in Primavera
Activity Duration Types Explained with example in PrimaveraActivity Duration Types Explained with example in Primavera
Activity Duration Types Explained with example in Primavera
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
What's New in Primavera P6 16.2
What's New in Primavera P6 16.2What's New in Primavera P6 16.2
What's New in Primavera P6 16.2
 
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
 
THE IMPORTANCE OF FDI IN THE MACEDONIAN ECONOMY - MBA магистерски студии
THE IMPORTANCE OF FDI IN THE MACEDONIAN ECONOMY - MBA магистерски студииTHE IMPORTANCE OF FDI IN THE MACEDONIAN ECONOMY - MBA магистерски студии
THE IMPORTANCE OF FDI IN THE MACEDONIAN ECONOMY - MBA магистерски студии
 
Chapter 1 (overview of derivatives)
Chapter 1 (overview of derivatives)Chapter 1 (overview of derivatives)
Chapter 1 (overview of derivatives)
 
7. curriculum vitae
7. curriculum vitae7. curriculum vitae
7. curriculum vitae
 

Similar to How to prepare recovery or revised schedule rev.2

Project Scope and Business Objective WorksheetA. General Informa.docx
Project Scope and Business Objective WorksheetA. General Informa.docxProject Scope and Business Objective WorksheetA. General Informa.docx
Project Scope and Business Objective WorksheetA. General Informa.docx
briancrawford30935
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
annettsparrow
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential Building
SHAZEBALIKHAN1
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
stilliegeorgiana
 
LibrePlan Audiovisual documentation
LibrePlan Audiovisual documentationLibrePlan Audiovisual documentation
LibrePlan Audiovisual documentation
LibrePlan Open Web Planning
 
MS Project 2010 Training
MS Project 2010 TrainingMS Project 2010 Training
MS Project 2010 Training
Vinit Kumar Singh
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance Analysis
Acumen
 
Sheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docx
Sheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docxSheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docx
Sheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docx
maoanderton
 
MS Project Guide.pdf
MS Project Guide.pdfMS Project Guide.pdf
MS Project Guide.pdf
MuhammadZahidQazi
 
09 Fine-tuning Assignment Details
09 Fine-tuning Assignment Details09 Fine-tuning Assignment Details
09 Fine-tuning Assignment Details
Soe Naing Win
 
Earned Effort Analysis
Earned Effort AnalysisEarned Effort Analysis
Earned Effort Analysis
Rodrigo Carvalho Pinho, PMP
 
GanttChartGantt ChartVersion 1.7.3© 2006-2014 Vertex42 LLCVert.docx
GanttChartGantt ChartVersion 1.7.3© 2006-2014 Vertex42 LLCVert.docxGanttChartGantt ChartVersion 1.7.3© 2006-2014 Vertex42 LLCVert.docx
GanttChartGantt ChartVersion 1.7.3© 2006-2014 Vertex42 LLCVert.docx
budbarber38650
 
Pm0011 – project planning
Pm0011 – project planningPm0011 – project planning
Pm0011 – project planning
smumbahelp
 
IRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project Schedule
IRJET Journal
 
Software Project Management Spm1176
Software Project Management Spm1176Software Project Management Spm1176
Software Project Management Spm1176
Ahmad Hammoud,CPM,IBA,MSE,NLP
 
7 cost PMBOK
7 cost PMBOK7 cost PMBOK
7 cost PMBOK
Waseem Siddique
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
Craig Brown
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
Tu Nguyen, PMP®,PMI-RMP®
 
Group 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdfGroup 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdf
alvieramada23
 
6 I need the overall earned value analysis.  (That is, overall i.docx
6 I need the overall earned value analysis.  (That is, overall i.docx6 I need the overall earned value analysis.  (That is, overall i.docx
6 I need the overall earned value analysis.  (That is, overall i.docx
alinainglis
 

Similar to How to prepare recovery or revised schedule rev.2 (20)

Project Scope and Business Objective WorksheetA. General Informa.docx
Project Scope and Business Objective WorksheetA. General Informa.docxProject Scope and Business Objective WorksheetA. General Informa.docx
Project Scope and Business Objective WorksheetA. General Informa.docx
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential Building
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
 
LibrePlan Audiovisual documentation
LibrePlan Audiovisual documentationLibrePlan Audiovisual documentation
LibrePlan Audiovisual documentation
 
MS Project 2010 Training
MS Project 2010 TrainingMS Project 2010 Training
MS Project 2010 Training
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance Analysis
 
Sheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docx
Sheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docxSheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docx
Sheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docx
 
MS Project Guide.pdf
MS Project Guide.pdfMS Project Guide.pdf
MS Project Guide.pdf
 
09 Fine-tuning Assignment Details
09 Fine-tuning Assignment Details09 Fine-tuning Assignment Details
09 Fine-tuning Assignment Details
 
Earned Effort Analysis
Earned Effort AnalysisEarned Effort Analysis
Earned Effort Analysis
 
GanttChartGantt ChartVersion 1.7.3© 2006-2014 Vertex42 LLCVert.docx
GanttChartGantt ChartVersion 1.7.3© 2006-2014 Vertex42 LLCVert.docxGanttChartGantt ChartVersion 1.7.3© 2006-2014 Vertex42 LLCVert.docx
GanttChartGantt ChartVersion 1.7.3© 2006-2014 Vertex42 LLCVert.docx
 
Pm0011 – project planning
Pm0011 – project planningPm0011 – project planning
Pm0011 – project planning
 
IRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project Schedule
 
Software Project Management Spm1176
Software Project Management Spm1176Software Project Management Spm1176
Software Project Management Spm1176
 
7 cost PMBOK
7 cost PMBOK7 cost PMBOK
7 cost PMBOK
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
 
Group 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdfGroup 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdf
 
6 I need the overall earned value analysis.  (That is, overall i.docx
6 I need the overall earned value analysis.  (That is, overall i.docx6 I need the overall earned value analysis.  (That is, overall i.docx
6 I need the overall earned value analysis.  (That is, overall i.docx
 

Recently uploaded

❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
nainakaoornoida
 
Cricket management system ptoject report.pdf
Cricket management system ptoject report.pdfCricket management system ptoject report.pdf
Cricket management system ptoject report.pdf
Kamal Acharya
 
🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...
🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...
🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...
adhaniomprakash
 
CSP_Study - Notes (Paul McNeill) 2017.pdf
CSP_Study - Notes (Paul McNeill) 2017.pdfCSP_Study - Notes (Paul McNeill) 2017.pdf
CSP_Study - Notes (Paul McNeill) 2017.pdf
Ismail Sultan
 
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call GirlCall Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
sapna sharmap11
 
BBOC407 Module 1.pptx Biology for Engineers
BBOC407  Module 1.pptx Biology for EngineersBBOC407  Module 1.pptx Biology for Engineers
BBOC407 Module 1.pptx Biology for Engineers
sathishkumars808912
 
The Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC Conduit
The Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC ConduitThe Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC Conduit
The Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC Conduit
Guangdong Ctube Industry Co., Ltd.
 
Call Girls Chandigarh 🔥 7014168258 🔥 Real Fun With Sexual Girl Available 24/7...
Call Girls Chandigarh 🔥 7014168258 🔥 Real Fun With Sexual Girl Available 24/7...Call Girls Chandigarh 🔥 7014168258 🔥 Real Fun With Sexual Girl Available 24/7...
Call Girls Chandigarh 🔥 7014168258 🔥 Real Fun With Sexual Girl Available 24/7...
shourabjaat424
 
Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)
Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)
Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)
Tsuyoshi Horigome
 
Basic principle and types Static Relays ppt
Basic principle and  types  Static Relays pptBasic principle and  types  Static Relays ppt
Basic principle and types Static Relays ppt
Sri Ramakrishna Institute of Technology
 
🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...
🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...
🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...
aarusi sexy model
 
💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...
💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...
💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...
rupa singh
 
Call Girls Madurai 8824825030 Escort In Madurai service 24X7
Call Girls Madurai 8824825030 Escort In Madurai service 24X7Call Girls Madurai 8824825030 Escort In Madurai service 24X7
Call Girls Madurai 8824825030 Escort In Madurai service 24X7
Poonam Singh
 
Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...
Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...
Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...
Banerescorts
 
Kandivali Call Girls ☑ +91-9967584737 ☑ Available Hot Girls Aunty Book Now
Kandivali Call Girls ☑ +91-9967584737 ☑ Available Hot Girls Aunty Book NowKandivali Call Girls ☑ +91-9967584737 ☑ Available Hot Girls Aunty Book Now
Kandivali Call Girls ☑ +91-9967584737 ☑ Available Hot Girls Aunty Book Now
SONALI Batra $A12
 
一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理
一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理
一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理
nonods
 
TENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineeringTENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineering
SnehalChavan75
 
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
sonamrawat5631
 
🚺ANJALI MEHTA High Profile Call Girls Ahmedabad 💯Call Us 🔝 9352988975 🔝💃Top C...
🚺ANJALI MEHTA High Profile Call Girls Ahmedabad 💯Call Us 🔝 9352988975 🔝💃Top C...🚺ANJALI MEHTA High Profile Call Girls Ahmedabad 💯Call Us 🔝 9352988975 🔝💃Top C...
🚺ANJALI MEHTA High Profile Call Girls Ahmedabad 💯Call Us 🔝 9352988975 🔝💃Top C...
dulbh kashyap
 
Data Communication and Computer Networks Management System Project Report.pdf
Data Communication and Computer Networks Management System Project Report.pdfData Communication and Computer Networks Management System Project Report.pdf
Data Communication and Computer Networks Management System Project Report.pdf
Kamal Acharya
 

Recently uploaded (20)

❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
❣Independent Call Girls Chennai 💯Call Us 🔝 7737669865 🔝💃Independent Chennai E...
 
Cricket management system ptoject report.pdf
Cricket management system ptoject report.pdfCricket management system ptoject report.pdf
Cricket management system ptoject report.pdf
 
🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...
🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...
🔥LiploCk Call Girls Pune 💯Call Us 🔝 7014168258 🔝💃Independent Pune Escorts Ser...
 
CSP_Study - Notes (Paul McNeill) 2017.pdf
CSP_Study - Notes (Paul McNeill) 2017.pdfCSP_Study - Notes (Paul McNeill) 2017.pdf
CSP_Study - Notes (Paul McNeill) 2017.pdf
 
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call GirlCall Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
Call Girls Goa (india) ☎️ +91-7426014248 Goa Call Girl
 
BBOC407 Module 1.pptx Biology for Engineers
BBOC407  Module 1.pptx Biology for EngineersBBOC407  Module 1.pptx Biology for Engineers
BBOC407 Module 1.pptx Biology for Engineers
 
The Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC Conduit
The Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC ConduitThe Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC Conduit
The Differences between Schedule 40 PVC Conduit Pipe and Schedule 80 PVC Conduit
 
Call Girls Chandigarh 🔥 7014168258 🔥 Real Fun With Sexual Girl Available 24/7...
Call Girls Chandigarh 🔥 7014168258 🔥 Real Fun With Sexual Girl Available 24/7...Call Girls Chandigarh 🔥 7014168258 🔥 Real Fun With Sexual Girl Available 24/7...
Call Girls Chandigarh 🔥 7014168258 🔥 Real Fun With Sexual Girl Available 24/7...
 
Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)
Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)
Update 40 models( Solar Cell ) in SPICE PARK(JUL2024)
 
Basic principle and types Static Relays ppt
Basic principle and  types  Static Relays pptBasic principle and  types  Static Relays ppt
Basic principle and types Static Relays ppt
 
🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...
🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...
🔥 Hyderabad Call Girls  👉 9352988975 👫 High Profile Call Girls Whatsapp Numbe...
 
💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...
💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...
💋Mature Women / Aunty Call Girls Gurgaon 💯Call Us 🔝 9999965857 🔝💃Independent ...
 
Call Girls Madurai 8824825030 Escort In Madurai service 24X7
Call Girls Madurai 8824825030 Escort In Madurai service 24X7Call Girls Madurai 8824825030 Escort In Madurai service 24X7
Call Girls Madurai 8824825030 Escort In Madurai service 24X7
 
Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...
Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...
Hot Call Girls In Bangalore ✔ 9079923931 ✔ Hi I Am Divya Vip Call Girl Servic...
 
Kandivali Call Girls ☑ +91-9967584737 ☑ Available Hot Girls Aunty Book Now
Kandivali Call Girls ☑ +91-9967584737 ☑ Available Hot Girls Aunty Book NowKandivali Call Girls ☑ +91-9967584737 ☑ Available Hot Girls Aunty Book Now
Kandivali Call Girls ☑ +91-9967584737 ☑ Available Hot Girls Aunty Book Now
 
一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理
一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理
一比一原版(psu学位证书)美国匹兹堡州立大学毕业证如何办理
 
TENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineeringTENDERS and Contracts basic syllabus for engineering
TENDERS and Contracts basic syllabus for engineering
 
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
🔥Young College Call Girls Chandigarh 💯Call Us 🔝 7737669865 🔝💃Independent Chan...
 
🚺ANJALI MEHTA High Profile Call Girls Ahmedabad 💯Call Us 🔝 9352988975 🔝💃Top C...
🚺ANJALI MEHTA High Profile Call Girls Ahmedabad 💯Call Us 🔝 9352988975 🔝💃Top C...🚺ANJALI MEHTA High Profile Call Girls Ahmedabad 💯Call Us 🔝 9352988975 🔝💃Top C...
🚺ANJALI MEHTA High Profile Call Girls Ahmedabad 💯Call Us 🔝 9352988975 🔝💃Top C...
 
Data Communication and Computer Networks Management System Project Report.pdf
Data Communication and Computer Networks Management System Project Report.pdfData Communication and Computer Networks Management System Project Report.pdf
Data Communication and Computer Networks Management System Project Report.pdf
 

How to prepare recovery or revised schedule rev.2

  • 1. HOW TO PREPARE THE RECOVERY / REVISED SCHEDULE Rev.2 By. Engr. Abdulhay Mohamed Ghanem Sr. Planning Engineer at Abdullah A. Alkodari Co.
  • 2. Purpose of this document : Purpose of this document is to explain recovery/revised schedule properly by using Who should read this document This document is for who is concern about schedulers, projects controllers and projects managers The guys who will read and utilize Primavera software like global changes, export effect on schedule updating and this equation BL Start). i.e A%C = (DD – BLST) / ( this document. Let us start with preparation of Firstly we have to know what is the meaning of recovery schedule? . We can simply say that the recovery schedule is a new baseline schedule to rectify any occurred delay to the whether by using crashing technique or fast track technique. My example in this document, I am schedule you have to make sure of the following: 1- No activities are out of sequence. 2- No activities with unsatisfied relation. 3- Remaining early start of all in progress activities is one day after data date Regarding point no. 3, I will explain why we should fulfill which will be applied. 4- Detach the baseline and separate the If the updated schedule has an assigned baseline you shall remove that baseline. is to explain and help how to use Primavera software to create a recovery/revised schedule properly by using Primavera tools. document: who is concern about Primavera and project management such planners, projects controllers and projects managers. utilize this document should be conversant the following tools and options in global changes, export and import in excel format, percent effect on schedule updating and this equation Activity % complete = (Data date – BLST) / (BLF – BLST), Which will be used to conclude the used Let us start with preparation of recovery schedule. Firstly we have to know what is the meaning of recovery schedule? . We can simply say that the recovery schedule is a new baseline schedule to rectify any occurred delay to the project to meet contractual end whether by using crashing technique or fast track technique. example in this document, I am using percent complete type physical, before prepare your recovery have to make sure of the following: are out of sequence. satisfied relation. Remaining early start of all in progress activities is one day after data date Regarding point no. 3, I will explain why we should fulfill this condition during explain the global changes and separate the current progress. If the updated schedule has an assigned baseline you shall remove that baseline. Data Date is 31.May.15 rimavera software to create a rimavera and project management such planners, should be conversant the following tools and options in percent complete type and its BL start) / (BL finish – Which will be used to conclude the used equation in schedule. Firstly we have to know what is the meaning of recovery schedule? . We can simply say that the recovery project to meet contractual end prepare your recovery Remaining early start of all in progress activities is one day after data date not more. lain the global changes If the updated schedule has an assigned baseline you shall remove that baseline. Data Date is 31.May.15
  • 3. Tip: If this message appeared to you. It means you have to release the old baseline from assigning to the current project. assign baselines and change to current pro If this message appeared to you. means you have to release the old baseline from assigning to the current project. and change to current project in mentioned tow positions, and then you can delete. means you have to release the old baseline from assigning to the current project. From project – ject in mentioned tow positions, and then you can delete.
  • 4. 5- Delete finish constraint of the project. In projects layout, select dates label then remove date in cell of must finish by.(highlight it then press delete) 6- Press F9 to run scheduling– scheduling options). Delete finish constraint of the project. layout, select dates label then remove date in cell of must finish by.(highlight it then press delete) – Using retained logic option before scheduling progressed activities (From layout, select dates label then remove date in cell of must finish by.(highlight it then press delete) option before scheduling progressed activities (From
  • 5. Now you can adjust the remaining duration in progress activities and the relations of not started activities to prepare a proper recovery schedule accordance with view of PM & CM and site Tip: If you are using duration type fix duration and units, you are using duration type fix duration and unit/time you will find your budgeted planned in your baseline schedule before creating the recovery sc end of this document how to solve. Now we will apply the following global change to the current project as follow a- Original duration of b- Planned start date and planned finish date to be equal actual date for completed activities. Now you can adjust the remaining duration (remember I am using physical type for percent complete type) in progress activities and the relations of not started activities to prepare a proper recovery schedule accordance with view of PM & CM and site requirement to close the project on contractual end ion type fix duration and units, you will find your budgeted total cost still the same. If you are using duration type fix duration and unit/time you will find your budgeted total cost is more than you planned in your baseline schedule before creating the recovery schedule. To solve this issue I will explain at the is document how to solve. Now we will apply the following global change to the current project as following: nal duration of completed activities. (Original should = actual) Planned start date and planned finish date to be equal actual date for completed (remember I am using physical type for percent complete type) of in progress activities and the relations of not started activities to prepare a proper recovery schedule in requirement to close the project on contractual end. you will find your budgeted total cost still the same. If total cost is more than you solve this issue I will explain at the . (Original should = actual) Planned start date and planned finish date to be equal actual date for completed
  • 6. C- Original duration of in progress activities. ( d - Planned start date to be equal actual date for in progress activities. After complete all steps. Did you asked yourself why PV of the new recovery baseline? And how we can adjust it to make EV = PV = 67,528,929.48 SAR in my example? you glanced to the snapshot below Original duration of in progress activities. (Original = actual + remaining ). Planned start date to be equal actual date for in progress activities. After complete all steps. Did you asked yourself why EV at Data date PV of the new recovery baseline? And how we can adjust it to make EV = PV = SAR in my example?(remember I am using percent complete type physical) you glanced to the snapshot below actual + remaining ). Planned start date to be equal actual date for in progress activities. date (31.May.15) not equal PV of the new recovery baseline? And how we can adjust it to make EV = PV = (remember I am using percent complete type physical). If
  • 7. In our example I used budgeted values to the others two options it will not affect on the result as shown in previous snapshot. From - admin - admin preferences In our example I used budgeted values with current dates (Default option) even you change it to the others two options it will not affect on the result as shown in previous snapshot. admin preferences (Default option) even you change it to the others two options it will not affect on the result as shown in previous snapshot.
  • 8. What if you are using bingeing in your baseline schedule before previous global changes default to at completion values with current dates 1- EV = PV but not equal 2- The activities percent complete will be changed as well to values more than the actual activities % complete Note: in this example, same data date is 68,876,923.16 Snapshot No.1 What if you are using percent complete type duration?. if you are using this type from bingeing in your baseline schedule before creating the recovery baseline, previous global changes then you changed the option of earned value calculation from default to at completion values with current dates you will find the following: EV = PV but not equal 68,876,923.16 SAR The activities percent complete will be changed as well to values more than the actual activities % complete at site. Please compare between snapshot No.1 and No.2. in this example, we are using percent complete type duration the earned value at the 68,876,923.16 SAR using this type from creating the recovery baseline, then you applied all then you changed the option of earned value calculation from will find the following: The activities percent complete will be changed as well to values more than the actual at site. Please compare between snapshot No.1 and No.2. we are using percent complete type duration the earned value at the
  • 9. Note: The variance between PL and EV in snapshot No. 2 available. With return to previous example (Physical), and the familiar equation of – BL start) / (BL finish – BL start) deferent formula. (Ghanem Equation Let us see how I concluded this equation A%C = (DD – BLST) / (BLF Also OD = ED + RD Where OD = Original duration of the activity. ED = Elapsed duration of in progress activity. RD = Remaining duration of in progress activity. Then A%C = (DD – BLST) / (ED + RD) A%C = ED / (ED + RD) Where ED = DD – BLST for in progress activity. A%C X ED + A%C X R A%C X RD = ED – A%C X ED RD = (ED / A%C) – ED RD = ED ((1 / A%C) While ED = DD – Then DD – BLST = RD / ((1 / A%C) Then BLST = DD Snapshot No.2 The variance between PL and EV in snapshot No. 2 due to condition No.3 in page No. example (Physical), and the familiar equation of Activity % complete = (Data date BL start) which I will use it to adjust EV = PL = 67,528,929.48 Ghanem Equation) BLST = DD – (RD / ((1 / A%C) – 1))) Let us see how I concluded this equation BLST) / (BLF-BLST) whereas BLF – BLST = OD Where OD = Original duration of the activity. ED = Elapsed duration of in progress activity. RD = Remaining duration of in progress activity. BLST) / (ED + RD) A%C = ED / (ED + RD) BLST for in progress activity. A%C X ED + A%C X RD = ED A%C X ED ED RD = ED ((1 / A%C) – 1) – BLST and ED = RD / ((1 / A%C) – 1) BLST = RD / ((1 / A%C) – 1) BLST = DD – (RD / ((1 / A%C) – 1))) due to condition No.3 in page No. 2 is not Activity % complete = (Data date 67,528,929.48 SAR but in 1))) BLST = OD
  • 10. Note: DD, A%C and RD are fixed to fulfill the requirement of a proper recovery baseline schedule. If you filtered the completed a problem will arise (EV not equal PV). issue. Export an excel sheet contain the following to work out from Enterprise menu DD, A%C and RD are fixed to fulfill the requirement of a proper recovery baseline If you filtered the completed activities you will find EV = PV. while in progress activities, problem will arise (EV not equal PV). therefore we will use the previous formula to solve this Export an excel sheet contain the following to work out the formula. Before exporting, create from Enterprise menu – user defined fields tow new fields as shown. DD, A%C and RD are fixed to fulfill the requirement of a proper recovery baseline V. while in progress activities, the previous formula to solve this . Before exporting, create
  • 11. With reference to third condition not available the new original duration vise is correct. So, this availability of this condition is very important to work out formula third condition in page No.2, if you look to the following you will find condition not available the new original duration will be less than the actual + remaining while this availability of this condition is very important to work out formula Condition is not available so 67+30 not equal 103 In Primavera Actual Duration of in progress activity is the elapsed duration (ED) condition in page No.2, if you look to the following you will find if the will be less than the actual + remaining while this availability of this condition is very important to work out formula. In Primavera Actual Duration of in progress activity is the elapsed
  • 12. Let us complete exporting operationLet us complete exporting operation Condition is available so 67+30 = 97 Only in progress activity n progress
  • 13. Then add comma from option DataThen add comma from option Data – Text to columns Copy – Past values
  • 14.
  • 15. Apply this global change to calculate the new actual start date.Apply this global change to calculate the new actual start date. Data Date Delete operation area then save then import to Priamvera Delete operation area then
  • 16. Then apply this global change to make actual start equal to New Act st. The result will be as shown below. Reuse global change No. C & D Then apply this global change to make actual start equal to New Act st. The result will be as shown below. to adjust the original duration, the result will be as the following: Note Then apply this global change to make actual start equal to New Act st. result will be as the following:
  • 17. Now EV = PV with variance 122,608 Put the contractual end (Must finish by) Wait for Rev.3 In rev.3 I will talk exhaustively about revised schedule, schedule and how to use excel sheet apply some changes on that base line schedule type of the activities. 122,608 SAR (variance = 0.18% of earned value can be neglected) (Must finish by), maintain, assign your new created recovery about revised schedule, How to save actual dates to and how to use excel sheet to transfer data from updated schedule to ba apply some changes on that base line schedule as mentioned in page No. 5 about 0.18% of earned value can be neglected) your new created recovery, enjoy. How to save actual dates to submit as built to transfer data from updated schedule to baseline schedule after as mentioned in page No. 5 about modifying duration
  • 18. My contacts informaiton Skype account : en_ghanem Email : Abdelhay.Ghanem@gmail.com Mobile Phone : +966-546810855 , +966-593068907
  翻译: