尊敬的 微信汇率:1円 ≈ 0.046239 元 支付宝汇率:1円 ≈ 0.04633元 [退出登录]
SlideShare a Scribd company logo
COLUMN BASE PLATES
- DESIGN TO ERECTION –
Tom Murray
Emeritus Professor
Virginia Tech
Blacksburg, VA

1
Column Base Plates

2
Types of Column Base Plates
Compressive Axial Loads

Base Plates with Small Moments

Tensile Axial Loads

Base Plates with Large Moments

3
AISC Design Guide 1

4
AISC Specification
PERTINENT SECTIONS AND TABLES
Chapter J Design of Connections
Table J3.2 Nominal Strength of
Fasteners and Threaded Parts
J8. Column Basses and Bearing on
Concrete

Chapter M Fabrication and Erection
M2.2 Thermal Cutting
M2.8 Finish of Column Bases
M4.4 Fit of Column Compression Joints
and Base Plates
5
Types of Column Base Plates
TOPICS
• Base Plate and Anchor Rod Material and Details
• Base Plates for Axial Compression
• Base Plates for Tension
• Base Plates for Axial Compression and Moment
• Shear Anchorage
• Column Erection Procedures
• Result of Poor Anchor Rod Placement
6
Base Plate and Anchor Rod
Materials and Details

7
Base Plate Material, Fabrication and Finishing
Base Plate Material
• Typical A36
• 1/8” (3mm) increments to 1-1/4 in (32 mm) then ½ in. (6 mm)
• Minimum thickness ½ in. (13 mm), typical ¾ in. (20 mm)
Fabrication and Finishing
• Plate is thermally cut
• Holes drilled or thermally cut
• Specification Section M2.2 has requirements for thermal cutting
• Finishing: Specification Section M2.8
< 2 in. (50 mm) milling not generally required
2 – 4 in.(50 – 100 mm) straightened by pressing or milling
> 4 in. (100 mm) milling required
Only mill where column bears
• Bottom surface with grout need not be milled
• Top surface not milled if complete-joint-penetration (CJP) welds
8
Base Plate Material, Fabrication and Finishing
Base Plate Welding
• Fillet welds preferred up to ¾ in. (20 mm) then groove welds
• Avoid all around symbol
• Weld for wide-flange columns subject to axial compression
Weld on one side of column flanges
to avoid rotating the section:

• HSS subject to axial compression: Weld flats only
• Shear, Tension, Moment, and Combinations
Size weld for forces not all around
No weld at fillets of wide-flange columns
Must weld at corners of HSS if tension or moment
• Shop welded preferred
• Very heavy base plates may be field welded after grouting
9
Anchor Rod Materials and Details
Anchor Rod Material

• Preferred ASTM F1554 Gr 36 except when high tension and or
moment.
10
Anchor Rod Materials and Details
Anchor Rod Material
• Unified Course (UNC) threads
• Standard Hex Nuts permitted but Heavy Hex nuts required for
oversize holes and with high strength anchor rods.
• Hooked anchor rods have very low pull-out strength but OK for
axial compression only.
• Headed rods or rods with nuts are preferred.

Headed Rods

Rods with Nuts
11
Anchor Rod Materials and Details
Anchor Rod Material
• Use of plate washers at bottom of rods can cause erection
problems and should be avoided.
• Drilled-in epoxy anchor rods may be used for light loads
• Wedge-type anchors should not be used because of potential
loosing during erection.

12
Anchor Rod Materials and Details
Anchor Rod Holes and Washers
• Oversize holes required because of placement tolerances.
• Recommended hole and washer sizes are in Design Guide 1
(Table 2-3) and AISC 14th Ed. Manual (Table 14-2).

• Smaller holes may be used when axial compression only.
• Plate washers required when tension and/or moment.
13
Anchor Rods Material and Details
Anchor Rod Sizing and Layout
• Recommendations
Use ¾ in. (22 mm) minimum diameter.
Use Grade 36 rod up to about 2 in. (50 mm) diameter.
Thread at least 3 in. (75 mm) beyond what is needed.
Minimum ½ in. (12 mm) distance between edge of hole
and edge of plate.
Use symmetrical pattern whenever possible.
• Provide ample clearance for nut tightening.
• Coordinate anchor bolt placement with reinforcement location.

14
Occupational Safety and Health Administration (OSEA)
OSEA Safety Standards for Steel Erection (2008)
• Minimum of four anchor rods.
• Base plate to resist eccentric gravity load of 300 lb (1,300 N) 18
in. (450 mm) from extrem outer face of column in each direction.
• 300 lb (1,300) represents weight of iron worker with tools.
• Exception: Post-type columns weighing less than 300 lb.
18 in.

Note: Smallest of anchor rods on
a 4 in. by 4 in. (100 mm by 100 mm)
pattern is generally sufficient.

300 lb

15
Column Base Plates
DESIGN CONSIDERATIONS
• Base Plate Bending Strength
• Concrete Crushing
• Concrete Anchorage for Tension Forces
• Shear Resistance
• Anchor Rod Tension Design
• Anchor Rod Shear Design
• Anchor Rod Embedment
• Constructability
16
Base Plates for
Axial Compression

17
Design for Axial Compression
Column Base Plate Design Limit States
• Base Plate Bending
• Concrete Crushing

18
Design for Axial Compression
Column Base Plate Bending

fpu = Ru /(BxN) = pressure due to reaction
Let m’ = max(n and m)
Mu= fpu (1) (m’2/2 < φMp
φMp = 0.9 Fy Zx = 0.9x 1 x tp2/4) Fy
Substituting:

t p , min

=

2 f pu ( m ' 2 )
0 .9 F y

19
Design for Axial Compression
Column Base Plate Bending
• Lightly Loaded Base Plate
• Required concrete bearing area is less than bfdc.
d

bf

Bearing Area
20
Design for Axial Compression
Column Base Plate Bending
• Lightly Loaded Base Plate
Replace m′ with l = max {m, n, λn′}, where
′
′
2 X
λ =
≤ 1 .0
1+ 1-X

1
n′ =
4

db f

2f pu l 2

t p ,min =
 4db f  Pu
0.9Fy

X=
 (d + b )2  φPp
f


Reference: Thornton, W.A., Design of Base Plates for Wide Flange
Columns – A Concatenation of Methods, AISC Engineering Journal,
21
Fourth Quarter, 1990.
Design for Axial Compression
HSS Sections
• Bend lines.

0.95h

0.95d

0.80d

22
Design for Axial Compression
Concrete Crushing
Specification Section J8. Column Bases and Bearing on Concrete
φc = 0.65
(a) On the full area of a concrete support
Pp = 0.85fc′A1
(J8-1)
(b) On less than the full area of a concrete support
(J8-2)
where Pp = 0.85fc A1 A 2 / A1 ≤ 1.7fc A1
′
′
fc’ = specified compressive strength of concrete, ksi (Mpa)
A1 = area of steel bearing on concrete, in.2
A2 = area of the portion of the supporting surface that is
geometrically similar to and concentric with the
loaded area, in.2
Note: The limit < 1.7f’c is equivalent to A2/A1 < 4
23
Design for Axial Compression -- Example

o

24”

18”

Ex.: Determine if the base plate shown is adequate.
Column: W10x33 d = 9.73 in. bf = 7.96 in.
PL 1-½ x 18 x 1’-6” A36
Concrete Pedestal:
24 in. by 24 in. (assume square)
fc′′=3.0 ksi
Pu = 250 kips
o
o

o
18”
24”

24
Design for Axial Compression -- Example
Concrete Crushing
A1 = 18 x 18 = 324 in2 (Plan area of base plate)
A2 = (24)(24) = 576 in2 (Plan area of concrete pedestal)
A2/A1 = 576/324 = 1.78 < 4

o

o

o

24”

= 0.65 (0.85 × 3.0 ) (324 ) 1.78
= 716 k > 250 k OK

o

18”

′
φPp = φ 0.85 f c A 1

A2
A1

18”
24”

25
Design for Axial Compression -- Example
Plate Bending
n = 5.82 in. m = 4.38 in.
7.96”

n ′ = (1 / 4 ) db f
= (1 / 4 ) 9 .73 x 7 .96
= 2 .20 in .
 4db f  Pu

X=
2  φP
 (d + b )
f

 p
 4x9.73x7.96  250

=
 (9.73 + 7.96 )2  716 = 0.333



4.38”
9.24”

9.73”

18”

4.38”

5.82 6.37 5.82
18”

26
Design for Axial Compression -- Example
Plate Bending
n = 5.82 in. m = 4.38 in.
7.96”

n ′ = (1 / 4 ) db f
= (1 / 4 ) 9 .73 x 7 .96
= 2 .20 in .
 4db f  Pu

X=
2  φP
 (d + b )
f

 p
 4x9.73x7.96  250

=
 (9.73 + 7.96 )2  716 = 0.333



4.38”
9.24”

9.73”

18”

4.38”

5.82 6.37 5.82
18”

27
Design for Axial Compression -- Example
Plate Bending
2 X
2 0 . 333
λ =
=
1+ 1-X
1 + 1 - 0 . 333
= 0 . 635 ≤ 1 . 0
λ n ' = 0 . 635 x 2 . 20 = 1 . 40 in .

7.96”

4.38”

9.73”

9.24”

l = max {m, n, λn′}
′
= max {4.38,5.82,1.40} = 5.82 in.

4.38”

fpu = Ru /BN = 250/(18x18)
= 0.772 ksi

18”

5.82 6.37 5.82
18”

28
Design for Axial Compression -- Example
Plate Bending

tp =

2f pu l 2
0.9Fy

=

2 x 0.772 x 5.82 2
0.9 x 36

7.96”

4.38”

= 1.27 in . ≤ 1.5in . OK
9.24”

9.73”

18”

4.38”

PL 1-½ x 18 x 1’-6” A36
is Adequate.

5.82 6.37 5.82
18”

29
Design for Axial Compression
Variation of φPn with Base Plate Thickness with Increasing Axial Force

φPn

m or n

c
c

c

BN = bfd
Required tp
30
Design for Axial Compression
Was the base plate too strong?

31
Base Plates for
Axial Tension

32
Design for Tensile (Uplift) Forces
Connection Limit States
• Anchor Rod Tensile Strength
• Concrete Pull-out Strength
• Concrete Anchorage Tensile Strength
• Base Plate Bending Strength

33
Design for Tensile (Uplift) Forces
Anchor Rod Tensile Strength
• Tensile Strength
φTn = φ FntAb
where φ = 0.75
Fnt = 0.75Fu
Fu = specified minimum tensile strength of anchor rod
= 58 ksi (300 MPa) for Gr 36
= 75 ksi (400 MPa) for Gr 55
= 125 ksi (650 MPa) for Gr 125
Notes: Ab is the nominal area of the anchor rod = πd2/4.
0.75 in 0.75Fu account for rupture (tensile) area.
See AISC 14th Ed. Manual Table 7-17 for actual areas.

34
Design for Tensile (Uplift) Forces
Ex.

Determine the design strength,φTn, for the limit state
of anchor rod tension rupture. 4 - ¾ in. (20 mm)
diameter, Grade 36 anchor rods

φTn = 4 x 0.75 (0.75Fu) Ab
= 4 x 0.75 (0.75x58)(π0.752/4)
= 4 x 14.4 kips (4 x 53 kN)
= 57.6 kips (212 kN)

35
Design for Tensile (Uplift) Forces
Concrete Pullout Strength
• Provisions in ACI 318-08, Section D5.3
• Design pullout strength of headed anchor
rod or anchor rod with nut:
φNp = φ ψ4Abrg8f’c
where φ = 0.70
ψ4 = 1.4 for no cracking, 1.0 if cracking exists
Abrg = net bearing area of the anchor rod head or nut, in2
f’c = specified compression strength of concrete, psi
Notes: Hooked anchor rods are not recommended with tensile
loadings.

36
Design for Tensile (Uplift) Forces
Concrete Pullout Strength
• AISC Design Guide 1 Table for Strengths with Heavy Hex Nuts

Note: kN = 4.448 x kips

N/mm2 = 6.895x10-3 x psi
37
Design for Tensile (Uplift) Forces
Concrete Breakout Strength
• Provisions in ACI 318-08, Section D4.2.2

Full breakout cone

Breakout cone for group anchors

Breakout cone near edge
38
Design for Tensile (Uplift) Forces
Base Plate Bending Strength
• AISC Design Guide 1 recommended bend lines.
g2

g1

Alternate Critical Section is the
full width of the base plate.

39
Design for Tensile (Uplift) Forces
Base Plate Bending Strength
• Other possible bend lines.

Critical
Section

Critical
Section
bf + 1 in.

Similar to Extended End-Plates

For all cases:
Define: x = distance from center of anchor bolt to critical section
w = width of critical section
Tu = force in anchor bolt
4Tu x
t p ,min =
φMn = 0.9Fywtp2/4 = Mu = Tux
0.9Fy w
40
Base Plates for Axial
Compression and Moment

41
Design for Axial Compression and Moment
Connection Limit States
• Concrete Crushing
• Anchor Rod Tensile Strength
• Concrete Pull-out Strength

O

• Concrete Anchorage Tensile Strength
• Base Plate Bending Strength
Cases
• T = 0 (Relatively small moment)
• T > 0 (Relatively large moment)
42
Design for Axial Compression and Moment
Limit for T = 0
∑Fy = 0 with T=0 Base Plate is B by N in plan.
Pr = qY = fpBY
∑Mo = 0
Pre = qY2/2 – PrN/2
Then
e = N/2 – Y/2 of if fp < fp,max
with
′
′
fp ,max = 0.65x0.85fc A 2 / A1 ≤ 0.65x 1.7fc
then
ecrit = N/2 –Pr/(2Bfp,max)
Therefore

If e < ecrit, T =0 and Y = N-2e
ecrit = N/2 –Pr/(2Bfp,max)
43
Design for Axial Compression and Moment
For T > 0
e > ecrit and fp = fp,max
∑Fy = 0
Pr – T – fp,maxBY =0
∑Mo = 0
T(N/2+f) + Pr(N/2) – Pre – fp,maxBY2/2 = 0
Solving the resulting quadratic equation
Note: If the quantity in the
radical is less than zero, a
larger base plate is required.

Y =(f + N / 2) − (f +

N 2 2Pr (e + f )
) −
2
fp ,max B

T = fp ,max BY − T

44
Design for Axial Compression and Moment
Ex. 1. Determine required plate thickness and anchor rod diameter.
Given: Pu = 376 kips Mu = 940 in-kips
W12x96 A992
N = 19 in. B = 19 in. A2/A1 = 1 < 4 bf = 12.2 in. d = 12.7 in.
fc’ = 4.0 ksi Fy = 36 ksi
f = 8 in.
Solution:
′
fp ,max = 0.65x0.85fc A 2 / A1
= 0.65x0.85x4.0 1.0 = 2.21 ksi

e = Mu/Pu = 970/376 = 2.50
ecrit = N/2 –Pr/(2Bfp,max)
= 19.0/2 – 376/(2x19.0x2.21)
= 5.02 in.
e < ecrit → T = 0 and Y = N-2e = 19.0 – 2x 2.50
= 14.0 in.
45
Design for Axial Compression and Moment
Ex. 1. Determine required plate thickness and anchor rod diameter.
Given: Pu = 376 kips Mu = 940 in-kips
W12x96 A992
N = 19 in. B = 19 in. A2/A1 = 1 < 4 bf = 12.2 in. d = 12.7 in.
fc’ = 4.0 ksi Fy = 36 ksi
f = 8 in.
Solution Continued:
fp = Pu/(NY)
= 376/(19.0x14.0) = 1.41 ksi
m = (N-0.95d)/2 = (19.0-0.95x12.7)/2 = 3.47 in.
m = (B-0.80bf)/2 = (19.0-0.80x12.2)/2 = 4.62 in.
tp =

2f pu n 2
0.9Fy

=

2 x1.41x 4.62 2
= 1.36 in .
0.9 x 36

Use PL 1½ x 19 x 1ft 7 in. A36
4 – ¾ in. Anchor Rods x 12 in. F1554 Gr 36
w/ heavy hex nuts at bottom.

46
Design for Axial Compression and Moment
Ex. 2. Determine required plate thickness and anchor rod diameter.
Given: Pu = 376 kips Mu = 2500 in-kips
W12x96 A992
N = 19 in. B = 19 in. A2/A1 = 1 < 4 bf = 12.2 in. d = 12.7 in.
fc’ = 4.0 ksi Fy = 36 ksi
f = 8 in.
Solution:
′
fp ,max = 0.65x0.85fc A 2 / A1
= 0.65x0.85x4.0 1.0 = 2.21 ksi

e = Mu/Pu = 2500/376 = 6.65
ecrit = N/2 –Pr/(2Bfp,max)
= 19.0/2 – 376/(2x19.0x2.21)
= 5.02 in.
N
2 P (e + f )
e > ecrit → T > 0 and Y =(f + N / 2) − (f + )2 − r
2

fp ,max B

47
Design for Axial Compression and Moment
Ex. 2. Determine required plate thickness and anchor rod diameter.
Given: Pu = 376 kips Mu = 2500 in-kips
W12x96 A992
N = 19 in. B = 19 in. A2/A1 = 1 < 4 bf = 12.2 in. d = 12.7 in.
fc’ = 4.0 ksi Fy = 36 ksi
f = 8 in.
Solution Continued:
N 2 2Pr (e + f )
Y = (f + N / 2 ) − (f + ) −
2
fp ,max B
19.0 2 2x 376(6.65 + 8.0)
) −
= (8.0 + 19.0 / 2) − (8.0 +
2
2.21x19.0
= 10.9 in.

fp = Pu/(NY)
= 376/(19.0x10.9) = 1.82 ksi

48
Design for Axial Compression and Moment
Ex. 2. Determine required plate thickness and anchor rod diameter.
Given: Pu = 376 kips Mu = 2500 in-kips
W12x96 A992
N = 19 in. B = 19 in. A2/A1 = 1 < 4 bf = 12.2 in. d = 12.7 in.
fc’ = 4.0 ksi Fy = 36 ksi
f = 8 in.
Solution Continued:
m = (N - 0.95d)/2 = (19.0-0.95x12.7)/2 = 3.47 in.
n = (B - 0.80bf)/2 =(19.0-0.80x12.2)/2 = 4.62 in.
tp =

2f pu m 2
0.9Fy

=

2 x1.82 x 4.62 2
= 1.54 in .
0.9 x 36

Need to check tensions side.

49
Design for Axial Compression and Moment
Ex. 2. Determine required plate thickness and anchor rod diameter.
Given: Pu = 376 kips Mu = 2500 in-kips
W12x96 A992
N = 19 in. B = 19 in. A2/A1 = 1 < 4 bf = 12.2 in. d = 12.7 in.
fc’ = 4.0 ksi Fy = 36 ksi
f = 8 in.
Solution Continued:
T = fp,max BY – Pu
= 2.21x19.0x10.9 – 376 = 80.4 kips
Try 2 – Anchor Rods each Side
Required plate thickness:
X = f – 0.95d/2 = 8.0 -0.95x12.7/2
= 1.96 in.
x
w = bf + 1.0 = 12.2 + 1.0 = 13.0 in.
f
4T x
4 x 80 .4 x1.96
t p ,min =
=
= 1.22 in .
0.9Fy w
0.9 x 36 x13 .0
Use PL 1½ x 19 x 1ft 7 in. A36 50
Design for Axial Compression and Moment
Ex. 2. Determine required plate thickness and anchor rod diameter.
Given: Pu = 376 kips Mu = 2500 in-kips
W12x96 A992
N = 19 in. B = 19 in. A2/A1 = 1 < 4 bf = 12.2 in. d = 12.7 in.
fc’ = 4.0 ksi Fy = 36 ksi
f = 8 in.
Solution Continued:
Trod = 80.4/2 = 40.2 kips per anchor rod
Try 1 -1/4 in. diameter
φTn = 0.75 (0.75Fu) Ab
= 0.75 (0.75x58)(π1.252/4)
= 40.0 kips ≈ 40.2 kips Say OK
Check Pullout:
From AISC Design Guide 1, Table 3.2, φTn = 50.2 kips OK
51
Shear Anchorage
of Base Plates

52
Shear Anchorage of Base Plates
Transferring Shear Forces (ACI 318-08 and ACI 349-06)
• Friction between base plate and grout or concrete surface.
φVn = φμPu < φ0.2fc’Ac or φ800Ac
where φ = 0.75
μ = coefficient of friction = 0.4
Pu = factored compressive axial force
Ac = plan area of base plate, BN
• Bearing of the column and base plate and/or shear lug against
concrete.

φPu,brg = 0.55fc’Abrg
where Abrg = vertical bearing area
53
Shear Anchorage of Base Plates
Transferring Shear Forces (ACI 318-08 and ACI 349-06)
• Shear strength of the anchor rods.
Not recommended because of oversize holes in base plate.
• Hairpins and Tie Rods

54
Column Erection
Procedures

55
Column Erection Procedures
Anchor rods are positioned and placed in the concrete before it
cures. Plastic caps are placed over the anchor bolts to protect
laborers.

56
Column Erection Procedures
Concrete block-outs may be made so that the base plate and
anchor bolts are recessed below floor level for safety and
aesthetics.

57
Column Erection Procedures
Slotted holes are allow for difference in standard field tolerances
between concrete and steel.

58
Column Erection Procedures
The column is leveled by adjusting the anchor bolt nuts below the
plate. Grout will be placed under and around the base plate to
transfer axial forces to the concrete below.

59
Column Erection Procedures
Grout will be placed under and around the base plate to transfer
axial forces to the concrete below. At least it should be.

60
61
Result of Poor
Anchor Rod Placement

The following slides are courtesy of Fisher &
Kloiber- AISC Field Fixes presentation.
62
Anchor Rod Placement
Anchor rods in the wrong location.

63
Anchor Rod Placement
Anchor rods in the wrong location.

64
Anchor Rod Placement
Anchor rods in the wrong location.

65
Anchor Rod Placement
Anchor rods too short.

66
Anchor Rod Placement
Anchor rods too long.

67
Anchor Rod Placement
Shop rework fo column and base plate.

68
Anchor Rod Placement
Anchor rods

69
Poor Anchor Rod Placement
Anchor bolts run over by a crane.

70
Poor Anchor Rod Placement
Anchor bolts run over by something.

71
Our next IMCA Manual, due to come out shortly, will state in the Code
of Standard Practice, that in addition to the requirement that the
contractor responsible for placing the anchors in site, present a drawing
showing the as-placed location of the anchors, that the supplier of the
structure provide the necessary templates for this purpose. They are to be
so designed as to insure the correct position, both vertically (including
the length of the anchor extending above the concrete surface) and
horizontally, show the location of the building axis relative to the anchor
group and leave permanent marks of the axis in the concrete surface. The
price of the templates is recommended to be the average price of the steel
structure. (We save so much on the cost of erection that we would be glad to
give the templates away free, but don't tell my clients.)
We have been using this method over the past 5 years in all
of our jobs. We are delighted in not having had a single problem in placing
the columns, the structures are all self-plumbing, the bolts all easily
inserted and the time for erection greatly shortened. On a job we are now
doing, from the date our bid was accepted, it took 7 weeks to design,
fabricate, erect the steel structure and install 20,000 sq. ft. of decking,
with shear anchors hand welded, for a three story school building, working
one 11 hr shift both at the shop and the site. A second similar 30,000
sq. ft. building will be finished this week, 8 weeks after the first one.

72
73
74
75
76
77
78
79
80
81
82
83

More Related Content

What's hot

Baseplate
BaseplateBaseplate
Baseplate
peerfn88
 
Design of steel beams
Design of steel beamsDesign of steel beams
Design of steel beams
Ir. David Puen
 
Wind_Load
Wind_LoadWind_Load
Wind_Load
Mithun Pal
 
Rcc structure design by etabs (acecoms)
Rcc structure design by etabs (acecoms)Rcc structure design by etabs (acecoms)
Rcc structure design by etabs (acecoms)
Md. Shahadat Hossain
 
Design notes for seismic design of building accordance to Eurocode 8
Design notes for seismic design of building accordance to Eurocode 8 Design notes for seismic design of building accordance to Eurocode 8
Design notes for seismic design of building accordance to Eurocode 8
Eur Ing Valentinos Neophytou BEng (Hons), MSc, CEng MICE
 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)
ahsanrabbani
 
Column design: as per bs code
Column design: as per bs codeColumn design: as per bs code
Column design: as per bs code
civilengineeringfreedownload
 
Detailed design of portal frames
Detailed design of portal framesDetailed design of portal frames
Detailed design of portal frames
karan prabhakar
 
Lecture 1 design loads
Lecture 1   design loadsLecture 1   design loads
Lecture 1 design loads
Morsaleen Chowdhury
 
CE72.52 - Lecture 3b - Section Behavior - Shear and Torsion
CE72.52 - Lecture 3b - Section Behavior - Shear and TorsionCE72.52 - Lecture 3b - Section Behavior - Shear and Torsion
CE72.52 - Lecture 3b - Section Behavior - Shear and Torsion
Fawad Najam
 
EC3 design
EC3 designEC3 design
EC3 design
Maria João Espada
 
Design of beams
Design of beamsDesign of beams
Design of beams
Sabna Thilakan
 
37467305 torsion-design-of-beam
37467305 torsion-design-of-beam37467305 torsion-design-of-beam
37467305 torsion-design-of-beam
Sopheak Thap
 
Etabs concrete-design
Etabs concrete-designEtabs concrete-design
Etabs concrete-design
mamilli
 
Rc corbel example
Rc corbel exampleRc corbel example
Rc corbel example
mamilli
 
Shear wall and its design guidelines
Shear wall and its design guidelinesShear wall and its design guidelines
Shear wall and its design guidelines
Muhammad Zain Ul abdin
 
Tower design using etabs- Nada Zarrak
Tower design using etabs- Nada Zarrak Tower design using etabs- Nada Zarrak
Tower design using etabs- Nada Zarrak
Nada Zarrak
 
Flexural design of Beam...PRC-I
Flexural design of Beam...PRC-IFlexural design of Beam...PRC-I
Flexural design of Beam...PRC-I
Irfan Malik
 
Design of floor slab
Design of floor slabDesign of floor slab
Design of floor slab
sathananthankartheep
 
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
Hossam Shafiq II
 

What's hot (20)

Baseplate
BaseplateBaseplate
Baseplate
 
Design of steel beams
Design of steel beamsDesign of steel beams
Design of steel beams
 
Wind_Load
Wind_LoadWind_Load
Wind_Load
 
Rcc structure design by etabs (acecoms)
Rcc structure design by etabs (acecoms)Rcc structure design by etabs (acecoms)
Rcc structure design by etabs (acecoms)
 
Design notes for seismic design of building accordance to Eurocode 8
Design notes for seismic design of building accordance to Eurocode 8 Design notes for seismic design of building accordance to Eurocode 8
Design notes for seismic design of building accordance to Eurocode 8
 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)
 
Column design: as per bs code
Column design: as per bs codeColumn design: as per bs code
Column design: as per bs code
 
Detailed design of portal frames
Detailed design of portal framesDetailed design of portal frames
Detailed design of portal frames
 
Lecture 1 design loads
Lecture 1   design loadsLecture 1   design loads
Lecture 1 design loads
 
CE72.52 - Lecture 3b - Section Behavior - Shear and Torsion
CE72.52 - Lecture 3b - Section Behavior - Shear and TorsionCE72.52 - Lecture 3b - Section Behavior - Shear and Torsion
CE72.52 - Lecture 3b - Section Behavior - Shear and Torsion
 
EC3 design
EC3 designEC3 design
EC3 design
 
Design of beams
Design of beamsDesign of beams
Design of beams
 
37467305 torsion-design-of-beam
37467305 torsion-design-of-beam37467305 torsion-design-of-beam
37467305 torsion-design-of-beam
 
Etabs concrete-design
Etabs concrete-designEtabs concrete-design
Etabs concrete-design
 
Rc corbel example
Rc corbel exampleRc corbel example
Rc corbel example
 
Shear wall and its design guidelines
Shear wall and its design guidelinesShear wall and its design guidelines
Shear wall and its design guidelines
 
Tower design using etabs- Nada Zarrak
Tower design using etabs- Nada Zarrak Tower design using etabs- Nada Zarrak
Tower design using etabs- Nada Zarrak
 
Flexural design of Beam...PRC-I
Flexural design of Beam...PRC-IFlexural design of Beam...PRC-I
Flexural design of Beam...PRC-I
 
Design of floor slab
Design of floor slabDesign of floor slab
Design of floor slab
 
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
 

Similar to Column base plates_prof_thomas_murray

chapter 4 flexural design of beam 2021.pdf
chapter 4 flexural design of beam 2021.pdfchapter 4 flexural design of beam 2021.pdf
chapter 4 flexural design of beam 2021.pdf
AshrafZaman33
 
Steel column base44
Steel column base44Steel column base44
Steel column base44
tapaswini Mohapatra Samant
 
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Hossam Shafiq II
 
Rcc member design steps
Rcc member design stepsRcc member design steps
Rcc member design steps
DYPCET
 
Design of short columns using helical reinforcement
Design of short columns using helical reinforcementDesign of short columns using helical reinforcement
Design of short columns using helical reinforcement
shivam gautam
 
Design of tension member.pptx
Design of tension member.pptxDesign of tension member.pptx
Design of tension member.pptx
mayur280524
 
Compression member
Compression memberCompression member
Compression member
Vikas Mehta
 
Shear lug verification example
Shear lug verification exampleShear lug verification example
Shear lug verification example
Joseph Marie TCHOUANI NANA
 
Weld_Portion.pdf
Weld_Portion.pdfWeld_Portion.pdf
Weld_Portion.pdf
Charbel44
 
Esd ppt 150180106093,111,160183106008 GECDAHOD
Esd ppt 150180106093,111,160183106008 GECDAHODEsd ppt 150180106093,111,160183106008 GECDAHOD
Esd ppt 150180106093,111,160183106008 GECDAHOD
yasir Khan
 
Design & Development of Rotating Work-piece Holding Mechanism for EDM Process
Design & Development of Rotating Work-piece Holding Mechanism for EDM ProcessDesign & Development of Rotating Work-piece Holding Mechanism for EDM Process
Design & Development of Rotating Work-piece Holding Mechanism for EDM Process
Sahil Dev
 
RCC column_Shortly Axially Loaded column.pptx
RCC column_Shortly Axially Loaded column.pptxRCC column_Shortly Axially Loaded column.pptx
RCC column_Shortly Axially Loaded column.pptx
HaswanthKollu
 
8 storyey presentation
8 storyey presentation8 storyey presentation
8 storyey presentation
Toe Myint Naing
 
Unit 3 Temporary and Permanent Joints.pptx
Unit 3 Temporary and Permanent Joints.pptxUnit 3 Temporary and Permanent Joints.pptx
Unit 3 Temporary and Permanent Joints.pptx
Charunnath S V
 
lacing and battening .pptx
lacing and battening .pptxlacing and battening .pptx
lacing and battening .pptx
mayur280524
 
Connections in steel structures
Connections in steel structuresConnections in steel structures
Connections in steel structures
anand bhatnagar
 
Lacing, battening
Lacing, battening Lacing, battening
Lacing, battening
Yash Patel
 
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdfDiv_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
LandelSmith1
 
Design of torsion reinforcement
 Design of torsion reinforcement Design of torsion reinforcement
Design of torsion reinforcement
MuskanDeura
 
Design of composite steel and concrete structures.pptx
Design of composite steel and concrete structures.pptxDesign of composite steel and concrete structures.pptx
Design of composite steel and concrete structures.pptx
SharpEyu
 

Similar to Column base plates_prof_thomas_murray (20)

chapter 4 flexural design of beam 2021.pdf
chapter 4 flexural design of beam 2021.pdfchapter 4 flexural design of beam 2021.pdf
chapter 4 flexural design of beam 2021.pdf
 
Steel column base44
Steel column base44Steel column base44
Steel column base44
 
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
 
Rcc member design steps
Rcc member design stepsRcc member design steps
Rcc member design steps
 
Design of short columns using helical reinforcement
Design of short columns using helical reinforcementDesign of short columns using helical reinforcement
Design of short columns using helical reinforcement
 
Design of tension member.pptx
Design of tension member.pptxDesign of tension member.pptx
Design of tension member.pptx
 
Compression member
Compression memberCompression member
Compression member
 
Shear lug verification example
Shear lug verification exampleShear lug verification example
Shear lug verification example
 
Weld_Portion.pdf
Weld_Portion.pdfWeld_Portion.pdf
Weld_Portion.pdf
 
Esd ppt 150180106093,111,160183106008 GECDAHOD
Esd ppt 150180106093,111,160183106008 GECDAHODEsd ppt 150180106093,111,160183106008 GECDAHOD
Esd ppt 150180106093,111,160183106008 GECDAHOD
 
Design & Development of Rotating Work-piece Holding Mechanism for EDM Process
Design & Development of Rotating Work-piece Holding Mechanism for EDM ProcessDesign & Development of Rotating Work-piece Holding Mechanism for EDM Process
Design & Development of Rotating Work-piece Holding Mechanism for EDM Process
 
RCC column_Shortly Axially Loaded column.pptx
RCC column_Shortly Axially Loaded column.pptxRCC column_Shortly Axially Loaded column.pptx
RCC column_Shortly Axially Loaded column.pptx
 
8 storyey presentation
8 storyey presentation8 storyey presentation
8 storyey presentation
 
Unit 3 Temporary and Permanent Joints.pptx
Unit 3 Temporary and Permanent Joints.pptxUnit 3 Temporary and Permanent Joints.pptx
Unit 3 Temporary and Permanent Joints.pptx
 
lacing and battening .pptx
lacing and battening .pptxlacing and battening .pptx
lacing and battening .pptx
 
Connections in steel structures
Connections in steel structuresConnections in steel structures
Connections in steel structures
 
Lacing, battening
Lacing, battening Lacing, battening
Lacing, battening
 
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdfDiv_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
 
Design of torsion reinforcement
 Design of torsion reinforcement Design of torsion reinforcement
Design of torsion reinforcement
 
Design of composite steel and concrete structures.pptx
Design of composite steel and concrete structures.pptxDesign of composite steel and concrete structures.pptx
Design of composite steel and concrete structures.pptx
 

Recently uploaded

一比一原版加拿大瑞尔森大学毕业证如何办理
一比一原版加拿大瑞尔森大学毕业证如何办理一比一原版加拿大瑞尔森大学毕业证如何办理
一比一原版加拿大瑞尔森大学毕业证如何办理
oydykuz
 
The Power to Battle! Slideshow by: Kal-el
The Power to Battle! Slideshow by: Kal-elThe Power to Battle! Slideshow by: Kal-el
The Power to Battle! Slideshow by: Kal-el
Kal-el Shows
 
一比一原版(falmouth毕业证书)法尔茅斯大学毕业证如何办理
一比一原版(falmouth毕业证书)法尔茅斯大学毕业证如何办理一比一原版(falmouth毕业证书)法尔茅斯大学毕业证如何办理
一比一原版(falmouth毕业证书)法尔茅斯大学毕业证如何办理
xnhwr8v
 
AI Explanations as Two-Way Experiences, Led by Users
AI Explanations as Two-Way Experiences, Led by UsersAI Explanations as Two-Way Experiences, Led by Users
AI Explanations as Two-Way Experiences, Led by Users
Design for Context
 
Value based approach to heritae conservation -.docx
Value based approach to heritae conservation -.docxValue based approach to heritae conservation -.docx
Value based approach to heritae conservation -.docx
JIT KUMAR GUPTA
 
Call Girls Jaipur 📞 8445551418 🌟Door Step Delivery We Offering You 100% Genuine
Call Girls Jaipur 📞 8445551418 🌟Door Step Delivery We Offering You 100% GenuineCall Girls Jaipur 📞 8445551418 🌟Door Step Delivery We Offering You 100% Genuine
Call Girls Jaipur 📞 8445551418 🌟Door Step Delivery We Offering You 100% Genuine
parulsinha
 
一比一原版美国加州大学戴维斯分校毕业证(ucdavis学位证)如何办理
一比一原版美国加州大学戴维斯分校毕业证(ucdavis学位证)如何办理一比一原版美国加州大学戴维斯分校毕业证(ucdavis学位证)如何办理
一比一原版美国加州大学戴维斯分校毕业证(ucdavis学位证)如何办理
twqryq79
 
SPICE PARK JUN2024 ( 6,826 SPICE Models )
SPICE PARK JUN2024 ( 6,826 SPICE Models )SPICE PARK JUN2024 ( 6,826 SPICE Models )
SPICE PARK JUN2024 ( 6,826 SPICE Models )
Tsuyoshi Horigome
 
The Color of Life Slideshow by: Kal-el Go
The Color of Life Slideshow by: Kal-el GoThe Color of Life Slideshow by: Kal-el Go
The Color of Life Slideshow by: Kal-el Go
Kal-el Shows
 
Delhi Call Girls 📞 9873940964 ❤️ Full enjoy at your Door Step Available 24x7
Delhi Call Girls 📞 9873940964 ❤️ Full enjoy at your Door Step Available 24x7Delhi Call Girls 📞 9873940964 ❤️ Full enjoy at your Door Step Available 24x7
Delhi Call Girls 📞 9873940964 ❤️ Full enjoy at your Door Step Available 24x7
yesp58846
 
一比一原版(brunel毕业证书)布鲁内尔大学毕业证如何办理
一比一原版(brunel毕业证书)布鲁内尔大学毕业证如何办理一比一原版(brunel毕业证书)布鲁内尔大学毕业证如何办理
一比一原版(brunel毕业证书)布鲁内尔大学毕业证如何办理
aprhf21y
 
💕SIMRAN VARMA💕Book Call Girls Jaipur ↘️8445551418↙️One Night Stand With Lonel...
💕SIMRAN VARMA💕Book Call Girls Jaipur ↘️8445551418↙️One Night Stand With Lonel...💕SIMRAN VARMA💕Book Call Girls Jaipur ↘️8445551418↙️One Night Stand With Lonel...
💕SIMRAN VARMA💕Book Call Girls Jaipur ↘️8445551418↙️One Night Stand With Lonel...
radika pandey
 
Call Girls Mumbai👉9910780858👉Premium Escorts in Mumbai 💃Available 24/7
Call Girls Mumbai👉9910780858👉Premium Escorts in Mumbai 💃Available 24/7Call Girls Mumbai👉9910780858👉Premium Escorts in Mumbai 💃Available 24/7
Call Girls Mumbai👉9910780858👉Premium Escorts in Mumbai 💃Available 24/7
nitachopra
 
美洲杯买球-美洲杯买球买球正规平台-买美洲杯买球的正规app|【​网址​🎉ac10.net🎉​】
美洲杯买球-美洲杯买球买球正规平台-买美洲杯买球的正规app|【​网址​🎉ac10.net🎉​】美洲杯买球-美洲杯买球买球正规平台-买美洲杯买球的正规app|【​网址​🎉ac10.net🎉​】
美洲杯买球-美洲杯买球买球正规平台-买美洲杯买球的正规app|【​网址​🎉ac10.net🎉​】
callottermanha18096
 
Independent Call Girls In Churchgate ( Mumbai ) 💯Call Us 🔝 9910780858 🔝💃Top C...
Independent Call Girls In Churchgate ( Mumbai ) 💯Call Us 🔝 9910780858 🔝💃Top C...Independent Call Girls In Churchgate ( Mumbai ) 💯Call Us 🔝 9910780858 🔝💃Top C...
Independent Call Girls In Churchgate ( Mumbai ) 💯Call Us 🔝 9910780858 🔝💃Top C...
pr971917
 
🔥VIP Call Girls Mumbai 🔝👉 9833363713 👈🔝High Calass Call Girl Mumbai
🔥VIP Call Girls Mumbai 🔝👉 9833363713 👈🔝High Calass Call Girl Mumbai🔥VIP Call Girls Mumbai 🔝👉 9833363713 👈🔝High Calass Call Girl Mumbai
🔥VIP Call Girls Mumbai 🔝👉 9833363713 👈🔝High Calass Call Girl Mumbai
Sifa Khan#i11
 
Call girl in 😱 jaipur !High Profile 💚 👉 8445551418 ☎️ Girls For Sex😱
Call girl in 😱 jaipur !High Profile 💚 👉 8445551418 ☎️ Girls For Sex😱 Call girl in 😱 jaipur !High Profile 💚 👉 8445551418 ☎️ Girls For Sex😱
Call girl in 😱 jaipur !High Profile 💚 👉 8445551418 ☎️ Girls For Sex😱
shardda patel
 
一比一原版(ucb毕业证书)英国伯明翰大学学院毕业证如何办理
一比一原版(ucb毕业证书)英国伯明翰大学学院毕业证如何办理一比一原版(ucb毕业证书)英国伯明翰大学学院毕业证如何办理
一比一原版(ucb毕业证书)英国伯明翰大学学院毕业证如何办理
qbydc
 
Call Girls In Thane ( Mumbai ) 💯Call Us 🔝 9967584737 🔝💃Top Class Call Girl Se...
Call Girls In Thane ( Mumbai ) 💯Call Us 🔝 9967584737 🔝💃Top Class Call Girl Se...Call Girls In Thane ( Mumbai ) 💯Call Us 🔝 9967584737 🔝💃Top Class Call Girl Se...
Call Girls In Thane ( Mumbai ) 💯Call Us 🔝 9967584737 🔝💃Top Class Call Girl Se...
pr971917
 
Connaught Place Call Girls 📞 9711199171 ❤️ Full enjoy at your Door Step Avail...
Connaught Place Call Girls 📞 9711199171 ❤️ Full enjoy at your Door Step Avail...Connaught Place Call Girls 📞 9711199171 ❤️ Full enjoy at your Door Step Avail...
Connaught Place Call Girls 📞 9711199171 ❤️ Full enjoy at your Door Step Avail...
yesp58846
 

Recently uploaded (20)

一比一原版加拿大瑞尔森大学毕业证如何办理
一比一原版加拿大瑞尔森大学毕业证如何办理一比一原版加拿大瑞尔森大学毕业证如何办理
一比一原版加拿大瑞尔森大学毕业证如何办理
 
The Power to Battle! Slideshow by: Kal-el
The Power to Battle! Slideshow by: Kal-elThe Power to Battle! Slideshow by: Kal-el
The Power to Battle! Slideshow by: Kal-el
 
一比一原版(falmouth毕业证书)法尔茅斯大学毕业证如何办理
一比一原版(falmouth毕业证书)法尔茅斯大学毕业证如何办理一比一原版(falmouth毕业证书)法尔茅斯大学毕业证如何办理
一比一原版(falmouth毕业证书)法尔茅斯大学毕业证如何办理
 
AI Explanations as Two-Way Experiences, Led by Users
AI Explanations as Two-Way Experiences, Led by UsersAI Explanations as Two-Way Experiences, Led by Users
AI Explanations as Two-Way Experiences, Led by Users
 
Value based approach to heritae conservation -.docx
Value based approach to heritae conservation -.docxValue based approach to heritae conservation -.docx
Value based approach to heritae conservation -.docx
 
Call Girls Jaipur 📞 8445551418 🌟Door Step Delivery We Offering You 100% Genuine
Call Girls Jaipur 📞 8445551418 🌟Door Step Delivery We Offering You 100% GenuineCall Girls Jaipur 📞 8445551418 🌟Door Step Delivery We Offering You 100% Genuine
Call Girls Jaipur 📞 8445551418 🌟Door Step Delivery We Offering You 100% Genuine
 
一比一原版美国加州大学戴维斯分校毕业证(ucdavis学位证)如何办理
一比一原版美国加州大学戴维斯分校毕业证(ucdavis学位证)如何办理一比一原版美国加州大学戴维斯分校毕业证(ucdavis学位证)如何办理
一比一原版美国加州大学戴维斯分校毕业证(ucdavis学位证)如何办理
 
SPICE PARK JUN2024 ( 6,826 SPICE Models )
SPICE PARK JUN2024 ( 6,826 SPICE Models )SPICE PARK JUN2024 ( 6,826 SPICE Models )
SPICE PARK JUN2024 ( 6,826 SPICE Models )
 
The Color of Life Slideshow by: Kal-el Go
The Color of Life Slideshow by: Kal-el GoThe Color of Life Slideshow by: Kal-el Go
The Color of Life Slideshow by: Kal-el Go
 
Delhi Call Girls 📞 9873940964 ❤️ Full enjoy at your Door Step Available 24x7
Delhi Call Girls 📞 9873940964 ❤️ Full enjoy at your Door Step Available 24x7Delhi Call Girls 📞 9873940964 ❤️ Full enjoy at your Door Step Available 24x7
Delhi Call Girls 📞 9873940964 ❤️ Full enjoy at your Door Step Available 24x7
 
一比一原版(brunel毕业证书)布鲁内尔大学毕业证如何办理
一比一原版(brunel毕业证书)布鲁内尔大学毕业证如何办理一比一原版(brunel毕业证书)布鲁内尔大学毕业证如何办理
一比一原版(brunel毕业证书)布鲁内尔大学毕业证如何办理
 
💕SIMRAN VARMA💕Book Call Girls Jaipur ↘️8445551418↙️One Night Stand With Lonel...
💕SIMRAN VARMA💕Book Call Girls Jaipur ↘️8445551418↙️One Night Stand With Lonel...💕SIMRAN VARMA💕Book Call Girls Jaipur ↘️8445551418↙️One Night Stand With Lonel...
💕SIMRAN VARMA💕Book Call Girls Jaipur ↘️8445551418↙️One Night Stand With Lonel...
 
Call Girls Mumbai👉9910780858👉Premium Escorts in Mumbai 💃Available 24/7
Call Girls Mumbai👉9910780858👉Premium Escorts in Mumbai 💃Available 24/7Call Girls Mumbai👉9910780858👉Premium Escorts in Mumbai 💃Available 24/7
Call Girls Mumbai👉9910780858👉Premium Escorts in Mumbai 💃Available 24/7
 
美洲杯买球-美洲杯买球买球正规平台-买美洲杯买球的正规app|【​网址​🎉ac10.net🎉​】
美洲杯买球-美洲杯买球买球正规平台-买美洲杯买球的正规app|【​网址​🎉ac10.net🎉​】美洲杯买球-美洲杯买球买球正规平台-买美洲杯买球的正规app|【​网址​🎉ac10.net🎉​】
美洲杯买球-美洲杯买球买球正规平台-买美洲杯买球的正规app|【​网址​🎉ac10.net🎉​】
 
Independent Call Girls In Churchgate ( Mumbai ) 💯Call Us 🔝 9910780858 🔝💃Top C...
Independent Call Girls In Churchgate ( Mumbai ) 💯Call Us 🔝 9910780858 🔝💃Top C...Independent Call Girls In Churchgate ( Mumbai ) 💯Call Us 🔝 9910780858 🔝💃Top C...
Independent Call Girls In Churchgate ( Mumbai ) 💯Call Us 🔝 9910780858 🔝💃Top C...
 
🔥VIP Call Girls Mumbai 🔝👉 9833363713 👈🔝High Calass Call Girl Mumbai
🔥VIP Call Girls Mumbai 🔝👉 9833363713 👈🔝High Calass Call Girl Mumbai🔥VIP Call Girls Mumbai 🔝👉 9833363713 👈🔝High Calass Call Girl Mumbai
🔥VIP Call Girls Mumbai 🔝👉 9833363713 👈🔝High Calass Call Girl Mumbai
 
Call girl in 😱 jaipur !High Profile 💚 👉 8445551418 ☎️ Girls For Sex😱
Call girl in 😱 jaipur !High Profile 💚 👉 8445551418 ☎️ Girls For Sex😱 Call girl in 😱 jaipur !High Profile 💚 👉 8445551418 ☎️ Girls For Sex😱
Call girl in 😱 jaipur !High Profile 💚 👉 8445551418 ☎️ Girls For Sex😱
 
一比一原版(ucb毕业证书)英国伯明翰大学学院毕业证如何办理
一比一原版(ucb毕业证书)英国伯明翰大学学院毕业证如何办理一比一原版(ucb毕业证书)英国伯明翰大学学院毕业证如何办理
一比一原版(ucb毕业证书)英国伯明翰大学学院毕业证如何办理
 
Call Girls In Thane ( Mumbai ) 💯Call Us 🔝 9967584737 🔝💃Top Class Call Girl Se...
Call Girls In Thane ( Mumbai ) 💯Call Us 🔝 9967584737 🔝💃Top Class Call Girl Se...Call Girls In Thane ( Mumbai ) 💯Call Us 🔝 9967584737 🔝💃Top Class Call Girl Se...
Call Girls In Thane ( Mumbai ) 💯Call Us 🔝 9967584737 🔝💃Top Class Call Girl Se...
 
Connaught Place Call Girls 📞 9711199171 ❤️ Full enjoy at your Door Step Avail...
Connaught Place Call Girls 📞 9711199171 ❤️ Full enjoy at your Door Step Avail...Connaught Place Call Girls 📞 9711199171 ❤️ Full enjoy at your Door Step Avail...
Connaught Place Call Girls 📞 9711199171 ❤️ Full enjoy at your Door Step Avail...
 

Column base plates_prof_thomas_murray

  • 1. COLUMN BASE PLATES - DESIGN TO ERECTION – Tom Murray Emeritus Professor Virginia Tech Blacksburg, VA 1
  • 3. Types of Column Base Plates Compressive Axial Loads Base Plates with Small Moments Tensile Axial Loads Base Plates with Large Moments 3
  • 5. AISC Specification PERTINENT SECTIONS AND TABLES Chapter J Design of Connections Table J3.2 Nominal Strength of Fasteners and Threaded Parts J8. Column Basses and Bearing on Concrete Chapter M Fabrication and Erection M2.2 Thermal Cutting M2.8 Finish of Column Bases M4.4 Fit of Column Compression Joints and Base Plates 5
  • 6. Types of Column Base Plates TOPICS • Base Plate and Anchor Rod Material and Details • Base Plates for Axial Compression • Base Plates for Tension • Base Plates for Axial Compression and Moment • Shear Anchorage • Column Erection Procedures • Result of Poor Anchor Rod Placement 6
  • 7. Base Plate and Anchor Rod Materials and Details 7
  • 8. Base Plate Material, Fabrication and Finishing Base Plate Material • Typical A36 • 1/8” (3mm) increments to 1-1/4 in (32 mm) then ½ in. (6 mm) • Minimum thickness ½ in. (13 mm), typical ¾ in. (20 mm) Fabrication and Finishing • Plate is thermally cut • Holes drilled or thermally cut • Specification Section M2.2 has requirements for thermal cutting • Finishing: Specification Section M2.8 < 2 in. (50 mm) milling not generally required 2 – 4 in.(50 – 100 mm) straightened by pressing or milling > 4 in. (100 mm) milling required Only mill where column bears • Bottom surface with grout need not be milled • Top surface not milled if complete-joint-penetration (CJP) welds 8
  • 9. Base Plate Material, Fabrication and Finishing Base Plate Welding • Fillet welds preferred up to ¾ in. (20 mm) then groove welds • Avoid all around symbol • Weld for wide-flange columns subject to axial compression Weld on one side of column flanges to avoid rotating the section: • HSS subject to axial compression: Weld flats only • Shear, Tension, Moment, and Combinations Size weld for forces not all around No weld at fillets of wide-flange columns Must weld at corners of HSS if tension or moment • Shop welded preferred • Very heavy base plates may be field welded after grouting 9
  • 10. Anchor Rod Materials and Details Anchor Rod Material • Preferred ASTM F1554 Gr 36 except when high tension and or moment. 10
  • 11. Anchor Rod Materials and Details Anchor Rod Material • Unified Course (UNC) threads • Standard Hex Nuts permitted but Heavy Hex nuts required for oversize holes and with high strength anchor rods. • Hooked anchor rods have very low pull-out strength but OK for axial compression only. • Headed rods or rods with nuts are preferred. Headed Rods Rods with Nuts 11
  • 12. Anchor Rod Materials and Details Anchor Rod Material • Use of plate washers at bottom of rods can cause erection problems and should be avoided. • Drilled-in epoxy anchor rods may be used for light loads • Wedge-type anchors should not be used because of potential loosing during erection. 12
  • 13. Anchor Rod Materials and Details Anchor Rod Holes and Washers • Oversize holes required because of placement tolerances. • Recommended hole and washer sizes are in Design Guide 1 (Table 2-3) and AISC 14th Ed. Manual (Table 14-2). • Smaller holes may be used when axial compression only. • Plate washers required when tension and/or moment. 13
  • 14. Anchor Rods Material and Details Anchor Rod Sizing and Layout • Recommendations Use ¾ in. (22 mm) minimum diameter. Use Grade 36 rod up to about 2 in. (50 mm) diameter. Thread at least 3 in. (75 mm) beyond what is needed. Minimum ½ in. (12 mm) distance between edge of hole and edge of plate. Use symmetrical pattern whenever possible. • Provide ample clearance for nut tightening. • Coordinate anchor bolt placement with reinforcement location. 14
  • 15. Occupational Safety and Health Administration (OSEA) OSEA Safety Standards for Steel Erection (2008) • Minimum of four anchor rods. • Base plate to resist eccentric gravity load of 300 lb (1,300 N) 18 in. (450 mm) from extrem outer face of column in each direction. • 300 lb (1,300) represents weight of iron worker with tools. • Exception: Post-type columns weighing less than 300 lb. 18 in. Note: Smallest of anchor rods on a 4 in. by 4 in. (100 mm by 100 mm) pattern is generally sufficient. 300 lb 15
  • 16. Column Base Plates DESIGN CONSIDERATIONS • Base Plate Bending Strength • Concrete Crushing • Concrete Anchorage for Tension Forces • Shear Resistance • Anchor Rod Tension Design • Anchor Rod Shear Design • Anchor Rod Embedment • Constructability 16
  • 17. Base Plates for Axial Compression 17
  • 18. Design for Axial Compression Column Base Plate Design Limit States • Base Plate Bending • Concrete Crushing 18
  • 19. Design for Axial Compression Column Base Plate Bending fpu = Ru /(BxN) = pressure due to reaction Let m’ = max(n and m) Mu= fpu (1) (m’2/2 < φMp φMp = 0.9 Fy Zx = 0.9x 1 x tp2/4) Fy Substituting: t p , min = 2 f pu ( m ' 2 ) 0 .9 F y 19
  • 20. Design for Axial Compression Column Base Plate Bending • Lightly Loaded Base Plate • Required concrete bearing area is less than bfdc. d bf Bearing Area 20
  • 21. Design for Axial Compression Column Base Plate Bending • Lightly Loaded Base Plate Replace m′ with l = max {m, n, λn′}, where ′ ′ 2 X λ = ≤ 1 .0 1+ 1-X 1 n′ = 4 db f 2f pu l 2 t p ,min =  4db f  Pu 0.9Fy  X=  (d + b )2  φPp f   Reference: Thornton, W.A., Design of Base Plates for Wide Flange Columns – A Concatenation of Methods, AISC Engineering Journal, 21 Fourth Quarter, 1990.
  • 22. Design for Axial Compression HSS Sections • Bend lines. 0.95h 0.95d 0.80d 22
  • 23. Design for Axial Compression Concrete Crushing Specification Section J8. Column Bases and Bearing on Concrete φc = 0.65 (a) On the full area of a concrete support Pp = 0.85fc′A1 (J8-1) (b) On less than the full area of a concrete support (J8-2) where Pp = 0.85fc A1 A 2 / A1 ≤ 1.7fc A1 ′ ′ fc’ = specified compressive strength of concrete, ksi (Mpa) A1 = area of steel bearing on concrete, in.2 A2 = area of the portion of the supporting surface that is geometrically similar to and concentric with the loaded area, in.2 Note: The limit < 1.7f’c is equivalent to A2/A1 < 4 23
  • 24. Design for Axial Compression -- Example o 24” 18” Ex.: Determine if the base plate shown is adequate. Column: W10x33 d = 9.73 in. bf = 7.96 in. PL 1-½ x 18 x 1’-6” A36 Concrete Pedestal: 24 in. by 24 in. (assume square) fc′′=3.0 ksi Pu = 250 kips o o o 18” 24” 24
  • 25. Design for Axial Compression -- Example Concrete Crushing A1 = 18 x 18 = 324 in2 (Plan area of base plate) A2 = (24)(24) = 576 in2 (Plan area of concrete pedestal) A2/A1 = 576/324 = 1.78 < 4 o o o 24” = 0.65 (0.85 × 3.0 ) (324 ) 1.78 = 716 k > 250 k OK o 18” ′ φPp = φ 0.85 f c A 1 A2 A1 18” 24” 25
  • 26. Design for Axial Compression -- Example Plate Bending n = 5.82 in. m = 4.38 in. 7.96” n ′ = (1 / 4 ) db f = (1 / 4 ) 9 .73 x 7 .96 = 2 .20 in .  4db f  Pu  X= 2  φP  (d + b ) f   p  4x9.73x7.96  250  =  (9.73 + 7.96 )2  716 = 0.333   4.38” 9.24” 9.73” 18” 4.38” 5.82 6.37 5.82 18” 26
  • 27. Design for Axial Compression -- Example Plate Bending n = 5.82 in. m = 4.38 in. 7.96” n ′ = (1 / 4 ) db f = (1 / 4 ) 9 .73 x 7 .96 = 2 .20 in .  4db f  Pu  X= 2  φP  (d + b ) f   p  4x9.73x7.96  250  =  (9.73 + 7.96 )2  716 = 0.333   4.38” 9.24” 9.73” 18” 4.38” 5.82 6.37 5.82 18” 27
  • 28. Design for Axial Compression -- Example Plate Bending 2 X 2 0 . 333 λ = = 1+ 1-X 1 + 1 - 0 . 333 = 0 . 635 ≤ 1 . 0 λ n ' = 0 . 635 x 2 . 20 = 1 . 40 in . 7.96” 4.38” 9.73” 9.24” l = max {m, n, λn′} ′ = max {4.38,5.82,1.40} = 5.82 in. 4.38” fpu = Ru /BN = 250/(18x18) = 0.772 ksi 18” 5.82 6.37 5.82 18” 28
  • 29. Design for Axial Compression -- Example Plate Bending tp = 2f pu l 2 0.9Fy = 2 x 0.772 x 5.82 2 0.9 x 36 7.96” 4.38” = 1.27 in . ≤ 1.5in . OK 9.24” 9.73” 18” 4.38” PL 1-½ x 18 x 1’-6” A36 is Adequate. 5.82 6.37 5.82 18” 29
  • 30. Design for Axial Compression Variation of φPn with Base Plate Thickness with Increasing Axial Force φPn m or n c c c BN = bfd Required tp 30
  • 31. Design for Axial Compression Was the base plate too strong? 31
  • 32. Base Plates for Axial Tension 32
  • 33. Design for Tensile (Uplift) Forces Connection Limit States • Anchor Rod Tensile Strength • Concrete Pull-out Strength • Concrete Anchorage Tensile Strength • Base Plate Bending Strength 33
  • 34. Design for Tensile (Uplift) Forces Anchor Rod Tensile Strength • Tensile Strength φTn = φ FntAb where φ = 0.75 Fnt = 0.75Fu Fu = specified minimum tensile strength of anchor rod = 58 ksi (300 MPa) for Gr 36 = 75 ksi (400 MPa) for Gr 55 = 125 ksi (650 MPa) for Gr 125 Notes: Ab is the nominal area of the anchor rod = πd2/4. 0.75 in 0.75Fu account for rupture (tensile) area. See AISC 14th Ed. Manual Table 7-17 for actual areas. 34
  • 35. Design for Tensile (Uplift) Forces Ex. Determine the design strength,φTn, for the limit state of anchor rod tension rupture. 4 - ¾ in. (20 mm) diameter, Grade 36 anchor rods φTn = 4 x 0.75 (0.75Fu) Ab = 4 x 0.75 (0.75x58)(π0.752/4) = 4 x 14.4 kips (4 x 53 kN) = 57.6 kips (212 kN) 35
  • 36. Design for Tensile (Uplift) Forces Concrete Pullout Strength • Provisions in ACI 318-08, Section D5.3 • Design pullout strength of headed anchor rod or anchor rod with nut: φNp = φ ψ4Abrg8f’c where φ = 0.70 ψ4 = 1.4 for no cracking, 1.0 if cracking exists Abrg = net bearing area of the anchor rod head or nut, in2 f’c = specified compression strength of concrete, psi Notes: Hooked anchor rods are not recommended with tensile loadings. 36
  • 37. Design for Tensile (Uplift) Forces Concrete Pullout Strength • AISC Design Guide 1 Table for Strengths with Heavy Hex Nuts Note: kN = 4.448 x kips N/mm2 = 6.895x10-3 x psi 37
  • 38. Design for Tensile (Uplift) Forces Concrete Breakout Strength • Provisions in ACI 318-08, Section D4.2.2 Full breakout cone Breakout cone for group anchors Breakout cone near edge 38
  • 39. Design for Tensile (Uplift) Forces Base Plate Bending Strength • AISC Design Guide 1 recommended bend lines. g2 g1 Alternate Critical Section is the full width of the base plate. 39
  • 40. Design for Tensile (Uplift) Forces Base Plate Bending Strength • Other possible bend lines. Critical Section Critical Section bf + 1 in. Similar to Extended End-Plates For all cases: Define: x = distance from center of anchor bolt to critical section w = width of critical section Tu = force in anchor bolt 4Tu x t p ,min = φMn = 0.9Fywtp2/4 = Mu = Tux 0.9Fy w 40
  • 41. Base Plates for Axial Compression and Moment 41
  • 42. Design for Axial Compression and Moment Connection Limit States • Concrete Crushing • Anchor Rod Tensile Strength • Concrete Pull-out Strength O • Concrete Anchorage Tensile Strength • Base Plate Bending Strength Cases • T = 0 (Relatively small moment) • T > 0 (Relatively large moment) 42
  • 43. Design for Axial Compression and Moment Limit for T = 0 ∑Fy = 0 with T=0 Base Plate is B by N in plan. Pr = qY = fpBY ∑Mo = 0 Pre = qY2/2 – PrN/2 Then e = N/2 – Y/2 of if fp < fp,max with ′ ′ fp ,max = 0.65x0.85fc A 2 / A1 ≤ 0.65x 1.7fc then ecrit = N/2 –Pr/(2Bfp,max) Therefore If e < ecrit, T =0 and Y = N-2e ecrit = N/2 –Pr/(2Bfp,max) 43
  • 44. Design for Axial Compression and Moment For T > 0 e > ecrit and fp = fp,max ∑Fy = 0 Pr – T – fp,maxBY =0 ∑Mo = 0 T(N/2+f) + Pr(N/2) – Pre – fp,maxBY2/2 = 0 Solving the resulting quadratic equation Note: If the quantity in the radical is less than zero, a larger base plate is required. Y =(f + N / 2) − (f + N 2 2Pr (e + f ) ) − 2 fp ,max B T = fp ,max BY − T 44
  • 45. Design for Axial Compression and Moment Ex. 1. Determine required plate thickness and anchor rod diameter. Given: Pu = 376 kips Mu = 940 in-kips W12x96 A992 N = 19 in. B = 19 in. A2/A1 = 1 < 4 bf = 12.2 in. d = 12.7 in. fc’ = 4.0 ksi Fy = 36 ksi f = 8 in. Solution: ′ fp ,max = 0.65x0.85fc A 2 / A1 = 0.65x0.85x4.0 1.0 = 2.21 ksi e = Mu/Pu = 970/376 = 2.50 ecrit = N/2 –Pr/(2Bfp,max) = 19.0/2 – 376/(2x19.0x2.21) = 5.02 in. e < ecrit → T = 0 and Y = N-2e = 19.0 – 2x 2.50 = 14.0 in. 45
  • 46. Design for Axial Compression and Moment Ex. 1. Determine required plate thickness and anchor rod diameter. Given: Pu = 376 kips Mu = 940 in-kips W12x96 A992 N = 19 in. B = 19 in. A2/A1 = 1 < 4 bf = 12.2 in. d = 12.7 in. fc’ = 4.0 ksi Fy = 36 ksi f = 8 in. Solution Continued: fp = Pu/(NY) = 376/(19.0x14.0) = 1.41 ksi m = (N-0.95d)/2 = (19.0-0.95x12.7)/2 = 3.47 in. m = (B-0.80bf)/2 = (19.0-0.80x12.2)/2 = 4.62 in. tp = 2f pu n 2 0.9Fy = 2 x1.41x 4.62 2 = 1.36 in . 0.9 x 36 Use PL 1½ x 19 x 1ft 7 in. A36 4 – ¾ in. Anchor Rods x 12 in. F1554 Gr 36 w/ heavy hex nuts at bottom. 46
  • 47. Design for Axial Compression and Moment Ex. 2. Determine required plate thickness and anchor rod diameter. Given: Pu = 376 kips Mu = 2500 in-kips W12x96 A992 N = 19 in. B = 19 in. A2/A1 = 1 < 4 bf = 12.2 in. d = 12.7 in. fc’ = 4.0 ksi Fy = 36 ksi f = 8 in. Solution: ′ fp ,max = 0.65x0.85fc A 2 / A1 = 0.65x0.85x4.0 1.0 = 2.21 ksi e = Mu/Pu = 2500/376 = 6.65 ecrit = N/2 –Pr/(2Bfp,max) = 19.0/2 – 376/(2x19.0x2.21) = 5.02 in. N 2 P (e + f ) e > ecrit → T > 0 and Y =(f + N / 2) − (f + )2 − r 2 fp ,max B 47
  • 48. Design for Axial Compression and Moment Ex. 2. Determine required plate thickness and anchor rod diameter. Given: Pu = 376 kips Mu = 2500 in-kips W12x96 A992 N = 19 in. B = 19 in. A2/A1 = 1 < 4 bf = 12.2 in. d = 12.7 in. fc’ = 4.0 ksi Fy = 36 ksi f = 8 in. Solution Continued: N 2 2Pr (e + f ) Y = (f + N / 2 ) − (f + ) − 2 fp ,max B 19.0 2 2x 376(6.65 + 8.0) ) − = (8.0 + 19.0 / 2) − (8.0 + 2 2.21x19.0 = 10.9 in. fp = Pu/(NY) = 376/(19.0x10.9) = 1.82 ksi 48
  • 49. Design for Axial Compression and Moment Ex. 2. Determine required plate thickness and anchor rod diameter. Given: Pu = 376 kips Mu = 2500 in-kips W12x96 A992 N = 19 in. B = 19 in. A2/A1 = 1 < 4 bf = 12.2 in. d = 12.7 in. fc’ = 4.0 ksi Fy = 36 ksi f = 8 in. Solution Continued: m = (N - 0.95d)/2 = (19.0-0.95x12.7)/2 = 3.47 in. n = (B - 0.80bf)/2 =(19.0-0.80x12.2)/2 = 4.62 in. tp = 2f pu m 2 0.9Fy = 2 x1.82 x 4.62 2 = 1.54 in . 0.9 x 36 Need to check tensions side. 49
  • 50. Design for Axial Compression and Moment Ex. 2. Determine required plate thickness and anchor rod diameter. Given: Pu = 376 kips Mu = 2500 in-kips W12x96 A992 N = 19 in. B = 19 in. A2/A1 = 1 < 4 bf = 12.2 in. d = 12.7 in. fc’ = 4.0 ksi Fy = 36 ksi f = 8 in. Solution Continued: T = fp,max BY – Pu = 2.21x19.0x10.9 – 376 = 80.4 kips Try 2 – Anchor Rods each Side Required plate thickness: X = f – 0.95d/2 = 8.0 -0.95x12.7/2 = 1.96 in. x w = bf + 1.0 = 12.2 + 1.0 = 13.0 in. f 4T x 4 x 80 .4 x1.96 t p ,min = = = 1.22 in . 0.9Fy w 0.9 x 36 x13 .0 Use PL 1½ x 19 x 1ft 7 in. A36 50
  • 51. Design for Axial Compression and Moment Ex. 2. Determine required plate thickness and anchor rod diameter. Given: Pu = 376 kips Mu = 2500 in-kips W12x96 A992 N = 19 in. B = 19 in. A2/A1 = 1 < 4 bf = 12.2 in. d = 12.7 in. fc’ = 4.0 ksi Fy = 36 ksi f = 8 in. Solution Continued: Trod = 80.4/2 = 40.2 kips per anchor rod Try 1 -1/4 in. diameter φTn = 0.75 (0.75Fu) Ab = 0.75 (0.75x58)(π1.252/4) = 40.0 kips ≈ 40.2 kips Say OK Check Pullout: From AISC Design Guide 1, Table 3.2, φTn = 50.2 kips OK 51
  • 53. Shear Anchorage of Base Plates Transferring Shear Forces (ACI 318-08 and ACI 349-06) • Friction between base plate and grout or concrete surface. φVn = φμPu < φ0.2fc’Ac or φ800Ac where φ = 0.75 μ = coefficient of friction = 0.4 Pu = factored compressive axial force Ac = plan area of base plate, BN • Bearing of the column and base plate and/or shear lug against concrete. φPu,brg = 0.55fc’Abrg where Abrg = vertical bearing area 53
  • 54. Shear Anchorage of Base Plates Transferring Shear Forces (ACI 318-08 and ACI 349-06) • Shear strength of the anchor rods. Not recommended because of oversize holes in base plate. • Hairpins and Tie Rods 54
  • 56. Column Erection Procedures Anchor rods are positioned and placed in the concrete before it cures. Plastic caps are placed over the anchor bolts to protect laborers. 56
  • 57. Column Erection Procedures Concrete block-outs may be made so that the base plate and anchor bolts are recessed below floor level for safety and aesthetics. 57
  • 58. Column Erection Procedures Slotted holes are allow for difference in standard field tolerances between concrete and steel. 58
  • 59. Column Erection Procedures The column is leveled by adjusting the anchor bolt nuts below the plate. Grout will be placed under and around the base plate to transfer axial forces to the concrete below. 59
  • 60. Column Erection Procedures Grout will be placed under and around the base plate to transfer axial forces to the concrete below. At least it should be. 60
  • 61. 61
  • 62. Result of Poor Anchor Rod Placement The following slides are courtesy of Fisher & Kloiber- AISC Field Fixes presentation. 62
  • 63. Anchor Rod Placement Anchor rods in the wrong location. 63
  • 64. Anchor Rod Placement Anchor rods in the wrong location. 64
  • 65. Anchor Rod Placement Anchor rods in the wrong location. 65
  • 66. Anchor Rod Placement Anchor rods too short. 66
  • 67. Anchor Rod Placement Anchor rods too long. 67
  • 68. Anchor Rod Placement Shop rework fo column and base plate. 68
  • 70. Poor Anchor Rod Placement Anchor bolts run over by a crane. 70
  • 71. Poor Anchor Rod Placement Anchor bolts run over by something. 71
  • 72. Our next IMCA Manual, due to come out shortly, will state in the Code of Standard Practice, that in addition to the requirement that the contractor responsible for placing the anchors in site, present a drawing showing the as-placed location of the anchors, that the supplier of the structure provide the necessary templates for this purpose. They are to be so designed as to insure the correct position, both vertically (including the length of the anchor extending above the concrete surface) and horizontally, show the location of the building axis relative to the anchor group and leave permanent marks of the axis in the concrete surface. The price of the templates is recommended to be the average price of the steel structure. (We save so much on the cost of erection that we would be glad to give the templates away free, but don't tell my clients.) We have been using this method over the past 5 years in all of our jobs. We are delighted in not having had a single problem in placing the columns, the structures are all self-plumbing, the bolts all easily inserted and the time for erection greatly shortened. On a job we are now doing, from the date our bid was accepted, it took 7 weeks to design, fabricate, erect the steel structure and install 20,000 sq. ft. of decking, with shear anchors hand welded, for a three story school building, working one 11 hr shift both at the shop and the site. A second similar 30,000 sq. ft. building will be finished this week, 8 weeks after the first one. 72
  • 73. 73
  • 74. 74
  • 75. 75
  • 76. 76
  • 77. 77
  • 78. 78
  • 79. 79
  • 80. 80
  • 81. 81
  • 82. 82
  • 83. 83
  翻译: